Atkinson v Warner [2003] QLRT 86
LAND AND RESOURCES TRIBUNAL
QUEENSLAND
CITATION: D. Atkinson & Ors v S. & P. Warner [2003] QLRT
86
PARTIES: In the Matter of Mining Lease 60117 – Application
by David, Jack and Tiffany Atkinson for
determination of compensation payable to Shane
and Peta Warner.
FILE NO/S: MLC00060/2003
PROCEEDING: Application for determination of compensation
DELIVERED ON: 28 August 2003
DELIVERED AT: Brisbane
HEARING DATE: Heard on the papers
PRESIDING MEMBER: Kingham DP
ORDER/S: 1. I determine compensation under s. 281(3) in the
sum of $44.67 (at [16])
2. In accordance with s. 281(4)(e), I award an
additional amount of $4.46 (at [16])
3. I direct that the miners pay the total
compensation of $49.13 to the landowners
within 1 month of the commencement of the
renewed term of the mining lease (at [16])
CATCHWORDS: MINING LEASE – DETERMINATION OF
COMPENSATION – UNIMPROVED VALUE –
WATER – PREVIOUS IMPROVEMENTS
Mineral Resources Act 1989, ss 50, 276, 281(3)&(4)
Land and Resources Tribunal Act 1999, s.50
Atkinson v Warner [2002] QLRT 18, applied
White v Warner [2003] QLRT 40, applied
Barry & Barrett [2002] QLRT 2, applied
Northern Safecorp Consultants Pty Ltd & G Bellino v
DP & JM Parsons [2001] QLRT 20, applied
COUNSEL: N/A
SOLICITORS: N/A
AGENTS: N/A
-- 1 of 5 --
Background
[1] The Applicants, David, Jack and Tiffany Atkinson (“the miners”), applied on 22
May 2003 to renew Mining Lease 60117 in the Quilpie mining district over a 1.5ha
parcel of leasehold land on the property known as “Bingara” held by the
Respondents, Shane and Peta Warner (“the landowners”). The mining lease
authorises mining for opal. The lease was granted on 27 January 1994. The current
term expires on 31 January 2004 but continues until the application to renew the
lease has been determined. The mining lease cannot be renewed until
compensation has been agreed between the parties or determined by the Tribunal.
The landowners and the miners have not agreed upon compensation and the miners
applied to the Tribunal for determination of compensation.
[2] Both parties were unrepresented and the application was heard on the papers.
Neither party relied upon expert evidence regarding the impact of the proposed
mining on the value of the land. Both parties filed statements, supporting material,
and written submissions. In determining compensation, I have taken into account
all of that material and the maps and documents provided to the Tribunal by the
Mining Registrar. In considering the likely impact, I have drawn upon my personal
observations of operations on opal mining leases. I have also considered the
environmental and mining conditions with which the miner will be required to
comply.1 In these reasons I refer to the salient points but not all the evidence that I
relied upon in making my findings.
Compensation claims
[3] The miners proposed total compensation of $18.33 calculated as follows:
Loss in value of land affected by the lease
(1.5ha x $33.35 discounted by 33.33%) $16.67
plus 10% for compulsory nature of grant $ 1.66
TOTAL $18.33
[4] The landowners claimed that compensation on the basis of $326.87 per ha
calculated as follows:
Loss of stock $222.00
Cost of re-muster $ 57.94
Cost of extra insurance $ 1.37
Cost of degradation $ 24.30
Cost of production loss $ 21.26
TOTAL $326.87/ha/yr
They also claimed $630 for the expense incurred in the preparation of the
compensation claim calculated as follows:
30 hrs landowners’ time @ $20/hr $600.00
phone calls & faxes $ 20.00
1 Section 276 MRA, Environmental Authority No. M3668 and Code of Environmental Compliance for Mining Lease
Projects.
-- 2 of 5 --
photocopying & postage $ 10.00
$630.00
Compensation principles
[5] Section 281(3) & (4) of the Mineral Resources Act 1989 (the Act) define the
landowners’ entitlement to compensation and list a number of matters that must be
considered by the Tribunal in assessing compensation. I have adopted the approach
generally taken by the Tribunal in such matters. That is that the matters set out in
the section are concepts to be taken into account in determining compensation,
rather than heads of compensation requiring separate and discrete treatment to
arrive at an accumulated figure. In determining compensation, the overriding
principle is of equivalence, ensuring that, so far as money can do it, the landowner
is placed in the same position as if the mining lease was not granted.
Discussion of compensation
[6] I have previously determined compensation for a mining claim on this property
held by one of the miners (the Atkinson determination).2 I have also recently
determined compensation in relation to another mining lease on this property (the
White determination).3 The material submitted by the landowners in this case is in
similar terms to the material submitted in support of the White determination. In
relation to the Atkinson determination, I note that activities authorised by a mining
claim are more restricted than those authorised by a mining lease and, therefore, the
impacts of a mining claim are likely to be less significant.4 This affects the
compensation payable and has been taken into account in my determination in this
matter.
[7] On the basis of the evidence before me, as in the Atkinson and the White
determinations, I have adopted the figure of $13.34 per ha as the value of the
property overall.5 As in the White determination, I accept that the per ha value of a
property can vary markedly over a property because of vegetation types and,
therefore, stocking capacities. On the evidence, I accept the landowners’
contention that the per ha value for the paddock in which the lease is situated is
higher, because this paddock has a stocking ratio three times higher than other areas
of the lease. That this paddock has a higher than average value is supported by
evidence regarding the vegetation type and by an independent assessment of its
stocking ratio. The landowners have not tendered any valuation evidence to
support the figure they put forward of $42.18 per ha for this paddock. No evidence
has been tendered to establish that a three fold stocking ratio directly equates to a
three fold value based on the average per ha value, as those areas with a lesser
stocking ratio must, of necessity, have a value below the average per ha value. In
the absence of any cogent evidence of the per ha value of this paddock, I have
adopted a figure that equates to 2.5 times the average per ha value of the property.
That is $33.35. I consider that is a reasonable basis for determining compensation
and I have adopted that figure in considering the impact of the mining lease on the
value of both the lease area and the paddock.
2 Atkinson v Warner [2002] QLRT 18.
3 White v Warner [2003] QLRT 40.
4 Sections 50, 235, 236.
5 Atkinson v Warner op cit at para [5], White v Warner op cit at para [9].
-- 3 of 5 --
[8] The landowners produced information regarding the impact of mining on ewes and
lambing and I have accepted that in determining compensation. Given the ten year
term of the lease, I have applied a discount of 50% to the loss of value taking into
account that a hypothetical prudent purchaser would assume that the entire area of
the lease was unavailable for that term.6 My determination of compensation,
therefore, includes the sum of $25 calculated on the basis of a loss of 1.5ha at
$33.35 per/ha discounted by 50%.
[9] I accept that the impact on the land will extend beyond the claim area. The
landowners submitted that, as a general proposition, the area made redundant by
mining is four times the area taken out by the mining lease. In other cases, I have
operated on the assumption that a 1ha lease can have an impact over the
surrounding 5ha. In this case, taking into account the number of other mining
tenements surrounding this lease, I have adopted the landowners’ formula of 4ha
for each ha.
[10] However, I do not accept that that area is rendered totally redundant. Nor, it
appears, do the landowners who adopted a figure of based on 12% of the value of
the area they claim is rendered redundant, not 100%. I do not accept that is a
reasonable figure and, instead, have included in my determination a sum calculated
on the basis of a 5% loss in value over a 6ha area (1.5ha x 4) at a per ha value of
$33.35, discounted by 50%. That is the amount of $5. In arriving at this figure I
have taken into account the landowners’ evidence regarding the number of tracks
which lead to this lease, regardless of which is said to be the official access track.
[11] The miners submitted that no amount should be included for access as the route
used is the same route as that used for access to David Atkinson’s mining claim. In
the Atkinson determination, I included a sum of $10 for the impact of the lease on
the surrounding land, including the access route. I do not accept the miners’
submission that no amount for access should be included in this award. There is no
evidence from the miners about the extent of traffic on the access road. In the
absence of evidence to the contrary, I consider it reasonable to assume that there
will be some use related to the mining lease that is additional to David Atkinson’s
use of the access for his mining claim. Consistently with the approach adopted in
the White determination, I have included in the award the sum of $4.67.
[12] This reflects a 5% loss in value, discounted by 50% for the 10 year term, over a
14ha area (2.8km long x 5m wide) at a value of $13.34/ha. I have adopted the
lower per ha value because most of the access falls outside the paddock and there is
no other evidence of its particular value. I consider this to be generous given 2.7km
of the access road is used by the landowners as well as other miners, and that the
landowners have also received some compensation for the access road from other
miners, including David Atkinson. I have taken into account the landowners
concern about erosion and environmental degradation from the access road. I have
also taken into account that the landowners are concerned about their potential
liability for the road and that they have incurred further public liability insurance
costs. However, I note the advice of the local authority that the “actual likelihood”
of liability is “low”.
6 The 33.33% discount figure adopted in the Atkinson determination and the White determination reflected the
shorter term of 5 years sought in those cases.
-- 4 of 5 --
[13] I consider it appropriate to include in the award some amount for the impact that
the renewal of the mining claim will have on the value of the property as a whole. I
have taken into account that the property was already significantly affected by
mining when the landowners purchased it. I have also taken into account that this
mining lease predated the purchase. Nevertheless, I consider the renewal of the
claim will involve a further blot on the title, as it extends the term of the mining. I
have included a nominal sum ($10.00) in the award.
[14] It appears that the mining lease will not cause severance and accordingly no
allowance for that has been made.
[15] The landowners claimed $630 for preparation costs comprised of a fee for their
time plus some outgoings. Whilst professional legal and valuation fees incurred in
formulating a claim for compensation can be claimed as a disturbance item for
compensation purposes, fees incurred by the landowners personally in presenting
the case before the Tribunal cannot.7 Such costs are dealt with by s. 50 of the Land
and Resources Tribunal Act 1999, which enables the Tribunal to award costs in
special circumstances. No such special circumstances have been established. In
any case, I have previously decided that the costs that may be awarded as costs of
the proceeding are confined to legal costs.8 Accordingly I have not included any of
the preparation costs in my formulation of compensation nor have I made any order
as to costs of this proceeding.
Determination of compensation
[16] Taking into account the matters set out above, I determine compensation under
s. 281(3) in the sum of $44.67. In accordance with s. 281(4)(e), I award an
additional amount of $4.46, which is 10% of the compensation determined above,
to reflect the compulsory nature of the grant of the mining claim. The total
compensation payable for the full term of the lease is $49.13. I direct the miners to
pay that sum to the landowners within 1 month of the commencement of the
renewed term of the mining lease.
7 Barry v Barrett [2002] QLRT 2 at para [35].
8 Northern Safecorp Consultants Pty Ltd & G Bellino v DP & JM Parsons [2001] QLRT 20 at para [9].
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QLRT/2003/086