Barooga Projects (Investments) Pty Ltd v Duncan [2003] QSC 442
State Reporting Bureau
^2003] <3* SC 44-3.
Queensland Government
Department of justice and Attorney-General
Transcript of Proceedings
Copyright in this transcript is vested in the Crown. Copies thereof must not be made or sold without the written authority
of the Director, State Reporting Bureau.
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
REVISED COPIES ISSUED
State Reporting Bureau
Date: 4 December, 2003
HELMAN J
No BS9541 of 2003
BAROOGA PROJECTS (INVESTMENTS) PTY Applicant
LTD (ACN 068 115 426) AS TRUSTEE
and
KEITH WILLIAM DUNCAN Respondent
BRISBANE
..DATE 26/11/2003
JUDGMENT
WARNING: The publication of information or details likely to lead to the identification of persons in some proceedings is a criminal
offence. This is so particularly in relation to the identification of children who are involved in criminal proceedings or proceedings for
their protection under the Child Protection Act 1999, and complainants in criminal sexual offences, but is not limited to those
categories. You may wish to seek legal advice before giving others access to the details of any person named in these proceedings.
1
4th Floor, The Law Courts, George Street, Brisbane, Q. 4000 Telephone: (07) 3247 4360 Fax: (07) 3247 5532
-- 1 of 8 --
1 HIS HONOUR: This is an amended application under s.70 of the
Property Law Act 1974 by the purchaser of 4.36 hectares of
land at 77 Swann Road, Bellmere, Queensland, under a contract
in writing dated 10 February 2003 for a declaration that the
vendor, the respondent to the application, is obliged to
complete the conveyance of the land on or before 5 December
2003 .
The contract includes, in annexure A, seven special
conditions, the first six of which concern a "development" of
the land by subdivision into residential allotments of various
sizes. Special condition 3 in annexure A, so far as it is
relevant, provides that the vendor acknowledges that the
development will be subject to the Caboolture Shire Council's
"issuing conditions" and that "those conditions must be
satisfactory in every respect" to the purchaser. Special
condition 6 in annexure A concerns completion of the contract:
"6. COMPLETION:
Settlement of this Contract will take place one
hundred and eighty (180) days of the date hereof or
within thirty (30) days of notification from the
buyer that it is in receipt of acceptable conditions
of approval, whichever is the later."
Clause 6 of the contract provides that time is of the essence
of the contract, except regarding any agreement between the
parties on the time of day for settlement.
It was not in dispute before me that since no time limit was
fixed in the .contract for satisfying the requirement of
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
10
30
50
2 JUDGMENT 60
-- 2 of 8 --
special condition 3 satisfaction within a reasonable time was
to be implied: Perri v. Coolangatta Investments Pty Ltd
(1982) 149 C.L.R. 537, at p.543 per Gibbs C.J., and at p.567
per Brennan J, with whom Stephen J agreed. It was not in
dispute either that I should decide this application on the
assumption that a reasonable time had expired by 26 September
2003 .
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
Prior to 26 September 2003 correspondence had passed between
the solicitors for the parties concerning special condition 3,
the details of which are not relevant to the issues before me.
On 26 September 2003 the vendor's solicitors sent a letter to
the purchaser's solicitors which, omitting formal parts, was
as follows:
"We refer to previous correspondence.
We note that the subject contract does not specify a date
by which the balance of the development conditions are to
be complied with.
We note further that Special Condition 6 provides:
COMPLETION
Settlement of this Contract will take place one
hundred and eighty (180) days of (sic) the date
hereof or within thirty (30) days of notification
from the buyer that it is in receipt of acceptable
conditions of approval, whichever is the later.
We note further that the period of one hundred and eighty
(180) days has elapsed some time ago and no notification
regarding the conditions of approval has been received by
our client.
In the absence of a specified date, the law implies a
reasonable time in which the buyer is to obtain
acceptable conditions of approval.
Our client considers that a reasonable time has now
elapsed.
1
10
20
30
40
50
3 JUDGMENT 60
-- 3 of 8 --
We now give you formal notice on behalf of the seller
that he requires the buyer to settle this contract within
twenty-one (21) days of the date hereof, that is, by 5.00
p.m. on Friday, 17 October 2003, failing which he
specifically reserves his rights as a consequence of the
buyer's failure to settle."
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
The demand for settlement on 17 October 2003 was repeated in a
further letter from the vendor's solicitors to the purchaser's
solicitors dated 16 October 2003 in which the former confirmed
that the vendor was ready, willing, and able to settle.
The settlement did not take place on 17 October 2003. On 24
October 2003 the purchaser's application was filed seeking a
declaration that it was not required to complete the purchase
of the land by 17 October 2003, the purchaser's contention
being - as set out in letters dated 8 October 2003, 17 October
2003, and 20 October 2003 from its solicitors to the vendor's
solicitors - that a reasonable time had not then elapsed for
the satisfaction of special condition 3 and that the shire
council had not issued satisfactory, or any, conditions.
On 5 November 2003 the purchaser's solicitors sent this letter
to the vendor's solicitors:
"We refer to previous correspondence in relation to this
matter and advise that our client has instructed us that
the Caboolture Shire Council has issued conditions for
the development and that those conditions are
satisfactory to the buyer.
The conditions were issued on our instructions on 4
November 2003 and the purpose of this letter is to
formally notify you of our client's satisfaction with the
conditions .
Our client has therefore indicated that it is now
prepared and ready to settle within the 30 day period and
1
10
30
50
4 JUDGMENT 60
-- 4 of 8 --
in fact is prepared to settle rather more quickly than
that if such is acceptable to your client.
Our client nominates settlement to take place on
Wednesday, 19 November 2003 at a mutually convenient time
to be fixed between us.
We would appreciate your urgent response confirming that
this is satisfactory to your client.
Once you confirm that your client is prepared and ready
to settle then our client will take steps to discontinue
the proceedings in the Supreme Court . We suggest that be
done at this stage on the basis that there be no order as
to costs.
We await your urgent response."
The vendor's response was in a letter from his solicitors
dated 10 November 2003:
"We refer to our letters of 26 September 2003 and 16
October 2003.
We note that your client failed to settle as required by
17 October 2003.
The contract is therefore terminated.
Our client otherwise reserves his rights generally. "
Special condition 3 was clearly enough a contingent and not a
promissory condition, included in the contract for the benefit
of the purchaser. It made the contract voidable. The
contract could have been avoided at the instance of either
party once a reasonable time for satisfying the requirement
had expired, but neither party need have done so; and, the
contract still being on foot, if one party having a right to
avoid it did not clearly exercise that right it was open to
the other party to enforce the contract against the former:
Suttor v. Gundowda Pty Ltd (1950) 81 C.L.R 418 at pp. 440-442.
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
1
10
20
30
40
50
5 JUDGMENT 60
-- 5 of 8 --
1 Further, once a party became entitled to elect for or against
rescinding the contract any act done by the party and
consistent only with the continuance of the contract on foot
would constitute an election against rescinding and an
election once made could not be retracted. A party in such a
case is not bound to elect at once. The party might keep the
question open so long as that party did nothing to affirm the
contract and so long as the other party's position was not
prejudiced in consequence of the delay: Tropical Traders Ltd
v. Goonan (1964) 111 C.L.R. 41, at p.55 per Kitto J.
The outcome of this application depends chiefly upon the
construction to be put upon the vendor's solicitors' letter of
26 September 2003. For the purchaser it was contended that it
was an irrevocable election to affirm the contract
notwithstanding the assumed expiration of the reasonable time
implied in special condition 3. On behalf of the vendor it
was submitted that the letter should not be construed as
electing to terminate the contract but rather as keeping the
question open while at the same time giving the purchaser the
opportunity to complete on 17 October 2003. It was not
necessary that the vendor give a notice calling on the
purchaser to complete: Perri v. Coolangatta Investments Pty
Ltd at p.546 per Gibbs CJ. Although it was not necessary to
give such a notice it would follow from the argument advanced
for the vendor that it was open to the vendor to do so and
that in doing so the vendor was not electing to keep the
contract on foot.
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
10
30
50
6 JUDGMENT 60
-- 6 of 8 --
1 In my view it simply is not possible to reach the conclusion
contended for on behalf of the vendor. He could not, in the
circumstances in which he was placed, on the one hand call for
completion of the contract and on the other refrain from
affirming it without a carefully-worded explicit reservation
of his right to rescind on the ground that the reasonable time
implied in the contract for the satisfaction of special
condition 3 had expired. The last paragraph of the vendor's
solicitors' letter does not do more, I think, than notify the
purchaser that failure to settle on 17 October would be
treated by the vendor as a repudiation of the contract by the
purchaser .
Three conclusions follow from that.
First, the contract was still on foot on 5 November 2003 when
the purchaser, through its solicitors, notified the vendor
that it was ready to settle on or before 5 December. In the
letter the purchaser indicated that the shire council had
issued conditions satisfactory to it. Before me, it was
conceded on behalf of the purchaser that although the
purchaser had been notified informally of the issuing of the
conditions the formal issuing had not taken place. In any
event the letter of 5 November may be construed as making it
clear either that the special condition 3 had been satisfied
or that the purchaser waived reliance on it.
Secondly, on 26 September the vendor made an election which
could not be retracted so that it was not open to him after
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
10
20
30
40
50
7 JUDGMENT 60
-- 7 of 8 --
that to treat the contract as at an end on the ground that
special condition 3 had not been satisfied.
Thirdly, the contract still being on foot on 5 November 2003
special condition 6 applied once - as happened - the purchaser
gave its notification of satisfaction or waiver. It was then
entitled to require settlement within thirty days.
The purchaser is entitled to the relief it seeks.
26112003 T1-3/SJ3 M/T 1/2003 (Helman J)
HIS HONOUR: The declaration will be that the respondent is
obliged to complete the conveyance, the subject of the
contract dated 10 February 2003, a copy of which is Exhibit
MHWA1 to the affidavit of Malcolm Henry William Allsopp filed
on 24 October 2003, on or before 5 December 2003.
HIS HONOUR: I order that the respondent pay to the applicant
its costs of and incidental to the application to be assessed.
1
10
£.y}
30
50
8 JUDGMENT 60
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2003/442