Clark, Bexton, Lane & Ors, Environmental Protection Agency, Re [2005] QLRT 118
LAND AND RESOURCES TRIBUNAL
QUEENSLAND
CITATION: Re Clark, Bexton, Lane & Ors, Environmental
Protection Agency [2005] QLRT 118
PARTIES: In the Matter of Mining Lease No. 50200 and in the
Matter of Environmental Authority MIM400147503
– Application by Barry Clark and Mark Bexton for
mining lease and environmental authority and
objections by Murray Lane and others to their
grant. Environmental Protection Agency as
statutory party in the matter of Environmental
Authority MIM400147503
FILE NO: AML95/03
ENO96/03
PROCEEDING: Application for order as to validity of environmental
authority (mining lease); to return application to the
Environmental Protection Agency; for costs and, in the
alternative, for particulars of application.
DELIVERED ON: 30 August 2005
DELIVERED AT: Brisbane
HEARING DATE: 29 August 2005
MEMBER: Kingham DP
ORDER/S: 1. All applications are refused. (at [12] & [13])
2. The costs of the application are reserved. (at
[14])
CATCHWORDS: MINING – ENVIRONMENT – APPLICATION FOR
ENVIRONMENTAL AUTHORITY – STANDARD
MINING ACTIVITY – VALIDITY OF
APPLICATION AND PROCESSING OF
APPLICATION – PARTICULARS OF
APPLICATION - COSTS -
Environmental Protection Act 1994, ss 146, 147,
Schedules 1A & 3
Environmental Protection Regulation 1998, Schedule 1
Mineral Resources Act 1989, ss 6, 6A, 234, 236
COUNSEL: Mr Skoien for the Applicants
Mr McGrath for the Respondents
-- 1 of 5 --
SOLICITOR/S: Tobin King Lateef for the Applicants
Environment and Local Government Legal Services for
the Respondents
AGENT/S: Mr Pepper for the Environmental Protection Agency
[1] KINGHAM DP: The Respondents sought orders to the effect that the application
for the environmental authority and its processing by the Environmental Protection
Agency (EPA) as a standard environmental authority, was not (or is no longer) valid
and that it should be returned to the EPA to be processed as a non-code compliant
application for a level 1 mining project. The Respondents also sought an order for
costs, including reserved costs. In the alternative, they sought an order that the
Applicants provide specified further and better particulars. The Applicants opposed
all orders sought and asked that the costs of these applications are reserved. The
EPA made submissions about the orders sought in relation to the application for and
processing of the application for an environmental authority. It made no submissions
as to the requests for an order for costs or for further particulars of the application.
[2] I have concluded that, on the basis of the material before me, there is no
inconsistency between the requirements of the Environmental Protection Act 1994
(EP Act) and the actions taken either by the Applicants or the EPA in relation to the
subject application for an environmental authority (mining activities). Before stating
the reasons for that conclusion it is necessary to describe the background to the
Respondents’ applications.
[3] The applications before the Tribunal are for a mining lease and for an environmental
authority (mining activities) to allow the Applicants to mine sandstone in block or
slab form for building purposes. After making that application, the Applicants
applied to the Gatton Shire Council for a development approval under the Integrated
Planning Act 1997 (IPA) over the same site to authorise it to operate a quarry. The
quarry will involve two “environmentally relevant activities” (ERAs) which are
“level 1” ERAs. These must be authorised under the EP Act. The development
application is in progress, the EPA has been consulted by the Gatton Shire Council as
required under IPA and, in due course, a decision on that application will be no doubt
be made.
[4] Chapter 5 of the EP Act makes special provisions for environmental authorities for
“mining activities”. Other types of activities are regulated under other provisions of
the EP Act, in this case Chapter 4. The scope of the definition of “mining activities”
is, therefore, central to the Respondents’ applications. Mr McGrath, counsel for the
Respondents, submitted that the ERAs covered by the development application are
properly characterised as “mining activities”, as defined by s. 147 of the EP Act.
More particularly, he relies on s147(2)(c)(i) which refers to an activity “that is
directly associated with or facilitates or supports, an activity mentioned in
paragraph (a) or (b)”. He argued that the ERAs are directly associated with, or
facilitate or support, the mining of sandstone blocks. As such, they should be
regulated under the environmental authority (mining activities) now before the
Tribunal.
-- 2 of 5 --
[5] The relevance of the ERAs being level 1 is that one of the criteria for standard
mining activities prescribed in Schedule 1A of the EP Act is that the mining
activities do not include a level 1 ERA. According to Mr McGrath, the consequence
of this is that the application for the environmental authority (mining activities) has
wrongly been made and processed as a standard mining activity. The EP Act was
recently amended such that there are no longer standard and non-standard mining
activities. The new terminology is of code compliant and non-code complaint
authorities. Nevertheless, the point of distinction and the consequence appears to be
the same for the purposes of the application. For a non-standard or non-code
compliant authority, the applicant must provide a greater level of detail about the
activity and the EPA must follow a different process.
[6] Mr McGrath submitted that if the two ERAs fall within the definition of mining
activities, the application has not properly made (because the required information
has not been provided) or validly processed (because the wrong process has been
used). However, he conceded that, if they do not fall within that definition, there is
no question before me as to the validity of the application or the EPA’s treatment of
it.
[7] It appears that this application is before the Tribunal because the mine and the quarry
will be conducted on the same site, albeit at different times and that, therefore, they
are perceived by the Respondents as being integrally connected activities. The
miners have to remove overburden material in order to reach the sandstone that can
be mined in block form. It is understandable that they would seek to do this in a
profitable manner, by way of quarrying, if possible. To that extent, they are
obviously associated. However, the quarrying is not a necessary precursor to the
mining. Depending on market circumstances and the nature, depth and quality of the
resource, a miner may instead choose only to remove and store the overburden for
subsequent rehabilitation of the site. Further, it is beyond doubt, in my view, that a
miner could not obtain approval for a quarry under the Mineral Resources Act 1989
(MRA) and by way of an environmental authority (mining activities).
[8] As for approval under the MRA, that Act provides for a mining lease to be granted
for the purpose of mining minerals (s234). Minerals are defined to include “(2)(k)
rock mined in block or slab form for building or monumental purposes” but to
exclude rock “other than rock mentioned in subsection (2)(k)) if it is to be used or to
be supplied for use, as sand, gravel or rock, whether intact or in broken form” (s.6).
A mining lease could not be granted, therefore, to mine rock in any way other than in
block or slab form and for building or monumental purposes. There is, however,
limited authority conferred on the holder of a mining lease to use sand, gravel or rock
on the mining lease area and for a purpose authorised by the mining lease (s.236).
This authorisation specifically exempts the holder from a requirement under any Act,
other than the EP Act, to obtain approval for that use. Clearly, any other use of such
resource, such as to remove it from the mining lease and sell it, is not authorised by
the MRA and is not so exempt.
[9] As for authorisation under an environmental authority (mining activities), the
relevant provisions (Chapter 5) only apply to “mining activities” (s.146). Section147
defines a mining activity as “(1)….an activity mentioned in subsection (2) that,
under the Mineral Resources Act, is authorised to take place”. Mr Pepper, senior
-- 3 of 5 --
legal officer of the EPA, and Mr Skoien, counsel for the Applicants, both submitted
that the list of activities in s.147(2) serves to qualify, not expand the definition of
mining activities in s147(1). That is, it is possible for an activity to be authorised
under the MRA yet not be a mining activity within the meaning of s.147 of the EP
Act, because it does not fall within the list of activities set out in subsection 2.
However, the list of activities in that subsection cannot serve to expand the definition
to encompass an activity that cannot be authorised under the MRA. I accept that
submission.
[10] I am satisfied that, if the proposed activities are activities that fall within the
descriptions of the two identified ERAs, they are not mining activities as defined in
s147. The two ERAs are: ERA 20 – extracting rock or other material…other than
rock mined in block or slab form for building purposes….; and ERA 22 - Screening
etc materials…other than under a mining tenement. Both ERAs, by their own terms,
are confined to activities that fall outside the authorisation provided by the MRA.
[11] ERA 20, by excluding the extraction of rock mined in block or slab form, reflects the
definition of mineral in the MRA and applies only to the extraction of rock that does
not fall within that definition. ERA 22 only applies to screening material other than
under a mining tenement. Mining tenement is defined in Schedule 3 (definitions of
mining tenement and mining lease) to include a mining lease granted under the
MRA.
[12] As the activities covered by both ERAs fall outside the authorisation conferred by the
MRA they must fall outside the definition of s.147. Accordingly, the Respondents’
applications for orders as to the validity of the application and its processing and to
require the application to be sent back to the EPA to be processed as a non-code
compliant application are refused.
[13] As to the particulars of the application, I note that some particulars have recently
been provided and that some further detail about the Applicants’ proposed mining
operation are included in expert reports and in other material filed in preparation for
the hearing. The purpose of particulars is to fairly apprise the other party of the
nature of the case to be met. I accept Mr Skoien’s submission that the Applicants
have done that in this case. Mr McGrath submitted that the remaining particulars the
Respondents require are the rate of extraction and the maximum depth of the mine.
Mr Skoien observed that the Applicants had applied for a mining lease and an
environmental authority which is not restricted by production levels or by mine
depth. As such they took the risk that an objector would seek such restrictions or the
EPA would propose them. I accept his submission that it is open to the Respondents
to propose limitations on the scope of the activity if they consider that to be
necessary to eliminate, limit or control any particular environmental impact. They
are not disadvantaged in the preparation of their case by the Applicants choosing not
to propose such restrictions. Accordingly, the request for an order for further
particulars is also refused.
[14] If successful, Mr McGrath requested an order in favour of the Respondents for costs
pursuant to s.50 of the Land and Resources Tribunal Act 1999, including the costs
reserved in this matter. The Respondents were not successful. There are already
costs reserved in these proceedings. I accept Mr Skoien’s submission that it is
appropriate to also reserve the costs of this application and I so order.
-- 4 of 5 --
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QLRT/2005/118