Brisbane City Council v Micalizzi & Anor [2000] QPEC 29
PLANNING AND ENVIRONMENT
COURT OF QUEENSLAND
CITATION:
PARTIES:
Brisbane City Council v P & L Micalizzi
BRISBANE CITY COUNCIL
(Appellant)
V.
PETER MICALIZZI AND LYDIA MICALIZZI
(Respondents)
FILE NO/S: 1238 of 2000
DIVISION: Planning and Environment Court
PROCEEDING: Appeal
DELIVERED ON: 12 April 2000
DELIVERED AT: Brisbane
HEARING DATE: 12 April 2000
JUDGE: Judge Brabazon QC
ORDER: Application Dismissed
CATCHWORDS: REGULATION OF CONSTRUCTION - Whether
respondent had commenced work under a building permit
sufficiently to enable the permit to stay current - Definition
of commencement of work - Differences under IPA and
Local Government (Planning & Environment) Act
COUNSEL:
SOLICITORS:
Mr M Hinson SC for the Appellant
Mr R Litster for the Respondent
Brisbane City Legal Practice for the Apellant
Deacons Graham & James for the Respondents
-- 1 of 11 --
..._ '-'-· .t' '-' .. .., .......... b ......, ..... Jl. '--' ...... 11,..a.
TRANSCRIPT OF PROCEEDiNGS
Copyright in this transcript is vested in the Crown. Copies thereof must not be made
or sold without the written authority of the Director, State Reporting Bureau.
PLANNING AND ENVIRONMENT COURT
JUDGE BRABAZON QC
Application No 1238 of 2000
BRISBANE CITY COUNCIL
and
PETER MICALIZZI and
LYDIA MICALIZZI
BRISBANE
.. DATE 12/04/2000
JUDGMENT
.L
REVISED COPfE.S ISSLE:D
State Reporting Bureau
Date I I I o ~ I oo
J:..ppellant
Respondents
-- 2 of 11 --
12042000 T01/AW20 M/T CMS 39/2000 (Brabazon DCJ)
HIS HONOUR: In this case the Court is concerned with the
suggestion that a Town Planning Consent Permit has expired,
because of the passing of time, without sufficient work
being done to preserve it.
On 24 January 1995 the Brisbane City Council issued Town
Planning Consent Permit 412 of 1995. That authorised the
erection and use of a building on land at 85 Stevenson
Street, Ascot. Under the provisions of The Local
Government (Planning and Environment Act) 1990 section
4.13(18) provided that a permit of that kind lapsed after
four years of the date of issue if the use of the land or
the use or erection of a building or other structure on the
land, the subjecc of the approval, had not been commenced
within that four years.
In this case tise passed. Finally on 15 January 1999 the
architects of the land's owners, Mr and Mrs Micalizzi,
received the building approval and told their clients that
it had been received. That approval had been preceded by
the usual steps taken when architects and engineers are
engaged on such a project.
Those steps took place between 7 July 1998 and the final
notification of building approval. Architects were
retained, engineers were retained, soil tests were done,
the report of the soils tests was provided, architectural
and engineering drawings were provided and in due course
2 JUDGMENT
10
20
30
40
50
60
I
-- 3 of 11 --
12042000 T01/AW20 M/T CMS 39/2000 (Brabazon DCJ)
they were all sent to the Council as part of the
application for approval.
The first question to be decided is whether or not the
coming into force of The Integrated Planning Act on
30 March 1998 had an influence on the status of the Town
Planning Consent Permit.
it did.
It is said by the Council that
Attention has to be paid to section 6.1.23 of The
Integrated Planning Act. That section deals with the
continuing effect of approvals issued before 30 March 1998;
that is under the former Planning and Environment Act.
The general effect of subsection (2) is that a cont:~u:ng
approval and a~y conditions attached tc that cont:~~1ng
approval have effect as if the approval and the conditions
were a development approval in the form of a preliminary
approval or development permit as the case may be. What
that means (in the language which has been us to describe
the processes of The Integrated Planning Act) is that the
continuing approval has been transitioned into the
framework of The Integrated Planning Act.
Then subsection (3) of The Integrated Planning Act provides
that:
"Subsection (2) has effect only for the period the
continuing approval would have had effect if the
repealed Act had not been repealed."
3 JUDGMENT
10
20
30
40
50
60
-- 4 of 11 --
12042000 T01/AW20 M/T CMS 39/2000 (Brabazon DCJ)
It must also be noted that approvals under The Integrated
Planning Act also lapse, according to the provisions in
section 3.5.21. The life of such approvals is now called
a currency period. The difference, it is said, between The
Planning and Environment Act provisions and The Integrated
Planning Act provisions are to be found in section
3.5.21(1) (c). A development application of this kind
lapses at the end of the four year period. But there will
be no lapse provided that "development under the approval
substantially starts before the end of the currency
period." (emphasis added)
That use of the expression "substantially starts" can be
contrasted with the less demanding hurdle found in section
4.13(18) of The ?lanning and Environment Act which o~ly
requires that certain things "commence" within the four
years of the issue of a permit.
In this case it is submitted for the Council that the
transition oft approval into The Integrated Planning Act
has the effect of also picking up the more demanding hurdle
in the new Act. It is then submitted, on the facts, that
work here had not substantially started before the end of
the currency period. Therefore, the approval is void.
There are a ' numDer of considerations which point to the
correct conclusion about the effect of the transitional
arrangements.
4 JUDGMENT
10
20
30
40
50
60
-- 5 of 11 --
12042000 T01/AW20 M/T CMS 39/2000 (Brabazon DCJ)
The provisions are partly dealt with in a decision of this
court, Friends of Stradbroke Island Association Inc v
Kennedy and others, 1999 Queensland Planning and
Environment Law Reports 117. There, it is pointed out that
permits of this kind are "continuing approvals" within the
meaning of section 6.1.23(1) (b) of The Integrated Planning
Act. The effect of subsection (3) is that the transitional
arrangements mean that the permit has effect only for the
period the continuing approval would have had effect if The
Planning and Environment Act had not been repealed.
That is a perfectly correct statement about the immediate
effect of subsection (3) of the IPA provisions. However,
in my opinion, that subsection has a further effect. Not
only does it have the effect of maintaining the four year
time limit under the old statute - it also has the effect
of keeping in force the conditions, both statutory ana
otherwise, applying to the permit. In my opinion, the
transitional arrangements do not go so far as to pick up
the new provisions in The Integrated Planning Act about
currency periods. Rather one has to continue to refer to
the provisions about the lapse of such permits to be found
in section 4.13(18) of The Planning and Environment Act.
If there were doubt about the matter, reference should be
made to the provisions of The Acts Interpretation Act to
reach the same conclusion. That is, section 20 provides
that the repeal of an Act does not affect:
5 JUDGMENT
10
20
30
40
50
60
-- 6 of 11 --
12042000 T01/AW20 M/T CMS 39/2000 (Brabazon DCJ)
"the previous operation of the Act or anything
suffered, done or begun under the Act or (c) effect to
right, privilege or liability acquired, accrued or
incurred under the Act."
If there were doubt about the matter, that provision would
be decisive in presuming that the old statute continues to
apply.
The result is that it is only necessary that something
described within subsection 18(a) must commence within the
four years. In this case it can be seen that it is
critical to see whether or not there has been such a
commencement before the expiry of four years which took
place at midnight on 24 January 1999.
There are a numcer of considerations that mignc be kepc
mind. First of all, as mentioned in The Friends of
Stradbroke Island case subsection 4 .13 (18) (a) requires that.
there be a complete absence of commencement of any activity
authorised by a permit within four years before the permit
lapses.
Secondly, as one can see from the decision in the High
Court of Australia in Owendale Pty Ltd v Anthony and
another 117 CLR 539, there is no need for substantial work
over a long period of time to have commenced.
In that case, a few hours work done on the day before the
expiration of a notice was sufficient where there was a
requirement that a lessee had to "commence to erect" a
6 JUDGMENT
20
rn
-- 7 of 11 --
12042000 T2/PAF23 M/T CMS39/2000 (Brabazon DCJ)
building within a prescribed period.
considerations apply here.
Similar
Also to the same effect are the views of Professor Fogg of
the University of Queensland, writing in his Study Guide
number 7, at page 13. The situation here can be contrasted
where there is a requirement that work "substantially
starts". That was the position, in effect, under the
former Local Government Act which required that
"substantial progress" had to be made (see section
33 (16D) (b) (i) (A)) . With the adoption of that higher
standard in the Integrated Planning Act the wheel has
turned full circle, but that difference must be kept in
mind in considering the provision under the Planning and
Environment Act.
Attention has to be paid to the decision of Connolly Jin
Dackfield (1983) QR page 10. There, some general
propositions were drawn from the established cases, but it
should be kept in mind that they were dealing with a test
of substantial commencement. In that case, Connolly J's
fourth proposition was to the effect that:
"Where a provision called for substantial commencement
of the work within a specified time, the work
concerned is that to which the approval itself refers
and work would not be commenced when nothing more had
been done than acts preparatory to the work the
subject of the approval."
7 JUDGMENT
10
20
30
40
so
60
-- 8 of 11 --
12042000 T2/PAF23 M/T CMS39/2000 (Brabazon DCJ)
Connolly J relied on the decision of the High Court of
Australia in Drummoyne Municipal Council and Lebnan (1974)
131 CLR 350 at 360 in deriving that fourth proposition. If
one reads that decision of the High Court of Australia, it
can be seen that the definition of "building work" led to a
probable conclusion that preparatory demolition work was
not included. However, Gibbs J at page 360 went on to say
that excavation work would be included within the work
allowed under the permit.
It is interesting to take into account the definition which
is relevant in this case in section 1.4 of the Planning and
Environment Act. The word "erect" includes "(a) erect or
commence or continue to erect; or (b) do or commence or
continue to do any work in the course of or for the purpose
of erecting." That definition with its inclusion of •,vork
which is done for the purpose of erecting is wider than
that considered by the High Court in Lebnan's case.
In the present case, work was actually done on this land
before the expiry of the four years. The soil testing by
the engineers was actually done before the approval was
issued. Then, after the approval was issued, some
demolition work was carried out. The town planning consent
approval itself had a condition that required all existing
buildings and structures to be removed from the land before
any building work was commenced. Some of that demolition
was achieved before the expiry of the four years, that is,
a laundry was demolished and a garage was demolished. Then
8 JUDGMENT
10
20
30
40
50
60
-- 9 of 11 --
12042000 T2/PAF23 M/T CMS39/2000 (Brabazon DCJ)
a trench about 5 metres long, half a metre wide and half a
metre deep was excavated on the alignment of the rear
footing of the project, as shown on the engineering
drawings. That trench was excavated for the ultimate
purpose of using it for the footings designed for the
southern wall of the project. A safety fence was erected
around the trench for the safety of the occupants of the
house not then demolished. The trench was inspected by the
consulting engineer to determine its adequacy in view of
the soil conditions that had been earlier found. In my
opinion, that work collectively amounts to a commencement
before the expiry date.
I should say that, in taking the view the demolition work
is included within work done under the town planning
consent, not only have I referred to the definition of the
word "erect" but also the decision of the House of Lords in
London County Council and Marks and Spencer Limited (1953)
Appeal Cases at 535. There, in a statutory requirement
which spoke of "the erection or alteration of a building
has been begun but not completed before the appointed day",
it was held that it was not necessary that work of a
constructional nature was done before the expiry of the
time. It was sufficient if demolition for the purpose to
enabling construction to be done was carried out. The same
considerations apply here.
Therefore it follows that commencement of the erection of a
building within the meaning of section 4.13(18) of the
9 JUDGMENT
10
20
30
40
50
60
-- 10 of 11 --
12042000 T2/PAF23 M/T CMS39/2000 (Brabazon DCJ)
Planning and Environment Act had been done. The
consequence is that the permit did not expire at midnight
on 24 January 1999.
The formal order should be that the council's application
is dismissed.
10 JUDGMENT
10
20
30
40
50
60
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2000/029