Cape York Land Council Aboriginal Corp v Boyland & Anor [2000] QCA 202
SUPREME COURT OF QUEENSLAND
CITATION: Cape York Land Council Aboriginal Corp v Boyland & Anor
[2000] QCA 202
PARTIES: GORDON CHARLIE
(first applicant)
CAPE YORK LAND COUNCIL ABORIGINAL
CORPORATION
(second applicant/appellant)
v
DESMOND EARNEST BOYLAND, EXECUTIVE
DIRECTOR (CONSERVATION), QUEENSLAND
DEPARTMENT OF ENVIRONMENT
(first respondent/first respondent)
CLYNDER PTY LTD ACN 009 857 425
(second respondent/second respondent)
FILE NO/S: Appeal No 7688 of 1999
SC No 6 of 1997
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Cairns
DELIVERED ON: 30 May 2000
DELIVERED AT: Brisbane
HEARING DATE: 15 May 2000
JUDGES: Davies JA, Douglas and Holmes JJ
Judgment of the Court
ORDER: Appeal allowed. Orders made below set aside and, in lieu,
orders made quashing the decision of the first respondent
made on 11 February 1997 and referring the matter back
to the director to decide the application in accordance
with the principle stated herein.
Order that the appellant have its costs of the proceedings
at first instance and in this Court against each of the
respondents.
CATCHWORDS: ADMINISTRATIVE LAW – JUDICIAL REVIEW
LEGISLATION – COMMONWEALTH, QUEENSLAND
AND AUSTRALIAN CAPITAL TERRITORY –
GROUNDS FOR REVIEW OF DECISION – ERROR OF
LAW – appellant in original action sought a statutory order of
review in respect of a decision made by first respondent to
approve an application by second respondent to construct
-- 1 of 8 --
2
certain buildings on Lizard Island – where first respondent
made decision based upon advice received from Crown
Solicitor – where advice stated approval of application to
construct buildings could not be reasonably withheld if the
second respondent established that the construction of the
improvements were bona fide for the purposes of the sub-
lease – whether advice given by Crown Solicitor incorrectly
stated the question to be asked – whether the correct question
was whether the application should be granted having regard
primarily to the cardinal principle – whether asking the
correct question would have resulted in a different answer
National Parks and Wildlife Act 1975, s 25, s 33, s 34, s 35,
s 51
Australian Broadcasting Tribunal v Bond (1990) 170 CLR
321, applied
Craig v South Australia (1995) 184 CLR 163, applied
COUNSEL: S J Keim for appellant
G J Gibson QC with S A McLeod for first respondent
P J Flanagan for second respondent
SOLICITORS: Miller Harris (Cairns) for appellant
Crown Solicitor for first respondent
Corrs Chambers Westgarth for second respondent
[1] THE COURT: This is an appeal from an order by a Supreme Court judge refusing
both a declaration of invalidity of a decision of the first respondent made on
11 February 1997 and an order that that decision be quashed. The application was
made pursuant to the Judicial Review Act 1991. The decision was one granting an
application for approval of the construction of buildings on land subleased by the
second respondent on Lizard Island.
[2] Lizard Island is and was at all relevant times a National Park. Nevertheless land on
the island, part of which the second respondent now holds on a sublease, had been
leased to Lizard Island Pty Ltd on 1 October 1975 for a term of 75 years subject to a
condition that development of tourist accommodation buildings and recreation
facilities be undertaken of a value of not less than $500,000 and that a tourist resort
be conducted on the leased land. The sublease of part of that land was granted to
the second respondent on 1 June 1983.
[3] Two relevant conditions of that sublease were:
"14(a) ...
The Sub-lessee covenants with the Sub-lessor that it shall perform
and observe all the Lessee's covenants and stipulations and whether
expressed or implied in the said Special Lease 39507 to the extent
that such covenants and stipulations have application to the demised
premises the subject of this Sub-lease.
(b) The Lessee shall use the demised premises for tourist and
recreation facilities only and before constructing any building or
-- 2 of 8 --
3
other fixed improvements thereon shall obtain all necessary permits
required by law therefor and in particular the permit of the Director
of National Parks and Wildlife Services."
[4] The lease and sublease were at all material times subject to the provisions of the
National Parks and Wildlife Act 1975,1 relevant provisions of which were as
follows:
"25. Principle of management of National Parks.
The cardinal principle to be observed in the management of National
Parks shall be the permanent preservation, to the greatest possible
extent, of their natural condition and the Director shall exercise his
powers under this Act in such manner as appears to him most
appropriate to achieve this objective."
"33. Power to grant special leases and permits.
(1) With the consent of the Director and subject to such
conditions for the preservation and protection of the National Park as
the Director thinks fit to recommend, special leases in respect of any
land within any National Park other than land declared as a primitive
area or a scientific area may be granted under sections 198 and 203
of the Land Act 1962-1981 and for the purpose of this subsection
such land shall be deemed to be land reserved and set apart for
public purposes, and the provisions of that Act so far as they are not
inconsistent with so much of this Act as relates to National Parks
shall apply and extend to all such special leases accordingly:
Provided that no such lease shall be granted with or subjected to any
condition unless the Governor in Council is satisfied that the objects
of this Division would not be thereby prejudiced or opposed."
"34. Interfering with forest products on National Parks.
(1) Notwithstanding anything to the contrary contained in any
other Act, a person shall not interfere with any forest products on
any National Park except under the authority of and in compliance in
every respect with the requirements of a permit granted pursuant to
this section by the Director."
"35. Permits, etc.
(1) Subject to this Act, the Director shall have power and
authority to grant or make with any person, exclusively or in
common with others, permits, leases or other authorities and
agreements or contracts under and for the purposes of this Act and to
extend any of the same from time to time and every permit, lease,
other authority, agreement or contract shall be granted, made or
extended subject to the payment by the permittee, lessee or the
person to whom the authority is granted or with whom the agreement
or contract is made, as the case may be, of such charges, rents, fees
or other moneys and to such provisions, conditions and reservations
as may be prescribed or, in so far as not prescribed, as the Director
may determine:
... ."
1 Nature Conservation Act 1992 s 165, substituted 1994 No 42 s 49, expired 19 December 1994.
-- 3 of 8 --
4
"51. Unlawfully using National Park.
(1) Any person who, except under the authority of and in
compliance in every respect with a permit or other right or authority
granted under this Act, or a lease, or other authority from the Crown,
on any National Park –
(a) ... ;
(b) occupies, resides upon, or encloses any land or waters, or
erects any hut or other structure whatsoever or grows crops upon any
land, or clears or breaks up any land for cultivation or for any other
purpose; or
(c) ... ;
(d) ...;
shall be guilty of an offence which shall be deemed to be a park
offence, against this Act."
Forest products are defined to include all vegetable growth, aboriginal remains,
artefacts or traces thereof and relics.
[5] The approval granted was to construct certain buildings on the subleased land for
the purpose of providing a tourist and recreational facility. The first respondent was
asked to and provided a statement, pursuant to s 33 of the Judicial Review Act,
containing the following reasons for his decision:
(a) a request had been made by Clynder Pty Ltd for construction to be
permitted pursuant to the requirements of cl 14(b) of the sublease;
(b) legal advice was obtained to the effect that approval could not
reasonably be withheld if Clynder Pty Ltd established that the
construction improvements were bona fide for the purpose of the
sublease; and
(c) the request was determined to be in keeping with the purposes for
which the lease and sublease were issued.
Only the second and third of these can be properly characterized as reasons.
[6] Before the learned primary judge and in this Court the appellant's argument centres
on par (b) of those reasons. First, it submits that the first respondent concluded that
the question which he had to decide was whether there was any reasonable basis for
refusing the application and that, consequently, he should refuse the application
only if some reasonable basis were shown for refusing it. This, it was submitted
was the wrong question.2 The correct question, it was submitted, was whether the
application should be granted having regard primarily to the cardinal principle
stated in s 25, bearing in mind the purpose for which the lease and sublease were
granted.
[7] Secondly, it is submitted, as par (b) of the reasons for decision and the first
respondent's other evidence show, the first respondent concluded that, once it was
established that the construction proposed was for the purpose of tourist
accommodation buildings and recreation facilities, approval could not reasonably
be withheld. And it was submitted that this was to fail to take into account the most
important consideration, the cardinal principle referred to in s 25. It was, in effect
conceded by Mr Gibson QC for the first respondent that this was the effect of
2 Craig v South Australia (1995) 184 CLR 163 at 179.
-- 4 of 8 --
5
par (b) of the reasons for decision and that, if that truly represents the first
respondent's reason, the decision must be quashed. However he submits that in
par (b) the first respondent mis-stated his reason and that, on his reasons as
explained in his affidavit and oral evidence, there was no error vitiating the
decision.
[8] As appears from par (b) of the reasons for decision the first respondent sought and
relied on legal advice from the Crown Solicitor as to the appropriate questions
which he should consider and as to the legal aspects of the answers to those
questions. In the principal letter of advice from the Crown Solicitor, dated
5 January 1995, the relevant question was stated in the following way:
"Can permission to construct this facility be reasonably withheld by
the Director, National Parks and Wildlife on the grounds that ... the
development scenario is not, in his opinion, in keeping with the
cardinal principle of the National Parks management as contained in
s 25 of the National Parks and Wildlife Act ... ?"
That question was then answered in the letter in the following way:
"On the basis of your instructions as set out in your letter, the answer
to your first question is that the permission may not be withheld
unless the use proposed is totally inconsistent with the purpose of the
sub-lease."
[9] That advice was confirmed in subsequent advices of 10 March and 8 May 1995 in
the following terms respectively:
" Even though the Director has a discretion under clause 14(b) in
my opinion that discretion would have to be exercised reasonably in
the circumstances: by taking into account all the relevant
considerations, including the purpose of the Head Lease and
Sublease. In other words, the discretion must be exercised having
regard to the purpose of the Head Lease and Sublease and could not
be unreasonably withheld so as to frustrate the purpose of the Head
Lease and Sublease.
As mentioned in my earlier advice it is not sufficient that the
proposed works are inconsistent with the cardinal principle of park
management because the cardinal principle has already been
compromised by the granting of the Head Lease and Sublease."
" In line with earlier Crown law advices dated 5 January 1995 and
10 March 1995, so long as Clynder Pty Ltd can establish that the
construction of the improvements are bona fide for the purpose of
the sub-lease, namely for 'tourist and recreation facilities' then the
Chief Executive could not unreasonably withhold his approval to the
construction and removal of trees and forest products so as to
frustrate the purpose of the lease."
[10] Paragraph (b) of the reasons appears to suggest that the first respondent accepted
this advice and, having concluded, as is common ground, that the proposed
construction was for tourist and recreation facilities, consequently concluded, in
effect, that he was bound to grant the approval. What is clear from those advices is
that the adviser considered, wrongly in our opinion, that the relevant question was
whether permission to construct the proposed buildings could be reasonably
withheld and that the answer to that question was that it could not if the
-- 5 of 8 --
6
construction was bona fide for the purpose of the sublease. And the reason why the
Crown Solicitor reached that conclusion appears to be that he thought that, in order
to withhold his permission pursuant to cl 14(b) the director had to be satisfied both
that the construction was not consistent with the purpose of the sublease and that it
unduly interfered with the cardinal principle. In the letter of advice of 5 January
1995 he said:
" Before the Director may reasonably withhold consent, he must be
satisfied that the proposed work are inconsistent with the purpose of
the sub-lease for example because it is unlikely that the works if
approved, will be consistently used for the purpose of 'tourist and
recreation facilities only'. It is not sufficient that the works are
merely inconsistent with the cardinal principle because the cardinal
principle has already been compromised by the grant of the lease.
A decision by the Director to refuse consent in this case should be
based on a combination of the cardinal principle of park
management and an assertion that the construction of the dwelling
house is inconsistent with the purpose of the head-lease and sub-
lease in the circumstances. In this context the importance of the
construction site to the surrounding environment and the likely
impact of the works and use thereof on the surrounding environment
are relevant considerations, but not the only ones. The decision must
be taken in the light of the fact that the lease has been granted for the
purpose of the construction of tourist and recreational facilities and
this necessarily contemplates the construction of dwellings."
[11] To similar effect is the advice quoted above from the letter of 10 March 1995.
Although what is said in these passages is not entirely clear it is consistent with the
interpretation we have placed on it and it appears to have been the interpretation
which the director placed on it for when taken to the second paragraph from the
letter of advice of 5 January 1995, quoted in [10], he agreed that he understood that
to mean that he had to have two reasons to refuse in combination, one being the
cardinal principle and the other an assertion that the construction of the dwelling
was inconsistent with the purpose of both the head lease and the sublease.
[12] The advices given by the Crown Solicitor to the director were therefore wrong in
three respects; they wrongly stated the question which he had to consider, they
advised him that he could withhold permission only if the use proposed was
inconsistent with the purpose of the sublease and, as the reason for that last
conclusion, they advised him that he could not withhold his permission unless he
was satisfied both that the proposed construction was not bona fide for the purpose
of the sublease and that it was inconsistent with the cardinal principle. It follows
that in our opinion the learned primary judge erred in his conclusion that the
advices given were correct.
[13] Notwithstanding par (b) of the reasons for refusal and the first respondent's
agreement with the proposition that he understood the advice from the Crown
Solicitor to mean that he had to have two reasons to refuse in combination, one the
cardinal principle and the other that the proposed construction was inconsistent with
the purpose of the sublease, Mr Gibson QC nevertheless contended that the first
respondent was not misled by these advices and exercised his discretion upon a
-- 6 of 8 --
7
correct basis. For that he relied on an affidavit sworn by the director and some
passages in his oral evidence. In his affidavit the director said:
"I did have regard to the 'cardinal principle' expressed in section 25
of the NPW Act, but considered that, consistent with Crown law
advice with which I had been provided, the operation of that
principle was to be assessed in light of the fact that the Land was
then undeveloped in any way, and that the Sub-lease obliged
Clynder to use the land for 'tourist and recreational facilities ... '.
The legal advice obtained from Crown law was to the effect that
provided the construction of the improvements were for 'tourist and
recreation facilities only', approval could not be unreasonably
withheld so as to frustrate the purpose of the lease. I considered that
having regard to the contents of the material before me (which
included material both in favour of and against approval of the
application) it would be unreasonable to withhold approval as the
design of the buildings was sympathetic to the natural environment;
the size of the proposed development was comparatively small for a
tourist facility; and in my opinion any adverse impact of the
development on the natural environment and cultural heritage values
of the Land and the Island was likely to be reasonably contained by
the imposition of appropriate conditions."
[14] Then in cross-examination the first respondent agreed that the advice which he had
was that before he could reasonably withhold consent he had to be satisfied that the
works were inconsistent with the purpose nominated in cl 14 of the sublease. He
then agreed, as mentioned earlier that he had to have two reasons in combination,
the cardinal principle and inconsistency with the purpose of the lease before he
could refuse. Then, in re-examination, he was asked what he considered his role to
be, having formed the view that it was for a tourist and recreational facility. His
answer was:
"Well, I believed that for a tourist and recreational facility it was
probably about the most minimal impact that could possibly occur
on a national – on a national park. The structure so built or was
proposed to be built was of that nature."
[15] Then came the following passage in re-examination:
"In light of your conclusion that this or any proposed development
was for tourist and recreational facilities, what discretion, if any, did
you then consider you had to refuse approval? -- Well, the discretion
I was looking at is to ensure there was relatively minimal impact on
the park and I believed the proposal that was put forth satisfied that
criteria.
HIS HONOUR: Did you believe you had a discretion to refuse? -- I
believed that I wasn't compelled to approve any building that came
forth.
To approve any development at all? -- Sorry, your Honour, is my
understanding you ---
You were asked by Mr Gibson a moment ago what discretion did
you believe you had to refuse --- ? -- Yes.
--- A proposal and you didn't quite answer his question, so I asked
you again? -- Sorry, your Honour. I did believe that I had some
-- 7 of 8 --
8
discretion to refuse because the wording from the legal advice, if I
recall correctly, was 'cannot be unreasonably withheld'. Now, if I
had very sound reasons for refusing the proposed development, then
I believe I was quite within my rights to do so."
[16] In the light of those passages, the highest that the matter can be put for the
respondents is that the first respondent accepted the advice given that the question
was whether permission could be reasonably withheld; and that he believed that he
could withhold permission only if very sound reasons for refusing it were shown. It
seems plain from this, in our opinion, that the first respondent asked himself the
wrong question. The correct question was what was the most appropriate way of
achieving the objective of the permanent preservation, to the greatest possible
extent, of the natural condition of the park having regard to all the circumstances
including the existence of the sublease for tourist and recreation facilities; whether
it was by refusing permission to construct the buildings or to grant it subject to
conditions or, as seems most unlikely, to grant it unconditionally. Having asked
himself the wrong question he appears to have answered it by concluding that, once
it was established that the proposed construction was bona fide for tourist and
recreational facilities, he could not reasonably refuse it or, perhaps, could only
reasonably have refused it for very sound reasons. He did not attempt to say what
very sound reasons might be and he seemed to think that, even if there had been an
application for a 30 storey building on the land he would merely have had
"reservations" about it.
[17] It is plain that, if the first respondent has asked himself the right question he might
have arrived at a different answer.3 It follows therefore that the appeal should be
allowed, the orders made below set aside and, in lieu, orders made quashing the
decision of the first respondent made on 11 February 1997 and referring the matter
back to the director to decide the application in accordance with the principle stated
above.
[18] We would also order that the appellant have its costs of the proceedings at first
instance and in this Court against each of the respondents.
3 Australian Broadcasting Tribunal v Bond (1990) 170 CLR 321 at 353, 384.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2000/202