Baulderstone Hornibrook Pty Ltd v Broen Australia Pty Ltd [2003] QSC 158 [2003] 2 Qd R 577
SUPREME COURT OF QUEENSLAND
CITATION: Re University of Queensland; Baulderstone Hornibrook Pty
Ltd v Broen Australia Pty Ltd [2003] QSC 158
PARTIES: BAULDERSTONE HORNIBROOK PTY LTD ACN 002
625 130
(applicant)
v
BROEN AUSTRALIA PTY LTD ACN 090 384 259
(respondent)
FILE NO/S: S1553 of 2003
DIVISION: Trial Division
PROCEEDING: Applications
DELIVERED ON: 29 May 2003
DELIVERED AT: Brisbane
HEARING DATE: 6 March 2003
JUDGE: Mullins J
ORDER: 1. The claim of Broen Australia Pty Ltd made in the
notice of claim of charge dated 18 December 2002 given to
the University of Queensland in the sum of $64,497.35 be
cancelled pursuant to s 21 of the Subcontractor’s Charges
Act 1974.
2. The amount of $64,497.35 paid into court by the
University of Queensland be paid to Baulderstone
Hornibrook Pty Ltd.
3. The application filed on 26 February 2003 be dismissed.
CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS –
SUBCONTRACTOR’S CHARGE- Subcontractors’ Charges
Act 1974 (Q) – where subcontractor gave a notice of claim of
charge to superior contractor and a subsequent notice of claim
of charge to the employer based on the same claim for works
undertaken by the subcontractor– where superior contractor
sought a declaration that the second notice was invalid on the
basis that the Act prevents a subcontractor from lodging more
than one notice of charge in respect of the same claim – the
Act permits a subcontractor to lodge two notices of claim of
charge based on the one claim where each of the notices is
given to a different contractor or employer – superior
contractor not entitled to a declaration that the second notice
of charge is invalid
BUILDING AND ENGINEERING CONTRACTS –
-- 1 of 10 --
2
SUBCONTRACTOR’S CHARGE – Subcontractors’ Charges
Act 1974 (Q) – where subcontractor gave a notice of claim of
charge based on a claim for work already paid for by the
superior contractor to the contractor which had engaged the
subcontractor – where superior contractor prejudicially
affected by the notice of claim of charge pursuant to s 21 (3)
of the Act - subcontractor’s claim cancelled
Subcontractors’ Charges Act 1974
Subcontractors’ Charges Amendment Act 2002
Hamilton Australia Pty Ltd v Milson Projects Pty Ltd [1997]
2 QdR 355
Hewitt Nominees Pty Ltd v The Commissioner for Railways
[1978] QdR 256
Hewitt Nominees Pty Ltd v The Commissioner for Railways
[1979] QdR 256
Re Radair Pty Ltd [1998] 2 QdR 539
Ronnor Pty Ltd v D&R Fabrications Pty Ltd [1983] 2 Qd R
455
COUNSEL: PJ Dunning for the applicant
BD O’Donnell QC for the respondent
SOLICITORS: Clayton Utz for the applicant
Dibbs Barker Gosling for the respondent
[1] MULLINS J: As a result of the University of Queensland (“the University”)
paying the amount of $64,497.35 into court, each of Baulderstone Hornibrook Pty
Ltd (“Baulderstone”) and Broen Australia Pty Ltd (“Broen”) has brought an
application seeking that the amount of $64,497.35 be paid to it.
[2] Baulderstone’s application was filed on 21 February 2003 and seeks an order
pursuant to s 21 of the Subcontractors’ Charges Act 1974 (“the Act”) cancelling the
charge claimed by Broen on moneys payable by the University of Queensland (“the
University”) to Baulderstone or, alternatively, a declaration that the notices given by
Broen to the University and to the applicant purportedly pursuant to the Act do not
create a charge within the meaning of the Act. By application filed on 26 February
2003, Broen seeks a declaration that the work done by Broen, as specified in its
notices of charge dated 28 November 2002 and 18 December 2002, was work as
defined in s 3AA(3)(a) of the Act. On 4 March 2003 Broen served a notice of
withdrawal of claim in respect of its notice of charge dated 28 November 2002 on
Baulderstone and Hamilton. Broen’s claim for relief is therefore based on its notice
of charge dated 18 December 2002.
Facts
[3] The University owns the molecular bioscience centre at its St Lucia campus. The
University entered into a contract with Baulderstone to construct the laboratories,
office and car park facilities at the molecular bioscience building. Baulderstone
engaged Hamilton Australia Pty Ltd (“Hamilton”) to manufacture, supply and
install fume cupboards at the site. Hamilton engaged Broen as sub-subcontractor to
-- 2 of 10 --
3
manufacture and fabricate the specific tapware components for the fume cupboards
at the site. That work was completed by Broen by 22 October 2002. The tapware
components were then installed.
[4] Mr Matthew Joiner and Mr Gerald Collins of Jefferson Stevenson & Co were
appointed joint administrators of Hamilton on 1 November 2002.
[5] The total amount claimed by Broen under the sub-subcontract was $161,412.35 of
which $96,915 was paid by Hamilton, leaving a balance of $64,497.35 which Broen
claimed was owing at the date of the appointment of the administrators to Hamilton.
[6] On or about 28 November 2002 Broen gave notice of claim of charge in form 1 to
Baulderstone in respect of the balance claimed of $64,497.35 and a notice to
contractor of claim of charge being given in form 2 to Hamilton.
[7] Broen’s solicitors made a request to Baulderstone on 4 December 2002 pursuant to
s 9A of the Act for information relating to the head contract. On 6 December 2002
Baulderstone informed Broen’s solicitors that at that stage there were no retention
moneys held and no moneys owing to Hamilton by Baulderstone in respect of the
subcontract and that as Hamilton had defaulted under its contract, Baulderstone had
engaged others to complete Hamilton’s works. Baulderstone also advised that it
had paid Hamilton for the items supplied by Broen. That has been sworn to by
Baulderstone’s project manager, Mr W E Styles, in his affidavit filed on 25
February 2003 and was not put in issue by Broen. By letter dated 9 December 2002
Baulderstone informed Broen’s solicitors of the information requested in respect of
the head contract.
[8] On 16 December 2002 Baulderstone received a facsimile from the solicitors for the
administrators of Hamilton enclosing a contractor’s notice in form 4 in which
Hamilton disputed Broen’s claim.
[9] On 18 December 2002 Broen gave a notice of claim of charge in form 1 which it
describes as the “leapfrogging charge” to the University in respect of the same
amount of $64,497.35 for the same works that were undertaken for Hamilton. That
notice sought to charge moneys that were or would be payable by the University to
Baulderstone. On or about the same day Broen gave notice to contractor of claim of
charge being given in form 2 to Baulderstone in respect of the leapfrogging charge.
[10] On 23 December 2002 Broen issued proceeding D5007 of 2002 in the District Court
of Brisbane to enforce the notices of charge.
[11] Hamilton was served with each of the applications, but did not appear on the
hearing of the applications.
Issues
[12] The applications raised two issues:
(a) whether Broen was entitled to issue the notice of charge dated 18
December 2002 to the University, after having issued the notice of
charge dated 28 November 2002 to Baulderstone; and
-- 3 of 10 --
4
(b) if the second notice of charge is valid, whether the court should
exercise the discretion pursuant to s 21 of the Act to cancel that
charge.
Relevant legislation
[13] The entitlement to the charge is conferred by s 5 of the Act. Subsections (1) to (3)
of s 5 provide:
“(1) If an employer contracts with a contractor for the performance
of work upon or in respect of land or a building, or other structure or
permanent improvement upon land or a chattel, every subcontractor
of the contractor is entitled to—
(a) a charge on the money payable to the contractor or a
superior contractor under the contractor’s, or superior
contractor’s, contract or subcontract; and
(b) subject to subsection (4), a charge on any security for the
contractor’s, or superior contractor’s, contract or
subcontract.
(2) The charge of a subcontractor secures payment in accordance
with the subcontract of all money that is payable or is to become
payable to the subcontractor for work done by the subcontractor
under the subcontract.
(3) The total amount recoverable under the charges of
subcontractors does not exceed the amount payable to the contractor
or subcontractor under the contract or subcontract, as the case may
be.”
[14] The means for causing the charge to attach are set out in s 10 of the Act. Section
10(1) of the Act provides:
“(1) A subcontractor who intends to claim a charge on money
payable under the contract to the subcontractor’s contractor or to a
superior contractor—
(a) must give notice to the employer or superior contractor by
whom the money is payable, specifying the amount and
particulars of the claim certified as prescribed by a qualified
person and stating that the subcontractor requires the
employer or superior contractor, as the case may be, to take
the necessary steps to see that it is paid or secured to the
subcontractor; and
(aa) if a person other than the employer or superior contractor
holds a security for the contract—must give notice in the
approved form of having made the claim to the person
holding the security; and
(b) must give notice of having made the claim to the contractor
to whom the money is payable.”
[15] The submissions of the parties raised the construction of ss 10(7) and (8) which
were inserted by the Subcontractors’ Charges Amendment Act 2002 (“the 2002
Act”). Subsections (7) and (8) of s 10 of the Act provide:
-- 4 of 10 --
5
“(7) To remove any doubt, it is declared that a subcontractor may
make 2 or more claims in relation to money payable or to become
payable to the subcontractor for work done by the subcontractor
under a subcontract.
(8) However—
(a) each claim must be about a separate and distinguishable item
of the work done by the subcontractor under the subcontract;
and
(b) there must not be more than 1 claim about any 1 item.”
[16] Section 21 of the Act provides:
“21 Application to court by person prejudicially affected
(1) A person who alleges that the person is prejudicially affected by
a claim of charge under this Act may at any time make application to
the court for an order—
(a) that the claim be cancelled; or
(b) that the effect of the claim be modified.
(2) The court must hear and determine summarily an application
made pursuant to this section and may make such order as it thinks
fit.
(3) Without limiting the circumstances in which a person may be
prejudicially affected for subsection (1), a person (the “affected
person”) is taken to be prejudicially affected by the claim of charge
of a subcontractor (the “claiming subcontractor”) if—
(a) because of the claim of charge—
(i) the payment of any amount to which the affected
person is entitled is delayed or otherwise affected;
or
(ii) the release of a security for a contract or
subcontract given by or for the affected person
is delayed or otherwise affected; and
(b) the affected person is a superior contractor in relation to
the claiming subcontractor; and
(c) the affected person has already paid, to a person who is a
contractor or superior contractor in relation to the
claiming subcontractor, an amount for work the subject
of the claim of charge.”
Entitlement to lodge a “leapfrogging charge”
[17] The issue of whether a subcontractor was entitled to lodge a charge under the Act in
respect of moneys payable to a contractor higher up the chain with whom that
-- 5 of 10 --
6
subcontractor had no contractural relationship arose in Hewitt Nominees Pty Ltd v
The Commissioner for Railways [1978] QdR 256 (“Hewitt Nominees No 1”). It was
held by Dunn J at 267 that the Act gives to a subcontractor an entitlement to one
charge only and the charge attaches to money due under one contract only. That
decision was the subject of an appeal which was allowed in Hewitt Nominees Pty
Ltd v The Commissioner for Railways [1979] QdR 256 (“Hewitt Nominees No 2”).
Although the wording of the Act now differs slightly from the wording of the
relevant provisions as they stood at the time of the decisions in Hewitt Nominees No
1 and Hewitt Nominees No 2, the substance of the provisions considered in those
cases remains the same.
[18] W B Campbell J (as he then was) (with whom the other members of the court
agreed) stated in Hewitt Nominees No 2 at 262 – 263:
“ The expression “superior contractor” is not defined although it
appears many times in the Act. His Honour took the view, as I have
mentioned, that “superior contractor” means a person with whom a
claimant subcontractor has a contract. But it seems to me that a
“superior contractor” must mean one who is further up the line than
the subcontractor with whom a claimant subcontractor lower down
the lines has a contract. As I have said, the “contractor”, where that
word is lastly used in s 5(1), as regards a subcontractor lower down
the line than the subcontractor who contracts directly with the head
contractor, should be read as the person with whom the claimant
subcontractor has a contract. If one reads s 5(1) with full regard to
the definition of “employer” “in relation to a subcontractor” together
with the definition of “contractor as regards a subcontractor” and the
definition of “subcontractor,” it does not seem to me to affect the
clear meaning of the words “superior contractor” in the subsection.
The phrase “as the case may be” does not appear in subsec (1)
although it is present in subsec (3) where it applies to limit the total
amount recoverable under charges to the amount payable to the
contractor or to the subcontractor, “as the case may be.” In my
opinion, s 5(1) grants to a subcontractor an entitlement to a charge on
money payable to the person with whom he contracts and a charge
on money payable to a superior contractor. I am unable to see
anything in the legislation which would prevent a “superior
contractor” from being the person who is also the head or first
contractor.”
[19] The Court of Appeal was asked to overrule Hewitt Nominees No 2 in Hamilton
Australia Pty Ltd v Milson Projects Pty Ltd [1997] 2 QdR 355. The Court of
Appeal refused to do so. The facts in that case were that the appellant had
contracted with the University for the performance by the appellant of construction
work. The appellant then subcontracted part of that work to M & H Industries Pty
Ltd (“MHI”) which in turn subcontracted part of its work to the respondent. The
respondent gave a notice of claim of charge pursuant to s 10 of the Act in respect of
moneys payable to it by MHI, but the claim was made on moneys payable by the
University to the appellant. When the notice was given, money was owing by the
University to the appellant, but the appellant did not owe money to MHI. Davies
JA and Mackenzie J in their joint judgment at 360 referred to the fact that the
decision in Hewitt Nominees No 2 had stood for nearly 18 years and that during that
-- 6 of 10 --
7
time the Legislature had amended the Act on several occasions, but did not choose
to amend s 5 which it could have done, if it had thought that the construction
adopted by the court in Hewitt Nominees No 2 did not reflect the legislative intent.
It followed that s 5(1) of the Act permitted a charge by a subcontractor upon money
payable to a contractor superior to the contractor which owes the subcontractor
money. Pincus JA in a separate judgment considered that the construction of s 5(1)
adopted in Hewitt Nominees No 2 was correct.
[20] The validity of a leapfrogging charge was also confirmed by the Court of Appeal in
Re Radair Pty Ltd [1998] 2 Qd R 539, 540 and 544. Dowsett J summarised the
effect of the decision in Hewitt Nominees No 2 at 544:
“The effect of that decision is that a person who can bring himself
within the definition of “subcontractor” is entitled to the benefit of a
charge pursuant to s 5 against moneys payable to the head contractor
or to any other subcontractor standing between the employer and the
claiming subcontractor in the chain of contract and subcontracts,
assuming that the other requirements of the Act are satisfied. That
proposition was not challenged in these proceedings. The so-called
“chain” is the sequence of contract and subcontracts linking the
employer at the “top” to the claiming subcontractor at the “bottom”.
[21] Dowsett J identified a possible problem in the operation of the Act at 549:
“A subcontractor who has given a notice of claim to another party is
entitled to a charge as against the amount payable by that party. The
source of the funds from which such payment is to be made is not
relevant. As I have previously observed, I can see no justification for
the view that the Act assumes that each contractor or subcontractor is
to be paid only from such amounts as are ultimately payable by the
employer at the top of the chain for the whole of the project.
Intermediate contractors may well find that they have to pay more to
their own subcontractors than they are to receive”.
[22] The version of the Act which is applicable to the subject charge is that which
incorporates the amendments made by the 2002 Act. One of the matters which the
2002 Act was intended to address was leapfrogging. The Hon R E Schwarten, the
Minister for Public Works and Housing, in moving that the relevant Bill be read a
second time stated:
“A further issue addressed by the Bill is the difficulty in the current
interpretation of “leapfrogging”.
Leapfrogging in relation to subcontractors’ charges occurs when
subcontractors or contractors lodge a charge against those persons
two or more steps higher up the contractual chain.
The Subcontractors’ Charges Amendment Bill 2001 clarifies that
“leapfrogging” will be allowed to continue to the extent that a
superior contractor is not be (sic) prejudicially affected through
having to make double payments for work the subject of the claim of
the charge, or having payments to them delayed when they have met
their contractual commitments.” (Hansard 27 November 2001 at p
3806)
-- 7 of 10 --
8
[23] The parties’ submissions differed on how the 2002 Act had achieved this intention
in respect of leapfrogging. Mr Dunning of counsel on behalf of Baulderstone
submitted that the insertion of ss 10(7) and (8) into the Act by the 2002 Act was
intended to prevent a subcontractor from lodging more than one notice of charge, as
“make claims” must be read as giving notices of charge, on the basis that a
subcontractor can make a claim only by giving a notice of charge. It was therefore
submitted that ss10(7) and (8) of the Act had the effect of limiting a subcontractor
to one notice or charge based on a claim for specified work and that if the
subcontractor had lodged a notice in respect of the moneys payable to the contractor
with whom he contracted, the subcontractor could not also lodge a leapfrogging
charge in respect of the same claim.
[24] Mr O’Donnell of Queen’s Counsel on behalf of Broen relies on the choice by the
Legislature of the word “claims” in ss 10(7) and (8) of the Act rather than the word
“charges”. He points out that the Act distinguishes between “claim”, “notice of
claim of charge” and “charge” (which is clear as a matter of construction of the Act
and has been authoritatively recognised such as in Ronnor Pty Ltd v D & R
Fabrications Pty Ltd [1983] 2 Qd R 455, 458) and that the expression “claims” in ss
10(7) and (8) of the Act should continue to be given the same meaning which it has
in the balance of the Act.
[25] The expression “claim” can be described as referring to an asserted entitlement to be
paid under the subcontract for specified work performed by the subcontractor under
the subcontract, upon which a notice of claim of charge given under s10(1) of the
Act is based, in order to obtain the entitlement of the charge which arises by
operation of s5(1) of the Act.
[26] It is submitted on behalf of Broen that there was only one claim in this matter which
supported the two notices of claim of charge and that ss 10(7) and (8) have no
application. That is clearly correct.
[27] Baulderstone also sought to limit Broen to its first notice of charge dated 28
November 2002 on the basis that Hewitt Nominees No 1 remained good authority
for restricting a subcontractor to giving one notice of claim of charge, even though
Hewitt Nominees No 2 allowed the appeal from the decision in Hewitt Nominees No
1.
[28] The construction of the Act which was the basis of the decision in Hewitt Nominees
No 1 was rejected in Hewitt Nominees No 2. In view of the context in which the
statement of Dunn J in Hewitt Nominees No 1 was made about entitlement to issue
only one charge, that statement cannot be transposed to the circumstances where a
leapfrogging charge is also recognised as permissible under the Act.
[29] There is nothing in the Act to preclude a subcontractor lodging two notices of claim
of charge based on the one claim where each of the notices is given to a different
contractor or employer. The extent to which the claim is satisfied under one charge
must affect the amount of the claim which can be pursued under the other charge.
This is facilitated by the process provided for in s 21(1)(b) of the Act. No such
problem arises in this case as there was no money to which the charge could attach
upon giving the notice of claim of charge dated 28 November 2002 to Hamilton.
In any case that charge has now been withdrawn. The Act permitted Broen to give
the notice of claim of charge to the University dated 18 December 2002.
-- 8 of 10 --
9
Baulderstone is not entitled to a declaration that the notice of charge dated 18
December 2002 is invalid.
Cancellation of the charge
[30] Both parties accept that the insertion of s 21(3) into the Act was to effectuate the
reforms intended to be achieved by the Legislature in respect of leapfrogging,
although the parties differ on how s 21(3) should be applied. This reform does not
reverse the effect of Hewitt Nominees No 2 in recognising the validity of a
leapfrogging charge.
[31] It is common ground that Baulderstone is a person “prejudicially affected” by
Broen’s notice of claim of charge dated 18 December 2002 by virtue of s 21(3) of
the Act.
[32] Baulderstone argues that, as it has already paid for the supply and installation of the
fume cabinets, including the tapware, by having paid Hamilton all moneys owing in
respect of those works, if the charge were not cancelled, Baulderstone would, in
effect, pay twice for this aspect of the work subcontracted to Hamilton. This is
because the funds paid into court by the University would otherwise have been paid
to Baulderstone under its contract with the University. If those funds are used to
pay Broen, Baulderstone misses out on payment from the University to the extent of
that amount.
[33] The Explanatory Notes for the Subcontractors’ Charges Amendment Bill 2001
confirms that the reform intended by the Legislature in respect of leapfrogging is
found in ss (3) of s 21 of the Act:
“Clause 16 inserts subsection 21(3) to provide for specific instances
in subsection 21(1) where a person may be prejudicially affected by
a claim of charge. If, because of a claim of charge, the payment or
release of security to a person (the affected person) higher up the
contractual chain than the subcontractor is delayed or otherwise
affected and the affected person has made payment to a person who
is a contractor or superior contractor of the claiming subcontractor,
the affected person is prejudicially affected within the meaning of
subsection 21(1). This provision effectively limits the circumstances
in which a subcontractor may successfully claim a “leap frog”
charge. The court can then determine whether a claim of charge
should be either cancelled or its effect modified.”
[34] The Legislature has endeavoured to remove the problem which can result with an
intermediate contractor in substance paying twice for the same work done by a
subcontractor. This has been done by giving the court the power to cancel the
leapfrogging charge which is otherwise valid or to modify it to avoid the
intermediate contractor having to pay again for work which is the subject of the
leapfrogging charge for which the intermediate contractor has already paid.
[35] It is argued on behalf of Broen that all that s 21(3) of the Act does is to enable a
superior contractor to have standing to cancel the charge for any of the accepted
bases on which the charge may be cancelled, but that it does not entitle
Baulderstone to cancellation of an otherwise valid charge. Broen relies on the
history of the Act and the fact that it has long represented a choice by the
Legislature that if a loss is to fall on one of two innocent parties, it will fall on a
-- 9 of 10 --
10
superior contractor, rather than the subcontractor. It is therefore submitted that in
the exercise of the discretion conferred by s 21 of the Act, the court should refuse to
cancel Broen’s charge.
[36] The court retains a discretion under s 21 of the Act as to whether or not to make an
order cancelling a claim or modifying the effect of the claim, even when satisfied
that a person has been prejudicially affected by a claim of charge under the Act.
The purpose of s 21 of the Act is to allow summary determination of the application
for cancellation or modification of the claim, with the consequent savings for all
parties.
[37] The fact that the Legislature has expressly chosen to deem a person in the position
of Baulderstone in relation to Broen’s notice of claim of charge dated 18 December
2002 to be prejudicially affected by that notice of claim of charge is a particularly
significant consideration as to whether the discretion conferred by s 21(2) of the Act
is exercised. The Legislature has introduced a departure from the approach of
protecting the subcontractor in preference to the superior contractor, when the
superior contractor has already paid for the work done by the subcontractor which is
the subject of the leapfrogging charge. The material filed in respect of these
applications does not suggest that there are any other matters relevant to the exercise
of that discretion which could be placed before me. There is no reason in the
circumstances of this matter not to give effect in a summary way to the intention of
the Legislature reflected by s 21(3) of the Act. Broen’s claim should be cancelled.
Orders
[38] It follows that the orders which should be made are:
1. The claim of Broen Australia Pty Ltd made in the notice of claim of
charge dated 18 December 2002 given to the University of Queensland in
the sum of $64,497.35 be cancelled pursuant to s 21 of the Subcontractors’
Charges Act 1974.
2. The amount of $64,497.35 paid into court by the University of
Queensland be paid to Baulderstone Hornibrook Pty Ltd.
3. The application filed on 26 February 2003 be dismissed.
[39] It will be necessary to hear submissions from the parties in respect of the costs of
each of the applications.
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2003/158