Alex Gow Pty Ltd v Brisbane City Council [2001] QLAC 51 (2001) 22 QLCR 292
IN THE LAND APPEAL COURT
OF QUEENSLAND
Re: A99-44
Appeals from decisions of the Land Court in the matter of
determination of compensation payable consequent upon
the resumption of land for road purposes and an Order for
payment of costs - Acquisition of Land Act 1967.
BETWEEN:
ALEX GOW PTY LTD
Appellant
AND:
BRISBANE CITY COUNCIL
Respondent
J U D G M E N T
Delivered at Brisbane this Fifth day of June 2001
Background
1. By Notification of Resumption published in the Government Gazette on 25
July 1987 the Brisbane City Council ("the respondent") took, for road purposes, land
described as Lot 3 on Plan 212543, Parish of North Brisbane, containing an area of
609 m², being part of a parcel of land owned by Alex Gow Pty Ltd ("the appellant"),
situated at the south-western corner of Breakfast Creek Road and Dunlop Terrace,
Newstead.
2. The purpose of the resumption was to effect the widening of Breakfast Creek
Road. There had previously been registered (7 May 1957) a Notice of Realignment
affecting a narrower strip containing 296 m².
3. The parent parcel contained an area of 5,881 m² before resumption, the
balance area being 5,272 m². The land was zoned "Residential B" at the date of
resumption, then rezoned in September 1987 to "Particular Development
(Undertakers Establishment)".
4. Development of the land as a funeral parlour had taken place in 1963 with the
consent of the respondent. As at the date of resumption, the complex comprised the
main funeral parlour structure containing a floor area of 453 m², two ancillary
workshop buildings, paved driveways and car-parking areas with a grassed, retained
and landscaped frontage to Breakfast Creek Road.
[2001] QLAC 51
-- 1 of 25 --
2
Land $210,000.00
Improvements $62,782.00
Severance (loss of profit) $247,731.00
Injurious affection (professional fees) $54,457.70
10.
Total
The amount of the valuation finally put in evidence by the
$574,970.70
respondent was in
5. The land taken accommodated the forward sloping street frontage landscaped
area, part of a paved driveway and assemblage area adjacent to the eastern elevation
of the principal funeral parlour structure, together with some advertising signage.
6. Subsequent to the resumption, the street frontage alignment was retained by a
high concrete retaining wall.
7. The works associated with the resumption were carried out between 24 August
1987 and 31 May 1988.
8. A claim for compensation was first served on the respondent in September
1995 then filed in the Land Court in September 1999.
9. The amount finally claimed by the appellant in the Land Court, excluding
interest, is summarised as follows:
the amount of $90,608 including professional fees.
11. On 5 October 2000 the Land Court awarded compensation in the amount of
$133,137 together with interest as calculated.
12. The award was particularised as follows:
Loss of land $12,000
Loss of improvements:
Re-erection of illuminated sign $1,335
Loss of 50 ft sign $1,680
Loss of 4 golden cypress pines $3,300
Cost of brick fence on top of retaining wall $47,409
Architect's fees for front fence $2,600
Engineering fees for front fence $800
Brisbane City Council fees $398 $57,522
Injurious affection -
Loss of profits 1987-1988 $27,229
Disturbance
Valuer's fees $7,000
Counsel's fees $ 6,400
Legal fees
Total disturbance
$ 22,986
$36,386
TOTAL $133,137
-- 2 of 25 --
3
13. Interest as ordered to 2 May 2000 amounted to $70,317.82.
14. After the handing down of the decision, both parties made submissions on the
matter of the costs of the hearing and determination of the compensation. The
decision on the applications for costs was given on 20 February 2001. The appellant
was ordered to pay an amount equal to 50% of the respondent's costs of and incidental
to the hearing and the determination of the claim for compensation.
Grounds of Appeal
15. The appellant appealed to this Court from the decision of the Land Court on
compensation on 13 grounds. The appellant also appealed from the decision on costs.
Both appeals were heard together.
16. The principal issues were identified by Mr Lyons, QC, who appeared with Mr
Howe of Counsel on behalf of the appellant in his written and oral submissions before
us, as being:
(1) the award for loss of land;
(2) the order for payment of interest;
(3) the order for payment of 50% of the respondent's costs.
17. We will consider the issues in that order.
Loss of Land
Capitalisation Approach - Before and After Resumption
18. Mr KP Walsh, the appellant's valuer, valued the property as a going concern in
the amount of $1,350,000 before resumption and $1,140,000 after resumption, the
resultant loss, exclusive of disturbance items, being assessed as $210,000.
19. Net maintainable profit was adopted by Mr Walsh, on accountancy advice, as
being $120,000 per annum at the date of resumption. Yields of 9% and 10.5% were
adopted before and after respectively, the difference in yield being Mr Walsh's
assessment of the difference in risk of maintaining the estimated profit.
20. There had been a sale to the one purchaser of three funeral parlours in
Brisbane in 1986, the sale prices reportedly based on a yield of 11%. No financial
details were available to Mr Walsh to allow confirmation of the yield. He accepted
the reported information as being reliable. His industry-related inquiries indicated
that later acquisitions which commenced in the 1989-1990 period were based on
yields of 9%.
-- 3 of 25 --
4
21. Mr Walsh considered the subject property, after resumption, to be superior in
location and exposure to the 1986 sale properties. For reasons associated with the
larger site area, easier management, greater separation of the key building from the
traffic on Breakfast Creek Road, more aesthetically attractive presentation and
considerations relative to greater market share potential, Mr Walsh believed a
differential in yield of 1.5% reflected the relative risk of maintaining the estimated
profit before and after the resumption. Furthermore it was of concern to him that
before resumption constraints on development had been occasioned by the original
Notice of Realignment.
22. Mr Slater, the respondent's valuer, agreed that the before and after valuation
approach was the preferred method in assessment of compensation in circumstances
where a partial resumption of land was involved. It was his evidence that funeral
parlour businesses were "sold on the cash flow and it's the risk to the cash flow that
determines the capitalisation rate". However he had made no attempt to conduct an
assessment on the before and after basis. He said he had not been sufficiently
confident to strike a capitalisation rate either before or after resumption due to the
lack of detailed market information available. In terms of assessment of difference in
yield before and after resumption, his oral evidence was that he could not see
justification "for much movement at all, if any".
23. The learned Member accepted, in the absence of any industry evidence to the
contrary, "Mr Walsh's figure of 11% for 1986" (the reported yield relative to the
sales), but, in view of the lack of any in-depth analysis of the 1986 sales, despite Mr
Walsh's opinion as to the superiority of the subject property, in comparison with the
sale properties, adopted 11% "as the appropriate capitalisation rate for the subject land
in the 'after' situation".
24. On his interpretation of evidence as to market forces operating subsequent to
the date of resumption, the learned Member had concluded that a trend had
commenced in 1986 and would have been influential at the date of resumption,
whereby in 1993 and 1994, the long-term bond rate was more closely reflecting the
appropriate capitalisation rate for funeral parlour businesses.
25. The learned Member could see "no correlation between the later industry
capitalisation rate of 9% (1994)" (when the long-term bond rate was said to have
averaged 9%) "and Mr Walsh's concluded capitalisation rate of 9% in the 'before'
situation in 1987" (when the long-term bond rate was said to have averaged 13%).
-- 4 of 25 --
5
26. On Mr Walsh's evidence that turnover in ownership in the funeral industry had
been largely non-existent, the learned Member agreed with the opinion of Mr Slater
"that it is not possible to arrive at a meaningful conclusion as to the difference in the
critical nature of the capitalisation rate" and was only able to accept a similar
capitalisation rate of 11% in both the before and after resumption scenarios.
27. The learned Member concluded that valuation by capitalisation of net
maintainable profits failed to identify loss and rejected that methodology accordingly.
There was no alternative valuation methodology presented to allow compensation to
be assessed on a before and after resumption basis.
28. It was the appellant's submission that the learned Member's reasoning by
which he rejected Mr Walsh's evidence as to appropriate capitalisation rates was
flawed in that he had given no consideration to Mr Walsh's professional opinion as to
the degree of superiority of the subject property before and after resumption, in
comparison with the 1986 sale properties.
29. It was further submitted that the learned Member misinterpreted Mr Walsh's
evidence as to the timing and measure of subsequent market capitalisation rates within
the industry and that there was no evidence which indicated, at the date of resumption,
a trend between long-term bond rates and appropriate capitalisation rates for funeral
parlour businesses.
30. The respondent through the submissions of Mr Hinson SC, suggested that
adoption by the learned Member of a capitalisation rate higher than that used by Mr
Walsh in the "after" resumption scenario, would have resulted in a lower capital value
and accordingly favoured the appellant. There is no substance in that argument
because the learned Member had found no difference in capitalisation rates, before or
after resumption.
31. The respondent submitted then, that it was open to the learned Member to
prefer the opinion of Mr Slater to the effect that there would have been no measurable
difference in the capitalisation rates before or after the resumption
Findings - Capitalisation Approach - Before and After Resumption
32. This Court suggested in its judgment in Queensland Railways v. Somerville
Funerals (unreported), delivered 3 March 1995, at p.5 -
"… the traditional test of 'before' and 'after' valuations might have better
identified the veracity of the claim for compensation - or the constructing
authority's valuation … Expert accountancy consideration of the
difference in 'yield' (or capitalisation rate) which the industry (and
-- 5 of 25 --
6
market) would have demanded in recognition of the risks introduced by
the resumption … would have, in our opinion, made the picture much
clearer for all involved."
33. The lack of precise analysis of the market evidence in relation to the actual
transactions within the funeral parlour industry weakened the evidential basis for
adoption of capitalisation of maintainable profits as a single, or even primary, method
of valuation in this matter. However, if it was to be accepted, as both valuers
suggested, that this type of business was marketed on the basis of its "cash flow" then
that valuation methodology should not have been excluded from cogent reasoning
simply because the task was made difficult through lack of direct proof.
34. While we accept that there was no evidence before the Land Court to allow
interpretation of a long-term bond rate/capitalisation rate correlation in the period
between 1986 and 1989-90, Mr Walsh's evidence could, arguably, have been
interpreted as indicative of some correlation in 1994.
35. We have found the capital value "before" and "after" approach taken by Mr
Walsh to be of assistance in the circumstances as a check against the veracity of the
quantum of claim.
The Piecemeal Approach
36. In our opinion, Mr Walsh's assessment of loss, in the amount of $210,000
should not be interpreted as representing "loss of land". His valuation, and one of the
advantages of the before and after methodology, assessed loss under all headings,
with the possible exception of temporary loss of profit and disturbance items. Mr
Walsh agreed that if mitigating works had reduced part of the risk in maintaining
profit, his assessment of loss could be reviewed relative to the cost of mitigation.
37. In his valuation report, Mr Walsh provided the opinion, based on evidence of
sales of land in the immediate locality, that, as at July 1987, the subject land when
considered in isolation would have possessed market value in the range of $180-
$200/m² (emphasis added). That opinion went unchallenged.
38. That statement suggests that the land, if vacant, had market value in the range
of $180-$200/m².
39. Mr Walsh did not dispute the suggestion put to him that any further
development of the site, assuming the buildings were in their position as existed at the
date of resumption, would logically have been to the rear of the site rather than close
to the noisy road frontage. However, it was his opinion that the site had equal pro-
-- 6 of 25 --
7
rata value overall, because "the site area controls things like plot ratios and car-
parking requirements and those sorts of things".
40. It was Mr Slater's opinion that "In the context of existing use, the site is fully
improved" and leaving aside severance, "the loss of land area does not result in a loss
in value of the improved property as it has no apparent impact on the trading of the
business conducted on the land". He recognised that "there may be argument that the
original development of the land was restricted by the need to set aside the area of the
future requirement". However, he thought that if this had been a factor in the siting of
improvements, it "would be fairly marginal considering the setback requirements and
the slope of the land". He found no monetary loss through the reduction of the site
area of the land.
41. When pressed in cross-examination as to what he meant by "fairly marginal"
his initial response was "There may be an effect there but it's so small that it's
impossible to quantify".
42. In the same general context as to his perception of the meaning of "marginal",
a discussion took place as to an acceptable margin of error in the valuation of the
"whole lock, stock and barrel, the funeral parlour" or the real property alone. Mr
Slater responded that as a matter of practice he did not have regard to an acceptable
margin of error "But I think, having said that, if you were within 5% you'd probably
be comfortable".
43. The learned Member interpreted that comment as a concession by Mr Slater
that any impact of the Notice of Realignment would have been "fairly marginal" upon
the value of the land subject of the resumption, "reflecting perhaps a factor of about
5% in the value in the before resumption situation". He then said that if he accepted
Mr Walsh's suggestion that, from sales evidence, the land value was "about $180 to
$200 per m²", then an impact of 5% would have allowed a conclusion that a "marginal
loss" for the 609 m² lost would be $6,090. He formed the opinion then, that $6,090
"could reflect any loss of the land in isolation, and without the benefit of a 'before' and
'after' analysis". However, in order to provide any benefit of doubt in the claimant's
favour he said he would "allow 10% for any marginal impact in the "after" situation or
say $12,000 for the loss of land."
44. The appellant submitted that the resumed land was a not unimportant part of
the total site providing the "public face" of the business, accommodating attractive
landscaping and important signage; extending the physical separation of the chapel
from Breakfast Creek Road; and part of the lost land was of operational significance
-- 7 of 25 --
8
being used for vehicular parking and access strategic to the management of the
business. It was submitted that there was no sensible basis for finding that the value
of the resumed land should be determined at a rate less than the average value of the
land as a whole.
45. It followed, in the appellant's submission, that the process by which the
learned Member reached his conclusion as to the loss in land value, was markedly
flawed in that he failed to appreciate the effect of that part of the evidence of Mr
Slater, which was directed not to the value of the land lost, but to the effect of the
Notice of Realignment having a marginal effect on the value of the property and not a
5% or 10% effect on the value of the resumed land.
46. The respondent suggested that it was in an arguably different context that Mr
Slater referred to an acceptable margin of error being 5%, because the effect of his
evidence was that the loss of land did not result in any loss of value of the whole
property, however, there may have been a fairly marginal effect on value if the
development of the land had been restricted by the need to keep the set-aside area (for
road widening) free of improvements. It was submitted on behalf of the respondent
that the learned Member plainly preferred the evidence of Mr Slater to that of Mr
Walsh, although arriving at a figure of $12,000 to resolve any doubts in the appellant's
favour.
Findings - Loss of Land
47. There was no challenge to the evidence of Mr Walsh as to the value of the
land, in isolation, being in the range of $180-$200/m² at the date of resumption. For
the purpose of our considerations we will adopt the median $190/m².
48. As land in isolation we would accept that the loss of 609 m² would have
equated a diminution in value of a rounded $116,000.
49. The land did not stand in isolation however. It was developed for use for
funeral parlour purposes. It was not disputed that such use represented the highest
and best use of the land.
50. Mr Walsh's valuation of the improved property as a going concern was, after
generous rounding, $1,350,000 before resumption. It would follow that if the yield he
adopted was too low then the capital value would be lower.
51. The value of the land before resumption was in isolation, at $190/m²,
$1,117,500 in rounded figures.
-- 8 of 25 --
9
52. The buildings and infrastructure, plant and machinery and the goodwill of the
business would on those figures add $232,500 to the value of the land, in isolation.
53. There is no evidence as to the depreciated replacement value of the buildings,
infrastructure, plant and machinery or the goodwill attributable to the business, but it
would seem a remarkable result for those items (having regard to the extent of them)
not to have significantly greater value than $232,500 as part of a going concern
representing the highest and best use of the land.
54. Mr Walsh's valuation as a going concern after the resumption was $1,140,000.
On a yield of 11%, as adopted by the learned Member, the capital value would reduce
to a rounded $1,090,000. The land value at $190/m² would then be a rounded
$1,000,000.
55. The added value of the buildings, infrastructure, plant and machinery and
business goodwill would be $140,000 on Mr Walsh's figures, or $90,000, if a
capitalisation rate of 11% was adopted. In the circumstances, that would provide just
as remarkable a result as in the before situation.
56. It seems to us to be obvious that, on the figures above, regardless of the
evidence that funeral parlour development represented highest and best use, as
developed, the land component did not equate its worth in isolation. There is,
however, no evidence as to a realistic apportionment of the components of the capital
value of the property.
57. We find the suggestion illogical, that the loss of land had no effect on the
improved value of the property before resumption. However, we are not persuaded by
the appellant's submission that the improved property had suffered the loss of the
value of the land in isolation, as well as effect on the value of the balance area as
developed. In our view an element of double dipping would result if loss of land, as a
component of total loss, was calculated on the basis of its worth in isolation.
58. We are persuaded however that the approach taken by the learned Member in
assessing compensation for "loss of land" was based on a misinterpretation of Mr
Slater's explanation of the "fairly marginal" effect of the restriction on the original
development.
59. If Mr Slater's explanation was to be construed as a suggestion that "fairly
marginal" effect could be equated to a deleterious effect of 5%, then that is interpreted
by us to have meant an effect on the improved value of the property as developed.
60. It is clear that Mr Slater did not accept that any loss in land value had been
caused by the resumption. It is observed that he had not inspected the property until
-- 9 of 25 --
10
1996 when mitigation works had been effected. As had Mr Walsh, he relied on
photography of the before resumption situation in forming his opinions.
61. This was not the type of case where the overall effects of the resumption were
clear cut or capable of assessment with strong evidential support. Mr Slater took the
final view that loss had been contained through the beneficial effects of the
construction of a brick wall screen. We have given close consideration to his
evidence both written and oral in the Court below. His overall approach seemed to
have been one of defence of the assertions of the appellant, rather than an attempt to
resolve doubt, (and it must reasonably have existed), in favour of the dispossessed
owner.
62. The original development of the site had been constrained by the Notice of
Realignment. Such Notice was a step in the process of resumption and its effect on
the value of the land as at the date of resumption is to be ignored (see Housing
Commission of New South Wales v. San Sebastian Pty Ltd (1978) 140 CLR 196). The
physical use of the road frontage land would have been constrained by normal
building-setback requirements, but that does not alter the fact that such land forms an
integral part of the full development potential of a site. The additional land resumed
then formed an integral part of the development which was permitted subsequent to
the Notice of Realignment. The whole of the resumed land was utilised to enhance
the external street presentation of the development and its advertising exposure
through landscaping and signage. The resumed land separated the chapel and
assemblage area from the original road carriageway.
63. While it was not the intended thrust of Mr Slater's evidence as to "fairly
marginal" effect, we have come to the conclusion that the loss of the "public face" of
the development with its specialised highest and best use, through the resumption of
the frontage land, could be reflected in a deleterious effect of 5% of the capital value
of the property before resumption. We have been assisted, to a degree, by Mr Walsh's
evidence as to the capital value of the property, in reaching the conclusion that the
learned Member's determination of compensation under the specific heading of "Loss
of Land" is inadequate and should be set aside. We will substitute an allowance of
$65,000.
Severance - Injurious Affection
64. The evidence was that the brick screen wall had been constructed by the
claimant in 1994, above the concrete wall retaining the balance land. This wall
-- 10 of 25 --
11
assisted in improving the visual amenity of the area in proximity to the chapel and
vehicle assemblage area, and mitigated against the internal visual effects of the
reduced separation of that area from the Breakfast Creek Road traffic. There was
evidence before the Land Court to the effect that no increase in noise levels, at the
façade of the chapel building, had resulted directly from the widening of the road and
the brick wall had reduced the pre-existing traffic noise level. The learned Member
had noted the probability of an increase in fumes from the heavy vehicles using the
road carriageway which was now closer to the subject development.
65. Mr Slater found the screen wall as being "not unattractive" and was of the
opinion "that the appearance of the wall and the reduction in traffic noise more than
offsets the loss of amenity caused by the taking of the landscaped area". Allowance
of the full cost of the wall "for the loss of amenity in isolation" would, in his opinion,
"over compensate the claimant company because of the reduction in traffic noise".
However he thought it would be reasonable to regard the extra benefit as offsetting
any loss arising from the interference to the vehicular parking and access in the
assemblage area. We accept that the beneficial effect of the screen wall in reducing
traffic noise could reasonably offset the loss of part of the assemblage and access
facilities. We also accept that the screen wall was necessary to improve the visual
amenity of the chapel and assemblage area, in mitigation of the injurious affection to
that area as a direct result of the resumption. We do not accept that the construction
of that wall mitigates against the injurious affection to the balance area caused by the
loss of land area, and consequences relative to pre-resumption development potential,
street presentation and advertising exposure.
66. The learned Member's findings of loss under the headings of improvements,
injurious affection and disturbance were not challenged and we see no reason to
disturb the quantum resulting from those findings. We will allow the cost of the
construction of the brick wall as mitigation against injurious affection to the balance
area, other than loss of land.
Summary of Determination of Compensation
67. We determine compensation as follows:
Loss of land $65,000
Loss of improvements
Injurious affection -
$6,315
Cost of brick wall, including professional
and Brisbane City Council fees $51,207
Loss of profits 1987-1988 $27,229 $78,436
-- 11 of 25 --
12
Disturbance - professional fees $36,386
Total $186,137
68. The appeal from the decision of the Land Court with regard to the quantum of
compensation should be allowed on the basis of grounds of appeal 1 and 6.
Compensation under all headings for the taking of the land is determined in the
amount of One Hundred and Eighty-six Thousand One Hundred and Thirty-seven
Dollars ($186,137).
Interest
69. The learned Member awarded interest on compensation payable from the date
of resumption to the date the claim for compensation was served on the respondent, 4
September 1995, then for half the period from that date until the date of
commencement of the hearing, 2 May 2000, and from then until the date that final
payment of compensation is made.
70. The appellant contended that interest should have been allowed for the whole
period, while the respondent argued that the learned Member's award should stand.
The Reasons of the Learned Member
71. The learned Member noted that some 30 years had elapsed since the first
notice of realignment of Breakfast Creek Road, plus a further 12 years from the date
of resumption to the date the claim for compensation was referred to the Land Court.
He also noted that as far as interest was concerned, he was restricted to the period
from the date of resumption.
72. In the Land Court, counsel for the respondent argued in his submission with
respect to interest that the claimant had been less than diligent in pursuing its claim
for compensation and requested the learned Member to exercise his discretion and
apportion responsibility for interest on a 50%/50% basis. The learned Member
observed that the usual practice of the Land Court was to award interest, except where
the dispossessed owner had remained in possession or derived some other benefit
from the resumed land after the date of resumption; I Small and Another v. Brisbane
City Council (1968) 35 CLLR 239.
73. In considering the conduct of the parties, the learned Member concluded that
the decision of the claimant to delay lodging a claim with the respondent from July
1987 until September 1995, was reasonable, as the claimant was "… seeking to
-- 12 of 25 --
13
identify whether any losses had in fact been incurred …". However, he noted that
throughout that extended period, the respondent had not made any advance payments
and that as a consequence the claimant had been at a financial disadvantage in terms
of loss of interest.
74. In seeking guidance on the impact of the behaviour of the parties, the learned
Member turned to the decision of the Land Appeal Court in Moyses and Others v.
Townsville City Council (1979) 6 QLCR 271. In that case, the Land Appeal Court
had thought it relevant to enquire into the conduct of the claimant, when considering
the Court's discretion with regard to costs.
75. The learned Member expressed his opinion that the principle of reasonable
behaviour was also a relevant consideration for the Court in the exercise of its
discretion with regard to an award of interest. He found that neither party had acted
unreasonably: the respondent could not be accused of unreasonably extending the
process of resumption and construction, while the delay by the appellant was
attributed to Mr Gow's very careful and thorough approach to ensure that his claims
were correct and supportable in the changing nature of the industry.
76. Having found that neither party had behaved unreasonably up until the time
the claim was lodged with the respondent in September 1995, a finding not challenged
by the respondent, the learned Member then found that "… there may have been some
contribution by both parties in delaying settlement of the issue", as once the claim was
lodged, it would have been open to either party to have brought the matter before the
Court at an earlier date.
77. In accordance with that reasoning and the piecemeal assessment approach
adopted, the learned Member found that interest should be paid to the appellant on
compensation for loss of land, profits and some improvements, from the date of
resumption until 4 September 1995 when the claim was lodged with the respondent
and then for half the period from September 1995, until the date of hearing of the
claim on 2 May 2000. He calculated the midway point between those dates to be 2
January 1998. He did not allow interest from that date to 2 May 2000, the date of
commencement of the hearing. However, he awarded interest from that date until the
date compensation is paid. He then allowed interest on other compensation heads,
such as costs associated with mitigating works and items of disturbance, from the date
of actual expenditure through to 2 January 1998, then from 2 May 2000 until the date
compensation is paid.
-- 13 of 25 --
14
78. The learned Member said that he found some guidance for that approach in the
unreported decision of the Land Court in Marshall v. Director-General, Department
of Transport (A92-77) 20 February 1998. In that case the Court found that the
claimant had been dilatory in not lodging his claim from 1986 to 1993, and awarded
interest from the date of resumption until the date the matter was referred to the Court,
and from the date of hearing until final settlement.
The Relevant Legislation
79. The power of the Land Court to award interest is contained in s.28 of the
Acquisition of Land Act 1967, which relevantly provides:
"28 (1) Subject to subsection (2), in respect of the period or any part of
the period commenced on and including the date on and from which any
land is taken and ending on and including the day immediately preceding
the date on which payment of compensation is made the Land Court or,
upon appeal, the Land Appeal Court may order that interest be paid upon
the amount of compensation determined by it.
(1A) Such interest shall be at such rate per centum per annum as the
Land Court or, on appeal, the Land Appeal Court, deeming reasonable,
fixes by the order.
(1B) Interest so ordered to be paid shall be payable as if it were part of
the compensation in question and shall be added to the amount thereof
and be payable by the constructing authority accordingly."
80. Under s.12(5) when land is taken, the estate and interest of the claimant is
converted into a right to claim compensation. Under s.20(2) compensation is to be
assessed according to the value of the estate or interest of the claimant in the land
taken on the date when it was taken.
81. Since compensation must be determined at the value of the land at the date of
resumption, rather than the date payment by the resuming authority is made, any delay
would cause economic disadvantage to the claimant, unless there was some
adjustment to the amount of compensation for the loss of earning power. One author
of a text on the subject has explained it thus:
"The purpose of awarding interest is to compensate the landowner for
waiting for the award to be paid. It compensates him or her for the
period when he or she is due to receive the compensation for the loss of
the land and when he or she is actually paid. It acts as a spur upon the
authority to make payment of compensation without undue delay."
Douglas Brown: "Land Acquisition", 4th Ed., Butterworths, 1996, page
158.
-- 14 of 25 --
15
The Usual Practice of the Land Court
82. The usual practice of the Land Court has been to order that interest be paid on
compensation from the date of resumption until compensation has been paid by the
resuming authority. However, as discussed in VH Cox v. Water Resources
Commission (1996-97) 16 QLCR 266, that long established practice has been subject
to two exceptions:
Where there has been unreasonable delay in lodging the claim for
compensation and/or in pursuing that claim; and
Where a dispossessed owner remains in possession of the land. (16 QLCR
273).
83. The second of those exceptions is not relevant in the present case, construction
of the works having commenced shortly after the date of resumption, but in terms of
the first exception, could there have been "unreasonable delay"? There has certainly
been considerable delay, both between the date of resumption (25 July 1987) and the
serving of the claim for compensation on the constructing authority (4 September
1995) and between that date and the date the matter was referred to the Land Court (1
September 1999).
The Practice in Other Courts
84. Counsel for the appellant submitted that there is some broad analogy with the
power of the Land Court to award interest and the power of the Supreme Court to
award interest under s.47 of the Supreme Court Act 1995, but with important
differences. For example, in a claim for personal injuries, an award for pain and
suffering and loss of amenities is fixed by reference to the value of money at the date
of judgment, not the value at the date when the cause of action arose. However,
damage is often suffered over an extended period of time, which has consequences for
how interest is awarded. In such cases it has been said that the reason for awarding
interest is to compensate the plaintiff for having been kept out of money which
theoretically was due to the plaintiff at the date of the accident: Parker v. Guardian
Fire Sprinkler Co (Qld) Pty Ltd [1982] Qd.R.709 at 710; Thompson v. Faraomio
(1979) 54 ALJR 231. In Hadzigeorgiou v. O'Sullivan [1983] 1 Qd.R. 55 at 57,
Andrews SPJ, with whom Thomas and Connolly JJ agreed, said that the proper
approach to an exercise of discretion as to the granting of interest is that it ought to be
granted unless there are proper reasons for withholding it.
-- 15 of 25 --
16
85. Interest may not be allowed from the date of loss where the plaintiff has been
guilty of unreasonable delay in prosecuting the claim: Serisier Investments Pty Ltd v.
English [1989] 1 Qd.R.678. In that case, the Court of Appeal said at 679:
"A far more common case in which interest is not allowed from the date
of the loss is where the plaintiff has been guilty of unreasonable delay in
prosecuting the claim. The public policy of having claims brought and
determined promptly seems to underlie this approach. Goff J thought
that 'this may be to encourage plaintiffs to prosecute their claims with
diligence, and also because such conduct may lull a defendant into a
false sense of security, leaving him to think that the claim will not be
pursued against him'. (BP Exploration (Libya) Co Ltd v. Hunt (No 2)
[1979] 1 WLR 783 at 847).
These examples are however exceptions to the normal position that in
order to remove the advantage that the wrongdoer has had from money
that ought to have been in the pocket of the plaintiff interest is awarded
from the date of loss. "
86. It would seem then that in such cases, while recognising that the award of
interest is in the absolute discretion of the Court, the general rule is that interest
should be granted unless there are proper reasons for withholding it. One of those
reasons would be where there was unreasonable delay on the part of the plaintiff in
prosecuting the plaintiff's claim.
87. However, mere delay should not disqualify the plaintiff from an award of
interest. In Bennett v. Jones [1977] 2 NSWLR 355, the New South Wales Court of
Appeal considered the period in which interest should be awarded in cases of damages
for personal injury. In considering how the Court should exercise its discretion in this
regard, Moffitt P at p.367, emphasised that the power to award interest is
compensatory and should not be used punitively; the delay in the conduct of a party is
relevant only so far as by reason of it there is, or may be, economic disadvantage to
the opposing party by awarding interest, or not awarding it.
88. Then his Honour said at p.370:
"I see no reason why the simple fact that a defendant does not have to
pay money when his liability arises, and has the benefit of non payment
for a period, should not provide a basis to make a discretionary order for
payment of interest for the whole period. One has the money, and the
other not."
He continued at p.371:
"Unless it can be seen that there is likely to have been some relevant
detriment to the defendant, it will be irrelevant if the plaintiff has not
proceeded with complete promptness, or … has not promptly and fully
complied with all court procedures. Such cases … are to be
-- 16 of 25 --
17
distinguished from cases of deliberate delaying tactics of a plaintiff or
defendant, where it appears there is likely to be financial detriment to the
other party. In these cases the conduct of the parties is relevant, because
of its detriment to the opposing party. Delay of the plaintiff in this
context is of particular significance where the delay is in commencing
proceedings. Delay thereafter will normally be of less significance,
because the defendant has some opportunity to prevent delay once
proceedings are instituted."
In the same case when commenting on the conduct of the parties, Hutley JA said at
p.375:
"I am by no means convinced that the conduct of the parties should
ordinarily affect the award of interest. If the fault is that of the
defendant, the plaintiff is adequately compensated by the award of
interest…"
The Respondent's Submissions
89. On the other hand, counsel for the respondent submitted that the learned
Member's order with respect to interest should stand. He argued that the award of
interest until 2 January 1998 gives the appellant the earning power of money into
which its interest in the resumed land was converted. The fact that interest was not
awarded from that date to the date of commencement of the hearing, simply reflects as
a matter of discretionary justice, that the contribution to the delay of the appellant and
the respondent should be apportioned equally.
90. He went on to submit that s.28 confers a discretion to award interest for the
whole period or any part of it. It was also submitted that the underlying intention of
the section is to encourage claimants to prosecute their claims with diligence; if they
do not and they are guilty of unreasonable delay in either lodging or pursuing the
claim, they cannot expect to be awarded interest for the entire period.
91. In the present case, the learned Member expressly found that there was no
unreasonable delay on the part of either party in the period between the date of
resumption and the date of lodgment of the claim with the constructing authority. But
he found that with respect to the delay between that date and the date of referral to the
Court "… there may have been some contribution by both parties …".
92. Counsel for the appellant submitted that if this amounts to a finding of equal
fault, then the ordinary rules should apply and interest should be payable for the
whole of the period. The respondent has had the benefit of the use of the lands since
the date of resumption, yet compensation is payable by reference to values at that
time; the respondent also has had the benefit of the use of the money since the date of
-- 17 of 25 --
18
resumption. If the fault is equal, then it is wrong in principle to make one party bear
the burden of it; the appellant is penalised but the respondent suffers no loss; if the
respondent's fault is to be ignored, so should the fault of the appellant. If that is so,
the usual rule should apply, the appellant has had possession of the property and of
the money.
93. Counsel for the respondent submitted that in the present case little assistance
can be derived from cases from courts of general jurisdiction. While it is true that
there are differences between those cases and the present situation, cases like Bennett
v. Jones in our view, do provide some guidance. The underlying principle with regard
to the award of interest is the same: interest should be awarded unless there are good
reasons for not awarding it. One of those reasons is where there was unreasonable
delay, but mere delay will not be sufficient for withholding an award of interest.
Whether delay is reasonable or unreasonable will depend on the circumstances of
each case.
94. The authorities from the courts of general jurisdiction emphasise that the
purpose of an award of interest is compensatory; not to award interest is punitive.
The purpose of s.28 of the Acquisition of Land Act 1967 has been discussed in a
number of cases, including that of I Small. It is to compensate the claimant for the
loss of earning power of money from the date of resumption to the date of payment.
Not to award interest would be to reduce the total amount of compensation that a
claimant would otherwise receive. There must, in our view, be good reason for the
claimant to be punished by withholding an award of interest for any of the period.
The Marshall Case
95. The learned Member said that he found some guidance for the approach that
he adopted in the unreported decision of the Land Court in Marshall v. Director-
General, Department of Transport (A92-77) 20 February 1998. In that case, the
Court considered a number of decisions of the Land Court and this Court, including
the decision of the Land Court in Ogle v. Director-General, Department of Transport
(1992) 14 QLCR 197, where the Land Court had considered earlier decisions before
concluding at 199:
"The common thread in these cases is that the respondent should not be
required to pay interest on compensation for a lengthy period where a
claimant has been dilatory in pursuing his statutory rights to the claim."
-- 18 of 25 --
19
96. The learned Member in Marshall agreed with that statement of principle.
Applying that test to the facts in Marshall, he found that a delay of 10 years in
commencing a hearing was not justified; he rejected the claimant's arguments that he
was awaiting the provision of flood study reports requested from the respondent; he
found that the claimant had been dilatory in pursuing his claim and that it would not
be just for the constructing authority to be required to pay interest for the full period.
However, he found that the claimant should not suffer a loss of interest for the period
between the commencement of the hearing and the date of payment of the balance of
the compensation due.
97. In our opinion, the present case can be distinguished from Marshall. There the
learned Member rejected the claimant's excuses for the delay. In the present case the
learned Member accepted the claimant's excuses for the delay up until the date the
claim was served on the Council, but held both the claimant and the respondent to be
equally at fault for the delay from then until the commencement of the hearing.
Conclusion
98. Counsel for the appellant submitted that as the learned Member apportioned
blame equally between the claimant and the respondent with regard to the lack of
diligence in lodging the claim for compensation in the Land Court, then to withhold
interest would be to punish the claimant for delay for which the respondent was found
to be equally at fault. We agree with that submission.
99. Therefore, we consider that in endeavouring to do justice between the parties
the learned Member's exercise of discretion has miscarried in not awarding interest for
the entire period when interest became payable in respect of each item of claim. In
our view, interest should be awarded at the appropriate rate from the dates identified
by the learned Member until the date of final payment.
100. There was no appeal against the rate of interest awarded by the learned
Member in respect of the various items of claim, or against the appropriateness of the
various disturbance items, which seem to have been agreed. We therefore feel that
we should not comment on those matters, except to say that we do not endorse the
approach taken by the appellant in calculating the additional interest from 2 January
1998 (Exhibit 3). We accept that this was merely to indicate the amount of interest
that would accrue if interest was awarded at 6% on the amounts in the learned
Member's determination of compensation from 2 January 1998 to 22 March 2001, the
date of hearing of this appeal.
-- 19 of 25 --
20
Costs
101. The grounds for appealing against the order for costs are directed at the
manner of the exercise of the discretion of the learned Member and, in particular, the
failure of the learned Member to have any adequate regard to the relevant evidence
including:
(a) that it was necessary for the appellant to proceed to court and fully litigate the
matter in order for the appellant to recover a sum which was above previous
offers made by the respondent and was significantly above what the
respondent submitted in court was the appropriate sum;
(b) the appellant's stance in pursuing the matter in the Land Court was reasonable;
(c) that the appellant relied on evidence of experts who were highly regarded and
well known to the court;
(d) the chronology of events and the substance of the correspondence which
passed between the parties during 4 September 1995 and 21 August 1998.
102. In both written and oral submissions the focus of the appellant's attack
on the learned Member's decision in relation to costs was an error of principle which
it was submitted was based on a misunderstanding of the decision in Moyses in
respect of the exercise of the discretion to award costs pursuant to s27(2) of the
Acquisition of Land Act 1967. Although no ground of appeal specifically raised that
error of principle, no objection was taken by the respondent to the argument based on
that error of principle. That was presumably because the appellant's argument then
proceeded to the effect that the learned Member's exercise of discretion miscarried as
a result of this error of principle identified by the appellant. That made the lack of a
ground of appeal specifically relying on that error of principle of no consequence.
103. The result of our reasons in relation to the compensation for loss of land
is to increase the overall amount of compensation. The amount of compensation
determined at $186,137 remains nearer to the amount of $90,608 finally put in
evidence by the respondent rather than the amount finally put in evidence by the
appellant of $574,970.70. During the argument on the hearing of the appeal Mr
Lyons QC made the point that if this Court increased the amount of compensation so
that it was closer to the appellant's claim, that would be relevant in the exercise of the
discretion to award costs in respect of the hearing in the Land Court. The increase in
compensation determined on the appeal is not so great, however, to affect the
-- 20 of 25 --
21
underlying principles and factors relevant to the exercise of the discretion to award
costs.
104. Sections 27(1) and (2) of the Acquisition of Land Act 1967 provide:
"27.(1) Subject to this section, the costs of and incidental to the hearing
and determination by the Land Court of a claim for compensation under
this Act shall be in the discretion of that court.
(2) If the amount of compensation as determined is the amount finally
claimed by the claimant in the proceedings or is nearer to that amount
than to the amount of the valuation finally put in evidence by the
constructing authority, costs (if any) shall be awarded to the claimant,
otherwise costs (if any) shall be awarded to the constructing authority."
105. The learned Member referred to the summary form of propositions taken from
judgments relevant to s27 of the Acquisition of Land Act 1967 set out in Yalgan
Investments Pty Ltd v Albert Shire Council (1997) 17 QLCR 401 at 406-408.
Paragraphs (j) and (k) of that summary set out at 408 are particularly relevant:
"(j) Section 27(2) of the Acquisition of Land Act 1967 should not be
regarded as a legislative suggestion that, where the claim is
substantially more than the amount awarded, and the amount put in
evidence by the constructing authority is not substantially less than
the amount awarded, the Court should not merely refrain from
awarding any costs to the claimant but should award costs to the
authority (Moyses at p. 274).
(k) Where the Land Court is considering whether it should award costs
to a constructing authority, it could be wrong to have regard
merely to the amounts of the claim and of the award and of the
value put in evidence by the authority. Usually it would be more
relevant to enquire whether the conduct of the claimant (such as,
for example, making an exorbitant claim) has been such as to force
the authority, unreasonably and unnecessarily, into litigation
(Moyses at p. 274) or whether the claimant has pursued a
vexatious, dishonest or grossly exaggerated claim or presented his
case in such a way as to impose unnecessary burdens on the
constructing authority or the Court (Banno at p. 53)."
106. The learned Member had regard to Yalgan in determining the key issues
relevant to the issue of costs as being the quantum of the amounts claimed; the actions
of the parties in seeking resolution of the matter; and the reasonableness of the claim.
Although the appellant described that as "a gloss on those principles" found in
Yalgan, it is apparent that the learned Member was identifying the relevant issues in
summary form. It is not suggested that what the learned Member identified were not
relevant issues.
-- 21 of 25 --
22
107. The learned Member's reasons for the decision on costs then proceeded under
three headings which reflect the key issues identified by him.
108. In dealing with the first issue of the quantum of the claims, the learned
Member stated:
"However, I note particularly the directions of the Land Appeal Court in
Moyses at page 274, where it directed that costs should be awarded to the
authority where the claim substantially exceeds the award, and where the
amount put in evidence by the authority is not substantially less than the
amount ordered. In the current matter the conditioning influence in
exercising discretion to the authority, in my opinion, is likely then to rely
upon an understanding of the words 'substantially less than the amount
awarded'."
109. We accept the submission of Mr Lyons QC that this passage reflects the
submission that was rejected in Moyses, rather than the view of the Land Appeal
Court in that case. The statement by the Land Appeal Court at p274 of Moyses was in
the following terms:
"Second, where the Court is considering whether it should award costs to
an authority, it could be wrong to have regard merely to the amounts of
the claim and of the award and of the value put in evidence by the
authority. We would think that usually it would be more relevant to
enquire whether the conduct of the claimant, including his making of an
exorbitant claim, if he has made one, has been such as to force the
authority; unreasonably and unnecessarily, into litigation."
110. Mr Hinson SC conceded that the passage of the learned Member's reasons set
out above which is relied on by the appellant for its submission that the learned
Member acted on a wrong principle was suggestive of a misunderstanding of what
was said in Moyses. Mr Hinson SC submitted, however, that the passage must be
considered in the context of the whole decision and it was then capable of being
understood as reflecting a proper understanding of the approach for which Moyses is
authority.
111. We accept that the earlier part of the learned Member's reasons did reflect a
correct appreciation of the nature of the discretion, but this passage occurs in the
critical part of the analysis of the relevance of the amount of compensation claimed by
the appellant and the amount put forward by the respondent.
112. In addition the appellant relies on the conclusion of the learned Member found
after he had completed his analysis of the other two issues. The learned Member
stated:
"On the balance of evidence, I believe it was inevitable that the matter
would eventually come to hearing. The actions of either party do not, in
-- 22 of 25 --
23
my opinion, lead me to move away from the normal conclusion that
costs should follow the event."
113. Mr Lyons QC submitted that this showed that the learned Member started
from the position that he should award costs to the respondent, rather then exercising
the discretion as to whether or not costs should be awarded to the respondent, because
the amount of the compensation determined was nearer to that contended for by the
respondent. Mr Hinson SC submitted that "the event" being referred to by the learned
Member was the fact that the compensation had been determined at an amount nearer
to that put in evidence by the respondent than the appellant's claim. Even if that were
accepted, the approach taken by the learned Member in the conclusion set out above
and in the passage which misstates the effect of Moyses reflects an assumption that if
the amount which is awarded is closer to the amount for which the respondent finally
contends than to the claim, prima facie an order for costs should be made in its
favour. That does not accord with the principle set out in Moyses at 274 and which
was restated in Yalgan at paragraphs (j) and (k) at 408.
114. We therefore accept that the learned Member's decision in relation to costs
proceeded on a wrong principle. It is apparent from the statement made by the
learned Member by way of conclusion that application of the wrong principle has
affected the requisite exercise of the discretion in relation to costs. The matters which
were relevant to the exercise of discretion such as the conduct of the appellant in the
making and pursuit of the claim and the corresponding conduct of the respondent in
responding to the claim were not considered by the learned Member in the context of
whether or not an award for costs should be made to the respondent.
115. The learned Member made a number of findings about the conduct of both
parties which are not challenged and are relevant to the exercise of the discretion in
respect of the costs of the hearing. They were:
(a) there was no evidence to discredit the reasonableness of the actions of
either party;
(b) there was some contribution by both parties in delaying settlement
after the claim was first lodged with the respondent in September 1995
until it was finally filed in the Land Court in September 1999;
(c) it was inevitable that the claim would need final resolution by the
Court both as a result of the extent of the claims made by the appellant
and the reluctance of the respondent to deal with the matter.
-- 23 of 25 --
24
There was no finding that the appellant's conduct had been such as to force the
respondent unreasonably and unnecessarily into litigation.
116. When costs were argued before the learned Member, the appellant submitted
that it was entitled to its costs. The respondent argued that the appellant should pay
three-quarters of the respondent's costs of the hearing. When submissions were made
in this Court on what was the appropriate order for costs of the hearing in the Land
Court, if it were concluded that the discretion of the learned Member as to costs had
miscarried, the appellant submitted that there should be no order as to costs of the
hearing of the claim and the respondent submitted that the appellant should be ordered
to pay half of the respondent's costs.
117. The respondent submitted that what was said in Kabale Holdings Pty Ltd v
Chief Executive, Department of Transport (1997) 18 QLCR 166 at 200 was relevant
to the exercise of the discretion on costs. That was an extreme case in that the
claimant elected to argue issues which the constructing authority had correctly said
were not supported by the law. Of the claim for disturbance of $7,578,117.44 only
the costs of preparing the compensation claim assessed at $74,878 were allowed.
Most of that claim was for damages for delay which the court had no jurisdiction to
consider. The circumstances in which the claimant in that case was ordered to pay
80% of the costs of the constructing authority can be distinguished from this matter
where the appellant put forward a case on a proper basis.
118. Even though the ultimate determination of compensation has been for an
amount which is nearer to that contended for by the respondent rather than that
contended for by the appellant, the appellant had to pursue its claim in the Land Court
to recover a sum significantly greater than that for which the respondent finally
contended. In fact the respondent's position that compensation should be determined
at an amount of $51,207 plus disturbance items and interest did not emerge until the
hearing. There was nothing in the history of the dealings between the parties to
support the position that the appellant could recover the amount that has ultimately
been determined as compensation by any means other than a hearing in the Land
Court.
119. On the basis of the findings made by the learned Member about the conduct of
both parties and that there was no finding that the appellant's conduct had forced the
respondent unreasonably and unnecessarily into litigation, we have concluded that
there should be no order as to costs of the hearing and determination in the Land
Court.
-- 24 of 25 --
25
Orders
We therefore make the following orders:
(i) The appeals are allowed.
(ii) The determination and orders made by the Land Court on 5 October
2000 are set aside.
(iii) The orders made by the Land Court on 20 February 2001 are set aside.
(iv) Compensation is determined in the sum of $186,137 and the
respondent is ordered to pay the appellant that amount.
(v) It is further ordered that the respondent pay interest to the appellant on
each item of the claim included in the determination of the
compensation from the dates and at the rates identified by the learned
Member in the reasons for judgment dated 5 October 2000 until the
date of final payment of each item of claim in accordance with these
reasons.
(vi) It is further ordered that each party have liberty to apply on 5 days'
notice in writing to the other in respect of the calculation of interest, if
the parties are unable to agree on the calculation required in
accordance with these reasons.
(vii) It is further ordered that there be no order as to costs in respect of the
hearing and determination of this claim for compensation in the Land
Court.
It will be necessary to determine the issue of the costs of the appeals to this Court.
Subject to any submissions from the parties on the question of these costs, because of
the success of the appellant on the appeals, it would follow that the appellant should
have its costs of the appeals.
(Mullins J)
JUSTICE OF THE SUPREME COURT
(JJ Trickett)
PRESIDENT OF THE LAND COURT
(RE Wenck)
MEMBER OF THE LAND COURT
-- 25 of 25 --
Official source: https://www.sclqld.org.au/caselaw/QLAC/2001/051