Aqua Blue (Noosa) Pty Ltd v Noosa Shire Council [2002] QPEC 42 [2003] 1 QPELR 83
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Aqua Blue (Noosa) Pty Ltd v Noosa Shire Council [2002]
QPEC 42
PARTIES: AQUA BLUE (NOOSA) PTY LTD
Applicant
and
NOOSA SHIRE COUNCIL
Respondent
FILE NO/S: 5866 of 2001
DIVISION: Planning and Environment
PROCEEDING: Application
ORIGINATING
COURT: Brisbane
DELIVERED ON: 24 July 2002
DELIVERED AT: Brisbane
HEARING DATE: 11 February 2002
JUDGE: Alan Wilson SC, DCJ
ORDER: Declare that the erection of a building on the land the
subject of the approval in respect of which the respondent
issued TPC 2645 on 1 July 1997 was commenced (within
the meaning of that term where appearing in LGPEA s
4.13(18) prior to 1 July 2001, and that TPC has not lapsed
within the meaning of that section.
CATCHWORDS: PLANNING AND ENVIRONMENT – Lapsing of
development permit under Local Government (Planning and
Environment) Act 1990, s 4.13(18) –whether variation in
conditions of approval prevents lapse – whether Integrated
Planning Act s3.5.21 applies where original approval issued
under former Act, but conditions of approval varied by order
after new Act in force
PLANNING AND ENVIRONMENT – whether applicant
had commenced work under a development permit sufficient
to prevent permit lapsing under Local Government (Planning
and Environment) Act 1990, s 4.13(18) – meaning of ‘erect’
and ‘erection of a building’ in s1.4 and s 4.13(18)
Local Government (Planning and Environment) Act 1990, s
1.4, 4.13(18)
-- 1 of 14 --
2
Integrated Planning Act 1997, s 3.5.21
Friends of Stradbroke Island Association Inc v Kennedy &
Ors (1999) QPELR 117
McRoss Development Pty Ltd v Douglas Shire Council
(2001) QPELR 98
BCC v Micalizzi (2000) QPELR 354 at 356B
COUNSEL: Mr C L Hughes SC for the applicant
Mr M Hinson SC for the respondent
SOLICITORS: Phillips Fox for the applicant
Wakefield Sykes for the respondent
[1] The applicant seeks declarations and consequential orders about the currency of a
development approval in respect of land situated at 94 Noosa Drive, Noosa Heads.
The relief sought is as follows:
“1. A declaration that upon a proper construction of the provisions of the
Integrated Planning Act 1997 (“the Act”), the Applicant’s right to develop land
situated at 94 Noosa Drive, Noosa Heads in the State of Queensland, more fully
described as Lot 2 on Surfers Paradise 110327, Parish of Weyba (“the subject
land”), in accordance with the Development Permit granted by Order of the Court
on 10 November, 1999, authorising assessable development to the extent stated in
that Order, and subject to those modified conditions forming part of that Order,
will not lapse until 10 November 2003;
2. An order that the standard Planning and Development Certificate dated 22
November, 2001, issued by the Respondent, be set aside and the Respondent issue
a fresh Certificate including, within the list of Decision Notices for Development
Approvals for the land which have not lapsed, reference to the said Development
Permit granted by Order of the Court on 10 November 1999;
3. Alternatively, if necessary, a declaration that the use of the subject land for the
use or erection of a building or other structure on the land, subject to the approval
in respect of which Town Planning Consent Permit No. 2645 was issued by the
Respondent on 1 July 1997, was ‘commenced’ (within the meaning of that term
where it appears in section 4.13(18) of the Local Government (Planning and
Environment) Act 1990 (‘the repealed Act’), prior to 30 June 2001;
4. Alternatively, if necessary, orders and directions to facilitate an application by
the Applicant for an extension of the period of Town Planning Consent Permit No.
2645 up to, and including, 10 November 2003 (or such other date as the Court
determines appropriate);
5. Such further or other order as the Court deems meet to facilitate the timely
development of the subject land in accordance with the Order of this Court made
on 10 November 1999.”
There is no doubt the Court has power to make declarations, and orders providing
ancillary relief: Integrated Planning Act 1997 (IPA) s 4.1.21; and, see McGrath
“Planning and Environment Courts Declaratory Powers” (2002) 22 Qld Lawyer
147.
-- 2 of 14 --
3
Relevant History
[2] The land is the balance of a parcel formerly described as Lot 2 on MCH 2618,
Parish of Weyba which was rezoned to the Special Facilities (Resort
Accommodation and Ancillary facilities) zone, Special purposes (Tourist facilities)
zone and Open Space zone by Order in Council published in the Government
Gazette on 25 October 1986. In 1993 a previous owner applied to the respondent
Council under s 4.12 of the Local Government (Planning & Environment) Act 1990
(LGPEA) for a permit to use the land for the erection of multiple dwellings (276
units) and associated facilities (administration, shop, restaurant and recreation
facilities). The application was subsequently approved but the owner appealed to
this Court (425/1995) against several conditions attached to the approval. On 19
June 1997 his Honour Judge Quirk allowed the appeal and approved the application,
subject to some revised conditions.
[3] On 1 July 1997 the respondent issued Town Planning Consent Permit No. 2645
(TPC 2645) setting out those conditions, as it was required to do under LGPEA s
4.13(12). In November 1998 the original Lot 2 was fully cancelled by a new plan
SP 110327 creating new Lots 1 and 2. Lot 1 was transferred by the owner at the
time to the respondent and dedicated as public parkland, at no cost to the respondent
(pursuant to a condition imposed in TPC 2645). The balance, comprising 5.844
hectares, was acquired by this applicant in that month, November 1998.
[4] In May 1999 this applicant applied under the Integrated Planning Act (IPA) s 3.5.33
to change the development proposal by altering the intensity of the development,
and to permit construction of it in three stages. On 10 July 1999 his Honour Judge
Quirk was persuaded the original conditions should be altered, and the matter was
adjourned to permit the parties to reach agreement about them. The major effect of
the changes was to reduce “population density” from 518 to 409 persons; and,
commensurately, to reduce the gross floor area of the development, and car parking
spaces.
[5] On 10 August 1999 his Honour made appropriate orders, agreed by the parties,
altering the conditions. Subsequently, however, work on the site indicated other
changes were necessary and in a further proceeding before his Honour on 10
-- 3 of 14 --
4
November 1999 an order was made which again altered the conditions. That order
shows on its face that it referred back to the previous application under IPA s 3.5.33
and that the applicant sought to change the conditions “imposed on a town planning
consent permit issued pursuant to an order of this Court given on 10 August 1999”.
[6] On 24 October 2001 the applicant’s solicitors asked the respondent to issue a
standard planning and development certificate under IPA s 5.7.10, for the purpose of
obtaining “a copy of every decision notice or negotiated decision notice for a
development approval that has not lapsed”. By letter 21 November 2001 the
respondent sent that certificate and advised that “development permit TPC 2645 is
not mentioned within that document as it is considered to have lapsed on 30 June
2001”.
[7] Under LGPEA s 4.13(18) a permit lapsed where the use of land or the use or
erection of a building or other structure had not been commenced within four years
of the date of issue of the permit, or such extended period as the Council (upon
application made to it) approved. The applicant contends, however, that its right to
develop the land only crystallised with the last order of Quirk DCJ of 10 November
1999, which set the lapsing period running again so it does not, now, expire until
2003; or, that it has commenced work which comprises “the use of the land or the
use or erection of a building or other structure on land”, since 1997, sufficient to
prevent lapse.
Does the four year Lapsing Period begin to run in 1997, or 1999?
[8] Essentially, the dispute concerns the question whether a development permit issued
under LGPEA, which has its conditions subsequently varied by a Court applying the
IPA legislation is, by that process, re-enlivened (for the purpose of lapsing
provisions) so that time in respect of it begins to run anew.
[9] TPC 2645 was issued by the respondent Council on 1 July 1997 under LGPEA s
4.13(12) which provides that, in respect of an applicant for consent which has been
determined by the Court after the hearing of an appeal (as occurred here), the
respondent’s chief executive officer must forthwith issue a Town Planning Consent
permit. That permit, and not the Court’s approval of the application for it, was the
-- 4 of 14 --
5
source of the entitlement under LGPEA to use this land for multiple dwellings, and
ancillary facilities: ss 4.12(1), 4.13(12), (16), and (17). Under 4.13(16) the permit
continued in force until (relevantly, here) it lapsed in accordance with s 4.13(18),
i.e. where the use of the land or the use or erection of a building had not been
commenced within four years “of the date of issue of the permit”, or such extended
period as the respondent, upon application made to it, approved. (No application for
an extension was ever made.)
[10] The procedure under IPA is quite different. Under s 3.1.5 a “development permit” is
required to authorise assessable development to occur. Under Schedule 10 a
“development approval” is defined as a decision notice, or a negotiated decision
notice that, e.g., approves development applied for in a development application.
[11] When an application is made to an assessment manager, the manager is required to
issue a decision notice under s 3.5.15, and that notice is taken to be a “development
approval” under s 3.5.19. In the case of an appeal to the Court against approval, or
the conditions attached to approval, the development approval takes effect when the
appeal is finally decided and notice of the decision is given to the assessment
manager: IPA, s 3.5.53(9).
[12] The LGPEA was repealed, and IPA commenced, on 30 March 1998. Under IPA s
6.1.23(1)(b) the “permit” comprised of TPC 2645 was a “continuing approval” and,
by s 6.1.23(2) had effect, despite the repeal of the LGPEA, as if it were a
development permit. Under s 6.1.23(3), however, the continuing approval of the
original permit had effect “…only for the period the continuing approval would
have had effect if the repealed Act (LGPEA) had not been repealed”.
[13] After 30 March 1998 it was not possible to apply under the LGPEA to modify the
original permit, or any condition attached to it. Any changes sought to be made had
to be brought under IPA s 3.5.33 to “…the entity that decided the condition or
required the condition to be imposed on or attached to the approval…”. This Court
was the “entity” which imposed the conditions in 1997 which, in turn, lead to the
issue, by the respondent, of TPC 2645 under LGPEA s 4.1.3(12). Hence, when
-- 5 of 14 --
6
application was made in 1999 to change the conditions, it was properly made to the
Court as the appropriate entity under IPA s 3.5.33(2).
[14] The applicant posits that the order of 10 November 1999 was, in effect, a
“development permit” which, under IPA s 3.5.21 would not lapse until 10 November
2003. On its face, however, that section deals with a “development approval” as
defined in Sch 10, meaning a decision notice, or negotiated decision notice. A
“decision notice” is a notice given under s 3.5.15 (and a “negotiated decision
notice” is one given under s 3.5.17(2)). In both cases they are notices given by an
“assessment manager” recording the decision made on a development application.
The Court is not, however, an assessment manager. When an application is made
under IPA s 3.5.33 to vary conditions, the Court’s decision is not, and cannot be, a
development permit; rather, it is merely a decision to change, or cancel a condition.
The Court was required, under s 3.5.33(9) to give the assessment manager (the
respondent) written notice of the change or cancellation.
[15] The applicant argues that the order of 10 November 1999 was both a development
approval under IPA s 3.5.21, and Schedule 10, and a “development permit” for the
purposes of IPA, vis-a-vis the former legislation. The applicant had no right, it is
said, to develop this land in accordance with the present plans until the order of 10
November 1999 and it was not until that “development approval” that the
applicant’s rights to develop in the new form crystallised, at which point time
should properly begin to run afresh; or, in other words, an entirely new
“development approval” issued, under IPA, with a new four lapsing period so that,
in effect, the original 1997 permit became entirely redundant, and irrelevant. The
argument ignores, I think, the fact that nothing in the IPA legislation suggests the
underlying approval contained in the development permit of 1997, or the conditions
attached to it, is subsumed in that way.
[16] The applicant relies upon McRoss Development Pty Ltd v Douglas Shire Council
(2001) QPELR 98, in which a town planning consent had issued in October 1994
for multiple dwelling units and associated facilities, followed by a permit under the
LGPEA. In 1996 the applicant sought to have the approval modified and the
respondent consented, but failed to issue a new permit for that modified approval, as
-- 6 of 14 --
7
required under LGPEA s 4.15(14). The respondent council contended, in the
proceedings which ultimately came before his Honour Judge Quirk on 23 August
2000, that the applicant’s right to develop the land in accordance with the modified
approval had lapsed pursuant to s 4.13(18) because the four year period commenced
to run when the original approval was given in 1994; but his Honour held that the
permit under s 4.15(14) was a necessary pre-requisite to the applicant’s right to
develop the land in accordance with the modified approval which could not, then,
have been exercised until that permit issued, so the lapsing period would not
commence to run until that occurred.
[17] Here, the position is quite different: this applicant’s right to develop the land
certainly came into existence on 1 July 1997 when TPC 2645 issued. After the
promulgation of IPA on 30 March 1998, that permit had continued force and effect,
and later changes to the conditions attached to it took effect from the day written
notice of the decision was given. IPA contains no provision corresponding to s
4.15(14), LGPEA. Further, all of these events occurred before IPA commenced and,
as Quirk DCJ points out at para 7 of the judgment, continued to be governed by the
former Act: IPA, s 6.1.25. The failure to issue the permit meant the outcome of the
application to modify had no force and effect. It was to that failure his Honour was
referring when he said:
“The modified approval involves a new package of rights which must be identified
in the relevant permit. No right to develop the land in accordance with the
modified approval could be exercised until the permit for the modified approval
had issued.”
This applicant’s reliance upon that passage here is, with respect, misconceived. The
proceedings before this Court in 1999 did not create a new “development approval”
under the IPA legislation, but simply varied the conditions of the original permit
under the former Act. The permit is the source of rights under the LGPEA: s
4.13(16). Under that section, where conditions are imposed the right created by the
permit is subject to them, or any modifications of them. Neither under LGPEA s
4.15, or IPA s 3.5.33 does a change in the conditions create a new right. Rather, the
change simply alters the terms upon which the right which derives from the permit
may be exercised.
-- 7 of 14 --
8
[18] The order made on 10 November 1999 might have contributed to the applicant’s
misconception of the position. It was ordered, first, that the application to change
the conditions be permitted; then, the following appears:
“It is further ordered that the subject application for Town Planning Consent be
approved…”
At the time there was no application for town planning consent before the Court but,
simply, a request under IPA s 3.5.33 to change conditions. No adverse consequence
flows but, as Mr Hinson SC submitted and I agree, the order in that respect went
further than was necessary, and further than lay within the Court’s jurisdiction.
[19] For the applicant, it is also contended that order was in effect an “appeal decision”
under IPA s 4.1.54 which provides, relevantly, that in deciding an appeal the Court
may make the orders and directions it considers appropriate including orders which
change the decision appealed against and which become, under s 4.1.54(3) the
decision of the “entity” referred to in s 3.5.33. The 1999 proceedings did not,
however, involve an appeal and his Honour Judge Quirk was not exercising
appellate jurisdiction but rather, original jurisdiction under s 3.5.33. The distinction
can be illustrated by example: had the respondent been the entity to which a request
to change or cancel conditions been made under s 3.5.33 and refused it, the
applicant might have appealed to this Court (under s 4.1.31) and in those
circumstances s 4.1.54(3) would have applied to the ultimate decision; but the 1999
application did not involve an appeal but, rather, an application clearly made under s
3.5.33.
[20] In summary, the applications in 1999 and the orders made in them involved no more
than a request to change conditions under IPA s 3.5.33, with the effect that the terms
upon which the rights arising under the original 1997 permit might be exercised
were changed; but, that right always remained one to develop the land for the use
which was originally approved (in this case, multiple dwellings and ancillary
facilities). That right continued with, simply, alterations to its conditions about
format and layout, etc. after the 1999 orders. No new right or “development
approval” was created by them.
Was the ‘use of the land or the use or erection of a building or other structure…
-- 8 of 14 --
9
commenced within four years’ of 1 July 1997 ?
[21] The applicant argues, in the alternative, that within the four year period after it was
granted TPC 2645 it undertook sufficient work on the land, referrable to the
development permit, to enable it to escape the proscription in LGPEA s 4.13 (18),
which provides:
“(18) A permit issued pursuant to subsection (12) lapses where –
(a) the use of the land or the use or erection of a building or other structure
on land, the subject of the approval in respect of which the permit was
issued, has not been commenced within 4 years of the date of issue of the
permit …”
[22] It is not in dispute that because, as I have found, the rights which govern this
development are based in the original permit issued on 1 July 1997, the question is
to be decided by reference to the former legislation: LGPEA s 6.1.23 (3); Acts
Interpretation Act, s 20; and, see BCC v Micalizzi (2000) QPELR 354 at 356B.
[23] In Micalizzi a town planning consent issued to the respondent on 24 January 1995
for the erection of a building on land at Ascot. On 15 January 1999, just within the
four year period, the respondent’s architects received a building approval. The issue
of that approval had been preceded, as his Honour Judge Brabazon QC found, by
activity on the part of architects and engineers retained by the respondent to
construct the building – soil testing and the provision of a report about it; and, the
preparation of architectural and engineering drawings, also provided to the Council
which, nevertheless, contended nothing had been done sufficient to avoid the effect
of s 4.13(18). In reasons which I respectfully adopt, his Honour said at 353E –
354G:
“The result is that it is only necessary that something described within
subs.(18)((a) must commence within the four years. In this case it can be seen that
it is critical to see whether or not there has been such a commencement before the
expiry of four years which took place at midnight on 24 January 1999.
There are a number of considerations that might be kept in mind. First of all, as
mentioned in The Friends of Stradbroke Island case subs.4.13(18)(a) requires that
there be a complete absence of commencement of any activity authorised by a
permit within four years before the permit lapses.
Secondly, as one can see from the decision in the High Court of Australia in
Owendale Pty Ltd v. Anthony and Another 117 C.L.R. 539, there is no need for
substantial work over a long period of time to have commenced.
In that case, a few hours work done on the day before the expiration of a notice
was sufficient where there was a requirement that a lessee had to “commence to
erect” a building within a prescribed period. Similar considerations apply here.
-- 9 of 14 --
10
Also to the same effect are the views of Professor Fogg of the University of
Queensland, writing in his Study Guide No. 7 at p.13. The situation here can be
contrasted where there is a requirement that work “substantially starts:. That was
the position, in effect, under the former Local Government Act which required that
“substantial progress” had to be made (see s.33(16D)(b)(i)(A))). With the adoption
of that standard in the Integrated Planning Act the wheel has turned full circle, but
that difference must be kept in mind in considering the provision under the
Planning and Environment Act.
Attention has to be paid to the decision of Connolly J in Dackfield (1983) Q.R.
p.10. There, some general propositions were drawn from the established cases, but
it should be kept in mind that they were dealing with a test of substantial
commencement. In that case, Connolly J’s fourth proposition was to the effect
that:
‘Where a provision called for substantial commencement of the work
within a specified time, the work concerned is that to which the approval
itself refers and work would not be commenced when nothing more had
been done than acts preparatory tot he work the subject of the approval.’
Connolly J relied on the decision of the High Court of Australia in Drummoyne
Municipal Council v. Lebnan (1974) 131 C.L.R. 350 at 360 in deriving that fourth
proposition. If one reads that decision of the High Court of Australia, it can be
seen that the definition of ‘building work’ led to a probable conclusion that
preparatory demolition work was not included. However, Gibbs J at p.360 went on
to say that excavation work would be included within the work allowed under the
permit.
It is interesting to take into account the definition which is relevant in this case in
s.1.4 of the Planning and Environment Act. The word ‘erect’ includes:
‘(a) erect or commence or continue to erect; or
(b) do or commence or continue to do any work in the
course of or for the purpose of erecting.’
That definition with its inclusion of work which is done for the purpose of erecting
is wider than that considered by the High Court in Lebnan’s case.
In the present case, work was actually done on this land before the expiry of the
four years. The soil testing by the engineers was actually done before the approval
was issued. Then, after the approval was issued, some demolition work was
carried out. The town planning consent approval itself had a condition that
required all existing buildings and structures to be removed from the land before
any building work was commenced. Some of that demolition was achieved before
the expiry of the four years, that is, a laundry was demolished and a garage was
demolished. Then a trench about five metres long, half a metre wide and half a
metre deep was excavated on the alignment of the rear footing of the project, as
shown on the engineering drawings. That trench was excavated for the ultimate
purpose of using it for the footings designed for the southern wall of the project. A
safety fence was erected around the trench for the safety of the occupants of the
house not then demolished. The trench was inspected by the consulting engineer
to determine its adequacy in view of the soil conditions that had been earlier found.
In my opinion, that work collectively amounts to a commencement before the
expiry date.
I should say that, in taking the view the demolition work is included within work
done under the town planning consent, not only have I referred to the definition of
the word ‘erect’ but also the decision of the House of Lords in London County
Council v Marks and Spencer Limited (1953) Appeal cases at 535. There, in a
statutory requirement which spoke of ‘the erection or alteration of a building has
been begun but not completed before the appointed day’, it was held that it was not
-- 10 of 14 --
11
necessary that work of a constructional nature was done before the expiry of the
time. It was sufficient if demolition for the purpose to enabling construction to be
done was carried out. The same considerations apply here.
Therefore it follows that commencement of the erection of a building within the
meaning of s.4.13(18) of the Planning and Environment Act had been done. The
consequence is that the permit did not expire at midnight on 24 January 1999.”
[24] It follows the applicant need merely establish, under the LGPEA definition of
‘erect’, (s 1.4) that it has commenced to erect a building or structure or performed,
or commenced to perform, work ‘in the course of or for the purpose of erecting’.
[25] The applicants material shows that, in the relevant four years 1 July 1997 to 2001, it
expended almost $1m on consultants’ fees (architects; civil, structural, hydraulic,
and water and water quality engineers; and licenced, quantity, and soil surveyors);
bank charges ( in respect of guarantees lodged with the respondent Council);
application fees paid to the Council; and, external roadworks contributions. In
exhibit 6, the applicant tabulated this expenditure and the various events, including
the issue of subsequent necessary approvals by the Council for such matters as
landscaping, sewerage and associated works, bulk earthworks, and building,
associated with it. Of interest is the fact that the Council issued a Decision Notice
approving building work in March 2000 which does not, on its face, expire until 16
March 2003. Exhibit 8 is a series of photographs showing survey markers, tree
numbering, trees marked with ribbons and, perhaps, a bore hole (the photos are not
of good quality); but, in any event, some obvious, clearing work undertaken in
connection with them.
[26] The affidavit of Linda Gaye Morris filed 10 December 2001 exhibits these
approvals for the various works, and the documents the applicant provided to obtain
them. They reveal a considerable amount of work undertaken to identify, mark and
map trees on the site; dig bore holes and take soil samples, and analyse them; survey
the site and, generally, perform tasks which had no apparent purpose other than to
progress the development of the site. It is helpful to set out parts of the table in
Exhibit 6 summarising steps taken in the period 1997 – 2000:
“06 05 99 Applicant submits two (2) trading bank guarantees totalling
$200,000 (pursuant to condition 43 of TPC 2645)
24 05 99 Applicant obtains P & E Court to change development
proposal, pursuant to section 3.5.33 of IPA
-- 11 of 14 --
12
10 08 99 Applicant obtains P & E Cuort order allowing changes to
conditions imposed by previous Court Order to permit a
different development proposal comprising multiple dwellings
(149 units) and ancillary facilities (conference centre,
restaurant, shop and recreation facilities), subject to conditions
10 11 99 Applicant obtains further P & E Court order changing
conditions imposed on the new development approval
15 11 99 Applicant obtains Council issued Decision Notice approving
application for operational works (access roads, filling)
22 12 99 Applicant enters agreement with Council and Thannhauser (re
construction of roundabout at intersection of Noosa Drive
and Leslie Drive)
04 01 00 Applicant obtains Council issued Negotiated Decision Notice
approving application for lot reconfiguration (reciprocal
easements and new road)
08 02 00 Applicant obtains Council issued Decision Notice approving
application for operational works (landscaping)
18 02 00 Applicant obtains Council issued Decision Notice approving
application for operational works (sewerage, pump station,
rising main)
09 03 00 Applicant obtains Council issued Decision Notice approving
application for operational works (bulk earthworks)
10 03 00 Applicant obtains Council issued Decision Notice approving
application for operational works (civil works)
16 03 00 Applicant obtains Council issued Decision Notice approving
building work (N.B. Expires 16 March 2003)
30 08 00 Applicant pays Council external roadworks contribution of
$140,908.00
15 09 00 Applicant submits bank guarantee for water supply and
sewerage headworks of $889,295.00
11 10 00 Applicant submits supplementary bank guarantee for
headworks of $168,516.00”
[27] Other exhibits corroborate the claim that, in preparing such things as the application
for bulk earthworks approval (Morris affidavit, exhibit 16) and an environmental
management plan, a large amount of work was undertaken on the site, and in the
preparation of reports and documents, in the way of geotechnical investigations and
the like. All the exhibits to the Morris affidavit are in total about 8cm thick, and
speak eloquently, I think, in support of the notion the applicant has not been sitting
on its hands.
-- 12 of 14 --
13
[28] For the respondent Council Mr Hinson SC argued the extended definition of ‘erect’
in LGPEA s 1.4 does not assist the applicant because it must envisage, at least, some
actual physical work on the land referrable to a building or structure – eg, the
demolition of existing structures, or the digging of trenches for foundations, etc (as
in Micalizzi (supra)). It is not apt, he submitted, to include work which, even if
extensive, does not alter or adapt the land in some way relevantly connected with
the erection of a building; and in the context of the definition, ‘work’ must involve
the exertion of manual or mechanical labour which is directed toward the
construction of a building – and, not the physical or mental labour involved in
merely securing authorisation legally required for construction to occur. Each of the
cases examined by Brabazon QC, DCJ involved, at least, demolition work or
something like a trench which was obviously related to a building. Each, of course,
also turns on the wording of the statute governing the circumstances arising in it.
None, in my opinion, establish a principle of the kind contended for by the
respondent; and, here, the statute sets a test which is, on its face, extraordinarily
light and very easy to satisfy.
[29] In Micalizzi Brabazon QC, DCJ affirmed s 4.13(18) is couched in terms that require
there be a complete absence of commencement of any activity authorised by a
permit within the four year period – a view which, in my respectful opinion, is
entirely in accord with the clear meaning and intent of that section read, as it must
be, in conjunction with the definition of ‘erect’ in s1.4. Plainly, the fact that the
recipient of a permit for development need do no more than ‘commence…any work
in the course of or for the purpose of erecting…’ (my underlining) does not impose
a requirement that, for example, a certain number of sods be turned, or a hole of
certain proportions be dug. Any work for the purpose of erecting must, in my view,
include almost any undertaking in the way of labour, mental or physical, which
bears a clear connection to the eventual construction of the approved development.
The section was designed to catch those who, having obtained approval, did
nothing. Its apparent leniency, and the lightness of the burden it imposed is now,
largely, of historical interest: IPA contains a much more stringent requirement that
work ‘substantially starts’.
[30] In this case the work performed by the applicant’s various professional agents could
have no purpose save one directed toward the aim of developing the project
-- 13 of 14 --
14
approved in 1997, and varied in 1999. Mr Hinson SC made the further points that
the applicant’s evidence did not show any specific work referrable to building since
the building permit issued in March 2000, and that much of the investigation and
reporting relied upon was preparatory to the submission of material to support the
application for that permit, but neither seems to me to detract from the fact the work
was obviously performed in the course, and for the purpose, of erecting the
approved structures.
[31] I declare that the erection of a building on the land the subject of the approval in
respect of which the respondent issued TPC 2645 on 1 July 1997 was commenced
(within the meaning of that term where appearing in LGPEA s 4.13(18) prior to 1
July 2001, and that TPC has not lapsed within the meaning of that section.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2002/042