Burdekin Shire Council v Pioneer Sugar Mills Pty Ltd & The State Of Queensland [2004] QPEC 28 [2005] QPELR 13
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Burdekin Shire Council v Pioneer Sugar Mills Pty Ltd & The
State Of Queensland [2004] QPEC 028
PARTIES: BURDEKIN SHIRE COUNCIL
Applicant
v
PIONEER SUGAR MILLS PTY LTD
Respondent
And
THE STATE OF QUEENSLAND
Co-Respondent
FILE NO: 3418 of 2002
DIVISION: Planning and Environment Court
PROCEEDING: Application
ORIGINATING
COURT: The Planning and Environment Court of Brisbane
DELIVERED ON: 1 July 2004
DELIVERED AT: Brisbane
HEARING DATE: 4 June 2004
JUDGE: Alan Wilson SC DCJ
ORDER: That the co-respondent pay the respondent’s costs of and
incidental to this application between 20 May 2004 and 4
June 2004 assessed on the standard basis, including costs
of Counsel’s appearance for the respondent on 28 May, 2
June and 4 June 2004
CATCHWORDS: ENVIRONMENT AND PLANNING – COSTS – discretion
of court – relevant considerations
Integrated Planning Act 1997 ss 4.1.23(2)
Local Government (Planning and Environment) Act 1990, ss
7.6(1) and 1(A)
Mudie v Gainriver Pty Ltd (No 2) (2003) 2 Qd R 271,
considered
COUNSEL: Mr W Cochrane for the applicant
Mr J D Houston for the respondent
Ms Brian for the State of Queensland
-- 1 of 6 --
2
SOLICITORS: MacDonnells for the applicant
Carter Newell fro the respondent
Crown Law for the State of Queensland
[1] This is an application by the respondent, Pioneer Sugar Mills Pty Ltd (‘Pioneer’) for
an order that the co-respondent, the State of Queensland (for the Department of
Main Roads) (‘DMR’) pay certain costs associated with DMR’s recent application
to be joined as a co-respondent in this matter.
[2] The applicant, Burdekin Shire Council (‘Council’) commenced these proceedings
against Pioneer on 13 August 2002. They concern a cane railway siding adjoining
the Bruce Highway and, plainly (as DMR now acknowledges) some road traffic
safety issues. Indeed, DMR officers were involved in discussions about the siding
from as early as September 19991 . In 1999 Pioneer constructed the siding without
obtaining a development permit from Council, and the question whether that was a
necessary step is the issue between them.
[3] Notice of the application was given to DMR’s chief executive on 12 August 2002
(as required by the Integrated Planning Act 1997 (‘IPA’) s 4.1.21(6)) . It did not
initially elect to join the proceedings2 but instead, on 3 September 2002, sought and
obtained leave for the State of Queensland to be joined as party on its behalf. A
month later, however, and despite urgings to the contrary from Council’s solicitors 3
the Crown sought and obtained leave for the State to withdraw. (DMR appears to
have taken the view that its interest in the matter would only be enlivened when and
if this court decided the question whether a development permit was necessary,
whereupon DMR would become a ‘concurrence agency’ under IPA. More recently,
it realised the State’s interests would be directly affected 4 .)
[4] The matter then proceeded between Burdekin and Pioneer and directions were given
on 2 October 2002, and 2 April 2004. The last order placed the matter in the pool of
proceedings to be heard in the month of June 2004, and to be allocated hearing dates
at a callover on 28 May. In the interim in April 2003 Burdekin had asked DMR’s
District Director to provide an affidavit concerning safety issues alleged to arise
concerning the siding and although he agreed to do so, nothing more happened 5 .
[5] Council’s continuing imprecations to DMR eventually bore fruit, however, and on
20 May 2004 Crown Law wrote to the Council’s solicitors authorising them to tell
the Court at the callover that DMR was reconsidering its position. At the callover
Pioneer sought to have the matter listed for hearing but, upon Counsel for the
applicant informing the Court of DMR’s changed circumstances, it was adjourned
for mention on 1 June. Pioneer had urged the Crown to appear on 28 May, but it
did not do so. It did appear on 2 June and was given leave to file an application, by
the State of Queensland, seeking leave to be joined as a party. That application was
1 Affidavit Rose, Exhibits IR 1 & 2.
2 As it could have done, eg, under the Integrated Planning Act 1997, s 4.1.21(7).
3 Affidavit Duane, Exhibits MD 1&2.
4 Affidavit Rose, paragraphs 17, 19.
5 Affidavit Rose, filed 4 June 2004, para 12.
-- 2 of 6 --
3
heard on 4 June and succeeded, and Pioneer now seeks an order that the State of
Queensland pay its costs on a standard basis from 20 May to 4 June 2004, including
the costs of Counsel’s appearances on 28 May, 2 June and 4 June.
[6] I am satisfied that the State, representing DMR was always a proper party to the
proceeding; that it should not have withdrawn from the matter in October 2002; and,
that but for its late application this matter should, and could have been set down for
hearing in June 2004. It follows that, but for DMR’s conduct, appearances by
Counsel on all three occasions in late May and early June would not have been
necessary; nor that Pioneer would be put to expense preparing material resisting
DMR’s application. In light of the history of the matter I am also of the view it was
reasonable for Pioneer to contest that application.
[7] Issues concerning costs in this jurisdiction are to be determined under IPA s 4.1.23
which relevantly provides:
“Costs
4.1.23 (1) Each party to a proceeding in the court must bear the party’s
own costs for the proceeding.
(2) However the court may order costs for the proceeding
(including allowances to witnesses attending for giving
evidence at the proceeding) as it considers appropriate in the
following circumstances –
(a) the court considers the proceeding is instituted merely to
delay or obstruct;
(b) the court considers the proceeding (or part of the
proceeding) to have been frivolous or vexatious;
(c) a party has not been given reasonable notice of intention
to apply for adjournment of the proceeding;
(d) a party has incurred costs because the party is required to
apply for an adjournment because of the conduct of
another party;
(e) a party has incurred costs because another party has
defaulted in the court’s procedural requirements;
(f) without limiting paragraphs (d) a party has incurred costs
because another party has introduced (or sought to
introduce) new material;
(g) if the proceeding is an appeal against a decision on a
development application and the applicant did not, in
responding to an information request, give all the
information reasonably requested before the decision
was made;
(h) the court considers an assessment manager, a referral
agency or a local government should have taken an
active part in the proceeding and it did not do so;
(i) an applicant, submitter, referral agency, assessment
manager or local government does not properly
discharge its responsibilities in the proceedings.
[8] The costs sought by Pioneer only relate to part of the “proceeding”, ie the Crown’s
application. The word is not defined under IPA but, pursuant to the Planning and
-- 3 of 6 --
4
Environment Court Rules 1999 6 means “… an appeal and a proceeding started by
an originating application”. Neither term properly describes an application brought
within a proceeding and IPA otherwise contains no provisions specifically dealing
with these kinds of interlocutory applications (although the Court does have the
power to give directions about a particular case: s 4.1.11(3)). Under the Acts
Interpretation Act 1954, however, a “proceeding” means “… the legal action or
proceeding” and that is plainly wider.
[9] As Mr Houston of Counsel for Pioneer submitted it would be an odd result, and an
unattractive construction of IPA if a party obtaining leave to join a proceeding and
thereby being, for example, the effective cause of the adjournment of a hearing
could nevertheless avoid or limit the consequences of its actions because the costs
rules would only apply to its conduct after the formal order for joinder was made.
To her credit, Ms Brian of Counsel for DMR did not make that submission.
[10] There are other indicia that s 4.1.23 should not be construed in that way. Sub-
section 4.1.23(2)(b), refers specifically to a part of a proceeding and is plainly
intended to thwart an argument of that kind, at least in respect of proceedings which
are frivolous or vexatious; and the Court of Appeal in Mudie v Gainriver Pty Ltd
(No 2) (2003) 2 Qd R 271 rejected the notion that costs were an “all or nothing”
issue under the equivalent section in the preceding legislation, the Local
Government (Planning and Environment) Act 1990 s 7.6(1A).
[11] In Mudie McMurdo P and Atkinson J said, at 282:
‘Although the interpretation contended for by the respondents is arguably open on
a literal interpretation of the words in section 7.6(1A) (A) the interpretation which
achieves the purpose of the Act is to be preferred, especially where the literal
interpretation produces an odd result.’
Any construction of IPA s 4.1.23(2)(a)-(i) other than one under which an award of
costs for part, but not necessarily the whole, of a proceeding could be awarded
would be surprising, and as their Honours went on to say at 282-3 :
‘The legislature must have intended to give the courts a discretion to award costs
when any party conduct the proceedings in a way that is frivolous or vexatious; it
could not have intended that respondents who behave in such a way should be
immune from a costs order against them. To accede to the respondent’s contention
would mean that a wealthy and powerful respondent could vexatiously and
oppressively prolong proceedings causing the financial ruin of a worthy but less
wealthy and less powerful appellant or applicant … section 7.6(1A)(a) should (not)
be interpreted as limited to instances where the conduct of the entire appeal or
proceedings is vexatious or oppressive; it extends to awarding costs to reflect a
party’s conduct of proceedings which is in part frivolous or vexatious …’ (my
emphasis)
[12] The principle ought to be applied, when necessary, in respect of the various
subsections in s 4.1.23(2). All other constructions carry the risk that conduct which
offends one or more of the subsections might unmeritoriously escape sanction in
costs.
6 Promulgated under IPA, s4.1.10.
-- 4 of 6 --
5
[13] Section 4.1.23(1) expresses the primary principle in this jurisdiction that, generally,
each party will bear its own costs. Sub-section (2) then sets out a number of
circumstances when orders for costs against a party may yet be made. In this Court
the section and its predecessor have been applied in a way which shows the exercise
of deciding costs questions is different from that which arises in civil proceedings,
where costs are the subject of a much broader discretion7 .
[14] The Explanatory Guide within IPA does suggest sub-sections (2)(a) and (b) contain
a fairly wide discretion:
(a) … it allows the court to consider the motivations behind the proceedings
in determining whether costs should be awarded;
(b) … in contrast to the ground of obstruction or delay, this ground allows
the court to consider the merits of the substance of the proceeding itself
but the provisions have been construed (with their predecessors) in a fashion
confirming comments from the learned authors of Planning and Development
Queensland 8 at 4094 - namely, that an applicant for costs under either sub-section is
required to meet a “high standard” before the actions of a party will be deemed to
have offended them. There are many instances, as the cases cited in the text at pp
4092/1-4905 show.
[15] Pioneer sought to invoke sub-sections 4.1.23(2)(c), (f), (h) and (i). As to (c), DMR
brought its application to rejoin very late, but it did not apply for an adjournment of
the hearing in June 2004 (although that was the probable consequence of its
application) and the sub-section does not apply.
[16] As to sub-section (2)(f) the affidavits in support of DMR’s application make it clear
it seeks to introduce traffic evidence in relation to the impacts of Pioneer’s use of
the siding on the safety and efficiency of a nearby, major road9 . DMR joined, and
then withdrew from the proceedings. Had it remained an active party, the evidence
it now seeks to put before the Court could have been provided at a much earlier time
without disruption of the proceedings. DMR has, then, sought to introduce new
material and although it did not, technically, do so at a time when it was a party, it
now occupies that position and persists with that plan.
[17] It was contended for DMR that traffic issues have always been part of the contest
between the Council and Pioneer and the absence of material about it meant the
matter was not truly ready to be set down for hearing, but that is not apparent from
the evidence and, in any event, ignores the contents of an affidavit from Mr Rose,
DMR’s District Director, in which he says DMR has interests which may not
coincide with Council’s10 , and sets out matters which, plainly, will be the subject of
further evidence and, therefore, new material. It does not sit comfortably for DMR
to do nothing in the matter and then attempt to criticise the parties for an alleged
failure to obtain evidence which, as Mr Rose’s affidavits show, was always in its
7 Uniform Civil Procedure Rules, Chapter 17 and esp. r 689.
8 Fogg, Meurling and Hodgetts
9 Affidavit Rose, para 20.
10 Affidavit Rose, para 14.
-- 5 of 6 --
6
possession or power. I am satisfied sub-section 2(f) has been offended, in
circumstances which warrant an exercise of the discretion against DMR.
[18] As to sub-sections 2(h) and (i) DMR has relied upon its status as a concurrence
agency to justify its application to join as a party11 but in submissions from Counsel
contended, I think correctly, that it did not attain that status under IPA until the
primary question - whether a development permit is necessary - is decided in this
proceeding12 . The recital of facts set out earlier shows DMR has known of its
interest in the matter since September 1999 and has expressed firm views about it,
yet has joined and left, and then persistently declined to rejoin the action, until the
last minute. Nevertheless, a strict construction of the terms used in the sub-sections
must mean DMR’s present position in the matter does not place it in any of the
categories mentioned in them, and these provisions do not avail Pioneer.
[19] DMR’s conduct (whatever the cause of it) has been disappointing. It has, in the
past, acted in a way which delayed the proper conduct of the application itself and,
very late in that proceeding, exacerbated that default by the untimely realisation of
its mistaken withdrawal. Those circumstances warrant the exercise of the discretion
arising under sub-section (2)(f) and the granting of the order Pioneer seeks that the
co-respondent pay its costs assessed on the standard basis from 20 May to 4 June
2004 inclusive, specifically including Counsel’s costs of appearance on 28 May, 2
June and 4 June 2004.
11 Affidavit Rose, para 2.
12 IPA, Dictionary, Schedule 10, definitions of ‘referral agency’ and ‘concurrence agency’.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2004/028