Davis v Walter Construction Group & Ors [2000] QSC 323
zf\14~
State Reporting Bureauscoo/ 3-;;._3
TRANSCRIPT OF PROCEEDINGS
Copyright in this transcript is vested in the Crown. Copies thereof must not be made
or sold without the written authority of the Director, State Reporting Bureau.
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
JONES J
No 17 of 1996
DOUGLAS MICHAEL DAVIS
and
WALTER CONSTRUCTION GROUP LTD
Plaintiff
(FORMERLY CONCRETE CONSTRUCTIONS PTY LTD) First Defendant
and
PERPETUAL TRUSTEE COMPANY LTD
and
REEF CORPORATE SERVICES LTD
CAIRNS
.. DATE 01/09/2000
JUDGMENT
1
th I ·11111r, Tht• I.aw Courts, (;('OI")..\~ Stred, Brish:111t•, Q ...t(HJO
Second Defendants
Td1:ph1111l': (07) J2...t7 -tJhO F:ix: (07) JZ-t7 .5.5..lZ
-- 1 of 3 --
01092000 D.1 T15/KEW M/T CNS611/2000 (Jones J)
HIS HONOUR: This is an application by the defendant for the
striking out of the plaintiff's application, and if successful
for leave to discontinue its counterclaim in the action. The
action was instituted to raise a claim pursuant to the
Subcontractors Charges Act, in respect of which the sum of
$91,064.88 has been secured by way of bank guarantee.
The plaintiff was a subcontractor to the defendant for work
associated with the construction of the Reef Casino in Cairns.
The work was carried out in 1995 and the plaintiff has already
been paid $1,160,230 for the work he performed. The details
of the outstanding claim are not particularly relevant in the
circumstances.
The writ was issued on 21 February 1996 and a statement of
claim delivered on 20 May 1996. The last step taken by the
plaintiff appears to have been the delivery of further and
better particulars of the statement of claim on 15 October
1996.
It is almost four years then since the plaintiff has taken any
step in the action, but more importantly the plaintiff has not
been in contact with his solicitors now for a prolonged
period. In fact the solicitors themselves have lost contact
lC
30
40
with the plaintiff altogether, and had it not been for the 50
short term of notice given of this application, they would
themselves have applied for leave to withdraw. This
application has been brought on in less than the seven days
necessary for them to make such an application.
2 JUDGMENT
60
-- 2 of 3 --
01092000 D.l Tl5/KEW M/T CNS611/2000 (Jones J)
This sort of delay in what is a commercial proceeding and for
which no excuse is given causes obvious prejudice to the
defendant. A trial to be taken after delay which will no
doubt exceed five years were the matter allowed to proceed,
would result in relevant evidence not being available to the
defendant and also of course the financial impost of having
the bank guarantee continue for an unconscionably long period.
From the plaintiff's inaction over that lengthy period of time
and lack of any explanation as to why the delay has occurred I
have to have regard to the defendants' position and the
prejudice which it obviously faces.
I am concerned however, to give the plaintiff a further chance
10
20
to apply to set aside the order for striking out which I am 30
about to make. I do that on the understanding that the
plaintiff's solicitors will renew efforts to make contact with
him and to bring to his attention the order which I will make.
My orders will be that unless the plaintiff applies within 28 40
days from today's date to set aside this order, the
plaintiff's action will be dismissed for the want of
prosecution. I give leave to the first defendant to
discontinue its counterclaim and I order that the plaintiff
pay the defendants' costs of and incidental to the action
including the cost of this application to be assessed.
Failing any variation of the order within 28 days I order that
the bank guarantee be released.
3 JUDGMENT
50
60
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2000/323