Clyde Contractors Pty Ltd v Northern Beaches Developments Pty Ltd [2001] QCA 314
SUPREME COURT OF QUEENSLAND
CITATION: Clyde Contractors P/L v Northern Beaches Dev. P/L
[2001] QCA 314
PARTIES: CLYDE CONTRACTORS PTY LTD T/A CLYDE
CONSTRUCTIONS ACN 060 294 975
(plaintiff/respondent)
v
NORTHERN BEACHES DEVELOPMENTS PTY LTD
ACN 052 996 371
(defendant/appellant)
FILE NO/S: Appeal No 7741 of 2000
DC No 71 of 2000
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
Application for Security for Costs
ORIGINATING
COURT:
District Court at Mackay
DELIVERED ON: 7 August 2001
DELIVERED AT: Brisbane
HEARING DATE: 19 July 2001
JUDGES: McMurdo P, Williams JA, Philippides J
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made.
ORDER: 1. Appeal dismissed
2. Application for security for costs dismissed
3. Order that the appellant pay the respondent’s costs of
and incidental to the appeal and the application for
security for costs to be assessed
CATCHWORDS: CONTRACTS – BUILDING ENGINEERING AND
RELATED CONTRACTS – PERFORMANCE OF WORK –
EFFECT OF ACCEPTANCE OR CERTIFICATE OF
PAYMENT ON RIGHTS OF OWNER – whether or not
practical completion had been achieved, and if so at what
time – where letter issued by superintendent stated that
practical completion had been reached – whether respondent
entitled to return of retention moneys
CONTRACTS – BUILDING ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT -
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – OTHER MATTERS - definition
of “practical completion”
-- 1 of 6 --
2
COUNSEL: A J Moon for the appellant
D V C McMeekin SC for the respondent
SOLICITORS: Deacons as town agents for Suthers Taylor Lawyers
(Townsville) for the appellant
Swanwick Murray Roche Lawyers (Rockhampton) for the
respondent
[1] McMURDO P: I agree with the reasons for judgment of Williams JA and with the
orders he proposes.
[2] WILLIAMS JA: The respondent/plaintiff entered into a contract with the
appellant/defendant pursuant to which the respondent was to carry out certain work
(earthworks, roadworks, drainage, water supply, and sewerage reticulation) with
respect to a land development for the appellant. General Conditions of Contract
AS2124-1992 (as amended) formed part of the contractual documents.
[3] The respondent claims that a stage of practical completion had been achieved on
22 March 1999, and that the appellant failed, in accordance with its contractual
obligations, to pay monies owing to it. Proceedings were commenced by the
respondent in the District Court seeking to recover two separate liquidated sums:
(i) $14,535 being the shortfall between the total of progress
payment certificates issued by the superintendent appointed
pursuant to the contract and the amount actually paid by the
appellant;
(ii) $35,670 being retention monies to be released in accordance
with the terms of the contract at the expiration of the defects
liability period which ran for 12 months from the date of
practical completion.
[4] Both the statement of claim and defence and counterclaim particularised progress
payment certificates totalling $790,837, and actual payments by the appellant of
$776,302. But the appellant denied that the balance, namely $14,535, was owing to
the respondent. No basis for that denial was alleged in the pleading. Further, the
defence admitted that the appellant was holding $35,670 as retention money, and
inferentially asserted that it had not been paid because the defects liability period
had not expired.
[5] The appellant counterclaimed against the respondent for liquidated damages on the
basis that practical completion had not been achieved; it claimed a right to
liquidated damages at the rate of $200 per day from 16 March 1999. The
counterclaim also sought $6,420.50 from the respondent on the basis that the
respondent had failed to carry out turfing and landscaping work as required.
[6] There was no allegation in the defence and counterclaim that the appellant was
entitled to set-off any amounts it owed the respondent (for example, the $14,535)
against the amount of its counterclaim.
[7] Against that background the respondent applied for summary judgment with respect
to each of the amounts it claimed, and also for summary dismissal of the appellant's
counterclaim. The learned District Court judge hearing that application gave
judgment for the respondent for $14,535 and $35,670 with interest, and also
-- 2 of 6 --
3
ordered that the counterclaim be dismissed. From that decision the appellant has
appealed to this Court.
[8] Counsel for the appellant conceded that, given the terms of the contract, the
appellant had no defence with respect to the respondent's claim for $14,535. In
accordance with the progress certificate and cl 42.1 of the general conditions that
amount was due and payable. All that counsel for the appellant could say with
respect to that amount was that, if the appellant had a viable claim for liquidated
damages, then (providing the defence and counterclaim was amended to allege an
entitlement to a set-off) the sum of $14,535 could be set off against such liquidated
damages.
[9] Counsel for the appellant also conceded that there was no foundation for the
appellant's claim for $6,420.50. Though there had been some mention in
pre-contractual documents of turfing and landscaping work, it is clear that such
work had been deleted prior to the acceptance of the respondent's tender. The
contractual documents and correspondence from the superintendent (all of which
were before the District Court judge on the hearing of the summary judgment
application) clearly established that the turfing and landscaping was the
responsibility of the appellant.
[10] The respondent's claim with respect to the $35,670 retention monies, and the
appellant's claim for liquidated damages were each dependent on whether or not
(and if so, when) a stage of practical completion had been achieved. The critical
letter is that of 19 May 1999 from the superintendent appointed in accordance with
the contractual provisions to the respondent; a copy thereof was also sent by the
superintendent to the appellant. That letter dealt with an application by the
respondent for an extension of time, primarily because of weather conditions. That
letter confirmed a grant by the superintendent of a total extension of time of 56 days
which took the date for practical completion to 16 March 1999. The letter then
went on, significantly for present purposes, to state:
"However in this instance we consider the works to have reached
practical completion on 22 March 1999 and as such practical
completion was reached 4 days beyond the revised date of practical
completion".
[11] That was followed by a letter the following day, 20 May 1999, from the
superintendent to the respondent which relevantly stated:
"Please find herewith Progress Certificate No 6 in the amount of
$10,234 for works completed to 30 April 1999.
The project is nearing completion and money is being withheld now
only on items 1.2, 1.3, 2.6, 2.10, 3.10, 3.12(b), 3.13, 4.6 and 4.7. In
addition the development is considered to have reached practical
completion and as such the security being held in the form of a bank
guarantee for $35,670 is attached. Also attached is a previously
submitted bank guarantee for $35,670 for retention, as retention is
now being withheld as cash".
In other words, on two separate occasions in May 1999 the superintendent informed
the respondent that a stage of practical completion had been reached. Further, the
superintendent returned bank security, undoubtedly on the basis that as a stage of
practical completion had been reached cash retention was adequate. Because the
-- 3 of 6 --
4
first letter (at least) was also forwarded to the appellant, it is clear that the appellant
was aware in May 1999 that the superintendent was asserting that a stage of
practical completion had been reached.
[12] The contract does not provide a specific form for a certificate of practical
completion, but in the absence of any evidence to the contrary the clear statement in
the letters of 19 and 20 May 1999 establishes that practical completion was reached
on 22 March 1999.
[13] In a letter dated 8 September 1999 the solicitor for the appellant wrote to the
respondent (in reply to a letter invoking certain contractual provisions applicable
where the appellant was in default of making a payment due pursuant to the
contract) stating that "our client is firmly of the belief that practical completion has
not yet occurred and accordingly we have advised our client that the liquidated
damages clause therefore applies". But significantly neither the appellant, nor its
solicitor then raised with the superintendent any issue as to the statements made by
the superintendent in the letters of 19 and 20 May 1999.
[14] The claim and counterclaim was filed on 24 February 2000 and the defence and
counterclaim on 12 May 2000. The application for summary judgment was then
filed on 20 July 2000 with a return date of 9 August 2000. An affidavit by the
appellant's solicitor, exhibiting some correspondence, was filed on the appellant's
behalf on 4 August 2000. Then a further affidavit by a director of the appellant was
filed on 8 August 2000. In that affidavit the director asserted that a stage of
practical completion had not been reached. He also swore:
"I have obtained correspondence from the Contract Superintendent
for which privilege is claimed, confirming that, as at 14 August
2000, no Certificate of Practical Completion had been issued".
It is difficult to see how a claim of privilege could be made with respect to such
correspondence, but importantly for present purposes no documentation was then
placed before the court substantiating the appellant's contention that practical
completion had not been achieved even by August 2000.
[15] On the day of the hearing another affidavit was filed on the appellant's behalf
exhibiting a letter from the superintendent bearing the date 8 August 2000 in the
following terms:
"We confirm that a Certificate of Practical Completion has not yet
been issued for Contract No 21199-0.
This is because 'As Constructed' documentation required under
Clause 1.12 of the specification has not been received".
Significantly, the superintendent did not address in that letter the statements made
in his letters of 19 and 20 May 1999. It is a matter of some significance that the
only document from the superintendent relied on by the appellant comes some
17 months after the critical letters and on the eve of the hearing of the summary
judgment application.
[16] "Practical Completion" is defined in the contract as the stage when "the Works are
complete except for minor omissions and minor defects" and when "documents and
other information required under the Contract which, in the opinion of the
Superintendent are essential for the use, operation and maintenance of the Works
have been supplied". Essentially "Practical Completion" is a question of fact and it
-- 4 of 6 --
5
is for that reason that the statements in the letters of 19 and 20 May 1999 are
significant. The appellant primarily concentrates on the absence of a certificate, but
a certificate is not essential; it is no more than evidence. No particulars have ever
been supplied identifying work yet to be done by the respondent. Further, insofar
as the supply of documents is relevant (given the terms of the definition) the
superintendent has not stated his opinion that documents "essential for the use,
operation and maintenance of the Works" have not been supplied. For those
reasons the letter of 8 August 2000 is not determinative of the position.
[17] There was an onus on the appellant to demonstrate that there was some issue to be
tried or some other good reason for the matter to go to trial. In all the
circumstances it cannot be said that the learned District Court judge was wrong in
concluding that on the evidence practical completion had been reached in March
1999 and there was no triable issue with respect thereto.
[18] Once it is accepted that practical completion was reached in March 1999 the only
remaining question is whether or not, pursuant to the terms of the contract, the
respondent is entitled to the return of the retention monies. They were strictly
repayable to the respondent once the Certificate of Final Completion issued. In
accordance with cl 42.8 of the general conditions, at the expiration of the period of
28 days after the defects liability period (12 months from practical completion) "the
Superintendent shall issue to the Contractor and to the Principal a final payment
certificate endorsed Final Certificate". Then within 14 days of the issue of that
certificate the retention monies must be released. Neither in the defence and
counterclaim, nor in submissions to the District Court judge, did the appellant take
the point that no final certificate had issued as a condition precedent to the release
of the retention money. That point was taken for the first time on the hearing of the
appeal. Counsel for the respondent answered that by saying that if the point had
been taken then the respondent would have formally applied for a final certificate
and, as the superintendent was obliged to issue it, an order could have been sought
from the court in that regard if the superintendent failed to do so. In other words, if
the point was taken below it could have been remedied. In any event there is no
material before this Court indicating any proper basis on which the superintendent
could refuse to issue a final certificate in accordance with the provisions of the
contract.
[19] It therefore follows that the respondent is entitled to retain the judgment which it
obtained in the District Court.
[20] The notice of appeal was filed 5 September 2000. On 26 October 2000 the solicitor
for the respondent wrote to the solicitor for the appellant expressing concern as to
the appellant's capacity to pay costs of the appeal and foreshadowing an application
for security for costs of the appeal if an appropriate response was not forthcoming.
In a further letter of 2 November the respondent's solicitors indicated that,
consequent upon there being no response to the earlier letter, steps were being taken
to make an application for security for costs. That application, and supporting
material, was filed on 10 November 2000. Thereafter there was correspondence
relating to satisfaction of the judgment. Again, on 13 December the solicitors for
the respondent sought material enabling them to determine whether or not to
proceed with the application for security for costs. Some material was forthcoming
from the appellant's solicitors on 15 January 2001 and ultimately on 16 January
2001 the solicitors for the respondent intimated that, in view of the documentation
-- 5 of 6 --
6
provided, the application for security for costs would be adjourned to a date to be
fixed.
[21] The application for security for costs was adjourned by consent and then brought
before the Court on the hearing of the appeal. The respondent seeks an order for
costs with respect to that application.
[22] The material before this Court indicates that there were reasonable grounds on
which to bring the application, and the appellant failed to respond in a timely way
to requests for information as to its capacity to satisfy an order for costs. In all the
circumstances the respondent should get the costs of and incidental to that
application.
[23] The orders of the Court will therefore be:
(1) Appeal dismissed.
(2) Application for security for costs dismissed.
(3) Order that the appellant pay the respondent's costs of and incidental to the
appeal and the application for security for costs to be assessed.
[24] PHILIPPIDES J: I agree with the orders proposed by Williams JA and with his
reasons.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2001/314