Barooga Projects (Investments) P/L v Duncan [2004] QCA 149
SUPREME COURT OF QUEENSLAND
CITATION: Barooga Projects (Investments) P/L v Duncan [2004] QCA
149
PARTIES: BAROOGA PROJECTS (INVESTMENTS) PTY LTD
ACN 068 115 426 AS TRUSTEE
(applicant/respondent)
v
KEITH WILLIAM DUNCAN
(respondent/appellant)
FILE NO/S: Appeal No 11107 of 2003
SC No 9541 of 2003
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 7 May 2004
DELIVERED AT: Brisbane
HEARING DATE: 10 March 2004
JUDGES: McMurdo P and White and Fryberg JJ
Separate reasons for judgment of each member of the Court,
each concurring as to the order made
ORDER: Appeal dismissed with costs
CATCHWORDS: CONTRACTS – DISCHARGE, BREACH AND
DEFENCES TO ACTION FOR BREACH –
REPUDIATION AND NON-PERFORMANCE –
ELECTION AND RESCISSION – EFFECT OF ELECTION
NOT TO RESCIND – where appellant entered into contract
for sale of land – where special condition regarding issuance
of development conditions for the benefit of the respondent –
where time of the essence – where appellant alleged that a
reasonable time for fulfilment of special condition had
elapsed and gave notice to respondent that he expected
settlement by a certain date – where no clear reservation of
right to terminate if settlement not effected – whether
appellant had elected to continue with contract – whether
appellant could later terminate contract for failure to fulfil
special condition within a reasonable time
Immer (No 145) Pty Ltd v Uniting Church in Australia
Property Trust (NSW) (1993) 182 CLR 26, applied
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR
537, considered
-- 1 of 9 --
2
Sargent v ASL Developments Ltd (1974) 131 CLR 634, cited
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418, cited
COUNSEL: M D Martin for the appellant
M M Stewart SC for the respondent
SOLICITORS: Georgeson & Company for the appellant
Paul Everingham & Co for the respondent
[1] McMURDO P: Barooga Projects (Investments) Pty Ltd, ("the respondent"),
sought a declaration in the Trial Division of this Court that Mr Duncan ("the
appellant") was obliged to complete the conveyance the subject of the contract dated
10 February 2003 of a 4.36 hectare property at Bellmere near Caboolture. The
learned primary judge sitting in applications granted a declaration. The appellant
appeals from that order.
[2] The following facts are not in dispute. The parties entered into a contract for the
sale of the land on 10 February 2003 which included the relevant special conditions:
"3. The seller acknowledges that the development will be subject to
the Caboolture Shire Council issuing conditions and that those
conditions must be satisfactory in every respect to the buyer. The
buyer will notify the seller within thirty (30) days of receipt of the
conditions whether they are satisfactory or not.
…
6. COMPLETION:
Settlement of this Contract will take place one hundred and eighty
(180) days of the date hereof or within thirty (30) days of notification
from the buyer that it is in receipt of acceptable conditions of
approval, whichever is the later.
…"
[3] Under cl 6 of the standard conditions of the contract time was of the essence of the
contract.
[4] On 26 September 2003 the appellant's solicitors wrote to the respondent's solicitors
in these terms:
"We note that the subject contract does not specify a date by which
the balance of the development conditions are to be complied with.
We note further that Special Condition 6 provides:
[as set out above]
We note further that the period of one hundred and eighty (180) days
has elapsed some time ago and no notification regarding the
conditions of approval has been received by our client.
In the absence of a specified date, the law implies a reasonable time
in which the buyer is to obtain acceptable conditions of approval.
-- 2 of 9 --
3
Our client considers that a reasonable time has now elapsed.
We now give you formal notice on behalf of the seller that he
requires the buyer to settle this contract within twenty one (21) days
of the date hereof, that is, by 5.00 pm on Friday, 17 October 2003,
failing which he specifically reserves his rights as a consequence of
the buyer's failure to settle." (my emphasis).
[5] The respondent's solicitors replied on 8 October 2003 that the respondent was under
no obligation under the contract to settle and:
"… If your client should seek after 17 October 2003, to rescind or
otherwise void the contract our client will immediately apply to the
court for a declaration that the contract remains valid and
enforceable.
Your client may rest assured though, that our client is doing all it
reasonably can to ensure the conditions are complied with."
[6] On 16 October 2003, the appellant's solicitors again wrote to the respondent's
solicitors confirming that their client was "ready, willing and able to settle" and that
they "require[d] settlement to be effected" at their office by 5 pm on Friday, 17
October 2003.
[7] The respondent's solicitors on 17 October 2003 wrote to appellant's solicitors stating
their efforts to meet the terms of the contract in obtaining acceptable conditions of
approval from the Caboolture Shire Council ("the Council"), that a reasonable
period of time had not elapsed, that there was no obligation upon them to settle on
17 October 2003 and that the contract remained "valid and enforceable".
[8] The respondent did not settle on 17 October 2003. On 5 November 2003 the
respondent's solicitors wrote to the appellant's solicitors stating that their client
instructed that the Council had issued conditions for the development satisfactory to
their client; the letter was formal notification of their client's satisfaction with the
conditions; the respondent was now prepared and ready to settle within 30 days or
earlier if acceptable and nominated Wednesday, 19 November 2003 as a mutually
convenient date of settlement.
[9] Despite the respondent's stated readiness to settle, on 10 November 2003 the
appellant's solicitors wrote to the respondent's solicitors in these terms:
"We refer to our letters of 26 September and 16 October 2003.
We note that your client failed to settle as required by 17 October
2003.
The contract is therefore terminated.
Our client otherwise reserves his rights generally."
[10] Mr Allsop, a director of the respondent, had negotiations with the Council and the
mayor. The Council's Town Planning Department's report had imposed conditions,
which were satisfactory to him, on the development of the land. Whilst he
understood it was still necessary for the Council to consider the application, in the
-- 3 of 9 --
4
light of the town planning report he regarded it as a foregone conclusion that the
Council would approve the development application for the land on the terms set
out in the town planning report.
[11] The learned primary judge noted in his reasons that it was not in dispute for the
purposes of this application that, since no time limit was fixed in the contract for
satisfying the requirement of special condition 3, satisfaction within a reasonable
time was to be implied and that by 26 September 2003 a reasonable time had
expired.1
[12] The learned primary judge reached the following conclusions. Special Condition 3
was a contingent and not a promissory condition, included for the benefit of the
respondent. Upon the expiry of a reasonable period without satisfaction of that
condition, the contract became voidable, (but not void), at the instance of either
party.2 By the letter of 26 September 2003 the appellant called for completion of
the contract without explicitly reserving his right to terminate on the grounds that
the reasonable period for satisfaction of the condition had expired and irrevocably
elected to affirm the contract.3 The respondent in its letter of 5 November 2003
was entitled to insist upon completion of the contract as it had waived the Special
Condition 3. As the contract was still on foot the respondent was then entitled to
call for settlement within 30 days under Special Condition 6.4
[13] The appellant's contention is that his Honour erred in concluding that the letter of 26
September 2003 amounted to an irretractable election to affirm the contract. The
letter was no more than an intention to refrain from making an election to affirm or
terminate the contract until 17 October 2003: Immer (No 145) Pty Ltd v Uniting
Church in Australia Property Trust (NSW).5 Alternatively the appellant contends
the letter of 26 September was effectively a notice to complete, similar to the
situation in Perri v Coolangatta Investments Pty Ltd.6 The appellant particularly
relies on the following remarks by Wilson J:
"If on the expiration of a reasonable time that property has not been
sold, then either party may initiate the steps which are necessary to
the termination of the agreement: cf Suttor v Gundowda Pty Ltd.
There being no default, the deposit will be refunded.
In my opinion, it is to be implied from the agreement that should the
… property not be sold within a reasonable time, then the fate of the
contract will be resolved according to the action which may be taken
by either party. The purchasers may elect to waive the condition, it
being one wholly for their benefit, and proceed to completion,
thereby holding the vendor to its contract. Alternatively, provided
that they have acted reasonably in their attempts to sell the property,
they may rely on the non-fulfilment of the condition to bring the
1 Reasons for judgment, pp 2-3.
2 Above p 5 and see also Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR 537, 543 per Gibbs
CJ and 565 per Brennan J, Stephen J agreeing; Sandra Investments Pty Ltd v Booth (1983) 153 CLR
153 and Associated Developers (Aust) Pty Ltd v Allied & General Pty Ltd, unreported, No 1089 of
1994, 16 August 1994 at p 4.
3 Reasons for judgment, pp 7-8.
4 Above, p 8.
5 (1993) 182 CLR 26.
6 (1982) 149 CLR 537.
-- 4 of 9 --
5
contract to an end, and recover their deposit. On the other hand, the
vendor may force the issue simply by serving a notice to complete. I
do not think it appropriate to contemplate a notice to the purchasers
requiring them to fulfil the condition, because the time agreed for
that will have expired, and in any event it does not lie within the
capacity of the purchasers to fulfil it. The effect of a notice to
complete is to give the purchasers, should they wish to waive the
condition, the opportunity to finalize the transaction; alternatively, it
serves to crystallise in the minds of both parties a common date on
which the contract will come to an end for non-fulfilment of the
condition. In the latter case, non-compliance with the notice to
complete will not fix the purchasers with any default such as would
deprive them of the right to the return of their deposit, although as I
have said, a failure to make reasonable efforts to sell the property
may expose them to an action for damages." 7 (my emphasis).
[14] The appellant did not contend at first instance or on appeal that the respondent's
failure to complete the contract on 17 October 2003 was a breach of that contract.
Did the appellant irrevocably affirm the contract by the letter of 26 September
2003?
[15] At the heart of the doctrine of election is that a party electing is confronted with two
mutually exclusive courses of action between which that party must, in fairness to
the other party, make a choice.8 The operation of the doctrine can have serious
consequences, for once that choice is made it is irrevocable, and the other course of
action – in this case rescission of the contract for non-fulfilment of Special
Condition 3 within a reasonable time – is no longer open. For this reason the words
or conduct said to constitute an election must be unequivocal, in the sense that they
are "consistent only with the exercise of one of the two sets of rights and
inconsistent with the exercise of the other".9 It follows that "if the act is also
consistent with the reservation of a right to terminate in certain events, the right to
terminate is not lost by the doing of the act".10
[16] An election to affirm a contract does not depend upon an actual intention; it will be
inferred from any conduct consistent only with the continued existence of the
contract.11 Whether the circumstances amount to an election to affirm the contract
will turn on the particular facts of each case.
[17] The appellant's letter of 26 September 2003 and his following correspondence of 16
October 2003, set out above, undoubtedly affirmed the appellant's commitment to
the contract. He unequivocally insisted on his most central right under the contract,
settlement, in calling on the respondent to complete the sale. Whether he intended
to do so or not, in the September letter and again in the letter of 16 October he did
7 At 560.
8 Spencer, Bower and Turner, The Law Relating to Estoppel by Representation (3rd edition, 1977)
313, approved in Immer (No 145) Pty Ltd v United Church in Australia Property Trust (NSW) (1993)
182 CLR 26, 41 per Deane, Toohey, Gaudron and McHugh JJ.
9 Sargent v ASL Developments Ltd (1974) 131 CLR 634, 646 per Stephen J, quoted with agreement in
Immer (No 145) Pty Ltd v United Church in Australia Property Trust (NSW) (1993) 182 CLR 26, 38-
39 per Deane, Toohey, Gaudron and McHugh JJ.
10 Immer (No 145) Pty Ltd v United Church in Australia Property Trust (NSW) (1993) 182 CLR 26, 30.
11 Tropical Traders Ltd v Goonan (1964) 111 CLR 41, 55 per Kitto J.
-- 5 of 9 --
6
not explicitly reserve until 17 October 2003 his right to terminate the contract on the
ground that a reasonable period for satisfaction of Special Condition 3 had expired.
[18] I am not persuaded that the appellant is assisted by the observations of Wilson J in
Perri set out earlier in these reasons. In that case, the majority of the High Court12
found that it was open to either party to a contract contingent upon the fulfilment of
a special condition that had not been fulfilled within a reasonable time, if not in
default, to elect to treat the contract as at an end. There the contract was avoided
when the vendors instituted proceedings against the purchasers. Wilson J agreed
with the majority that the vendor was entitled to rescind the contract but also found
that reasonable notice was a prerequisite to this rescission. His Honour was the
only member of the court to elaborate on the effect of a notice to complete in those
circumstances. His Honour's observations are authority for the uncontroversial
proposition that a party to a contract confronted with a choice whether to continue
with or terminate a contract need not make that choice immediately and may before
doing so seek the other party's agreement to continue the contract, whilst reserving
the right to terminate in the event that no such agreement can be reached. Wilson
J's observations do not change the appellant's clear affirmation of the contract in the
letters of 26 September and 16 October 2003 into an extension of the time in which
to make the decision whether or not to affirm the contract until 17 October 2003.
This would require an unequivocal reservation of the right to terminate upon failure
to settle on that date. The letters simply did not contain that reservation.
[19] The respondent's letter of 5 November 2003 effected a waiver of the benefit of the
contingent Special Condition 3. It follows that under Special Condition 6 the
respondent was entitled to settlement within 30 days of its waiver of Special
Condition 3, that is, on 5 December 2003. The learned primary judge was right to
declare that the appellant was obliged to complete the conveyance the subject of the
contract dated 10 February 2003 on or before 5 December 2003.
[20] The appeal should be dismissed with costs.
[21] WHITE J: I have read the reasons for judgment of the President where she has set
out the relevant facts. There is little in dispute between the parties save the
fundamental question whether the appellant’s letter of 26 September 2003
constituted an election to affirm the contract which could not be retracted.
[22] Against the background of the contract for the sale of the land and the fact that the
respondent had not obtained acceptable conditions of approval from the Caboolture
Shire Council the appellant wrote the letter of 26 September 2003 the significant
passage of which read:
“We now give you formal notice on behalf of the seller that he
requires the buyer to settle this contract within twenty one (21) days
of the date hereof, that is, by 5.00pm on Friday, 17 October 2003,
failing which he specifically reserves his rights as a consequence of
the buyer’s failure to settle.”
This was followed by his letter of 16 October 2003 which the President has set out.
[23] As the learned judge below noted, Special Condition 3 was a contingent and not a
promissory condition which was included in the contract for the benefit of the
12 Gibbs CJ, Stephen and Brennan JJ.
-- 6 of 9 --
7
purchaser. The contract thereby became voidable at the instance of either party
once a reasonable time for satisfying the requirement had expired, but in the
absence of either party doing so the contract remained on foot, Suttor v Gundowda
Pty Ltd (1950) 81 CLR 418 at 440 and ff.
[24] As the learned primary judge noted, once a party becomes entitled to elect for or
against rescinding a contract any act done by a party objectively consistent only
with the continuation of the contract would constitute an election against rescinding
and, having been made, could not be retracted. There was no obligation on the
appellant to do anything and the contract would remain extant until one of the
parties took action one way or another.
[25] The appellant clearly and unequivocally was affirming the continuation of the
contract by calling on the respondent to settle. But since the respondent was not
obliged to settle because of Special Condition 3 the general reservation of rights
made by the respondent was ineffectual. What was required, as his Honour
recognised, was a carefully worded, explicit reservation of his right to rescind on
the ground that the reasonable time implied in the contract for the satisfaction of
Special Condition 3 had expired.
[26] Accordingly the contract was still on foot on 5 November 2003 when the
respondent notified readiness to settle on or before 5 December 2003 having either
waived reliance on Special Condition 3 or was satisfied about the conditions
imposed by the Council.
[27] His Honour was right to make the declaration. I agree with the orders proposed by
the President.
[28] FRYBERG J: I agree with the reasons for judgment of the President. There are
however a few additional matters which have affected my judgment.
[29] The application to the Council, lodged in accordance with the contract on 20 May
2003, sought a “material change of use” within the meaning of the Integrated
Planning Act 1977 and was made in respect of four contiguous allotments, only one
of which belonged to the appellant. It sought a development permit for rezoning,
another permit for stage one of the subdivision and preliminary approval for the
balance of the subdivision. It appears that it was not determined by the Council
within the time frames provided by the Act for cases where the developer does not
stop time running. The question whether the application conformed to the
requirements of condition 2 of the contract was not and is not before the court; and
there has been no suggestion that the respondent was guilty of delay. Presumably it
would not have advanced the appellant's position to have raised such issues.
[30] On the other hand the case has been decided on a concession and an assumption
favorable to the appellant. The respondent did not dispute that as no time was
prescribed by condition 3 for the Council to issue conditions, it was to be implied
that this would occur within a reasonable time; and the judge at first instance
assumed without opposition from the parties that a reasonable time had expired by
26 September 2003. Had these been live issues it would have been material to have
considered the whole of condition 3, not simply the part quoted by the President.
[31] As the President has noted the appellant submitted that the letter of 26 September
2003 showed no more than an intention to refrain from making an election to affirm
-- 7 of 9 --
8
or terminate the contract until 17 October. That submission was supported by
reference to Immer (No 145) Pty Ltd v Uniting Church in Australia Property Trust
(NSW)13, where four members of the High Court said:
“If a party to a contract, faced with the choice of terminating the
contract or keeping it on foot, terminates the contract that party will
ordinarily have acted in a way that leaves no doubt as to the choice
made. And that choice will be clearly inconsistent with the exercise of
the right to keep the contract on foot because the contract no longer
exists. But where, as here, the situation is the converse the question is
not answered so readily ….
As Spencer Bower and Turner point out in the passage quoted earlier,
at the heart of election is the idea of confrontation which in turn
produces the necessity of making a choice. But in a case such as the
present one, the choice is not merely one of affirming the agreement; it
involves as well the abandonment of the right to rescind.
Abandonment is more readily inferred in some circumstances, for
instance where the choice arises once and for all. Here, by reason of
cl.7 of the deed, Immer was entitled at any time after 1 April 1989 to
rescind the deed. There is of course a danger of circularity here
because the Uniting Church says: "Yes, so long as Immer did not elect
not to rescind." The point is that where the right to rescind is a
continuing one, it is not so readily concluded that the party entitled to
rescind has abandoned that right completely as opposed to taking no
action to exercise the right at the time in question.”
[32] As Mr Martin for the appellant submitted, the present is also a case where what is
alleged is not merely affirmation of the agreement. It also involves, on the
respondent's case, abandonment of the right to rescind. Once upon a time that might
have been called waiver. In the present context that word is no longer favoured.14
The preferred term is election. The name does not matter. The question is whether
the inference of abandonment should be drawn.
[33] It was not drawn in Immer because at the time of the relevant conduct the stage had
not been reached where the purchaser was required to make an election. Its conduct
in forwarding documents was based on a mistaken belief of fact, namely that the
Council had approved the transfer. Its conduct caused the vendor no prejudice. The
present case is different. The appellant was very much aware of all relevant facts,
having wanted to terminate the contract almost from its inception. He had signed an
earlier contract with the respondent which had been terminated only two days
before the contract the subject of the present proceedings was signed. That occurred
because the appellant refused to grant an extension of time for fulfillment of a
condition. After referring to the signing of the present contract he deposed:
“Within a few days I realized what I had done, which was to sign a
contract I had just expended solicitor’s fees and considerable time in
attempting to terminate, and instructed my solicitors to terminate the
contract at the first available opportunity, which was in June 2003, by
13 (1993) 182 CLR 26.
14 Sargent v ASL Developments Ltd (1974) 131 CLR 614; Commonwealth of Australia v Verwayen
(1990) 170 CLR 394.
-- 8 of 9 --
9
relying on the applicant’s failure to notify me of the outcome of the
special condition relating to contamination, although on legal advice I
later withdrew the notice terminating the contract.”
Moreover the letters sent on his behalf had the potential to cause prejudice to the
respondent.
[34] Mr Martin also relied on Perri v Coolangatta Investments Pty Ltd15 for the
proposition that sending a notice to complete in such circumstances does not
amount to an affirmation of the contract or an election to abandon the right to
terminate. It is true that giving the notice to complete in that case was not held to
amount to an election to abandon the right to terminate; but that is because it was
not considered. In any event, each case must depend upon its own facts.
[35] Two features of the appellant's letters of 26 September and 16 October should be
noted. First, at no point did the appellant specifically reserve the right to terminate,
either expressly or implicitly. Second, he unconditionally demanded settlement,
without any suggestion that he was contemplating an alternative course of action. It
is true that in the first letter he reserved his rights as a consequence of the buyer’s
failure to settle. That does not help his case. His right to terminate did not arise as
a consequence of the buyer’s failure to settle but as a result of the non-fulfilment of
condition 3 within a reasonable time. Moreover the words quoted were apt to cover
a right to affirm the contract and sue for damages, if such a right existed.
[36] The appeal should be dismissed with costs.
15 (1982) 149 CLR 537.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2004/149