Collins v Carey & Anor [2002] QSC 417
SUPREME COURT OF QUEENSLAND
CITATION: Collins v Carey & Anor [2002] QSC 417
PARTIES: LANCE STANLEY COLLINS
(plaintiff)
v
PAULA J CAREY and GREGORY J CAREY
(first defendants)
GRACE WORLDWIDE (AUSTRALIA) PTY LTD
(second defendant)
FILE NO/S: S 11531 of 2001
DIVISION: Trial Division
PROCEEDING: Further Order
ORIGINATING
COURT: Supreme Court Brisbane
DELIVERED ON: Judgment delivered on 3 December 2002
Further Order delivered 12 December 2002
DELIVERED AT: Brisbane
HEARING DATE: 3 December 2002
JUDGE: Philippides J
FURTHER
ORDER:
That the defendants pay the plaintiff’s costs of and
incidental to the proceeding to be assessed on the
standard basis on the District Court scale where the
amount recovered exceeds $50,000.
CATCHWORDS: COSTS – SCALE – where plaintiff succeeded in personal
injuries action – where amount awarded within monetary
jurisdiction of District Court – whether costs should be on
Supreme or District Court scale
COSTS – OFFERS TO SETTLE – where plaintiff had
offered to settle on liability – where plaintiff succeeded on
statement of claim amended at outset of trial – where costs to
follow event – whether costs should be on indemnity or
standard basis
COSTS – DISCRETION – whether solicitors’ costs should
be increased by 30% – whether certification for two counsel
should be made – whether costs should be reduced because
plaintiff failed on certain issues
Uniform Civil Procedure Rules 1999 (Qld), r 360(1),
r 360(2), r 690(5), r 698, r 698(1), r 698(3)
Cameron v Nominal Defendant [2000] QCA 137, 18 April
-- 1 of 5 --
2
2002
Charter Pacific Corporation Ltd v Belrida Enterprises Pty
Ltd [2002] QSC 319, 17 October 2002
Cretazzo v Lombardi (1975) 13 SASR 4
Davies v Fay [1995] 1 Qd R 509
Forster v Farquhar [1893] 1 QB 564
Nielson Investments (Qld) P/L & Ors v Spud Mulligan’s P/L
& Ors [2002] QSC 295, 27 September 2002
Sweeney v Attwood Marshall [2002] QSC 294, 27 September
2002
Walz Construction Co P/L v ASP Ship Management (A Firm)
& Ors; Qld Alumina Ltd v Walz Construction Co P/L & Ors;
Walz Construction Co P/L v Suncorp Insurance & Finance
[2002] QCA 155, 3 May 2002
COUNSEL: R Lilley for the plaintiff
P Hackett for the first defendants
J Rolls and A Kitchen for the second defendant
SOLICITORS: Murphy Schmidt for the plaintiff
HBM Lawyers for the first defendants
Phillips Fox for the second defendant
[1] PHILIPPIDES J: Judgement was given in the plaintiff’s favour on his claim for
damages for personal injuries, with the plaintiff being awarded $103,311.05 (after
deduction of the WorkCover refund of $26,751). The issue of costs now falls for
determination. There are a number of issues that require consideration:
(a) whether costs should be ordered on the District Court or Supreme
Court scale;
(b) whether costs should be ordered on an indemnity basis in respect of
the issue of liability, in view of an offer to settle made by the
plaintiff on 22 August 2002;
(c) whether a certificate for an increase of solicitors’ costs should be
made pursuant to rule 690(5) of the Uniform Civil Procedure Rules
1999 (“UCPR”);
(d) whether the order for costs should be reduced so that the plaintiff
does not recover the costs in respect of issues upon which he did not
succeed;
(e) whether a certificate for two counsel should be made.
The Appropriate Scale
[2] The quantum of the award recovered by the plaintiff fell within the monetary
jurisdiction of the District Court. Rule 698 of the UCPR provides:
“(1) Subrule (2) and (3) apply unless the court otherwise orders.
…
-- 2 of 5 --
3
(3) If the only relief obtained by a plaintiff in a proceeding in
the Supreme Court is relief that, when the proceeding began,
could have been given by the District Court, but not a
Magistrates Court, the costs the plaintiff may recover must
be assessed as if the proceeding had been started in the
District Court.”
[3] The plaintiff submits that pursuant to r 698(1) the court has a discretion to award
costs on the Supreme Court Scale and that this is an appropriate case for the
exercise of that discretion. The defendants, while accepting that there is such a
discretion, contend that the discretion should not be exercised and that District
Court costs should be given pursuant to r 698(3). In urging that the discretion
should be exercised in his favour, the plaintiff accepts that r 698 requires the
plaintiff to bear the onus of demonstrating that an order other than that specified in
r 698(3) is appropriate (see Walz Construction Co P/L v ASP Ship Management (A
Firm) & Ors; Qld Alumina Ltd v Walz Construction Co P/L & Ors; Walz
Construction Co P/L v Suncorp Insurance & Finance [2002] QCA 155, 3 May
2002, at [9]; Nielson Investments (Qld) P/L & Ors v Spud Mulligan’s P/L & Ors
[2002] QSC 295, 27 September 2002, at [3] and [14]; Sweeney v Attwood Marshall
[2002] QSC 294, 27 September 2002, at [7]-[12]).
[4] Proceedings were initially commenced in the District Court on 1 October 1998, but
were transferred to the Supreme Court on 1 November 2001 on the basis of an
affidavit by the plaintiff’s solicitor that there were “reasonable prospects that the
plaintiff’s damages will exceed $250,000”. Nevertheless, on 8 August 2002, the
plaintiff made an offer to settle for $200,000 inclusive of statutory refunds plus
costs. In support of the plaintiff’s contention, it is submitted that the plaintiff’s
claim had unusual aspects to it, in particular the aspects concerning the plaintiff’s
loss following his change of occupation, for which a substantial claim was made.
The claim was said to involve an aspect of novelty and complexity.
[5] I am not persuaded that there was anything unusual or exceptional about this case
which warrants an exercise of my discretion so as to depart from the general rule in
r 698(3). Accordingly, costs to be recovered by the plaintiff are to be assessed on
the District Court scale.
Costs on a Standard or Indemnity Basis?
[6] Rule 360 of the UCPR provides:
“(1) If –
(a) the plaintiff makes an offer to settle that is not
accepted by the defendant and the plaintiff obtains
judgment no less favourable than the offer to settle;
and
(b) the court is satisfied that the plaintiff was at all
material times willing and able to carry out what was
proposed in the offer;
the court must order the defendant to pay the plaintiff’s costs
calculated on the indemnity basis unless the defendant shows another
order for costs is appropriate in the circumstances.
-- 3 of 5 --
4
(2) If the plaintiff makes more than 1 offer satisfying sub-rule (1), the
first of those offers is taken to be the only offer for this rule.”
[7] The first defendants contend that the plaintiff made three offers that satisfy r 360(1).
On 25 October 2001, the plaintiff offered to settle for $319,000, inclusive of
statutory refunds plus costs. On 8 August 2002, the plaintiff offered to settle for
$200,000, inclusive of statutory refunds plus costs. On 22 August 2002, the
plaintiff offered to settle liability on the basis that the defendants were 100% liable.
It was submitted by the first defendants that, in view of r 360(2), the third offer
cannot be taken into consideration. That submission must fail because the offer
referred to in r 360(2) is an offer “satisfying sub-rule (1)” (see Cameron v Nominal
Defendant [2000] QCA 137, 18 April 2002). The first and only offer made which
satisfied r 360(1) was the offer of 22 August 2002 to settle liability.
[8] The defendants do not dispute that that offer is a good offer per se for the purposes
of Part 5 Chapter 9 of the UCPR and I accept that it is (see Davies v Fay [1995] 1
Qd R 509; Charter Pacific Corporation Ltd v Belrida Enterprises Pty Ltd [2002]
QSC 319, 17 October 2002). The defendants submit, however, that notwithstanding
the offer of 22 August 2002 an order for indemnity costs is not appropriate in the
circumstances of this case.
[9] It is said that the plaintiff’s claim against the first defendants was founded both in
negligence and in scienter, the plaintiff failing in the latter claim, which it persisted
in notwithstanding that an unsuccessful application to strike it out identified the
flaws in the claim. Further, as to the negligence action, the first defendants point
out that the plaintiff succeeded in only one of the four particulars of negligence,
which particular was not in the Statement of Claim at the date of the offer, but only
inserted by leave at the outset of the trial. The second defendant made similar
submissions concerning the lateness of the amendments to the pleading. It also
submitted that if indemnity costs were awarded against it, it would have to bear the
costs of the scienter issue, even though that issue was not litigated against it.
Additionally, it was submitted that were indemnity costs to be awarded, they should
be confined to only those costs incurred 14 days after the expiration of the offer or,
at the earliest, the date of the offer on 22 August 2002, having regard to the late
amendment of the pleadings upon which the plaintiff ultimately succeeded and the
lateness of the offer, which meant most costs had already been incurred.
[10] There is much weight in the defendants’ submissions that this is a case where it has
been shown that an order other than that in r 360(1) is appropriate. The amendment
to the pleading on which the plaintiff succeeded was made on 4 September 2002
and was therefore not part of the pleadings when the offer of 22 August 2002 was
made. In the circumstances I consider that costs should be awarded on a standard
basis only.
Increase of 30%
[11] The plaintiff submits that this is an appropriate case for the exercise of the
discretion pursuant to r 690(5) to order that the solicitors’ component of any costs
assessed on a standard basis be increased and that in this case an increase by 30%
should be made (see Sweeney v Attwood Marshall [2002] QSC 294, 27 September
2002). Rule 690(5) provides:
-- 4 of 5 --
5
“If the nature and importance, or the difficulty or urgency, of a
proceeding and the justice of the case justify it, the court may allow
an increase of not more than 30% of the solicitor’s costs allowed on
the assessment of the costs of the proceeding.”
[12] I do not consider that this is a case where any discretion should be so exercised.
The case was not of such a nature and importance, nor of such difficulty or urgency
as to bring the discretion in r 690(5) into play.
Unsuccessful Issues
[13] The first defendants contended that there ought to be some reduction in any costs
ordered in favour of the plaintiff, because the plaintiff failed on the scienter issue
and on three of four particulars of negligence (see Forster v Farquhar [1893] 1 QB
564; Cretazzo v Lombardi (1975) 13 SASR 4 at 12). I do not consider that such an
approach is warranted in this case, the scienter evidence and the evidence of
negligence being closely interwoven.
Two Counsel
[14] Since costs are to be limited to the District Court scale, a certification is required
pursuant to Item 83 of the District Court Scale of Fees. The plaintiff contends that
the certification for two counsel is appropriate because the case was complex and
involved management of a large volume of material, in circumstances where both
liability and quantum were in issue and where the second defendant saw fit to retain
two counsel. I do not consider that any such certification is warranted. The case
was not of a complexity or nature that such a certification should be made.
Order
[15] I order that the defendants pay the plaintiff’s costs of and incidental to the
proceeding to be assessed on the standard basis on the District Court scale where the
amount recovered exceeds $50,000. I make no certification for two counsel.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2002/417