Crystal Creek Pty Ltd v Cairns City Council [2001] QSC 9
SUPREME COURT OF QUEENSLAND
CITATION: Crystal Creek Pty Ltd v Cairns City Council [2001] QSC
009
PARTIES: CRYSTAL CREEK PTY LTD.
(Plaintiff)
v
CAIRNS CITY COUNCIL
(Defendant)
FILE NO/S: No 164 of 1995
DIVISION: Trial
PROCEEDING:
ORIGINATING
COURT: Supreme Court at Cairns
DELIVERED ON: 7/02/01
DELIVERED AT: Cairns
HEARING DATE:
JUDGE: Jones J
ORDER: 1. That the plaintiff have leave to take a further step in
the action by the delivery of a Statement of Claim within
28 days of today’s date.
2. That the plaintiff pay the respondent’s costs of and
incidental to this application to be assessed.
CATCHWORDS: PRACTICE – LEAVE TO PROCEED - LIMITATION OF
ACTIONS – WHEN TIME BEGINS TO RUN
Whether plaintiff to be granted leave to proceed with action
pursuant to rule 389(2) of the UCPR notwithstanding no step
taken in action for more than 2 years – whether reasons for
delay adequate
Uniform Civil Procedure Rules 1999 (Qld)
Limitation of Actions Act 1974 (Qld)
Local Government (Planning and Environment) Act 1990
(repealed)
Tyler v Custom Credit Corporation Ltd (2000) QCA 178
COUNSEL: Mr. D. Turnbull for the Applicant/Plaintiff
Mr. M. Jonsson for the Defendant/Respondent
SOLICITORS: Dale Treanor for the plaintiff
MacDonnells for the defendant
-- 1 of 4 --
2
[1] JONES J: This is an application by the plaintiff pursuant to Rule 389 of the
Uniform Civil Procedure Rules (“UCPR”) for leave to proceed with the action
notwithstanding that no step has been taken for more than two years.
[2] The plaintiff’s claim is for the repayment of monies allegedly paid by mistake to the
defendant local authority as headworks charges in connection with a subdivisional
development. The claim is one of a number of similar claims by other developers
paid in respect of various subdivisions in a number of local authority areas. In the
instant case the monies were paid to the Mulgrave Shire Council which has since
been amalgamated as part of the new Cairns City Council area. The plaintiff
alleges that the council was entitled to charge developers the headworks rate
applicable as at 1 September, 1998 and relies upon s.6.2(6)(a) of the Local
Government (Planning and Environment) Act and the terms of various by-laws and
policies which make provisions for the method of calculation of such charges.
[3] The plaintiff in this case paid the charges in 1988, some 12 years ago. The action
was commenced on 14 November, 1995, a date outside the six year period of
limitation prescribed by s.10 of the Limitation of Actions Act 1974.
[4] The entry of appearance was filed on 31 October, 1996 and is the last step taken in
the action. Since then three notices of intention to proceed have been delivered
respectively on 14 March, 1998, 9 March 1999 and 25 May, 2000.
[5] I am informed that the defendant proposes to raise a defence based on the
Limitation of Actions Act that the plaintiff will contend that s.38(1)(c) applies,
namely that the monies were paid as a consequence of a mistake and the period of
limitation did not begin to run until the plaintiff discovered, or could have with
reasonable diligence discovered, the mistake. This is not an issue upon which any
judgment can be made on the present material and it therefore does not assist the
respondent’s argument that the leave to proceed should not be granted because of
this particular defence.
Reason for delay
[6] The plaintiff first became aware of the circumstances upon which the claim is based
in or around January, 1995 and thereafter, through its legal advisers, made
application under the Freedom of Information legislation for the disclosure of local
authority documents relating to the policies and the manner of calculations for
headworks charges. That process took in excess of a year to complete and was a
necessary precursor to the plaintiff obtaining legal advice on its position. As a
consequence of the legal advice obtained further inquiries were necessary, further
discovery of council documents was requested and there were delays attending the
provision of those documents.
[7] Since the institution of these proceedings the applicant’s solicitors have instituted
similar proceedings against the defendant on behalf of five other claimants. Those
proceedings were instituted on various dates between October 1996 and June 2000.
[8] One of those actions – (Kamerunga Villa Pty Ltd) in which the proceedings were
further advanced than the present case - was the subject of an interlocutory dispute
as to whether this Court had jurisdiction to determine the issue or whether the claim
-- 2 of 4 --
3
should properly have been heard in the Planning and Environment Court. On 14
March, 1997 it was determined that the claims were properly brought in the
Supreme Court. The defendant appealed against this ruling but such appeal was
dismissed on 10 February, 1998. Proceedings in respect of all of the respective
claims were put on hold pending the determination of this jurisdictional point.
[9] As a number of the claimants have retained the same firm of solicitors there was
agreement between the claimants that a “test” case should be agreed upon on the
basis that all claimants would contribute to the costs of that test case. Such a
strategy would result in considerable savings of legal costs, not only for the
claimants but also for the defendant.
[10] It appears from the affidavit of Mr. Dale Treanor that the first test case was
discontinued for reasons beyond control of the other claimants. The second test
case, that of SBK Pty Ltd, was then advanced ahead of the other claims but it still
awaits determination.
[11] When this action was commenced the solicitors for the respondent sent a letter
dated 10 November, 1999 formally suggesting that the instant case await the
determination of the SBK case. The proposal was expressed in the following
terms:-
“It is proposed that the claim by SBK Pty Ltd. be proceeded with as
the sole case so as to enable the issues to be litigated without the costs
associated with multiple litigation. The proposal is that the claims by
the other parties be held in abeyance pending the outcome of the SBK
Pty Ltd. claim on the basis that the other claimants will not be
prejudiced in respect of any time limitations as a consequence.
Accordingly, if any claim becomes statute barred whilst being held in
abeyance, the council will not argue that the claim is statute barred
and will not utilise any time limit under the rules of the Court to
prejudice any of these claimants.” 1
[12] There was no immediate response to that proposal until a reminder letter was sent
on 10 March, 2000. On 29 March, 2000 solicitors for the defendant local authority
advised they would not agree to the proposal using SBK Pty Ltd as a test case. This
advice placed the applicant in the position then of having to make this application
which was done after giving the further notice of intention to proceed on 25 May,
2000.
[13] Mr. Treanor has sought legal advice from senior counsel which is to the effect that
the plaintiff has a good cause of action. This is not a matter in which I should
embark upon any detailed consideration except to note that on behalf of the
defendant it is suggested that the claim will be defended on four bases, namely –
(a) the payments were not charged by the local authority but were voluntary
payments made by the plaintiff;
1 Ex. DRT 36 Affidavit of Dale Robert Treanor 29/11/2000
-- 3 of 4 --
4
(b) that the payment was not made pursuant to any causative mistake of fact or
law;
(c) any right to restitution is lost because the parties cannot be restored to their
former positions; and
(d) the claim is statute barred
[14] I have already commented on the issue in respect of the limitation period. Having
perused the draft proposed statement of claim and considered the matters likely to
be raised in a defence to that claim it seems to me that the issues between the
parties will be determined, mainly on the interpretation of the relevant legislation
and policy documents and by reference to contemporaneous documents which
ought to be available to the parties. As these documents are not before me I cannot
form any view as to the strength of the plaintiff’s case but there is sufficient in the
material to show that the claim involves a significant amount and that the plaintiff
has always maintained an intention to pursue the claim.
[15] The defendant has also raised the question of prejudice arising from the fact that the
Mulgrave Shire Council and the Cairns City Council have amalgamated, that there
is a new record system adopted by the amalgamated council and that three potential
witnesses for the defendant have left its employ. The defendant also points to the
passage of time and its effect on the recollection of witnesses and the availability of
documents. Given that the outcome of the case will most likely turn on the
construction of documents the question of prejudice will not be of such concern that
might otherwise arise in a case of where there has been such an extensive delay.
[16] In the exercise of the discretion inherent in Rule 389 and having due regard to the
principles recently stated in Tyler v Custom Credit Corporation Limited 2 I have
come to the view that the plaintiff ought to be allowed to pursue its claim.
[17] My orders will be –
1. That the plaintiff have leave to take a further step in the action by the delivery
of a statement of claim within 28 days of today’s date.
2. That the plaintiff pay the respondent’s costs of and incidental to this
application to be assessed.
2 (2000) QCA 178
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2001/009