Concept Constructions (Qld) Pty Ltd v Asphalt Pavements Pty Ltd (in liq) [2000] QSC 269
SUPREME COURT OF QUEENSLAND
CITATION: Concept Constructions (Qld) P/L v Asphalt Pavements P/L
(In Liquidation) [2000] QSC 269
PARTIES: CONCEPT CONSTRUCTIONS (QLD) PTY LTD
ACN 063 669 198
(applicant)
v
ASPHALT PAVEMENTS PTY LTD (In Liquidation)
ACN 010 157 543
(respondent)
FILE NO/S: No 5212 of 2000
DIVISION: Trial Division
PROCEEDING: Application pursuant to s 21 Subcontractors’ Charges Act
1974 (Qld)
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 17 July 2000
DELIVERED AT: Brisbane
HEARING DATE: 7 July 2000
JUDGE: Williams J
ORDER: Applicant granted leave to commence and pursue the
application, but application dismissed with costs to be
assessed.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING &
RELATED CONTRACTS – REMUNERATION –
SUBCONTRACTORS’ CHARGE ACT (Q) – application
pursuant to s 21 for an order that a claim of charge made by
respondent pursuant to the Act be cancelled – where
applicant head contractor contracted with respondent for
latter to carry out certain earthworks for a specified sum –
where respondent was subsequently wound up – where on
that basis leave of court pursuant to s 500(2) of the
Corporation Law required to commence and pursue this
application – leave granted – whether respondent has valid
claim of charge against applicant – whether there was money
payable or to become payable to respondent under
subcontract at material time – where parties are in dispute as
to whether respondent in fact fulfilled its obligations to
complete works under contract – factual issues determinative
of whether or not respondent has a valid charge cannot be
resolved summarily – application dismissed.
-- 1 of 6 --
2
Corporations Law, s 500(2)
Subcontractors’ Charges Act 1974 (Qld), s 5(2), s 10(1A),
s 21
Milgun Pty Ltd v Austco Pty Ltd & State of Queensland
[1988] 2 Qd R 670, followed
Re: An Application by James Hardie Building Systems Pty
Ltd (1999) 15 BCL 199, distinguished
Re: Androma Pty Ltd [1987] 2 Qd R 131, applied
Re: Gordon Grant & Grant Pty Ltd (1982) 6 ACLR 727,
applied
Re: Westpac Australia Pty Ltd (unreported, Nos 859 and 897
of 1994, judgment 15 November 1994), followed
Riteway Constructions Pty Ltd v Baulderstone Hornibrook
Pty Ltd [1998] 2 Qd R, distinguished
COUNSEL: K A Barlow for the applicant
J K Bond SC for the respondent
SOLICITORS: Allen Allen & Hemsley for the applicant
Doyles for the respondent
[1] WILLIAMS J: This is an application brought pursuant to s 21 of the
Subcontractors' Charges Act 1974 ("the Act") for an order that a claim of charge
made by the respondent pursuant to the Act be cancelled.
[2] The applicant, Concept Constructions (Qld) Pty Limited, was the head contractor
responsible for carrying out certain earthworks for Eastern Suburbs Leagues Club
Limited ("the Club"). By documents dated 30 September 1999 the applicant
contracted with the respondent, Asphalt Pavements Pty Ltd, for the latter to carry
out certain parts of the total works, being these parts particularised in the
subcontract documents, for the contract sum of $211,195. It will be necessary to
refer to the subcontract in more detail later.
[3] The respondent proceeded with the subject works, and on 9 November 1999
administrators were appointed to that company. Subsequently on 16 December
1999 the respondent was wound-up and the administrators became its liquidators.
[4] According to M J Chamberlain, a director of the respondent up until the winding-
up, the subcontract works were completed by or on 16 December 1999. That
appears from paragraphs 50 and 72 of his affidavit.
[5] Then on 21 January 2000 the respondent, under the hand of its liquidators, gave
notice of claim of charge pursuant to the Act in the sum of $130,394. Pursuant to
that notice of charge the Club paid that amount into the District Court at Brisbane.
[6] This application is brought seeking an order cancelling the charge. Because the
respondent is now in liquidation leave of the court pursuant to s 500(2) of the
-- 2 of 6 --
3
Corporations Law is required. I am satisfied that in accordance with principles
discussed in Re: Gordon Grant & Grant Pty Ltd (1982) 6 ACLR 727 and Re:
Androma Pty Ltd [1987] 2 Qd R 131 at 147 leave should be granted to commence
and pursue this application.
[7] The main contention of the applicant is that the respondent has no valid claim of
charge because at the material time there was no money payable or to become
payable to it under the subcontract as required by sections 5(2) and 10(1A) of the
Act. Section 5(2) provides:
"The charge of a subcontractor shall secure payment in accordance
with the subcontract of all money that is payable or is to become
payable to the subcontractor for work done by the subcontractor
under the subcontract."
[8] Section 10(1A) provides:
"The claim shall be in respect of –
(a) money payable to the subcontractor at the date of the notice;
(b) money to become payable to the subcontractor after the date
of the notice for work done by the sub-contractor prior to
that date."
[9] Counsel for the applicant relied on the way those provisions were applied by
Derrington J in Riteway Constructions Pty Ltd v Baulderstone Hornibrook Pty Ltd
[1998] 2 Qd R 218 especially at 220-221, and by Shepherdson J in Re: An
Application by James Hardie Building Systems Pty Ltd (1999) 15 BCL 199. In
each case the judge concluded that, given the terms of the relevant contract, no
money was payable to, or was to become payable to, the subcontractor for work
done prior to the date on which notice of the charge was given. Counsel for the
respondent submitted that the approach adopted by the judge in each of those cases
was erroneous and that I ought not follow them. I do not regard either case as
laying down any principle other than that the subcontractor must establish that there
is money payable or to become payable with respect to work done prior to the date
of the charge before the charge can be legally effective; so much necessarily
follows from the statute. To that extent there is no error in the reasoning in those
cases; it is not for me to express any view as to whether or not that principle was
correctly applied to the facts of each of those cases.
[10] As the reasoning of Dowsett J in Milgun Pty Ltd v Austco Pty Ltd & State of
Queensland [1988] 2 Qd R 670 and of Ambrose J in Re: Westpac Australia Pty Ltd
(unreported, Nos 859 and 897 of 1994, judgment 15 November 1994) demonstrates,
the mere fact that there is some dispute as to whether or not an amount is payable
does not necessarily mean that no charge can attach.
[11] Given the submissions of each counsel it is necessary to refer to some provisions of
the sub-contract. The Particulars of Engagement contain the following provisions:
“CONTRACT SUM
14. The Sub-Contractor will be paid on (a) Lump Sum
the following basis: [See Clause
19(a)]
-- 3 of 6 --
4
15. Contract Sum [See Clause 19(b)] $211,195.00 (Two
(If lump sum applies, specify sum hundred and eleven
opposite) thousand, one hundred
and ninety-five dollars
only)”.
[12] That part of the sub-contract entitled "Concept Constructions Conditions of Sub-
Contract" contained the following relevant clauses:
"19. Contract sum
(a) The Sub-Contractor will be paid either on a lump sum basis or
schedule of rates basis, as stated in the Particulars of Engagement
(paragraph 14).
(b) If payment is to be made on a lump sum basis, the Contract Sum
is the lump sum stated in the Particulars of Engagement (paragraph
15), adjusted by any additions or deductions in accordance with the
Sub-Contract.
. . .
20. Payments
(a) The Sub-Contractor may submit progress claims to Concept
Constructions each month in the form set out in the Particulars of
Engagement (Attachment D)". Progress claims must not be
submitted by facsimile. . . .
(b) Every progress claim must be fully substantiated with
information and documentary evidence sufficient to allow Concept
Constructions to assess each Progress Claim and must be
accompanied by statements . . .
No payment will be made without this information, documentary
evidence and the statements.
(c) Provided the progress claim is submitted within the time
specified in this clause, and subject to the Sub-Contractor complying
with all conditions precedent to payment, Concept Constructions
will assess the amount to be paid to the Sub-Contractor pursuant to
Clause 20(e) and will make a progress payment to the Sub-
Contractor and the time specified in clause 20(d). . . .
. . .
(h) After the Defects Liability Period expires and all defects have
been made good, the Sub-Contractor must submit a Final Payment
Claim (endorsed as such). Any claim in any way connected with or
arising from the Sub-Contract Works which is not included in the
Final Payment Claim will be barred."
[13] Clauses 14 and 15 of the Terms of Engagement and clause 19 of the Conditions
make it clear that this was a lump sum contract. However, the respondent could, if
it was so minded, make claims for progress payments pursuant to clause 20 of the
Conditions, and the applicant could then make progress payments pursuant thereto.
The use of the word "may" in clause 20(a) to my mind makes it clear that the
progress claim procedure was optional so far as the respondent subcontractor was
concerned. But as the subcontract was a "lump sum" one, once the works were
completed in accordance with the contract the subcontractor was entitled to
payment of the lump sum (subject to any necessary adjustments) .
-- 4 of 6 --
5
[14] In this case the respondent in fact made claims for progress payments. Claims 1
and 2 were apparently processed without any problem. Progress claim number 3
for the sum of $61,344 appears to have been first submitted by the respondent on or
about 1 December 1999. The applicant objected that it was not in the form required
by the contract and requested that it be resubmitted. The administrators of the
respondent resubmitted progress claim number 3 bearing date 6 December 1999;
the applicant contends that was received on 13 December and that can be accepted
for present purposes.
[15] The applicant's submission is that as that progress claim had not been assessed by
21 January 2000 when the notice of claim of charge was given there was as at 21
January no amount payable to the respondent pursuant to the subcontract. The
applicant subsequently proceeded to assess that claim and forwarded its
"assessment" to the respondent on 4 February 2000. That document reveals that the
applicant deducted some $59,000 being the value of work done by others to
complete what the applicant contends was the respondent's responsibility under the
subcontract. With that deduction, and other adjustments, the applicant arrived at a
negative figure of $4,017.17, and in consequence assessed the amount payable to
the respondent as "$Nil".
[16] The respondent rejects the contention that work had to be done by others to
complete works it was obliged by the subcontract to carry out. That dispute is not
something which can be resolved on a summary application such as this.
[17] After their appointment the liquidators submitted what was called progress claim
number 4 dated 28 December 1999 in the sum of $69,050. It will be noted that the
sum of progress claims 3 and 4 equates the amount specified in the notice of claim
of charge. Because the applicant asserts that progress claim 4 was not in the proper
form it has not yet been assessed.
[18] It is in those circumstances that the applicant contends that the charge should be
extinguished because there is no money payable or to become payable to the
respondent pursuant to the subcontract. But, in my view, whether or not there was
an amount payable or to become payable by the applicant to the respondent as at 21
January 2000 with respect to work done prior to that date can only be answered
after factual matters in dispute between the parties have been resolved by a trial. If,
as the respondent contends, the works were completed in accordance with the
contract by 16 December 1999 it could be argued that the contract sum of $211,195
(with any agreed adjustments and less any progress payments made) was then due
and payable. As the contract was a lump sum contract that would arguably be the
case without the necessity of any assessment with respect to a progress claim. If the
applicant be correct in contending that the works were not completed by the
respondent in accordance with the contract, it may well be that no money was
payable or was to become payable as at the date notice of charge was given and the
consequence would be that the charge would then be extinguished.
[19] On that analysis this case raises issues unlike those which were considered by
Derrington J and Shepherdson J in the decisions referred to above.
[20] For the above reasons the issues which will determine whether or not the
respondent has a valid charge cannot be resolved summarily. Counsel for the
-- 5 of 6 --
6
respondent addressed further arguments to the court which could lead to the same
result, but it is not necessary for me to consider them in the light of what I have
already said.
[21] In all the circumstances I would order that the applicant have leave to commence
and pursue the application, but I would dismiss the application with costs to be
assessed.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2000/269