Century Drilling Ltd v Toll North Pty Ltd [2002] QDC 366
DISTRICT COURT OF QUEENSLAND
CITATION: Century Drilling Limited v. Toll North Pty Ltd [2002] QDC
366
PARTIES: CENTURY DRILLING LIMITED (Plaintiff)
v.
TOLL NORTH PTY LTD (Defendant)
FILE NO/S: 1796 of 2002
DIVISION:
PROCEEDING: Application in a Claim
ORIGINATING
COURT: District Court Brisbane
DELIVERED ON: 10 December 2002
DELIVERED AT: Brisbane
HEARING DATE: 29 November 2002
JUDGE: Robin DCJ
ORDER: Paragraphs 11.3.3 & 12A of the amended defence struck
out. Defendant to pay the plaintiff’s costs of the
application to be assessed.
CATCHWORDS: Uniform Civil Procedure Rules r171(1)(a) and (b), r 483 –
successful application to strike out part of defence on ground
it “discloses no reasonable defence” – proper test considered
– whether certain remaining paragraphs apparently rendered
devoid of effect should be struck out too – defendant carrier
sought to rely on the Hague Rules to exonerate it from
liability on grounds an “independent contractor” shipping
company engaged by it (or that shipping company’s
stevedore) was responsible for delay – shipping company (or
its personnel) held the “servants or agents” of the defendant
within Hague Rules – Hague Rules also relied on to limit
liability – “sea freight payable for the goods delayed” held to
refer only to sum identifiable within the arrangements made
by the parties – no such sum was claimed to be identifiable.
Carriage of Goods by Sea Act (Cth) 1991, Schedule 1A
Hague Rules, Article 4A, Article 4 bis
Madden v. Kirkegard Ellwood & Partners (1975) Qd.R. 363
G Hawkins & Sons Pty Ltd v. Commissioner of Main Roads
(unreported) Supreme Court of Queensland, 336 of 1991,
Cooper J, 20 March 1992.
-- 1 of 19 --
2
General Steel Industries Inc v. Commissioner for Railways
(NSW) (1964) 112 CLR 125
Queensland University of Technology v. Project
Constructions (Aust) Pty Ltd (In Liq) (2002) QCA 224
Bernstrom v. National Australia Bank Ltd (2002) QCA 231
Swain v. Hillman (2001) 1 All ER 91
COUNSEL: Mr Gynther for the applicant plaintiff
Mr McLeod for the respondent defendant
SOLICITORS: Corrs Chambers Westgarth for the applicant plaintiff
Phillips Fox for the respondent defendant
[1] This is an application by the plaintiff pursuant to r.171 of the Uniform Civil
Procedure Rules seeking that paragraphs 11.3 and 12A of the amended defence be
struck out. Somewhat belatedly, Mr. Gynther, for the plaintiff, sought to amend the
application to add a request for separate decision of the relevant questions under
Uniform Civil Procedure Rules r.483. The court indicated that if it contemplated
proceeding in that way, the defendant would have an opportunity to be heard before
an order providing for separate decision was made.
[2] The only aspect of r.171 which could be relied on is that relating to a part of a
pleading which “(a) discloses no reasonable defence”, although Mr. Gynther
suggested (b) might also be available.
[3] The plaintiff’s current pleading is its second amended statement of claim filed on 10
September 2002. The responding pleading is the amended defence which had
already been filed on 1 August 2002. It has been expanded by particulars given
recently.
[4] The plaintiff claims it had a contract requiring provision by it of certain drilling
services in Vietnam, involving use of its drilling rig to drill wells, that (in aid of its
-- 2 of 19 --
3
performing that contract) it “entered into an agreement with the defendant for the
mobilisation and delivery of certain equipment by the defendant to Vietnam (the
“Service Contract”).” The Service Contract required performance by the Defendant
(which appears to be called “Carpentaria”) of defined services, including provision
of personnel and equipment, cleaning of equipment and shipping to Haiphong,
Vietnam and Batam Island, Indonesia, of cargo. The consideration for performance
of “the Works as defined” appears to have been US$370,874, an amount in excess
of what may be claimed by the plaintiff. The plaintiff contends it was the
defendant’s obligation under the service contract to deliver the main rig and
equipment required to support its operation (called the Brisbane Load) in Haiphong
on 10 December 2001, that the defendant knew of the plaintiff’s obligations under
the Drilling Contract, and that the purpose of the Service Contract was to fulfil
those obligations, delay in delivery of the Brisbane Load being likely to result in
delay and loss. Somehow, the Brisbane Load, having been unloaded in Port
Moresby, was not reloaded upon the Haiphong-bound vessel. The equipment was
delivered to Haiphong (late, according to the plaintiff) by Hercules aircraft, pursuant
to arrangements the defendant caused to be made. Although the claim is for
“damages for breach of contract or alternatively breach of duty”, Mr. Gynther has
identified the alternative claim as one for breach of duty as bailee.
[5] A major issue in the action is whether the defendant was under an obligation to
deliver in Haiphong by or on the date indicated.
[6] The contentious provisions of the amended defence are:
“11.3 Pursuant to Article 4A of the amended Hague Rules the
defendant, as a ‘carrier’ within the meaning of the amended
Hague Rules, is not liable for any loss as alleged by the
plaintiff because:
-- 3 of 19 --
4
11.3.1 the delay in the delivery of the Container was excusable;
11.3.2 the defendant undertook all reasonable measures to avoid
any delay and its consequences in that it engaged a
competent shipping agent to transport the Container;
11.3.3 the delay was caused by circumstances beyond the
reasonable control of the defendant.
…
12A If the plaintiff suffered any loss and damage as alleged at
paragraph 15 of the amended statement of claim (which is
denied) then Article 4A Section 6 of the amended Hague
Rules provides that such loss and damage is limited to the
lesser of:
12A.1 the actual amount of the loss;
12A.2 two and half times the sea freight payable for the goods
delayed;
12A.3 the total amount payable as sea freight for all goods shipped
under the contract of carriage.
The defendant will further particularise the limitation of the alleged
loss at the trial or earlier hearing of this matter.”
[7] As to what occurred in Port Moresby, the pleading states:
“9.1 The Brisbane load was transported by Crocodile Lines
Shipping Company (“Crocodile Lines”) from Townsville to
Port Moresby where it was accepted and loaded aboard a
vessel owned and/or operated by Crocodile Line for delivery
by Crocodile Line to Haiphong, in accordance with Bill of
Lading No TSVHPG0002;
9.2 The defendant did not authorise or participate in the
offloading of any container at Port Moresby;
9.3 The container was off loaded at Port Moresby in Papua New
Guinea as a result of the negligence of Crocodile Lines
and/or Port Services PNG Pty Ltd and not the defendant.”
The parties (the plaintiff on 12 November 2002, the defendant on 21
November 2002) have signed a consent pursuant to r.666 to the Registrar’s
making an order giving the defendant leave to issue third party proceedings
against China Steam Navigation Company trading as Crocodile Lines.
-- 4 of 19 --
5
[8] The amended Hague Rules are applicable by reason of the (Commonwealth)
Carriage of Goods By Sea Act 1991 to which they form Schedule 1A. Schedule 2
comprises the Hamburg Rules which, it seems, are regarded as more advanced,
although the Hague Rules have been amended as occasion demanded. It is
contemplated that at some future time, Australia may be ready to embrace the
Hamburg Rules; our country seems inclined to follow, rather than lead its main
trading partners.
[9] Mr. Gynther sought to rely on Parliamentary material indicating that, at least in
respects presently relevant, the Hamburg Rules and the Hague Rules have the same
meaning, with a view to inducing the court to act on what he submitted (I think
justifiably) was the meaning of rather clearer drafting in the Hamburg Rules. I have
some difficulty with this approach. None of the Parliamentary speeches relied on
was by the relevant Minister. It was not shown that speeches by the Minister’s
Parliamentary Secretary, let alone speeches by Backbenchers, as proposed by the
plaintiff, could qualify as extrinsic material under the relevant provisions of the Acts
Interpretation Act 1901 as amended of the Commonwealth. Nor was it shown that
the very comprehensive Report of the Marine Cargo Liability Working Group -
September 1995 in respect of Australia’s cargo liability regime, which appears to be
a Department of Transport and Regional Services document, rather than a
Parliamentary one, could be used by the court in aid of statutory interpretation. In
the circumstances, my approach has been that it is not appropriate to go beyond the
amended Hague Rules and relevant case law.
[10] Article 4A (as taken from a folder of documents handed up by Mr. Gynther,
presumably by consent) is as follows:
-- 5 of 19 --
6
“1. Despite Article 4, a carrier is liable to a shipper for loss
(including but not limited to, pure economic loss, loss of markets or
deterioration) caused to the shipper by the shipper’s goods being
delayed while the carrier is in charge of the goods unless the carrier
establishes, on the balance of probabilities, that:
(a) the delay was excusable; and
(b) the carrier (or, if at the time of the delay, the goods were
under the control of servants or agents of the carrier, those
servants or agents) took all measures that were reasonably
required to avoid the delay and its consequences.
[NOTE: For the meaning of “in charge of the goods”, see paragraph
2 of Article 1.]
2. For this Article, goods have been delayed if they are not
delivered at the port of discharge specified in the relevant contract
for carriage of goods:
(a) within the time allowed in the contract for that purpose; or
(b) if the contract does not specify a time for that purpose –
within a reasonable time for delivery, at that port, of similar
goods carried by a diligent carrier (having regard to any
particular circumstances of the case and the intentions of
the shipper and the carrier).
[NOTE: For the meaning of ‘delivered’, see paragraph 1A of Article
1.]
3. For paragraph 1(a) of this Article, a delay is excusable only
if:
(a) it is caused by a deviation authorised by the shipper, or by a
term in the contract of carriage; or
(b) it is caused by circumstances beyond the reasonable control
of the carrier or its servants or agents; or
(c) it is reasonably necessary to comply with an express or
implied warranty; or
(d) it is reasonably necessary for the safety of the ship or its
cargo; or
(e) it is for the purposes of saving human life or aiding a ship in
distress; or
(f) it is reasonably necessary for the purpose of obtaining
medical or surgical aid for a person on board; or
(g) it is caused by barratrous conduct of the master or crew; or
(h) paragraph 4 of this Article applies.
4. For paragraph 1 (a) of this Article, a delay caused by
industrial action is excusable if the industrial action was not
substantially caused, or substantially contributed to, by
unreasonable conduct of the carrier.
-- 6 of 19 --
7
5. For paragraph 4, conduct of servants or agents of the
carrier is not taken to be conduct of the carrier if the servants or
agents engaged in the conduct without the carrier’s express or
implied authority.
6. The quantum of the carrier’s liability for loss caused by the
delay is limited to whichever is the lesser of:
(a) the actual amount of the loss; or
(b) two and a half times the sea freight payable for the goods
delayed; or
(c) the total amount payable as sea freight for all of the goods
shipped by the shipper concerned under the contract of
carriage concerned.
7. To avoid doubt, nothing in Article 4 or this Article prevents
a carrier being liable to be a shipper under both Article 4 and this
Article.
Article 4 bis follows:
“1. The defences and limits of liability provided for in this
Convention these Rules shall apply in any action against the
carrier in respect of loss or damage to goods covered by a
contract of carriage whether the action be founded in
contract or in tort.
2. If such an action is brought against a servant or agent of the
carrier (such servant or agent not being an independent
contractor), such servant or agent shall be entitled to avail
himself of the defences and limits of liability which the
carrier is entitled to invoke under this Convention these
Rules.
3. The aggregate of the amounts recoverable from the carrier,
and such servants and agents, shall in no case exceed the
limit provided for in this Convention these Rules.
4. Nevertheless, a servant or agent of the carrier shall not be
entitled to avail himself of the provisions of this Article, if it
is proved that the damage resulted from an act or omission
of the servant or agent done with intent to cause damage or
recklessly and with knowledge that damage would probably
result.”
[11] Following the procedure at the hearing, para. 12A will be considered first. The only
one of the limitations that could be of concern is that to “two and a half times the
sea freight payable for the goods delayed”. In particulars of 11 November 2002, the
defendant has said that the amount of sea freight payable for the goods delayed was
“approximately $US2,500”. It is clear that the amount has no reference to any
freight component actually identified in dealings between the parties. I agree with
-- 7 of 19 --
8
Mr. Gynther’s submission that “two and a half times the sea freight payable for the
goods delayed” is not an apt use of language to describe or attempt to describe
either:
(a) a reference to what the market would charge for carrying the same
goods on the same journey; or
(b) some hypothetical obligation or contract of carriage.
[12] If the amount of the limitation in Article 4A Rule 6(b) is to be applied, then, in my
view, it is vital to identify the amount of “the sea freight payable for the goods
delayed” by reference to actual arrangements between the parties. It is patent, in my
view, that the purpose of Rule 6 is to introduce a notion of proportionality into the
assessment of the carrier’s liability, to ensure that any amount the carrier has to pay
for delay is not disproportionate to the reward the carrier did or stood to obtain for
its services. This means there is an onus on the carrier wishing to preserve
entitlement to such a limitation to specify separate sea freight payable for
components of the totality of goods shipped, in accordance with its best judgment
about the extent to which that may be a useful precaution. In default of doing so,
the carrier is left to take its chances between (a) and (c) of Rule 6, each of which
represents a rational approach towards achieving “proportionality”.
[13] In fairness to Mr. Gynther’s attempt to rely on extrinsic aids to statutory
interpretation, I would note that the relevant Explanatory Statement, as downloaded
from the internet, states that “Rule 6 sets limits to the quantum of the carrier’s
liability, similarly to the limits in the Hamburg Rules”. I would not regard this as a
warrant for turning to the language of the Hamburg Rules, rather than focus on the
language of Rule 6 of Article 4A, the proper interpretation of which, indicated
-- 8 of 19 --
9
above, seems to me clear. Mr. Gynther is correct that if reference to some kind of
“market price” concept was intended, there would have been no difficulty about
specifying that.
[14] He also submitted that if para. 12A(2) of the amended defence is to be struck out (as
I think it should be) the whole of para. 12A should go, as offending r.171(1)(a),
quoted above and also (b), by reason of a “tendency to prejudice or delay the fair
trial of the proceeding” if the balance of 12A remains. The “pleadings
housekeeping” Mr. Gynther contends is called for under the strict approach of
Madden v. Kirkegard Ellwood & Partners (1975) Qd.R. 363 at 363-64 and 366 and
in G Hawkins & Sons Pty Ltd v. Commissioner of Main Roads (unreported)
Supreme Court of Queensland, 336 of 1991, Cooper J, 20 March 1992 could mean
that other provisions of the amended defence which have no useful work remaining
to do ought to go as well. These were para. 4.3 under which the defendant:
“ …. Says further that pursuant to Article 1(g) of Schedule 1A
(amended Hague Rules) of the Carriage of Goods By Sea Act 1991
(Cwth) (the Act) the Service Contract was a ‘sea carriage
document’”
and para. 5.6 under which the defendant:
“… says that pursuant to ss.8 and 11 of the Act the Service Contract
is subject to the application of the amended Hague Rules.”
[15] If it comes to the point, I think Mr. McLeod (counsel for the defendant) ought to
have an opportunity to say why those provisions should be allowed to remain if (as
will happen) there is no other reference to the amended Hague Rules.
[16] The parties appeared to accept that the relevant principle in this striking out
application was to be found in General Steel Industries Inc v. Commissioner for
Railways (NSW) (1964) 112 CLR 125, referred to with approval by the Court of
-- 9 of 19 --
10
Appeal in Queensland University of Technology v. Project Constructions (Aust) Pty
Ltd (In Liq) (2002) QCA 224 at [7] per Holmes J, with whom Davies JA and
Mullins J agreed, in considering r.293. It was submitted by the plaintiff that the
Court of Appeal decision, likewise that in Bernstrom v. National Australia Bank Ltd
(2002) QCA 231, placing emphasis on the language of rr. 292 and 293 (“no real
prospect of succeeding”) and Lord Woolf’s comments about that expression in
Swain v. Hillman (2001) 1 All ER 91, 94 may indicate a similar approach to be
taken under r.171. The argument was that a claim or defence is not “reasonable”
within r.171 if it can be said that there is no real prospect of it succeeding. The
General Steel test indicates “that great care must be exercised to ensure that under
the guise of achieving expeditious finality a plaintiff is not improperly deprived of
his opportunity for the trial of his case.” Whichever approach is applied, I consider
that there is no sufficiently promising prospect of Article 4A Rule 6 applying to
limit the defendant’s liability to justify this remaining as a live issue in the action.
[17] Mr. McLeod’s argument in respect of para. 12A was:
“15. In light of the defendant’s reliance upon Article 4A of the
Amended Hague Rules, para. 12A complies with the relevant
provisions relied upon therein and accordingly there is no basis for
the paragraph to be struck out.”
Mr. McLeod’s submission as to the general approach to be taken in the application
was:
“Pursuant to r.171 of the UCPR, the plaintiff seeks an order that
paragraphs 11.3 and 12A of the amended defence be struck out. The
power to strike out a pleading as disclosing no reasonable ground of
defence should be sparingly employed. In General Steel Industries
Inc v. Commissioner for Railways (NSW) (1964) 112 CLR 125 at
129-130, Barwick CJ expressed the view that a Court will generally
only strike out a part of a pleading where it can be clearly
demonstrated, on an interlocutory basis, that the pleading is so
untenable that it cannot possibly succeed. To similar effect see
-- 10 of 19 --
11
Hodges v. New South Wales ALR 1 at 2-3 and Effem Foods Pty Ltd
v. travel Industries of Australia Pty Ltd (1993) 43 FCR 510.”
I think there was some oversimplification here of the effect of General Steel. The
view attributed to the Chief Justice was one of a variety of judicial statements of a
test; when he used them without quotation marks, it followed acknowledgement
that the necessary conclusion might follow fairly complex inquiry and/or
argument. It is useful to consider the reference in context of the full passage
referred to by Mr. McLeod:
“… There is no need for me to discuss in any detail the various
decisions, some of which were given in cases in which the inherent
jurisdiction of a court was invoked and others in cases in which
counterpart rules to Order 26, r.18, were the suggested source of
authority to deal summarily with the claim in question. It is
sufficient for me to say that these cases uniformly adhere to the view
that the plaintiff ought not to be denied access to the customary
tribunal which deals with actions of the kind he brings, unless his
lack of a cause of action – if that be the ground on which the court is
invited, as in this case, to exercise its powers of summary dismissal –
is clearly demonstrated. The test to be applied has been variously
expressed; ‘so obviously untenable that it cannot possible succeed’;
‘manifestly groundless’; ‘so manifestly faulty that it does not admit
of argument’; ‘discloses a case which the Court is satisfied cannot
succeed’; ‘under no possibility can there be a good cause of action’;
‘be manifest that to allow them’ (the pleadings) ‘to stand would
involve useless expense’.
At times the test has been put as high as saying that the case must be
so plain and obvious that the court can say at once that the statement
of claim, even if proved, cannot succeed; or ‘so manifest on the
view of the pleadings, merely reading through them, that it is a case
that does not admit of reasonable argument’; ‘so to speak apparent at
a glance’.
As I have said, some of these expressions occur in cases in which the
inherent jurisdiction was invoked and others in cases founded on
statutory rules of court but although the material available to the
court in either type of case may be different the need for exceptional
caution in exercising the power whether it be inherent or under
statutory rules is the same. Dixon J (as he then was) sums up a
number of authorities in Dey v. Victorian Railways Commissioners
(1) where he says (2): ‘A case must be very clear indeed to justify
the summary intervention of the court to prevent a plaintiff
submitting his case for determination in the appointed manner by the
court with or without a jury. The fact that a transaction is intricate
-- 11 of 19 --
12
may not disentitle the court to examine a cause of action alleged to
grow out of it for the purpose of seeing whether the proceeding
amounts to an abuse of process or is vexatious. But once it appears
that there is a real question to be determined whether of fact or law
and that the rights of the parties depend upon it, then it is not
competent for the court to dismiss the action as frivolous and
vexatious and an abuse of process’. Although I can agree with
Latham CJ in the same case when he said that the defendant should
be saved from the vexation of the continuance of useless and futile
proceedings (1), in my opinion great care must be exercised to ensure
that under the guise of achieving expeditious finality a plaintiff is not
improperly deprived of his opportunity for the trial of his case by the
appointed tribunal. On the other hand, I do not think that the
exercise of the jurisdiction should be reserved for those cases where
argument is unnecessary to evoke the futility of the plaintiff’s claim .
Argument, perhaps even of an extensive kind, may be necessary to
demonstrate that the case of the plaintiff is so clearly untenable that it
cannot possibly succeed.
In the present applications the defendants seek an exercise of the
inherent jurisdiction of the Court to stay actions which are frivolous
and vexatious and an abuse of process.”
[18] The defendants’ applications succeeded. If I am correct about Article 4A Rule 6,
the limitations defence in paragraph 12A.2 as pleaded and particularised cannot
possibly succeed. Of course, the situation would be different if the amended
defence pleaded that arrangements between the parties had in some way identified
the amount of US$2,500. (The particulars mentioned state that the defendant agreed
to pay Crocodile Lines A$348,162.25 sea freight to deliver cargo from Townsville
to Haiphong.)
[19] Paragraph 11.3 of the amended defence is setting up Article 4A Rule 1 which
qualifies an underlying provision recognising the liability of a carrier to a shipper
for delay by a proviso giving the carrier the opportunity to establish that:
“(a) the delay was excusable; and
-- 12 of 19 --
13
(b) the carrier (or, if at the time of the delay the goods were under the
control of servants or agents of the carrier, those servants or agents)
took all measures that were reasonably required to avoid the delay
and its consequences.”
Rule 3 provides that for purposes of (a) above, delay is excusable only if:
“(b) it is caused by circumstances beyond the reasonable control
of the carrier or its servants or agents.”
This is the only one of the eight categories of the excusable delay which is claimed
to be relevant. For this aspect of the defence to avail the defendant, it must
establish both 1(b) and 3(b). In the circumstances it has to show that Crocodile
Lines was not its “servant or agent”. In the context of this proceeding, in my view,
it is not sufficient to show that Crocodile Lines was an independent contractor.
Presumably that is what is intended by para. 11.3.2 (and perhaps 11.3.3). Mr.
McLeod relied upon what Fullager J said in Wilson v. Darling Island Stevedoring
and Lighterage Co Ltd (1956) 95 CLR 43, at 69-70:
“ Before proceeding further I would make two general observations.
In the first place, Lord Sumner’s view, as expressed, clearly does not
go beyond the case of the owner of a chartered ship. On the other
hand, the view expressed by Scrutton L.J. in the Court of Appeal
although it also does not in terms go beyond a case of owner and
charterer of a ship, was (with the concurrence of Bankes L.J.) in
Mersey Shipping & Transport Co. v. Rea Ltd. expanded into a wide
general rule to the effect that, if A agrees to do work for B on
condition that he is not to be liable for negligence, and C is engaged
by A (whether as a servant of A or as an independent contractor with
A) to do the work, C will not be liable to B in tort if his own personal
negligence causes damage to B. There is, in my opinion, no
foundation whatever for suggesting that there is any such general
rule of law. Owen J. in Gilbert, Stokes & Kerr Pty. Ltd. v. Dalgety &
Co. Ltd. said :- “I would have thought that no such general principle
was to be found in the law of agency, and would have agreed entirely
with the statement to that effect by Jordan C.J. in Williams v.
Commissioner for Main Roads”. I also would agree with that
statement. According to Denning L.J. in Adler v. Dickson a
distinction is to be drawn, and, if A stipulates with B that he will not
be liable for the negligence of his servants or agents, his servants and
agents are not protected, but, if A stipulates with B that neither he
nor his servants or agents are to be liable for negligence, his servants
-- 13 of 19 --
14
and agents will be protected. I should have thought it clear that,
unless from special circumstances (such as existed in Hall’s Case) a
contract including the exempting clause could be inferred between B
and a particular servant or agent of A, the servants and agents of A
would not be protected in either case.
I cannot leave this subject without observing that the word “agent”
appears to me to be often misused in this connection, and one cannot
help feeling that this misuse is largely responsible for at least of the
views which have been entertained of the Elder Dempster Case. It
seems to me quite wrong to say that a stevedoring company engaged
by a shipowner to load or unload a ship is an “agent” of the
shipowner, just as it would be wrong to say that a builder is an
“agent” of a building owner. If A engages B to lay out a garden for
him, and B engages C to do the actual work, C is not in any
intelligible legal sense B’s agent. B is an independent contractor,
and C is either A’s servant or an independent contractor with A.
Agency in the legal sense simply does not come into the matter.
The second observation I would make is this. What has been
supposed to be a principle involved in the Elder Dempster Case
(although there is a conspicuous lack of unanimity as to what that
principle really is) has, as will be seen, been extended so as to give a
stevedore exemption from liability for negligence by virtue of a
provision in a bill of lading to which the stevedore is not a party, and
which is really no concern whatever of the stevedore. This appears
to me to be a “development” of the common law which is altogether
out of character, and which is exactly the opposite of what one would
have expected and felt to be justified. It is all the more remarkable in
view of the fact that the modern tendency has been to expand the
field of liability in tort. The common law has, I think, from quite
early times – consistently with its general policy of freedom of
contract – allowed the validity of provisions in a contract which limit
or exclude liability for negligence. But it has always frowned upon
such provisions and insisted on constructing them strictly.”
His Honour was one of a three:two majority holding that a stevedore was not a
party to a contract evidenced by a certain bill of lading, that it could neither sue nor
be sued on it and that nothing in it could relieve it from the consequences of a
tortious act of its servants. Dixon CJ agreed with Fullagar J’s judgment.
[20] The present question is not whether a contract excludes or limits liability of the
defendant, but whether the Hague Rules have that effect. In them it is specifically
contemplated that the expression “servant or agent” may extend to an independent
-- 14 of 19 --
15
contractor. Thus, in Article 4bis Rule 2 there is reference to an action brought
against “a servant or agent of the carrier (such servant or agent not being an
independent contractor)” (in which cases “such servant or agent shall be entitled to
avail himself of the defences and limits of liability which the carrier is entitled to”).
In the circumstances, my opinion is that the proper interpretation of the Hague
Rules requires that the same meaning be accorded to “servant” and “agent”
throughout. Mr. Gynther has located a respectable group of authorities decided
upon provisions of the equivalent of the Hague Rules in the Carriage of Goods By
Sea Act 1924, in particular Brown & Co Ltd v. Harrison (1927) All ER Rep.195 and
Leesh River Tea Co Ltd v. British India Steam Navigation Co Ltd (1967) 2 QB 250.
In Brown, Bankes LJ set out the relevant provision at 201:
“Any other cause arising without the actual fault or privity of the
carrier, or without the fault or neglect of the agents or servants of the
carrier, but the burden of proof shall be on the person claiming the
benefit of this exception to show that neither the actual fault or
privity of the carrier nor the fault or neglect of the agents or servants
of the carrier contributed to the loss or damage”.
and said at 202:
“The last point is that the servants of the stevedore in this particular
case being employed by the stevedore, and the stevedore himself
being employed as an independent contractor by the shipowner to
carry out the discharge, the servants of the stevedore are not agents
of the carrier within the meaning of r.2(q). I think counsel for the
shipowners has answered that point himself, because he points out in
a case which he referred to for another purpose, Machu v. London
and South-Western Rail Co (10), that, in a very similar case, the
court held that, for the purpose of construing an Act of Parliament in
somewhat similar terms to this statute, the servants of the
independent contractor would be the agents of the railway company
for the purpose of the construction of the statute; and so here, it
seems to me impossible to put any reasonable construction on this
statute except by regarding the servants of the persons who are
employed by the shipowner in order to fulfil his statutory obligation
to discharge the vessel as being his agents for that purpose. On all
points, therefore, I think that the judgment of the learned judge was
right and that the appeal must be dismissed.”
-- 15 of 19 --
16
Atkin LJ described one argument as “the worst point that has ever been taken in
the Court of Appeal in my time” and went on on p.204 to consider one apparently
a little more meritorious:
“The other question is the question whether or not the servants of the
master stevedore at Vera Cruz can be said to be, within the meaning
of r.2(q), the agents or servants of the ship. Counsel for the
shipowners did not dispute that the master stevedore himself was to
be considered an agent of the ship, and I think he was quite right in
so holding. There was a statutory obligation on the ship to discharge,
and they performed that duty by entering into a contract with the
master stevedore, who, for that purpose, was their agent in
performing their statutory duty. To my mind, that in itself would be
sufficient to support the matter, because it is plain that the master
stevedore, according to our law, would be responsible for the tortious
acts of his servants done in the scope of their employment. But,
quite apart from that, I think that the servants of the stevedore for this
purpose are also the agents of the ship, and I think that is made plain
by the reasoning of the court in the case that my Lord referred to of
Machu v. London and South-Western Rail Co (10) where they had to
deal with words which were narrower in their meaning, where they
had to deal with the word “servants” and where the court held that
the servants of the sub-contractor of the carrier were, within the
meaning of the Carriers Act, servants of the carrier. I think that that
is sound and applies to this case.”
[21] In Leesh River Tea, Sellers LJ at 272 said that Brown “established that although
stevedores appointed, as here, are independent contractors, the men employed by
them to discharge the cargo must be regarded as servants of the shipowner for that
purpose within the meaning of sub-clause (q).” Mr. Gynther relied on Machu v. The
London and South-Western Railway Co (1848) 2 Ex 415 at 425-26 on which Brown
was based:
“I have paid great attention to the argument, and the whole matter
comes to this: - It appears that Chaplin & Horne had contracted with
the Railway Company to do this part of the business for them; that
they were not the servants to the Company, but were its agents; and
that the persons whom Chaplin & Horne employed, whom they paid,
and to whom they gave orders, and had power to dismiss – these
persons were still further removed from the Company, as being
servants to Chaplin & Horne, and not to the Company. Then it is
said by Mr. Martin, that the act of parliament in question distinctly
gives the Railway Company, as carriers, indemnity against
responsibility from loss, unless certain conditions are complied with;
-- 16 of 19 --
17
that the 8th section re-imposes their common-law liability under
certain circumstances only, and that, in order to bring the plaintiff
within that section, he must show that the felonious act was
committed by an actual servant of the Company. In proceeding to
put a construction up on this statute, I have allowed the fullest scope
to Mr. Martin’s argument, and I thoroughly comprehend its force . I
also perfectly agree that we have no right to make an act of
Parliament; that it is only our duty to construe those that are made;
and that we ought to consider, not what the legislature might have
done, but what they have done: and with a perfect perception of the
force of the argument derived from the expressions of Mr. Justice
Littledale, in the case of Laugher v.; Pointer, I am still of the opinion
that this rule ought to be discharged. And I think it ought to be
discharged upon the general ground, which I prefer to any other, that
there was an employment of Johnson by the Company, leaving out of
consideration, for the present, all that relates to the holding him out
as a servant of the Company. Taking it that the document in question
proves that on the Company receiving this parcel in the country, it
was the undertaking on their part to deliver it in London, I am of the
opinion that Johnson was, within the meaning of the 8 th section of the
act, a servant in their employ. A state of things perhaps altogether
different from what existed at the time of the passing of the statute,
has sprung up, in consequence of railroads having come more
extensively into use; but the general object of the act was to give
protection to carriers in respect of small parcels of great value placed
under their care, without any notice of their value, thus compelling
them to incur considerable risk with but little remuneration; and the
legislature has effected this by requiring the value of such parcels to
be declared, and an additional sum to be paid to the carrier by way of
insuring their safe delivery; and nothing can be more just than such
an enactment. In order, however, to guard the public against the
consequences of effecting such insurance – for one consideration for
the insurance is the disclosure to the carrier’s servants by such notice
of the value of the goods to be transmitted – the legislature, whilst it
says that the carrier shall not be liable unless the article sent be
insured, goes on to provide that, whether it be insured or not, the
carrier shall still be liable “to answer for loss or injury to any goods
or articles whatsoever arising from the felonious acts of any
coachman, guard, bookkeeper, porter, or other servant in his
employ.” And I am of the opinion that this liability cannot be
disposed of by the introduction of the term ‘agent’, or by giving a
principal name to the employment of any one employed to discharge
the duty undertaken by the carrier. In the case which was put in the
course of the argument, where a carrier confines himself to receiving
goods and making contracts for their carriage, and avails himself of a
sub-contract to transfer to some one else the whole duty which he has
undertaken to perform, I think that all the parties who come in under
that subsequent contract, whether directly or by the sub-contract – I
think that all the parties actually employed in doing the work which
the carrier undertook to do, either by himself or by his servants, are
his servants within the meaning of the 8th section of the act in
-- 17 of 19 --
18
question. I therefore think that, within the meaning of this section,
Chaplin and Horne were the servants of the Company; they were
employed by the company to take these goods from the railway
station, and to deliver them in Bunhill-row; and that any persons
whom Chaplin and Horne employ for the same purpose are also
servants of the Company for that purpose, within the meaning of the
act. Although the Company could not dismiss the partners, inasmuch
as the contract was made between those parties and Chaplin and
Horne, and not with the Company, yet substantially they were
servants in the employ of the Company, as doing what the Company
had engaged to do. On the general question, therefore, which turns
upon the proper construction of the act of Parliament, seeing, as I do,
that this Railway Company received these goods upon an
undertaking to carry them, and to deliver them in Bunhill-row, I
think that everything done with respect to the carriage of the goods is
to be considered as done by the servants employed by the Company,
and that the substitution of any other words, such as ‘agent” or “sub-
contract”, cannot have the effect of taking them out of the meaning
of the act.”
Mr. Gynther claimed further support from the Privy Council decision in Port
Jackson Stevedoring Pty Ltd v. Salmond & Spraggon (Aust) Pty Ltd (1980) 144
CLR 300, at 309 (and the decision of the High Court of Australia in the same case:
(1978) 139 CLR 23).
[22] His argument was broadened to bring in bailment cases more broadly. He cited
Palmer on Bailment (2nd ) at 1346-1348. He also made particular reference to what
Windeyer J said in Hobbs v. Petersham Transport Co Pty Ltd (1971) 124 CLR 220,
at 242-43:
“Although the Hobbs brothers were independent contractors, the
defendant is, by well-established common law rules, liable for their
negligence in relation to the carriage of the plaintiff’s goods. That is
because the defendant impliedly promised the plaintiff that the goods
would be carried to their destination with due care. If it procured
someone else to perform the carriage for it, it became liable for his,
the sub-contractor’s negligence: Doolan v. Midland railway Co. (1);
John v. Bacon (2); Machu v. London and South-Western Railway Co
(3). The rationale of this may be debatable. But I think that
Professor Atiyah, who discussed it in his book Vicarious Liability in
the Law of Torts (1967) (at pp. 361-362), rightly describes it as a
form of vicarious liability. In Riverstone Meat Co Pty Ltd v.
-- 18 of 19 --
19
Lancashire Shipping Co Ltd (4) Lord Radcliffe spoke of it as ‘the
carrier’s responsibility for the diligence of all those whom he
employs to discharge his own primary duty’. I think therefore that
the plaintiff would be entitled to recover damages from the defendant
if it proved that the accident occurred by negligence for which the
Hobbs brothers were responsible either because their vehicle was
negligently driven, or because there had been negligence in
maintaining it so that it was not in a serviceable condition. But to
establish liability on the part of the defendant it would be necessary
for the plaintiff to prove this negligence. The onus was on it. It
could not found its case on the onus that a bailee has; for the
defendant was not a bailee. It could claim that the fact that the
vehicle ran off the road spoke for itself of negligence, and called for
an explanation. But the explanation of the accident in a broken axle
left it upon the plaintiff to prove that this was the result of
negligence. The mere fact that the mechanism of a vehicle fails does
not itself show that the owner or driver was negligent. No doubt a
failure to maintain a vehicle in good order may in some cases amount
to negligence.”
[23] Again, if my interpretation of the Hague Rules is correct, the defence pleaded in
para. 11.3.3 cannot succeed. It does not matter what control the defendant may
have had over Crocodile Lines. For purposes of those Rules, Crocodile Lines was
its servant or agent. Mr. Gynther is correct that it does not matter which. It may be
noted that notwithstanding the apparent reference in para. 9 of the amended defence
to a stevedore in Port Moresby, it is only against Crocodile Lines that the defendant
has begun to prosecute any claim. It seems somewhat ironic that if it was the
stevedore which was negligent or otherwise in breach of its duty, the defendant
apparently contends that Crocodile Lines bears the responsibility!
[24] Paragraph 11.3.3 should be struck out, along with para. 12A in the amended defence
and the defendant should be ordered to pay the plaintiff’s costs of the application to
be assessed.
-- 19 of 19 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2002/366