Abigroup Contractors Pty Ltd v Multiplex Constructions Pty Ltd & Ors [2003] QSC 173
SUPREME COURT OF QUEENSLAND
CITATION: Abigroup Contractors Pty Ltd v Multiplex Constructions Pty
Ltd & Ors [2003] QSC 173
PARTIES: ABIGROUP CONTRACTORS PTY LTD
ABN 40 000 201 516
(plaintiff / first respondent)
v
MULTIPLEX CONSTRUCTIONS PTY LTD
ABN 96 008 687 063
(first defendant / first applicant)
and
WATPAC AUSTRALIA PTY LTD
ABN 71 010 462 816
(second defendant / second applicant)
and
THE CROWN in the right of the STATE OF
QUEENSLAND through the DIRECTOR GENERAL,
DEPARTMENT OF PUBLIC WORKS
ABN 46 752 917
(third defendant / second respondent)
FILE NO/S: No S 3723 of 2003
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court
DELIVERED ON: 5 June 2003
DELIVERED AT: Brisbane
HEARING DATE: 28 May 2003
JUDGE: Philippides J
ORDER: Pursuant to s 21 of the Subcontractors’ Charges Act 1974
the first respondent’s notices of claim of charge dated 1
April 2003 and 2 May 2003 be cancelled
CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS –
Subcontractor’s charge – claim for uncertified amounts –
application pursuant to s 21 of the Subcontractors’ Charges
Act 1974 for cancellation or modification of first respondent’s
claims – whether claim for money payable or to become
-- 1 of 10 --
2
payable under the subcontract – whether claim for money, the
payment of which is governed by a provision of the
subcontract still to be complied with
Subcontractors’ Charges Act 1974 s 5(2), s 5(6), s 9, s
10(1A), s 21, s 23
Groutco (Australia) Pty Ltd v Thiess Contractors Pty Ltd
[1985] 1 Qd R 238
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd
(2002) 18 BCL 322
Riteway Constructions Pty Ltd v Baulderstone Hornibrook
Pty Ltd [1998] 2 Qd R 218
Re An Application by James Hardie Building Systems Pty Ltd
(1999) 15 BCL 199
COUNSEL: Mr H Fraser QC and Mr P Hastie for the applicants
Mr J Bond SC and Mr D Kelly for the first respondent
No Appearance by the second respondent
SOLICITORS: Minter Ellison for the applicants
Carter Newell for the first respondent
No Appearance by the second respondent
PHILIPPIDES J:
Background Facts
[1] In May 2001, the applicants, an unincorporated joint venture, entered into a
managing contract with the Department of Public Works for the redevelopment of
Lang Park. In April 2002, the applicants entered into a subcontract with the first
respondent, Abigroup, under which that part of the project known as the
Community Infrastructure West Works was subcontracted to the first respondent.
[2] The first respondent claims two charges pursuant to Subcontractors’ Charges Act
1974 (“the Act”) over monies payable to the applicants by the Department of Public
Works. These concern a notice of charge delivered on 1 April 2003 for the sum of
$1,559,158.70 and a further notice of charge delivered on 2 May 2003 for the sum
of $1,735,548.10.
[3] The applicants bring this application for cancellation or modification of the charges
and for consequential orders pursuant to s 21 of the Act. The applicant’s primary
submission is that the notices claim monies that have not been certified as payable
to the first respondent by the joint venture, and that accordingly the claims are not
for monies payable to the subcontractor under the subcontract within the meaning of
the Act.
[4] Clause 42 of the General Conditions (AS2545-1993) provides for a system of
claims, certificates and payments. On the 25th day of each month the subcontractor
is required to deliver to the “main contractor’s representative” 1 the claim for
payment. Such claims for payment are to include the value of work carried out by
1 By cl 2 of the Special Conditions, this term means the “Managing Contractor’s Representative”.
-- 2 of 10 --
3
the subcontractor in the performance of the contract together with all amounts then
due to the subcontractor arising out of or in connection with the subcontract or for
any alleged breach thereof. Within 21 days after the claim, the representative is
required to issue to the main contractor and the subcontractor a payment certificate
stating the payment which is to be made (relevantly) by the main contractor to the
subcontractor. The quantum of a payment certificate is the payment which, in the
opinion of the main contractor’s representative, is to be made. Within 35 days after
receipt by the representative of a claim for payment or within 14 days of the issue of
a payment certificate (whichever is the earlier), the main contractor is to pay to the
subcontractor the amount shown on the certificate (or if no payment certificate has
been issued, the amount of the subcontractor’s claim).
[5] All of the unpaid claims, the subject of the notice of charge, are for uncertified
sums, being the difference between the amounts in the progress claims and the
amounts certified. For present purposes the claims fall into three categories:
(a) Claims by the first respondent for work where the representative has
certified his opinion that a lesser percentage of work has been
completed compared to the percentage claimed by the first
respondent;
(b) Claims by the first respondent for amounts in relation to variations
which the representative has not yet assessed, but has paid some of
the claimed amount on account;
(c) Claims for variations which the representative has rejected.
Is the Absence of a Certificate Fatal ?
[6] On behalf of the applicants is was submitted that as the amounts claimed have not
been certified, they are not amounts “payable under the subcontract” and
accordingly a charge cannot be sustained. In making this submission, the applicants
relied upon Groutco (Australia) Pty Ltd v Thiess Contractors Pty Ltd (“Groutco”)
[1985] 1 Qd R 238. In that case Campbell J (with whom McPherson and Sheahan
JJ agreed) said (at 243 – 248):
“It can be seen that subsec. (2) of s. 5 sets up two separate criteria,
each of which must be satisfied before a charge can be supported.
These are that the charge shall secure (a) payment in accordance with
the subcontract, and (b) payment of all money that is payable or is to
become payable to the subcontractor for work done by him under the
subcontract.
…
The expression “contract price” is defined (s. 3(1)) to include “the
money payable for the performance of work under a contract or
subcontract, express or implied, whether or not the price is fixed by
express agreement”.
…
Although ss. 5, 10, 11 and 12 do not refer to “contract price” the
definition in the Act of “contract price” supports the construction that
s. 5(2), when it refers to moneys payable “in accordance with the
subcontract”, is limited to the money payable in accordance with the
payment terms of that subcontract relating to the work to be
performed under it. The reference to “the debt secured by a charge”
-- 3 of 10 --
4
in s. 9 and to “the right of a person to whom a debt is due and owing
for work done” in s. 23 also support this view. I do not consider that
the word “debt” in these sections can be construed so as to include
unliquidated damages for breach of contract: …”
[7] McPherson J delivered additional reasons, stating (at 252):
“When in ss. 9 and 23 that Act uses the expression “debt” it does so
in the prevailing sense of that term, as meaning a liquidated sum of
money presently due, owing and payable by one person to another
and one which, as s. 5(2) adds, is so payable “in accordance with”
the subcontract. That excludes a claim for unliquidated damages for
breach of contract, together, it may be thought, with a claim for
liquidated damages recoverable only upon proof by the claimant of a
breach of contract by the contractor. What the claimant is seeking
here falls outside those limits.”
[8] The first respondent argues that the absence of a certificate covering the claims is
not fatal and puts forward three contentions:
1. The first respondent argued that it is a sufficient answer to the application to
demonstrate that payment of the amounts claimed are governed by a
provision of the subcontract still to be complied with within the terms of s
5(6) of the Act, so that the monies can be said to be monies that are “to
become payable” under the subcontract. In this case, it is said that the
parties have not yet complied with contractual provisions which establish a
procedure for the resolution of disputes in relation to the rejection of the first
respondent’s claims.
2. In addition, the first respondent argued that the reason why it did not have a
relevant payment certificate was that the certifier has rejected the first
respondent’s claims about the proper value of the work (including varied
work). It was said that the failure to obtain a certificate, in respect of the
claims the subject of the charges, occurred in circumstances amounting to a
breach of contract by the applicants, such that the first respondent had an
arguable case that it was absolved from the necessity of obtaining it.
3. Thirdly, the first respondent contended that the construction of the statute
which underlies the applicants’ argument was erroneous. It was argued that,
on the proper construction of ss 5(2), 5(6) and 10(1A) of the Act, it was not
essential that the first respondent be able to establish that there was a debt
accrued due to it (even if not yet payable) as at the date on which it seeks to
claim a charge.
Section 5(6) of the Act
[9] Section 5(2) of the Act provides that the charge “secures payment in accordance
with the subcontract of all money that is payable or is to become payable to the
subcontractor for work done by the subcontractor under the subcontract”. Section
10(1A) of the Act provides that the claim of charge must be in respect of money
payable at the date of the notice of the charge and “money to become payable to the
-- 4 of 10 --
5
subcontractor after the date of the notice for work done by the subcontractor prior to
that date.”
[10] Section 5(6) of the Act throws light on the ambit of the words “money that is
payable or is to become payable to the subcontractor for work done by the
subcontractor under the subcontract”. It provides :
“Money that is or is to become payable to a subcontractor for work
done by the subcontractor under a subcontract, and the payment of
which is secured under subsection (2) –
(a) includes money the payment of which is governed by a provision of
the subcontract still to be complied with, including for example the
following –
(i) a provision establishing a procedure for the certificate of the
amount, quality or value of work that had been performed;
(ii) a provision establishing a procedure for the resolution of a
dispute about the amount, quality or value of work that has
been performed; and
(b) does not include the following –
(i) damages for beach of contract or in tort;
(ii) an amount payable on the basis of extra-contractual remedy,
including, for example, as reasonable compensation for
work done;
(iii) damages or other relief under another Act or an Act of
another State or the Commonwealth, including damages or
other relief under the Trade Practices Act 1974 (Cwlth).”
[11] The first respondent argued that the claims were for monies to become payable to it
for work done under the subcontract, given that the claims fell within s 5 (6)(a) of
the Act and did not fall within any of the categories excluded by s 5(6)(b) of the
Act. The first respondent submitted that the claims were for “money, the payment
of which is governed by a provision of the subcontract still to be complied with” for
the purposes of s 5(6)(a)(ii) of the Act, that is, “a provision establishing a procedure
for the resolution of a dispute about the amount, quality or value of work that has
been performed”. The provision of the subcontract relied upon for the purposes of s
5(6)(a)(ii) is cl 47 of the special conditions of the subcontract, which provides for a
system of dispute resolution, in combination with cl 42.1 of the general conditions.
[12] Clause 42.1 of the general conditions provides, inter alia:
“… A payment made pursuant to this Clause shall not prejudice the
right of either party to dispute under Clause 47 whether the amount
so paid is the amount properly due and payable and on determination
(whether under Clause 47 or as otherwise agreed) of the amount so
properly due and payable, the Main Contractor or Subcontractor, as
the case may be, shall be liable to pay the difference between the
amount of such payment and the amount so properly due and payable
…”.
[13] Clause 47 of the general conditions was amended by the special conditions, by the
deletion of cl 47 of the general conditions and the insertion of a new cl 47. Clause
47.1 of the special conditions provides as follows:
-- 5 of 10 --
6
“Notice of Claim Other Than Progress Claims & Final Payment
Claim
This clause 47 applies in respect of each of the following:
(a) Any dispute that the Subcontractor has with the determination of a
claim made by the Subcontractor under clause 46.
(b) Any claim in tort, equity or under any statute in relation to, or arising
out of the Subcontract or the Subcontract Works against the
Managing Contractor.
If this clause 47 applies, the Subcontractor shall notify the Managing
Contractor’s Representative in writing of the dispute or claim. The notice
shall specify adequate details of the Subcontractor’s dispute or claim,
including the legal basis for the dispute or claim and the amount claimed. If
the amount is not ascertainable at that time, the notice must state the
Subcontractor’s best estimate of the likely amount of its claim.
The notice required by this clause shall be given within thirty (30) days
following the day on which any of the following happens:
(a) The Subcontractor receives written notice of the determination
under clause 46.
(b) In the case of a claim said to arise in tort, the date on which the
breach of duty occurred.
(c) In the case of a claim said to arise under statute or in equity, the day
on which the last event happened that gives rise to the cause of
action constituting the claim.”
[14] The first respondent contended that the effect of cl 42.1 of the general conditions is
that either party had a right to dispute under cl 47, whether the amount certified and
paid was the amount properly due and payable. It was submitted that on
determination of the amount properly due and payable, there would arise an
obligation to pay the difference between the amount paid and the amount which was
properly due and payable. The charges, as I have mentioned, are claimed for
uncertified components of payments claims where the certifier has disagreed with
the first respondent’s assessment of the extent of the completion of the subcontract
work and the first respondent’s assessment of either the fact, value or extent of the
completion of variation work. The first respondent referred to the affidavit evidence
of the its project manager, Mr Tracey, that for each charge, the information in the
claim of charge was correct and that of Mr Gore, a registered engineer, who had
certified that that he had examined the claim and had certified that it was prima
facie proper to proceed.
[15] On behalf of the applicants, it was submitted that s 5(6)(a)(ii) of the Act does not
apply, because there is no procedure for the resolution of the present disputes about
the claims. It was said that the dispute resolution system provided for in cl 47 was
confined to the matters specified therein. The applicants argued that cl 47 had no
application to the present claims, given that the claims were not claims “in tort,
equity or under any statute”, nor were they made under clause 46 of the subcontract.
Clause 47, it was argued, did not apply to a dispute concerning a claim for payment
of an amount claimed to form part of the contract sum, nor any payment for what
was claimed to be a variation directed by the main contractor’s representative or to
-- 6 of 10 --
7
be made pursuant to cl 12.3. Consequently, it was argued that s 5(6)(a)(ii) had no
application.
[16] Even if the first respondent’s interpretation of cl 42.1 were to be accepted so that it
conferred a right to dispute resolution such as to extend to the present
circumstances, a difficulty arises concerning the ambit of cl 47. I accept the
applicants’ submissions that cl 47 is of confined ambit. I find that clause 47 does
not extend to the circumstances of the present claims. This is reinforced by the fact
that the time frame for the giving of notices for the purpose of cl 47.1 refers back to
the matters specified in cl 47.1 (a) and (b) and is clearly not apposite to impose time
periods in respect of other matters. Thus, even if cl 42.1 confers the right contended
for by the first respondent, it would give rise to an inconsistency with cl 47. The
subcontract provides 2 that any inconsistency between the terms and provisions of
the general conditions and the special conditions is to be resolved in favour of the
special conditions. This has the consequence that cl 47, being a special condition,
prevails over cl 42.1, being a general condition.
[17] Accordingly, I find that there is no provision in the subcontract establishing a
procedure for the resolution of a dispute concerning the claims in issue. Section
5(6)(a)(ii) has no application.
Is the absence of the certificate irrelevant because it can be said that its absence is the
result of the applicants’ breach of contract?
[18] Relying on cl 23 of the subcontract and authorities such as Peninsula Balmain Pty
Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322, the first respondent argued
that the Managing Contractor’s Representative, Mr Ghannoum, was required to
exercise his discretion independently from the managing contractor, that is, the
applicants. The first respondent argued that it was apparent from the affidavit of
Mr Taylor that Mr Ghannoum had abdicated any independent role and was not
exercising an independent discretion. The applicants, however, argued that Mr
Taylor’s affidavit should not be construed in the manner argued by the first
respondent. I accept those submissions. Mr Taylor’s affidavit merely deposes to
the process by which the payment certificates were provided to Mr Ghannoum. I do
not accept that any arguable case of there being a breach of contract is disclosed
concerning the issuing of the certificates.
[19] The first respondent also submitted that cl 23 of the subcontract requires the
Managing Contractor’s Representative to “arrive at a reasonable measure of value
of works”. It was contended that there was an arguable case a reasonable figure
was not arrived at by Mr Ghannoum and that that failure constituted a breach of
contract. It was said that if at trial it was determined that the first respondent’s
assessment of value was in fact reasonable, it would also follow that the applicants’
assessment was not reasonable in breach of cl 23. In making this submission, the
first respondent sought to rely on a line of authority said to establish the proposition
that if one contracting party prevents the fulfilment by another party of a condition
precedent, it cannot rely on the non completion of condition precedent. 3
2 See cl 3 of the Formal Instrument of Agreement which provides for an order of precedence.
3 See Peter Turnbull & Co Pty Ltd v Mundus Trading Company (Australia) Pty Ltd (1954) 90 CLR
235 at 246-7. Se also Qline Interiors Pty Ltd v Jezer Construction Group Pty Ltd [2002] QSC 088 at
[60] to [70] and Barclay Mowlem Constructions Pty Ltd v Ishikawajima-Harima Heavy Ind Co Ltd
[2003] QSC 010 at [19] to [20].
-- 7 of 10 --
8
[20] The difficulty with this argument is that even if the first respondent were able to
point to an arguable breach of cl 23, that merely gives rise to a claim for damages
and not a claim to which the Act applies. Accordingly, the submission fails.
Is a certificate required in any event?
[21] The first respondent contended that the construction of the statute which underlies
the applicants’ argument is erroneous and argued that on the proper construction of
ss 5(2), 5(6) and 10(1A) of the Act it was not essential that the first respondent be
able to establish that there was a debt accrued due to it (even if not yet payable) as
at the date on which it seeks to claim a charge. The first respondent submitted that
amendments to the Act, in the form of s 5(6) of the Act, are such as to permit a
construction of s 5(2) which leads to the conclusion that a notice may be given
under the Act, despite the absence of certification.
[22] It was submitted that s 5(6) of the Act was the legislative response to a line of
authorities, such as Riteway Constructions Pty Ltd v Baulderstone Hornibrook Pty
Ltd [1998] 2 Qd R 218 (Riteway) and Re An Application by James Hardie Building
Systems Pty Ltd (1999) 15 BCL 199, 4 which seemed to suggest that in subcontracts,
where the determination of the amount payable depended on the determination of a
certifier, the subcontractor could have no entitlement to a charge in the absence of a
relevant determination, because it could not establish the existence of the money
which was payable or to become payable to it. Whether or not those cases are
properly regarded as authority for any such proposition, 5 it was submitted that, since
the introduction of s 5(6) of the Act, such an interpretation of s 5(2) of the Act is no
longer open.
[23] The first respondent submitted that s 5(6) of the Act not only overrode decisions
such as Riteway, but also indicated that the construction of s 5(2) on which the
decisions proceeded is no longer correct. That construction is said to be erroneous
because it is based on an interpretation of the statutory words “payable or … to
become payable” as if they required the existence of at least a present debt, albeit
one not payable until some time in the future, imposing an unnecessary requirement
for which there was no statutory warrant.
[24] The first respondent does not cavil with the reasoning that the statutory words
“payable or … to become payable” require a person claiming a charge to
demonstrate objectively and by reference to the contract that the sum claimed at
least arguably would become payable under the contract. The first respondent’s
argument was with the proposition that where the amount payable depends upon the
assessment of any factor within the judgment of an intermediary, no sum could ever
be identified as an amount “to become payable”, until that determination is made.
The first respondent further argued that the fact that the language of existing or
accrued debt was not used in s 5 of the Act was an indication that Parliament did not
intend that charges would only exist where a subcontractor could prove such debt.
(Equally, it was said that the use of the language of debt in s 9 and s 23 of the Act
4 See also Henry Walker Etlin Contracting Pty Ltd v Mostia Construction (2003)19 BCL 147.
5 In this regard, the respondent relied upon statements of Williams J in Concept Constructions (Qld)
Pty Ltd v Ashphalt Pavements Pty Ltd [2000] QSC 269 at para 9 that the cases do not lay “down any
principle other than that the subcontractor must establish that there is money payable or to become
payable with respect to work done prior to the date of the charge before the charge can be legally
effective …”.
-- 8 of 10 --
9
did not indicate that Parliament meant that s 5(2) should be interpreted as referring
only to existing debt). The introduction of s 5(6) of the Act was said to be
confirmation of the validity of this general approach to legislative intention.
[25] The first respondent submitted that the ordinary and natural meaning of the
reference to money that is “… payable or is to become payable to the subcontractor
for work done by the subcontractor under the subcontract” simply required the
subcontractor ultimately to prove that the amount claimed would become
contractually payable. It was thus argued that the absence of a certificate (in a
contract which provides that mechanism) did not inevitably mean that the monies
were not monies “to become payable”. By illustration, the first respondent argued
that, firstly, evidence might be adduced to demonstrate that a certificate would issue
in at least the amount claimed. Secondly, it was said that evidence might be
adduced to demonstrate that there was a contractual mechanism by which the
absence of a certificate (or existence of a certificate with which the subcontractor is
dissatisfied) might be overcome and that mechanism would operate so that the
amounts claimed would eventually become payable under the subcontract. Thirdly,
the first respondent extended the line of reasoning to argue that, in addition, there
was a further category (into which the present case is said to fall) where evidence
might be adduced suggesting an arguable case that a court would adjudicate that the
amounts claimed were payable under the contract. The first respondent contended
that in the present case, it had shown an arguable case that the monies claimed
would become payable pursuant to the subcontract consequent upon the decision of
a c0ourt.
[26] While the first and second propositions are undoubtedly correct, I do not consider
that the introduction of s 5(6) of the Act has the wide reaching consequences
contended for by the first respondent in the third example offered by the first
respondent.
[27] The statutory extension of the words “… money that is or is to become payable to
the subcontractor for work done by the subcontractor under the subcontract” by s
5(6) of the Act is of deliberately limited ambit. The extension is to money the
payment of which is governed by a provision of the subcontract yet to be complied
with. Inclusive examples are given. I reject the view that in enacting s 5(6) of the
Act the legislature evinced an intention not only to reverse decisions such as
Riteway, but also to permit an interpretation of s 5(2) which would have the wide
compass contended for by the first respondent. The amendment to s 5 introduced
by s 5(6) is not of such a nature as to render the construction of s 5(2) of the Act by
the Court in Groutco no longer correct. Indeed, s 5(6)(b) reinforces the dicta in
Groutco.
[28] The subcontract, requiring certification of progress claims as a precondition for
payment, and that certification procedure having been completed, but not covering
the amounts claimed, in circumstances where there is no contractual provision for
dispute resolution upon a dispute arising as to the quantum of the certification, the
first respondent is unable to establish an arguable case that the amounts claimed are
for monies payable or to become payable under the subcontract.
[29] I find that the charges are not permitted under the Act and should be cancelled. It
follows that it is not necessary to consider the question of modification of the
charges.
-- 9 of 10 --
10
Orders
[30] Pursuant to s 21 of the Act, I order that the first respondent’s notices of claim of
charge dated 1 April 2003 and 2 May 2003 be cancelled.
[31] I shall hear submissions as to costs.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2003/173