Caswell & Anor v Maroochy Shire Council [2004] QPEC 78 [2005] QPELR 379
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Caswell & Anor v Maroochy Shire Council [2004] QPEC 078
PARTIES: ROGER CASWELL and THE VILLAGE BUILDING
CO LIMITED (Appellants)
v
MAROOCHY SHIRE COUNCIL (Respondent)
FILE NO: BD 4004 of 2004
PROCEEDING: Application for directions after deemed refusal
DELIVERED ON: 24 November 2004
DELIVERED AT: Brisbane
HEARING DATE: 17 November 2004
JUDGE: Judge Brabazon QC
ORDER: Declare a deemed refusal of application
CATCHWORDS: PLANNING LAW – Integrated Planning Act (Qld) –
Information request – Limits of authority of Council to make
requests for information – Whether Council went beyond that
authority.
ADMINISTRATIVE LAW – Integrated Planning Act (Qld) –
Information request – Severance – Where questions asked
that are unauthorised by the statute – Whether the whole of
the request is ineffective.
Integrated Planning Act s.3.3.6(6); s. 3.3.20(b); s.3.5.1(2)(a);
s.4.1.27; s.
Amalgamated TV Services v ABT (1989) 88 ALR 287
Dyson v Attorney-General (1912) 1 Ch 158
Olsen v City of Camberwell (1926) VLR 58
Thames Water Authority v Elmbridge Borough Council
(1983) 1 QB 570
COUNSEL: Mr J Haydon for the applicant
-- 1 of 12 --
2
Council solicitors for the respondent
SOLICITORS: Mullins Lawyers for the applicant
Mr G. Phillips, Maroochy Shire Council for the respondent
The Issue
[1] In this case Mr Caswell and The Village Building Co made an application for
operational works (engineering works) to the Maroochy Shire Council on 15 June
2004.
[2] The applicants say that the Council is now deemed to have refused their application.
The Council denies that, saying that the decision making stage of the application has
not yet commenced.
[3] The applicants filed a Notice of Appeal on 9 November. They wish to proceed with
the appeal. The Council says that the appeal is premature, and void.
[4] To resolve the dispute, it is necessary to focus on the role played by an information
request, issued by Council. That, the statutory framework needs to be understood.
The Integrated Planning Act
[5] A disappointed applicant to a local authority can appeal at any time after a decision
should have been made. See IPA s.4.1.27. There will be a “deemed refusal” if a
decision is not made by the end of the decision making period. See the definition of
‘deemed refusal” in Schedule 10 to IPA.
-- 2 of 12 --
3
[6] After an application is made, the information referral stage comes to and end if an
information request is made by Council, and the applicant has finished responding
to that request. See IPA s.3.3.20(b). When that happens, the decision making
period starts on the day the applicant responds to the information request –
s.3.5.1(2)(a).
[7] The right to deliver an information request is set out in s.3.3.6. In this case, the
assessment manager might ask the applicant by written request to give further
information needed to assess the application. That written request is the
information request. The notice must be given within 10 business days after the
giving of the acknowledgement notice. That is the information request period.
[8] Section 3.3.8 deals with an applicant’s response. It must respond, in one of three
ways –
(a) it may give the Council all of the information requested; or
(b) it may give the Council part of the information requested, together with a
notice asking the Council to proceed with the assessment of the application;
or
(c) it may give the Council a notice stating that the applicant does not intend to
supply any of the information requested, and asking the Council to proceed
with the assessment of the application.
The Information Request
-- 3 of 12 --
4
[9] Council wrote to Mr Caswell on 21 July. Appropriate reference is made to the
application for operational works. A heading indicates that the letter is an
information request, given under IPA. The first paragraph advises that: “Our
preliminary assessment identifies the need for further information to enable the
proper consideration and determination of the application …”.
[10] Then follows about three pages of text, which is under the headings of Roadworks
and Drainage, Hydrology, Sewerage and Water Supply, and Environment.
[11] It is immediately apparent that large parts of the letter are not requests for
information.
[12] Under the heading of “Roadworks and Drainage the first two bullet points may be
recognised as a request for information. However, the third bullet point is simply a
reference to a requirement of Maroochy Plan 2000, while the fourth bullet point is a
request to amend the application with respect to a drainage line.
[13] Under the head “Hydrology”, the letter raises concerns about the effect of drainage
at the site. Some criticisms are made of the proposal, in that respect. It observes
that “Drainage issues relating to the drainage of Lots 1 to 22 have not been properly
addressed”. Then, under the heading of “Information Requests” the letter continues:
“The applicant is requested to provide an amendment to the drainage
and stormwater quality and quantity management plan to
demonstrate compliance with the conditions of approval of the
permit for reconfiguration of lots and compliance with non-worsting
of existing water regimes and quality requirements as stated in …”
That is not a request for information. It is a request to amend the application.
-- 4 of 12 --
5
[14] Under the heading “Sewerage and Water Supply” the first request is to: “Show the
house junctions drainage and level of the long sections”. That is an appropriate
request for information.
[15] However, then follow seven references to the proposal, requiring either the
elimination of something which is proposed, or the provision of something which
has not been proposed. All those things would amount to amendments to the
application. They are not requests for information. Indeed, the letter does not
contain any heading to that paragraph, saying that it is an information request.
[16] On the topic of the Environment, an issue with respect to acid sulphate soils is
identified. There is then a reference to an information request: “The applicant is
requested to demonstrate compliance with the Maroochy Plan 2000 Code …”.
That is an information request, as information is requested about how there will be
compliance with the appropriate standards.
[17] A second issue with respect to erosion and sediment control is identified. Some
criticisms of the application are made, and amendments suggested. Under the
heading of “Information Request”, the letter continues:
“Accordingly, it is recommended that the erosion and sedimentation
control measures be re-evaluated in light of the above concerns and a
plan of layout showing the revised erosion and sediment control
measures be provided prior to approval.
A management plan should also be included with the required
management commitments and titles of people responsible for
undertaking all necessary action. …”
[18] While a request for a management plan may be seen as a proper request for
information, about how something is going to be achieved, the request here is made
-- 5 of 12 --
6
in the light of a recommendation for a “re-evaluation” of the application. That is
not a request for information.
[19] The Council officer responsible for the information request, has misunderstood the
power given by IPA. The Council’s authority extends to asking for further
information needed to assess the application, and no further. The information
request should have been limited to that. Council had no authority to go beyond the
request for information. Suggestions about amendments and the like were
inappropriate, and ineffective. That is, they went beyond the power to request
information.
[20] When an information request contains both proper questions and other things which
go beyond the request for information, it is necessary to consider if the whole
request is ineffective, and can be ignored. In principle, there is a helpful discussion
of the issue in Administrative Law by Wade and Forsyth, 8th ed., p.294:
“Partial Invalidity
An administrative act may be partially good and partially bad. It
often happens that a tribunal or authority makes a proper order but
adds some direction or condition which is beyond its powers. If the
bad can be cleanly severed from the good, the court will quash the
bad part only and leave the good standing.
…
Where an order is not divisible into component parts but is a single
whole the court may decline to sever the bad from the good, as it did
where the Secretary of State for Transport miscalculated the sum
which he ordered the Greater London Council to pay to London
Regional Transport and unlawfully overcharged them by some
£10m. But there is no ‘blue pencil rule’ requiring the bad part of the
order to be identifiable in the order itself. Thus a local authority’s
order which appropriated land for planning purposes, but which
included a small plot which was outside its powers, was held to be
severable and valid as regards the remainder, even though it treated
all the land as a single area. These cases depend not upon rigid rules
but upon the balance of advantage as perceived by the court.
-- 6 of 12 --
7
It may be no easier to draw the line where the authority is
empowered to demand information and demands more than is
permitted. In the well-known case of Dyson v. Attorney-General
(1912) 1 Ch 158, where the Act required the taxpayer to make a
return under penalty, it was held that the tax commissioner’s demand
was wholly invalid where they included an unauthorised question in
the form of return which they required. This was because the
penalties of the Act applied to a return which was one and indivisible
and which could not be split into good and bad parts. But where the
power is to demand such information as is thought necessary or as
may be required for some purpose, a demand which is partly within
the power and partly in excess of it may be severed, so that it is valid
to the extent that it falls within the Act and no further. The mere
inclusion of an unauthorised item will not therefore exonerate the
recipient. But ‘it may well be that if the excess is so entwined with
the valid as to be separable from it only with difficulty, then the
whole of the requirement will be bad: the subject ought not to be
required to perform delicate feats of surgery upon what is in
substance a single requirement’.”
[21] There is a very helpful discussion about the conduct of local authorities, in Thames
Water Authority v Elmbridge Borough Council (1983) 1 QB 570. The Court of
Appeal held that, where a local authority acted in excess of its powers, the court was
entitled to look not only at the documents but also at the factual situation. If the
excess of power was easily identifiable from the valid exercise of power, then the
court could give effect to the valid part.
[22] It was pointed out, that good public administration required a court to hesitate
before declaring that the whole of a decision, or document demanding something, is
wholly invalid. The same approach is to be taken in this country. See Olsen v City
of Camberwell (1926) VLR 58, and Amalgamated TV Services v ABT 88 ALR 287
at 312.
[23] Here, those principles show that it is appropriate to ignore the ineffective parts of
the request and to preserve the effective ones. They are identified above.
-- 7 of 12 --
8
[24] It must not be thought that this judgment is meant to be any discouragement to local
authorities from communicating with applicants for development. It is obviously
desirable for councils to exchange information, criticism, and suggestions with
developers. Many difficulties can be overcome by negotiation. The important thing
to make clear is that such informal contact should not be mixed up with the formal
request for information. That is a statutory process which is an important step along
the path to an approval, or a refusal, or a deemed refusal. It is not surprising that the
applicants’ complained to Council about the approach of the officer, who wrote the
letter of 21 July 2004. They were justified in doing so.
A Deemed Refusal?
[25] The affidavits show an exchange of correspondence from 21 July through to 26
October. The applicants had not given a notice pursuant to s.3.3.8(1)(c) stating that
they did not intend to provide the information requested. (The applicants’ letter of
15 September 2004, in its last paragraph, asks that: “Our application be processed
promptly”. Clearly enough, that request is not enough to amount to such a notice.)
[26] It is necessary to turn to the affidavit evidence to see if all of the necessary
information has been given to the Council.
[27] The first valid request, with respect to roadworks and drainage, was for the
submission of a traffic management plan. At first, the applicants were inclined to
argue about the appropriateness of that. However, after an exchange of
correspondence, their letter of 17 August included a traffic management plan. It is
not suggested that any other information remains to be provided.
-- 8 of 12 --
9
[28] The second request was for a “specific stormwater management strategy plan as per
Condition 31 of REC03/0171”.
[29] It is necessary to pay attention to the time within which Council had the power to
make an information request. The starting point is the lodgement of a properly
made application. In this case, that was 23 June, when the missing signature of a
director of The Village Building Co was supplied. The 10 day period then began on
24 June.
[30] On 7 July, the last day of that period, a letter from Council extended the information
request period by 10 days. That was in order – see IPA s.3.3.6(6). Accordingly, the
extended period expired on 21 July. That is the day on which the information
request was given.
[31] On 29 July the Council’s hydrology assessment officer sent a memorandum to the
officer who prepared the information request. It sets out some concerns, and
suggests some information that the applicants might be asked to supply.
[32] Council officers may exchange memoranda on any topic of interest to them.
However, in this case, the memorandum was sent to the applicants. In a fax dated
11 August 2004 (well after the expiry of the information request period) it said:
“Herewith attached outstanding issues for further information request from (the
hydrology assessment officer) dated 29.07.04”. (Emphasis added). There is no
power to make a further information request outside the period. The memorandum
should be ignored..
-- 9 of 12 --
10
[33] In the fax of 11 August 2004, Council’s officer responded to the provision of the
stormwater management strategy plan in this way: “The site specific stormwater
management is about water quality not how its going to work”. That cryptic remark
led to this statement, in the applicants’ further letter of 17 August:
“The site specific stormwater management plan addresses both water
quality and quantity items listed in the reconfiguration decision
notice. Would you please clarify what further information is
required. We are unable to address the ‘information request’ as
worded in your facsimile dated 11 August 2004.”
[34] The fax of 9 September 2004 says: “The further information request asked for
stormwater quantity management plan. Please provide same”.
[35] The applicants’ letter of 27 September discusses this topic:
“The site specific management plan has been revised and attached to
this letter. The revised report incorporates both stormwater quantity
and quality management plans. Additional stormwater quantity
information has been added to the report to address your information
requests. In particular, the following information has been added.
…”
[36] It will be appreciated that the evidence before the court on this occasion is
obviously incomplete, with respect to the contact between the parties and their
discussions and correspondence about the information request. The conclusion to
be drawn from the available information is that the applicants did provide
appropriate information about the stormwater management strategy plan. Then, as
the exchanges continued, they really became a negotiation about the appropriate
ways in which the applicants could satisfy the Council’s demands. See the letter of
17 August which asks for clarification about what further information is required. It
then appears, from Mr Caswell’s letter of 15 September 2004, that :
“Stormwater quality has been re-analysed by Cardno MBK who
sought Council’s view on further information they may require to
assess the revised stormwater quality management plan. … Cardno
-- 10 of 12 --
11
MBK’s revised design was submitted to Council on 1 September
2004. Mr Jacobs responded to the revised design … in his fax of 9
September 2004. A copy of that fax is attached to this letter.”
[37] It therefore appears, at least by 27 September, that any request for further
information, or clarification of the applicants’ responses, had been overtaken by
negotiations which resulted in a revised site specific management plan. Even if the
Council still regards this as a matter of continuing concern (assuming in favour of
Council that its email of 26 October 2004, Exhibit TNJ-07, refers to the plan), then
it is really part of an ongoing negotiation.
[38] The final information request relates to the acid sulphate soils. A response was
given in the applicants’ first letter, of 5 August 2004. There is nothing after that to
indicate that Council was entitled to any further information.
[39] Therefore, at least by 27 September 2004, the applicants had given all of the
required information to Council. The Council had 20 business days after the receipt
of the information in the ordinary course of mail. That would give the Council until
26 October to decide the matter. That was not done. Thereafter, there has been a
deemed refusal of the application.
Directions
[40] It is now appropriate to give directions for the hearing of the appeal. In the event
that Council is deemed to have refused the application, those directions are largely
agreed between the parties.
[41] There will be a declaration about the deemed refusal. Otherwise, the parties are
encouraged to agree to a draft order for directions. If there is any disagreement, (the
-- 11 of 12 --
12
identity of the mediator may be an issue) then the matter can be mentioned at a time
to be arranged.
-- 12 of 12 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2004/078