AMCI (CQ) Pty Ltd & Anor, Re [2005] QLRT 129
LAND AND RESOURCES TRIBUNAL
QUEENSLAND
CITATION: Re AMCI (CQ) Pty Ltd & Anor [2005] QLRT 129
PARTIES: Re Application for Mining Lease No. 70340 by
AMCI (CQ) Pty Ltd and Nebo Central Coal Pty Ltd
FILE NO/S: AML152/05
PROCEEDING: Application for mining lease
DELIVERED ON: 30 September 2005
DELIVERED AT: Brisbane
HEARING DATE: Heard on the papers
MEMBER: Koppenol P
ORDER/S: Recommendation made that Application for Mining
Lease No. 70340 applied for by the Applicants be
granted for the purpose, area and term applied for.
(at [19])
CATCHWORDS: MINING – MINING LEASE APPLICATION –
RECOMMENDATION
Mineral Resources Act 1989, ss 245, 252(1), 269(4)
Environmental Protection Act 1994
COUNSEL: N/A
SOLICITORS: N/A
Application
[1] This is an application by AMCI (CQ) Pty Ltd (75%) and Nebo Central Coal Pty Ltd
(25%) (the applicants) under section 245 of the Mineral Resources Act 1989 (the
Act) for a mining lease over a 1,754ha area of land situated 20km west of Coppabella
for the mining of coal. The application was lodged with the mining registrar for the
Emerald mining district on 2 February 2005. No objections to the application were
lodged during the public objection period which ended on 13 September 2005.
-- 1 of 5 --
Hearing on the papers
[2] The applicants requested that this application be heard by the Tribunal on the papers
and without an oral hearing. That procedure is appropriate in the present case.
Tribunal’s statutory function
[3] In cases such as this, the Tribunal’s statutory function under section 269 of the Act is
to take into account and consider a number of prescribed factors and then to make a
recommendation to the Minister for Natural Resources and Mines about whether the
application should be granted or rejected. In doing so, I have considered all of the
material that was provided to the Tribunal by the applicants and the mining registrar.
However these reasons only refer to such of the evidence as is relevant or necessary
for my decision.
Section 269(4) recommendation
[4] Section 269(4) provides as follows:
“269 Tribunal’s recommendation on hearing
…
(4) The tribunal, when making a recommendation to the Minister that an application for a
mining lease be granted in whole or in part, shall take into account and consider whether—
(a) the provisions of this Act have been complied with; and
(b) the area of land applied for is mineralised or the other purposes for which the
lease is sought are appropriate; and
(c) if the land applied for is mineralised there will be an acceptable level of
development and utilisation of the mineral resources within the area applied for;
and
(d) the land and the surface area of the land in respect of which the mining lease is
sought is of an appropriate size and shape in relation to—
(i) the matters mentioned in paragraphs (b) and (c); and
(ii) the type and location of the activities proposed to be carried out under the
lease and their likely impact on the surface of the land; and
(e) the term sought is appropriate; and
(f) the applicant has the necessary financial and technical capabilities to carry on
mining operations under the proposed mining lease; and
(g) the past performance of the applicant has been satisfactory; and
(h) any disadvantage may result to the rights of—
(i) holders of existing exploration permits or mineral development licences; or
(ii) existing applicants for exploration permits or mineral development licences;
and
(i) the operations to be carried on under the authority of the proposed mining lease
will conform with sound land use management; and
(j) there will be any adverse environmental impact caused by those operations and, if
so, the extent thereof; and
(k) the public right and interest will be prejudiced; and
(l) any good reason has been shown for a refusal to grant the mining lease; and
(m) taking into consideration the current and prospective uses of that land, the
proposed mining operation is an appropriate land use.
… .”
[5] I will deal in turn with the factors set out in section 269(4).
[6] Section 269(4)(a): On 16 August 2005, the mining registrar issued a certificate of
application. Pursuant to section 252(1) of the Act, the mining registrar can only do
-- 2 of 5 --
so if satisfied that the applicants are eligible to apply for the mining lease and have
complied with the requirements of the Act with respect to the application. The
applicants have lodged with the mining registrar statutory declarations certifying
compliance with the statutory requirements for notifying the application. I note the
land the subject of this application comprises freehold land, a statutory grazing
homestead perpetual lease and a dedicated road, and that the native title provisions of
the Act do not therefore apply. The mining registrar has certified that the owners of
the affected restricted land (shed, yards and dams) and reserve land (a highway) have
consented to the grant of this application. I am satisfied that the provisions of the
Act have been complied with.
[7] Section 269(4)(b): The applicants said that they knew that the proposed mining lease
area was mineralised because drilling and other exploration activities carried out on
the area have indicated that the area is mineralised. I am satisfied that the area is
mineralised.
[8] Section 269(4)(c): The coal will be mined by underground mining techniques. This
mining lease (Annandale, ML 70340) comprise a coal preparation plant, rail loop and
associated infrastructure. It also contains deep (greater than 350m) underground coal
resources that are intended to be accessed from the Carborough Downs mining lease
(MLA 70339). Carborough Downs is directly south of Annandale and adjoins it.
Both mining leases are owned by the same joint venture. Initial underground mining
on Annandale is expected to commence in March 2007. This will be as part of the
investigatory development program for Stage 1 of the Carborough Downs project—
which involves continuous miner operations developing 2 panels from nearer the
subcrop on Carborough Downs to the deeper coal measures on Annandale. Once
these panels have been developed and the mining conditions assessed, a decision will
be made for the longer term production methods for the underground mine. The
mine may continue as a continuous miner operation, or further capital may be
injected to install a longwall mining or higher capacity mining system. Following
approximately 6 months of the initial investigatory development underground at
Annandale, mining will not recommence again for several years. The shallower
more accessible underground coal on Carborough Downs will be extracted in
preference to the underground coal on Annandale. Annandale is located between
Carborough Downs and the Broadlea North area which includes Broadlea MLA
70338. The principal use for the land at Annandale is to construct a coal preparation
plant to centrally process the coal from the 2 project areas and also construction of a
rail loop and load-out facility to load and rail the coal via the established rail
infrastructure network. The coal will be trucked from Carborough Downs in the
south and Broadlea in the north to Annandale for processing. As such, the
Annandale ML will also contain haul roads and facilities for the haulage contractor.
Sediment dams and some diversion ponds will be constructed to ensure any runoff
from stockpiles are contained on site. A raw water dam will also be constructed to
provide a storage area for water taken from the Sunwater pipeline. The coal
preparation plant is expected to be commissioned in February 2006 and the rail loop
and load-out would be available to transport product coal in March 2006.
Carborough Downs and Broadlea are expected to commence coal mining in January
2006. This allows for coal delivery and build up of ROM stockpiles at Annandale in
time for the coal preparation plant commissioning. I am satisfied that there will be
-- 3 of 5 --
an acceptable level of development and utilisation of the mineral resources within the
area applied for.
[9] Section 269(4)(d): The application said that the area and shape applied for was in
order to economically fully recover the coal reserves (194 million tonnes, including
coal within the adjacent ML 70339), meet environmental obligations and to construct
a rail loop. There is no evidence to indicate that the size and shape is not
appropriate.
[10] Section 269(4)(e): A term of 30 years is sought. That term was nominated to fully
exploit the coal reserves and complete mining rehabilitation. I am satisfied that the
term sought is appropriate.
[11] Section 269(4)(f): The applicants are subsidiaries of AMCI Holdings Australia Pty
Ltd. Other subsidiary companies own the Glennies Creek underground coal mine in
the Hunter Valley, New South Wales and formerly owned the Coppabella and
Moorvale Mines in Queensland. The applicants’ directors have extensive experience
in coal mining. Supporting material provided with the application indicates that the
applicants have the requisite financial and technical capabilities.
[12] Section 269(4)(g): The applicants and their directors have never had any notices to
rectify non-compliance or damage, notices to show cause, tenures cancelled,
penalties imposed or convictions under the Act.
[13] Section 269(4)(h): The evidence indicates that there are no such underlying tenures
which are not held by the applicants.
[14] Section 269(4)(i): The current land use is for agricultural purposes, primarily the
grazing of cattle. It is apparently otherwise capable of being used for coal mining
purposes only. The mining activities will be carried out in accordance with the draft
environmental authority issued under the Environmental Protection Act 1994. After
mining, the land will be appropriately rehabilitated. I am satisfied that the proposed
mining operations conform with sound land use management.
[15] Section 269(4)(j): The mining activities will be carried out in accordance with the
draft environmental authority (mining activities) issued by the Environmental
Protection Agency. The applicants must comply with the various environmental
conditions set out in that document. There were no objections to the issue of that
authority. I am not satisfied that there will be such an environmental impact caused
by the proposed mining operations as to warrant an unfavourable recommendation in
the present application.
[16] Section 269(4)(k): There was no evidence before me that indicated that the public
right and interest would be prejudiced. A highway traverses the southern boundary
of the mining lease area and the owner of the highway has consented to the inclusion
of the surface area of the highway in ML 70340, subject to certain conditions. Power
lines and water pipelines traverse the mining leases area from west to east but the
applicants’ mining plans do not involve any disturbance to them.
-- 4 of 5 --
[17] Section 269(4)(l): There was no evidence before me that indicated any good reason
why this application should be refused.
[18] Section 269(4)(m): On the basis of the evidence and other material referred to above,
I consider that the proposed activity is an appropriate land use.
Recommendation
[19] Taking into account all of the evidence and other material before me and in particular
that referred to above, I recommend to the Honourable the Minister for Natural
Resources and Mines that Application for Mining Lease No. 70340, applied for by
the applicants, be granted for the purpose, area and term applied for.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QLRT/2005/129