Austin Engineering Pty Ltd v D A Story Pty Ltd & Ors [2000] QSC 97
S"C CX?/O'fJ
SUPREME COURT OF QUEENSLAND
CITATION:
PARTIES:
Austin Engineering Pty Ltd v DA Story Pty Ltd & Douglas
George Arundel Story and Marilyn Story
AUSTIN ENGINERRING PTY LTD
(plaintiff/applicant)
V
DA STORY PTY LTD
(first defendant/first respondent)
V
DOUGLAS GEORGE ARUNDEL STORY and
MARILYN STORY
(second defendants/second respondents)
FILE NO: Sl 757 of 1991
DIVISION: Trial Division (Brisbane Registry)
DELIVERED ON: 28 April 2000
DELIVERED AT: Brisbane
HEARING DATE: 30 March 2000
JUDGE: Mullins J
ORDER: 1. Application adjourned to a date to be fixed for
submissions on appropriate orders and costs.
CATCHWORDS: PRACTICE - SPECIAL REFEREE'S REPORT-
Amendment of defence and counterclaim after reference.
COUNSEL:
SOLICITORS:
Judicature Act 1876
Supreme Court Act 1995
Gordon v Macgregor (1909) 8 CLR 316
Netanya Noosa Pty Ltd v Evans Harch Constructions Pty Ltd
[1995] 1 QdR 650
Nichols v Stamer [1980] VR 479
Shepherd v Felt & Textiles of Australia Ltd (1931) 45 CLR
359
State of Queensland v JL, Holdings Pty Ltd (1997) 189 CLR
146
Mr H B Fraser QC and Mr A P J Collins for the applicant
Mr R J Douglas SC for the respondents
Grays Lawyers for the applicant
Bowdens Lawyers for the respondents
-- 1 of 14 --
2
(l] MULLINS J: This is an application in relation to the amendments made in the
respondents' defence and counterclaim which are found in the document entitled
"Further Amended Defence and Counterclaim of the First Defendant and Second
Defendants" dated 10 December 1999 ("the amendments"). The application
involved a scrutiny of the amendments. Ultimately it was not necessary to decide
whether leave was required to make the amendments or whether the application was
a strike out application, because the same principles were applicable.
(2] The action was commenced by writ issued on 1 October 1991. A precis of the
issues in the applicant's amended statement of claim is that the applicant contends
that it joined with the first respondent in a contract of partnership or joint venture
under which each did different parts of the subcontracted steel fabrication and
erection of steelwork for a superior contractor; that the project was delayed; that the
superior contractor settled a large claim made by the first respondent (on behalf of
the applicant and the first respondent) by paying $2 million to the first respondent;
and that the respondent has failed to account to the applicant for its one-half of the
net proceeds of the $2 million settlement received by the first respondent.
[3] The defences raised in the amended defence and counterclaim delivered 4 June
1997 were that it was the first respondent that had entered into the contract with the
superior contractor for the fabrication of structural steelwork and the first
respondent made an agreement with the applicant to carry out part of that
fabrication; there was neither a partnership nor joint venture agreement between the
applicant and the first respondent; and that by letter dated 10 August 1991 the first
respondent had terminated the agreement on the basis that test results by an
ultrasonic testing company Intico (Qld) Pty Ltd ("Intico") retained by the first
respondent established that the applicant had seriously breached its contractual
obligations as to the quality of its welding.
(4] The testing that was carried out by Intico was described in par 5(b) of the amended
defence and counter.claim as follows:
"(b) say that such testing was carried out pursuant to an express
term of the head contract which provided that the steelwork
fabricated was to comply with minimum quality
requirements analysed by quality assurance testing, namely:
(i) 5% ultrasonic examination on all special purpose
welds thereon;
(ii) 2% magnetic particle inspection on all special
purpose welds thereon;
(iii) 5% lamination checking of portal knee and crane
(mixing); ·
(iv) 100% visual inspection on all special purpose
welds."
(5] In pars 5(c ), (d) and ( e) of the amended defence and counterclaim the respondents
alleged that Intico carried out that testing of the steelwork fabricated by the
applicant which was the box trusses, there was a significant level of failure upon
such testing of the box trusses and that such failures still existed, almost in whole,
upon repeated testing of the box trusses.
-- 2 of 14 --
3
[6] In its amended reply and answer delivered 3 June 1997 the applicant alleged that
Intico failed to carry out the testing in a proper, workmanlike and professional
manner.
[7] After the alleged termination of the arrangement between the applicant and the first
respondent, the first respondent engaged another testing company SGS Australia
Pty Ltd ("SGS") to test 100% of the welds. Prior to SGS's testing, the applicant had
agreed to replace any welds which SGS marked "DNC". SGS marked certain welds
"DNC". Those welds have been replaced. The first respondent intended to rely at
trial upon SGS's test results as evidence supporting Intico's test results. The
applicant complained that SGS's test were badly done and its recorded test results
vastly overstated any imperfections in the welds.
[8] On 16 May 1997 Moynihan SJA ordered that the applicant deliver a list of
issues/questions to be referred to the special referee on or before 4 pm on 3 June
1997. The parties were also ordered to attempt to agree a list of technical
questions/issues which arise in the action, a date for the reference and the identity
of the referee within 14 days of the delivery of the applicant's amended reply and
answer and list of issues.
[9] The parties liaised and agreed upon 23 questions which dealt with the technical
issues in the action concerning the applicant's welding. The questions went to the
quality of the applicant's welding work and the quality of testing works undertaken
by the testing firms Intico and SGS.
[10] On 16 July 1997 the court by consent appointed an engineer, Mr Ken Hinds, as
special referee to inquire into and report upon those questions under s 255(1) of the
Supreme Court Act 1995.
[11] Pre-trial directions by the referee for the exchange of reports were made. There
were some seven directions hearings before the referee. There were 25 hearing
days between 18 August 1997 and 15 June 1999 and 191 exhibits were tendered.
Both sides were represented by solicitors and counsel. Twelve or 13 experts gave
evidence and were cross-examined. There were meetings of experts from each side
to attempt to resolve the issues.
[12] The 191 page report of the referee dated 24 August 1999 was delivered to the court
on 25 August 1999. It provided detailed answers to the questions asked of the
referee.
[13] On 15 October 1999, upon the parties agreeing that answer #6(b)(ii) of the report of
the special referee should be read and construed as:
"The majority of those butt welds marked DNC by SGS were
suitable for their intended purpose. I would estimate that most likely
about 95% by number of all butt welds were always suitable for their
intended purpose."
it was ordered by Derrington J that the report of the special referee be accepted
and adopted by the court for the purposes of the proceedings.
-- 3 of 14 --
4
[14] Section 255 of the Supreme Court Act 1995 is the relocation of sll of the
Judicature Act 1876. In order to work out the effect of s255 of the Supreme Court
Act 1995, it is useful to compare ss256 and 257 of that Act which are the relocation
ofss12 and 13 of the Judicature Act 1876.
[t5] Whereas s255 deals with the referral of any question for inquiry and report to a
special referee, s256 deals with the ordering of any question or issue of fact to be
tried before a special referee to be appointed by the court or judge. Section 257(2)
provides that the report of any referee upon any question of fact on any such trial
shall "unless set aside by the court" the equivalent to the verdict of a jury. Section
257(2) therefore relates to the effect of a trial before a referee under s256.
[16] It is clear from s255(1) itself that for the report of a special referee under that
section to be enforced as a judgment by the court, that it must be adopted either
wholly or partially by the court. This is different to the effect which is given to a
report of a referee upon the trial of a question or issue of fact under s256(1) by
virtue of s257(2). Reference to that distinction in respect of equivalent provisions
in the Judicature Act 1873(UK) is made by Brooking Jin Nichols v Stamer [1980]
VR 479, 487. There is a similar discussion in the judgment of Lee Jin Netanya
Noosa Pty Ltd v Evans Harch Constructions Pty Ltd [1995] 1 QdR 650, 653-655.
[17] The last mentioned decision was in respect of an application by one party for an
order pursuant to s 11 of the Judicature Act 187 6 that certain questions be referred
to a special referee for inquiry and report. The statement at p654 of the report:
"The object of the report being to better enable the Court to decide
the ultimate issues; Longman at 159 per Cotton L.J., s.11 does not
permit the court to abdicate its fact finding function in favour of
reference to some external tribunal. That function always remains a
function of the Court, it being given the sole discretion to decide
what assistance, if any, is to be derived from the referee's report."
must be understood in that context. It was a reference to the status of the report,
before it is adopted by the court. The discretion to decide what assistance is
derived from the report is a reference to the discretion exercised by the court in
deciding whether to and to what extent to adopt the report.
[18] To the extent that the report under s255 is adopted by the court, it becomes the
findings of the court in respect of the matters the subject of the report.
[19] The report in this case is the answers to the 23 questions referred to the referee and
the discussion of the evidence and reasons which resulted in those answers (against
the background of the evidence and submissions made to the referee).
[20] The order of Derrington J made on 15 October 1999 therefore had the consequence
that the findings of fact in the referee's report became the findings of the court on
those facts.
[21] It is therefore relevant to consider the amendments in the context of part of the
evidence of the proceedings being heard and findings made in respect of that
evidence with the rest of the trial due to take place at a subsequent date.
-- 4 of 14 --
5
[22] Mr Douglas SC who appeared for the respondents relied on State of Queensland v
JL Holdings Pty Ltd (1997) 189 CLR 146 to support the amendments and, in
particular, the principle that amendments are ordinarily allowed so as to ensure the
court decides the rights of the parties.
[23] Mr Fraser QC who appeared with Mr Collins of Counsel for the applicant submitted
that the approach in State of Queensland v JL Holdings Pty Ltd had no application
in a case where the application for amendment was made after the trial of the
relevant issues.
[24] Although the facts of State of Queensland v JL Holdings Pty Ltd are distinguishable
from the facts of the present case, the overriding principle adopted by the High
Court on the making of amendments to pleadings remains applicable. Dawson,
Gaudron and McHugh JJ stated at p 155:
"Justice is the paramount consideration in determining an application
such as the one in question. Save in so far as costs may be awarded
against the party seeking the amendment, such an application is not
the occasion for the punishment of a party for its mistake or for its
delay in making the application. Case management, involving as it
does the efficiency of the procedures of the court, was in this case a
relevant consideration. But it should not have been allowed to
prevail over the injustice of shutting the applicants out from raising
an arguable defence, thus precluding the determination of an issue
between the parties. In taking an opposite view, the primary judge
was, in our view, in error in the exercise of her discretion."
[25] In that judgment reference was made to the particular litigation being of a
commercial nature, so that there was nothing to indicate any personal strain which
would justify the conclusion that costs were not an adequate remedy for prejudice
caused by the amendments sought to the pleadings.
[26] In this matter Mr Austin has deposed to the litigation and the trial of the technical
issues before the referee having taken a great personal toll on himself and Mrs
Austin. Mr and Mrs Austin are both directors of the applicant. With or without the
amendments, Mr and Mrs Austin will have to endure the balance of the trial in this
matter. The personal strain that may flow from any additional evidence required as
a result of any amendments must therefore be considered in the context of what it
would add to the trial that was already anticipated.
[27] In general terms, the applicant describes the essence of the amendments as the
allegation in par 5(k) that the applicant evinced an intention not to be bound and
was not ready, willing and able to perform the agreement which is based on a large
collection of detailed allegations involving technical issues about the applicant's
welding. The applicant points out that at the time of the reference there was no
allegation about repudiatory conduct and that par 5 of the amended defence and
counterclaim at that time made it clear that the first respondent's purported
termination was based upon allegations of actual breaches of specific terms which
the pleading identified.
[28] In general terms, the respondents seek to make amendments which incorporate the
content of the referee's report. There are other amendments which the respondents
-- 5 of 14 --
6
seek to make which have arisen out of evidence given in the course of the hearing
before the referee, but which is not the subject of findings by the referee.
[29] The respondents acknowledge that they are now seeking to plead repudiatory
conduct for the first time, but rely on the principle (which is not disputed by the
applicant) that a party seeking to vindicate a termination is entitled to rely upon
grounds which were unknown to it at the date of termination: Shepherd v Felt &
Textiles of Australia Ltd (1931) 45 CLR 359.
[30] Consistent with the overriding principle of achieving justice between the parties
when considering whether amendments to a pleading should be allowed, as
espoused in State of Queensland v JL Holdings Pty Ltd, the amendment of a
pleading to include an alternative basis for terminating a contract, even at a late
stage, is not necessarily objectionable. Generally, the test must be what additional
factual matters are raised by the amendment and whether that causes prejudice to
the other party which cannot otherwise be accommodated.
[31] Because of the report of the special referee in this case, there is the complication
that the raising of factual matters at this stage which are either covered or could
have been covered by the report must be considered in the light of the report.
[32] Mr Douglas submitted that the issue as to whether or not the first respondent was
entitled to terminate the "arrangement" with the applicant was an issue that was
always to be determined by the trial judge and that the reference of issues to the
referee for inquiry and report was not intended to conclude the cause or matter or
even finally determine the rights of the parties or issues in dispute between them.
[33] It is true that the findings of the referee on the technical issues do not result in the
determination of any ultimate issue in the action which involves mixed questions of
fact and law. Each ultimate issue has been left to the trial judge. To the extent that
those technical issues are steps in the ultimate finding process, the adoption of the
report in this matter has disposed of those technical issues. That does not
necessarily preclude further technical issues now being raised. It depends on
whether doing justice between the parties permits amendments to be made at this
stage which would have the effect of raising further technical issues. The question
of justice must taken into account all relevant considerations, as they affect both
parties. One of the relevant considerations is that the original intention of the
parties and the court was that the technical issues in the action were to be dealt with
by the referee.
[34] If the factual matters raised by any of the amendments were disposed of by the
report, as the report has been adopted, those factual matters cannot now be raised,
except as found in the report. This raises the issue of whether it can be determined
on this application whether and how a factual matter has been disposed of by the
report. It is implicit in the applicant's submissions that it can be done. On the other
hand, it is submitted on behalf of the respondents that the question of the
amendments is being considered on an interlocutory basis and it is a matter for the
trial judge to consider what any particular part of the report means.
[35] The report is extremely comprehensive. In relation to each question, the referee has
set out each party's proposed answer, the submissions and evidence put forward by
-- 6 of 14 --
7
each party, a full discussion of that evidence and the reasons of the referee and,
finally, the answer to the question which accords with the discussion on evidence
and reasons.
[36] Even though this is an interlocutory application, where the respondents rely on the
report for making the amendment and it is clear that the amendment is not
supported by the report, the amendment should not be allowed.
[37] I shall deal with each of the amendments in the same order and groupings as set out
in the applicant's written outline of submissions (Exhibit 1).
5(d)-(e)
[38] Firstly, the respondents foreshadowed in their solicitors' letter dated 2 February
2000 to the applicant's solicitors that they propose to replace the word "failure" in
par 5(d) and the word "failures" in par 5(e) with the words '"does not comply'
results" in addition to the amendment which is shown on the further amended
defence and counterclaim of inserting the words "recorded by Intico" in par 5(d)
and the word "recorded" in par 5(e). During oral submissions, Mr Douglas stated
that it was intended that par 5( d) refer to Intico's test when engaged by the applicant
and that par 5( e) was a reference to testing undertaken by Intico at the request of the
respondents.
[39] Secondly, Mr Douglas sought leave to make a related amendment to par 5(k) by
substituting "sub-paragraph (gi)" for "sub-paragraphs (a) to (gi)".
[40] Without that amendment to par 5(k), the facts pleaded in pars 5(d) and (e) were
relied on for supporting the allegation of repudiatory conduct on the part of the
applicant set out in par 5(k). As a result of that related amendment, the allegations
in pars 5(d) and (e) are not relied on in relation to termination. That is also
consistent with par 5(1).
[41] Mr Douglas also sought leave to amend par 5(1) to rely on the repudiatory conduct
pleaded in par 5(k) to justify the alleged termination. This was a technical
amendment necessary in order to give some effect to par 5(k).
[42] Mr Douglas submitted that the allegations in pars 5(d) and (e) were relevant to the
allegation against the second respondents, made against them as directors of the
first respondent, that they acted in disregard to their duties as directors of the first
respondent, as pleaded in par 20 of the amended statement of claim. It was
submitted that the respondents wished to rely upon the fact of what the Intico
reports on their face recorded, irrespective of the findings of the referee as to
whether these recorded results were correct or not.
[43] Mr Douglas also submitted that the amendments in pars 5(d) and (e) did not raise
any new technical issue.
[44] The applicant relied on the referee's answers to questions #7(a), #7(b)(ii) Extent,
#7(b)(iii) Significance, #S(a) and #S(b)C and made the submission that pars 5(d)-(e)
were inconsistent with the referee's answers.
-- 7 of 14 --
8
[45] The justification put forward by the respondents that the amendments to the
allegations in pars 5(d) and (e) are required to meet the issue of the mala fides of
the second respondents is not reflected by the amendments. One difficulty with the
amendments is that the respondents have tried to keep the wording changes to a
minimum. Even changing the word "failure" to "does not comply result" leaves the
description of the test results referred to in both pars 5(d) and (e) as being a
significant level of "does not comply results". That does not accord with the
referee's answer #7 (b )(iii).
[46] There would be no difficulty making an amendment that did not raise technical
issues, but relied historically on the test results recorded by Intico in respect of the
second respondents actions' in relation to termination, but the present amendments
to pars 5(d) and (e) do not effect what is intended and, as presently worded, are
inconsistent with the answers in the report relied on by the applicant. The
amendments to pars 5( d) and ( e) will not be allowed.
5(gi)i
[47] During the course of submissions Mr Douglas obtained instructions to give an
undertaking that in respect of the amendments proposed to par 5(gi)i to viii, the
respondents would not lead any further evidence at trial, other than to rely on the
referee's report.
[48] One of the bases on which the applicant opposed the amendment to par 5(gi)i was
that it would be manifestly unjust to allow the respondents to now call contrary
evidence to that called before the referee. The undertaking not to call further
evidence at trial on the issue raised by the amended par 5(gi)i overcomes this
objection.
[49] The other basis for objecting to this amendment was that the applicant considers
that the allegation is contradicted by the report. The respondents rely particularly
on the second and third paragraphs on page 60 of the report to support the
allegation made in the amendment.
[50] The second and third paragraphs on page 60 of the report relate to answer #4B(b)
which is set out on pages 60-61 of the report. The answer accepts that ". .. a
percentage of the total butt welds carried out by Austin may have contained
imperfections which, upon appropriate testing and assessment in accordance with
AS1554.l, would have been found to have exceeded the levels in Table 6.3 of
AS1554.1-1985". It is then relevant to consider the subsequent discussion of the
evidence by the referee in dealing with question #4B(c) and the statement in the
second last paragraph on page 95:
"I accept that a reasonable interpretation of AS1554, consistent with
my experience, is that Austin are not non-compliant just because the
maximum level of imperfections permitted by Table 6.3 of
AS1554.1 is exceeded."
[51] The allegation in par 5(gi)i therefore does not accord with the report and should not
be allowed.
-- 8 of 14 --
9
5(gi)ii
[52] The applicant's complaint is about the use of the words "at least" when the finding
in the report (as modified by the order made on 15 October 1999) at answer
#6(b )(ii) is that "I would estimate that most likely about 95% by number of all butt
welds were always suitable for their intended purpose". The respondents rely on
the final paragraph on page 134 of the report:
"I am of the opinion that a figure of 95% being suitable for the
purpose, on the balance of probability, is likely to be correct given
the facts, but, on any reasonable view of the evidence a figure
greater than 90%."
[53] The corollary of the findings as incorporated in answer #6(b )(ii) is that about 5% by
number of all butt welds were not suitable for their intended purpose.
[54] The other objection which the applicant had to par 5(gi)ii was that it would require
experts and lay witnesses to be called to give evidence about the significance of the
level of unfit welds. That objection is met by the respondent's undertaking not to
call any further evidence in relation to this amendment.
[55] In the light of that undertaking and provided the words "at least" are substituted
with the word "about" or similar words, par 5(gi)ii should be allowed to remain.
5(gi)iii-viii
[56] Par 5(gi)iii reflects answer #1 in the report. Par 5(gi)iv refle~ts the first paragraph
on p31 of the report. In the light of the undertaking not to call further evidence,
they should be allowed.
[57] During oral submissions Mr Douglas sought leave to further amend par 5(gi)v by
deleting the word "permit" and substituting the word "require". That would make
par 5(gi)v read as follows:
"the approved workshop drawings did not require reinforcement but
complete penetration full strength butt welds;"
The use of the word "require" rather than "permit" makes par 5(gi)v accord more
closely with the statement in par 2 on p 29 of the report. It is then appropriate to
allow that amendment, having regard to the undertaking not to call further evidence.
[58] Paragraph 5(gi)vi reflects the statement made by the referee in the first sentence of
the last paragraph on page 131 of the report:
"I accept the evidence of Austin that reinforcement was present in
the vast majority of welds but not on all welds."
In the light of the undertaking not to call further evidence, it is appropriate to
allow the amendment to par 5(gi)vi.
[59] Paragraph 5(gi)vii is based on the first sentence of the third paragraph on page 28 of
the report. It is apparent, however, from the balance of that paragraph and the
following paragraph that the referee considered that full strength could also be
achieved with reinforcing of the butt weld as an alternative to complete penetration
-- 9 of 14 --
10
of the butt weld. As par 5(gi)vii does not reflect the report, it should not be
allowed.
[60) Paragraph 5(gi)viii appears to be based on the second last paragraph on page 28 of
the report. The statement made on that paragraph has been taken out of context in
the manner in which it has been incorporated in par 5(gi)viii. Paragraph 5(gi)viii
purports to be a statement that all butt welds fabricated by the applicant were
welded with reinforcement to compensate for lack of fusion. That is not consistent
with the evidence accepted by the referee that despite Mr Austin's considering that
the term FSBW did not require complete penetration, complete penetration welds
were being attempted by Austin (second last paragraph on page 148 of the report).
[61) The statement made in the second last paragraph on page 28 is made in the context
of answering the question #3 about the meaning of the FSBW which stands for full
strength butt welds. The statement which is the genesis of par 5(gi)viii is not a
finding that all butt welds were not complete penetration butt welds. It is a
statement that if a butt weld was not complete penetration, it could have lack of
fusion which could not be classed full strength without reinforcing. As par 5(gi)viii
does not reflect the report, it should not be allowed.
S(gi)ix, xi
[62] Mr Douglas conceded that evidence may need to be led on these issues at the trial.
He submitted, however, that it did not involve opening any issue on the sufficiency
of the welding, but evidence on sufficiency of procedures. Each paragraph clearly
raises technical issues.
[63] In relation to par 5(gi)ix, the respondents relied on lines 12 to 15 of page 1305 of
the transcript of the examination-in-chief of Mr Austin. In relation to par 5(gi)xi,
the respondents rely on pages 1342, 1351 to 1355 of the transcript of the cross-
examination of Mr Austin. There is therefore no finding of the referee which is the
basis for including these two paragraphs.
[64] The applicants submits that the evidence given by Mr Austin about these issues was
in a context in which there was no allegation of breach or conduct evidencing
repudiation. The applicant relied on the statement made by Griffith CJ in Gordon v
Macgregor (1909) 8CLR 316,321:
11 ••• it is a very dangerous thing after the close of the evidence to
allow an amendment to raise a point founded on some oral statement
by a witness, which may be perfectly complete so far as it is relevant
to the issues which are being tried, but which if it were given with
reference to entirely different issues would be incomplete. It is like
allowing a party to rise a new case on appeal when the Court has not
all the materials before it. 11
[65] The reliance on that passage from Gordon v Macgregor would have greater
significance, ifthere were no further opportunity for evidence on these issues. What
is more critical is whether a technical issue should be allowed to be raised by an
amendment to the pleading at this stage, after the technical issues in the action have
been dealt with by the referee.
-- 10 of 14 --
11
[66] There is no material from the applicant to suggest that the technical evidence
required in respect of these two new paragraphs would be significant. The personal
strain on Mr and Mrs Austin of having to put on further technical evidence in
respect of the further hearing of this matter must be weighed up against the need to
afford the respondents the opportunity to pursue factual matters which arose out of
the evidence of Mr Austin.
[67] Notwithstanding that pars 5(gi)ix and 5(gi)xi raise technical issues which could
have been the subject of questions directed to the referee, if raised at an earlier
stage, on balance I consider that the justice of the matter favours allowing these
amendments.
S(gi)x
[68] Paragraph 5(gi)x is based on page 1342 of the transcript of the cross-examination of
Mr Austin. The applicant objects to this paragraph on the basis that it must raise
technical issues, and that the evidence about the ETRS test at the hearing before the
referee was given in a context other than that the ETRS test result evidenced
repudiation by the applicant. The applicant also submits that the referee's other
answers are inconsistent with the proposition that the alleged "non-compliance" rate
of 30-40% on the ETRS test was an accurate reflection of the quality of the
applicant's welding.
[69] The allegation in par 5(gi)x links to the allegation made in par 5(gi)xi. For the
same reasons that I have allowed pars 5(gi)ix and xi, I consider par 5(gi)x should be
allowed.
S(gi)xii
[70] The respondents rely on pages 1357 and 1366 of the transcript of the cross-
examination of Mr Austin for the allegations set out in par 5(gi)xii. The
respondents wish to say that Mr Austin on behalf of the applicant by adopting the
position that the butt welds marked FSBW were not required to be complete ..
penetration full strength butt welds amounted to the applicant repudiating the
arrangement with the first respondent.
[71] The applicant relies on the fact that at the hearing before the referee the first
respondent accepted (and relied upon for a different purpose) and the referee found
(at the second last paragraph of page 148 of the report) that the applicant despite Mr
Austin's belief nevertheless set out to achieve complete penetration butt welds. ·
[72] It is therefore inconsistent with the course adopted by the respondents at the hearing
before the referee and with the referee's finding that complete penetration welds
were being attempted by the applicant for the respondents to now allege that Mr
Austin's belief about the meaning of FSBW amounted to repudiatory conduct.
[73] The particulars of the contentions in par 5(gi)xii are stated to be those set out in pars .
5(h),(i) and (i). The applicant relied on the matters set out in pars (h),(i) and (i)
being events which occurred after the alleged date of termination. Mr Douglas
conceded that the matters set out in pars 5(h),(i) and (i) postdated the alleged date of
termination, but submitted that evidence both before and after termination was
-- 11 of 14 --
12
relevant to whether Mr Austin prior to the alleged date of termination had the belief
and contention set out in par 5(gi)xii. The applicant submitted that it was the work
undertaken by the applicant, rather than any uncommunicated belief of Mr Austin
which was relevant.
[74] The finding made by the referee that complete penetration welds were being
attempted by the applicant makes irrelevant an allegation now based on a belief of
Mr Austin that was uncommunicated prior to the alleged termination. Paragraph
5(gi)xii should not be allowed on the basis that it is inconsistent with the report of
the referee.
S(gi)xiii-xiv
[75] The respondents submit that no technical issues are involved in the allegations in
par 5(gi)xiii-xiv and that they are questions of fact which would never have been
referred to the referee now can be dealt with by the trial judge. Mr Douglas
conceded that further evidence would be required on these issues and there may
need to be evidence about whether the time limit mentioned in par 5(gi)xiii could be
complied with. Mr Douglas suggested that there might need to be the evidence of a
fabricator, but that it was more likely that expert evidence would be required.
[76] The applicants submitted that a great deal of evidence was led in the reference
about what was involved in the applicant's work and in the testing and repairs and
that the time within which the fabrication (including and necessary testing and
repairs) could have been achieved raises new technical issues which could have
been the subject of questions in the reference.
[77] There is no material from the applicant to suggest that the technical evidence
required in respect of par 5(gi)xiii would be significant. For similar reasons to my
decision in respect of pars 5(gi)ix and 5(gi)xi, I consider that, on balance, the justice
of the matter favours allowing these amendments, even though technical issues may
be raised by par 5(gi)xiii.
S(gi)xv
[78] Mr Douglas conceded that this amendment will entail expert evidence being led at
the trial.
[79] The applicant submitted that this paragraph incorporates assumptions that the
previous paragraphs are permissible and contain accurate allegations and raises new
and extensive technical issues which should. have been the subject of specific
questions to the referee.
[80] It is difficult to see how the allegation incorporated in this amendment about an
engineer is one of the facts now relied on as repudiatory conduct of the applicant.
[81] The problem with par 5(gi)xv is that it does incorporate statements that are
inconsistent with the referee's report. In particular the allegation implicit in this
amendment that the box trusses fabricated by the applicant contained butt welds
which did not comply with the requirements of AS1554-1985 is not consistent with
answer #4B(b) of the report and the allegation that the butt welds were not fit for
-- 12 of 14 --
13
their intended purpose is not consistent with the finding in answer #6(b)(ii), as
adopted by the court.
[82] On the basis of inconsistency with the referee's report, paragraph 5(gi)xv should not
be allowed.
5(gi)xvi
[83] This amendment follows on from pars 5(gi)xiii and xiv. It therefore should be
allowed.
5(k)-(l)
[84] As I have allowed some of the amendments to par5(gi) which form the basis of the
allegation in par 5(k) and the amendment to par 5(1), these amendments should also
be allowed. The amendments to these paragraphs for which leave was sought
during the oral submissions should also be allowed.
2(e)
[85] This amendment sets out that:
"it was an express term of the head contract that welding of
structural steelworks was to be in accordance with certain Australian
Standards including AS1554-1985;"
[86] The applicant objects to this amendment on the basis that it is irrelevant, except to
support the contentious amendments to par 5.
[87] Having regard to the stage at which this action has reached, when a further hearing
is due to take place and that this amendment raises a question of fact, the
amendments should be allowed.
2(f)ii
[88] Paragraph 2(±) deals with the implied tenns alleged by the respondents in respect of
the arrangement between the applicant and the first respondent. Paragraphs 2(f)ii.
(2) and (3) are new allegations. They are that the steelwork fabricated by the
applicant would be "suitable for its intended purpose under the head contract" and
"in accordance with approved workshop drawings". Particulars are given of the
circumstances by which the terms. were implied. They are set out as pars A to H.
The applicant objects that particulars B, D, E and F also raise previously unpleaded
technical issues.
[89] The respondents rely on evidence of some of the expert witnesses at the hearing of
the reference to support the matters alleged in pars B, D, E and F. The ambit of the
issues raised by those paragraphs does not appear significant and was not suggested
to be so by the applicant. Otherwise, the matters raised by amendments are factual
matters which were not the subject of findings by the referee.
[90] Doing justice to both parties favours allowing the amendments to par 2(f)ii.
5(a)
-- 13 of 14 --
14
[91] Although the applicant objects to the amendments to par 5(a)-(c), the only
amendment which appears to have been made is to par 5(a).
[92] In the amended defence and counterclaim, the allegation in par 5(a) was that on
various occasions in 1990 and 1991 the first respondent engaged Intico to carry out
quality assurance testing in respect of the steelwork fabricated by the applicant.
The amendment made to par 5(a) has substituted the applicant for the first
respondent, ie the allegation is now that the applicant engaged Intico to carry out
the quality assurance testing
[93] That is a factual matter which can still be dealt with at the future hearing in this
action. It was not a matter which was the subject of a finding by the referee. The
amendment should therefore be allowed.
Conclusion
[94] I am therefore prepared to order that leave be given to amend:
(a) paragraph 5(gi)v by deleting the word "permit" and substituting the word
"require";
(b) paragraph 5(k) by deleting "sub-paragraphs (a) to (gi)" and substituting
"sub-paragraph (gi)";
(c) paragraph 5(1) by deleting "sub-paragraph (gi)" and substituting "sub-
paragraphs (gi) and (k)".
[95] I propose to disallow the amendments made to pars 5(d), 5(e), 5(gi)i, 5(gi)vii,
5(gi)viii, 5(gi)xii and 5(gi)xv of the further amended defence and counterclaim
dated 10 December 1999.
[96] I note that I have allowed the amendments to pars 5(gi)ii-5(gi)vi on the basis of the
undertaking given by Mr Douglas on behalf of the respondents that the respondents
will not lead any further evidence at trial in respect of those issues other than to rely
on the referee's report.
[97] The three amendments foreshadowed during all oral submissions for which I am
prepared to give leave may now not suit the respondents in the light of my
disallowance of some of the amendments made in the defence and counterclaim
dated 10 December 1999. The respondents may also wish to consider whether they
wish to proceed with all the amendments which I have allowed, in the light of my
disallowance of some amendments. In addition, my allowance of par 5(gi)ii is
dependent on an appropriate wording change to the words "at least".
[98] I will therefore allow the parties an opportunity to submit an order which reflects
these reasons which is acceptable to both parties or I will otherwise entertain
submissions on a convenient date to the parties as to the appropriate form of orders
and an appropriate order for costs.
[99] I therefore order that the application be adjourned to a date to be fixed for
submissions on appropriate orders and costs.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2000/097