Beralt Pty Ltd v Japaul Pty Ltd [2000] QSC 89
SUPREME COURT OF QUEENSLAND
CITATION: Beralt P/L v Japaul P/L [2000] QSC 089
PARTIES: BERALT PTY LTD ACN 060064 020
(applicant)
v
JAPAUL PTY LTD ACN 077 823 459
(respondent)
FILE NO: S7339 of 1999
DIVISION: Trial
DELIVERED ON: 18 April 2000
DELIVERED AT: Brisbane
HEARING DATE: 30 September 1999
JUDGE: Muir J
CATCHWORDS: CORPORATIONS LAW – APPLICATION TO SET ASIDE
STATUTORY DEMAND – CONSEQUENCES OF
SERVICE OF DEMANDS IN DIFFERENT STATES –
SERVICE REQUIREMENTS - WAIVER –
CORPORATIONS LAW S 459G
COUNSEL: Mr Hackett for the applicant
Mr Barlow for the respondent
SOLICITORS: Colwell Wright for the applicant
Russell and Company for the respondent
[1] The applicant served a statutory demand on the respondent on 26 July 1999. It
demanded payment of $34,444. In excess of $21,000 of that sum was claimed for
painting services “pursuant to the external contract dated 25 February 1999”. The
claim was divided into three progress claims dated 29 January 1999, 26 February
1999 and 17 March 1999 respectively. The balance was claimed under a heading
“painting services provided pursuant to the internal contract dated 25 February
1999”. Two progress claims dated 26 February 1999 and 17 March 1999 were
referred to under that heading.
[2] The matter first came before me in Supreme Court Chambers on 30 September
1999. The respondent sought to have the application dismissed as being made out of
time. Various technical points were put forward in support of that submission. As
the legal representative of the applicant did not appear to be in a position to deal
fully with the points raised, I adjourned the matter and gave the parties the
opportunity of making further submissions in writing. That was done. On 11
November 1999 I decided the preliminary point against the respondent. It is now
necessary for the application to be decided on its merits.
-- 1 of 3 --
2
[3] It is submitted on behalf of the respondent that –
(a) there is no genuine dispute; and
(b) the affidavit filed within time made no mention of an
offsetting claim and did not attempt to quantify one.
Consequently, as no such claim was raised within the time
permitted by s 459G it was not open for the applicant to
raise one;
(c) alternatively, if the application were to be granted it should
be granted only on condition that the applicant pay the
amount of the respondent’s claim into court.
[4] The applicant submits that the claims which form the basis of the statutory demand
are ill-founded as both of the relevant contracts are lump sum contracts. It further
submits that there is evidence that the subject works are incomplete and defective.
In respect of the allegation that the works are incomplete it points to an alleged
admission contained in a letter from the respondent.
[5] The contract for the external painting dated 25 February 1999 is specified to be a
“lump sum” contract for a contract price of $25,920. Clause 4, however, provides –
“(a) Progress Payments shall be made (as provided in the
Schedule) by the Principal or by the Construction Manager
on behalf of the Principal.”
A schedule provides for a commencement date of 20 January 1999 and a
completion date of 19 February 1999. It also provides for progress payments to be
made monthly on the basis of claims “by 30th day of each month” and “payment
within approx 25 days”. The contract for internal painting for a “lump sum” price of
$15,300 is similarly worded.
[6] Although there is an element of ambiguity in the contracts arising from the lump
sum description, it is plain enough that they make provision for monthly progress
payments. The specific provisions of the contract spelling out the way in which
progress claims may be made must be taken to override the more general reference
to the contract as being one for a “lump sum”. Accordingly, this contention of the
applicant fails.
[7] In my view the applicant has not demonstrated existence of a genuine dispute. The
affidavit filed in support of the application made a complaint that the exterior paint
works were defective “… in that not enough coats of paint have been applied to the
surfaces and the finish does not look even”. The deponent does not state any
contractual basis for the claim of insufficiency of coats. The deponent also asserts
that the painting has not been completed but does not state the extent to which the
work is incomplete, let alone the cost of remedying any deficiency.
[8] The affidavit received some modest support from Mr Ell, Project Manager and,
possibly, from a painter who did alleged remedial work, Joshua Ford. Indeed, Mr
Ford and Mr Ell, in speaking of alleged defects are probably merely describing
uncompleted work. The applicant’s affidavit material generally is very short on
specifics and much of the applicant’s complaints concern ill-founded allegations
based on the erroneous premise that the respondent was not entitled to make
progress claims.
-- 2 of 3 --
3
[9] The material discloses that when the progress claims were made no objection was
taken to them by or on behalf of the applicant. Rather, the applicant intimated that it
was experiencing liquidity difficulties but that payment would be forthcoming in
due course. Included in the respondent’s material is an affidavit by the person who
was the applicant’s construction manager at relevant times. He deposes to the
adequacy of the respondent’s workmanship and to having approved the
respondent’s progress claims.
[10] The applicant was thus in breach of contract in failing to pay the progress claims.
The respondent, however, did not terminate the contract in reliance on the
applicant’s breach, as it was entitled to do. When requested to continue with the
work it sought to impose conditions (including provision of a bank guarantee) as a
prerequisite to its further performance. There was no lawful justification for this
course of conduct. However there is no evidence that the applicant, before having
the alleged outstanding work done, took steps to make time of the essence or
otherwise to make the site available to the respondent to permit it to perform its
obligations. There is evidence, in an affidavit sworn on behalf of the applicant, that
the plaster work was inadequate and needed re-doing. The material before me
suggests a mutual abandonment of the contract. Both parties manifested an
intention not to perform their respective obligations. In the case of the respondent it
would only perform further if the applicant met its unsustainable demand for a bank
guarantee. In the case of the respondent, it wanted further work done but would not
pay for work already done as it was obliged to do. It made it impossible for the
respondent to perform by having the work completed. Abandonment of the
contracts, of course, would not relieve the applicant of its obligation to pay the
respondent for progress claims duly made.
[11] Another difficulty faced by the applicant is that its initial affidavit supporting the
application was inadequate to support its contention of a claim or cross-claim. It
made no attempt at any quantification of the alleged claim or cross-claim. Nor did it
show any cross-claim equal to or greater in amount than the amount claimed by the
respondent. One was left to speculate as to the nature and extent of any claim for
damages or cross-claim. There was thus no affidavit which met the requirements of
s459G(3) of the Corporations Law. Even the material subsequently filed in support
of the application does not reveal a cross-claim which is capable of quantification.
[12] Accordingly, I order that the application be dismissed. I will hear submissions as to
costs.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2000/089