Beard, Re [2000] QMW 89
IN THE WARDEN’S COURT OF QUEENSLAND
HELD AT BRISBANE
IN THE MATTER OF: APPLICATION UNDER PART 7 OF THE MINERAL
RESOURCES ACT 1989 FOR A MINING LEASE
(NUMBER 30205) IN THE GEORGETOWN DISTRICT
BEFORE: MR F W WINDRIDGE
MINING WARDEN
APPLICANT: ARTHUR STANLEY BEARD
REPORT:
The applicant (hereinafter referred to as the miner or applicant miner) seeks a mining
lease under section 234 of the provisions of part 7 of the Mineral Resources Act 1989
(hereinafter referred to as the MRA or the Act) for the purpose of mining for GOLD,
LEAD ORE, SILSVER ORE, ZINC ORE, and the establishment of a TREATMENT
PLANT, LIVING QUARTERS and ORE and OVERBURDEN STOCKPILE. The
application is for surface area of 6.00 hectares and is situated on LOT 5173 on PLAN PH
807, County of PERCY, Parish of PERCY, being part of Percyvale Holding. Access is
through the same property. The lease, if granted, is to be known as ‘JULIE K”.
Power to grant such a lease is vested in the Governor-in-Council pursuant to section 234
of the Act after recommendation by the Minister. Except for the reservation in section
8(3), all minerals are the property of the Crown. The grant of a lease does not create any
estate or interest in the land (s.10), although there is the power to determine title to land
[2000] QMW 89
-- 1 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 2
(s.363(5)). The landowner has no right of veto. The use of the land for the purposes
nominated is a permitted use under s.319 of the MRA. Any mining tenure is not subject
to the provisions of the Integrated Planning Act, being exempt from the provisions of the
Local Government Planning and Environment Act 1990 by virtue of s.319 (Part 8) of the
MRA.
The application was lodged at the Mining Registrar’s Office at GEORGETOWN on 26
JUNE 2000. A certificate of application was issued on the same date (s.252 (1)) setting
31 JULY 2000 as the last date for receipt of objections (s.252 (2)).
No objections were lodged pursuant to section 260(1) of the Act. The following matters
have been taken into account and considered in making my recommendations. (s.269(4).
(Sinclair v Maryborough Mining Warden (1975) 132 CLR 473 p.481).
(a) Have the provisions of the Act been complied with?
The material indicates that the applicant is an eligible person as defined in section 5 of
the act and is entitled to make the application under s.232 of the act.
The application area is not located on or forming part of any reserve as defined in s.5. I
find that the application is therefore not in respect of land over which, pursuant to
s.238(1) of the MRA, a mining lease shall not be granted without the consent of another
person or persons. There is no relevant permanent building or relevant feature on the
land as defined in s.5 requiring the consent of any person (s.238(2)).
At the time of marking out and lodging the application, the applicant was the holder of
PROSPECTING PERMIT 31285(s.232 (1)). The area is within EPM 12521 held by
Kidston Gold Mines Limited. Written consent has been given to the applicant to peg and
apply for this mining lease.
A declaration of posting was lodged on 1 AUGUST 2000 (s.252 (9)), and service of
documents was in accordance with s.399.
-- 2 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 3
I am satisfied, on the material, including the uncontested information in the application
form and the declaration of posting and advertising that all the provisions of the act (other
than the provisions requiring the hearing) have been complied with or substantially
complied with. (s.392).
I find that I am satisfied that, (a) the provisions of the act have been complied with, (b)
there is no valid objection, and (c) the consent of any trustee or other person is not
required. I therefore dispense with the hearing and proceed under the provisions of s.270
(1) of the act. An inspection was conducted on 29 AUGUST 2000.
(b) Is the land mineralised or is the other purpose for which the lease is sought
appropriate?
I am satisfied that the resources sought are minerals (s.5), and that the proposed
infrastructure is necessary to assist in the winning of those minerals. (s.234 (1)).
I accept the applicant’s advice and I am satisfied on the information given that the
purpose for which the lease is sought is appropriate. The application area is within an
area recognised for the production of alluvial gold and hard rock gold both historically
and in the 1980’s. The area has been disturbed by costeaning and shafting. The economic
viability of the project is a matter for the applicant’s commercial assessment, but I am
satisfied that there is sufficient evidence of mineralisation to warrant the grant of a lease.
(c) Will there be an acceptable level of development and utilisation of the
resources within the area applied for?
From documentation lodged with the application, I am satisfied the applicant has
sufficient resources to progress development to an acceptable level.
-- 3 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 4
(d) Is the area sought an appropriate size and shape?
There is nothing in the information supplied by the applicant to suggest that the surface
area of the land over which the mining lease is sought is not an appropriate size and
shape. It appears that there is no conflict with the boundary of any other lease or
tenement and therefore the cost and delay of a survey would appear to be not warranted.
(e) Is the term sought appropriate?
The term of lease applied for is 21 years. I am satisfied that the term sought is
appropriate and will allow for mining and rehabilitation to be completed. The applicant
has the option of renewal under s.286 or surrender at an earlier date under s.309.
(f) Has the applicant the necessary financial and technical capabilities to carry
on mining operations under the proposed mining lease?
From the information supplied, I am satisfied the applicant has the necessary financial
and technical capabilities or access to those resources to carry out the mining operation.
Mining for alluvial gold is basically an extractive industry utilising shallow open cuts and
does not require extensive plant, processing equipment, or large injections of capital. The
applicant has mined gold and been involved in the industry for a number of years and in
my opinion has the experience necessary to complete the mining operation. [Carr –v-
Simnovec (1980) 26 SASR 263 at 268, and Pacminex –v- Aust. Nephrite Jade Mines
(1974) 7 SASR 401 at 415].
(g) Has the past performance of the applicant been satisfactory?
There is no material before me to suggest that the past performance of the applicant has
been unsatisfactory. The local Field Officer and Environmental Officer will be available
to monitor performance and rehabilitation and report any breach of conditions. The
Inspectorate should monitor the methods adopted for mining, ensuring that industry
-- 4 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 5
standards are maintained and that all machinery is operated in a safe and competent
manner by licensed persons.
(h) Is there any disadvantage to the holder of or applicant for exploration
permits or mineral development licences?
The applicant was the holder of the relevant pre-requisite title under s.232 of the MRA at
the time of marking out. The holder of the EPM (Kidston Gold Mines) has given written
consent. It does not appear that the holder of or applicant for any other exploration
permit or mineral development licence has been affected.
(i) Will the operations to be carried on under the proposed lease conform with
sound land use management?
The land appears to be used for low intensity grazing under favourable conditions, and it
seems the proposed mining operation will cause no significant disturbance to stock or
stock watering or management facilities. The general nature of the land is described as
“rocky hills with spear grass”. There is no arable top soil. Rainfall is low. Stock fodder
is generally of poor quality on the application area with little or no fodder in deficit
rainfall years.
Information has been supplied as to the Applicant’s site management proposals. The
evidence leaves me with no reason to believe that the proposed mining operations do not
conform with sound land use management.
(j) Will there be adverse environmental effects caused by the proposed
operation, and if so, the extent thereof?
An Environmental Management Overview Strategy (EMOS) has been lodged with the
Registrar and accepted under delegation, subject to any recommendation of this Court
and any further requirement of the Minister.
-- 5 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 6
The proposed mining activity is in an isolated area away from human habitation. The
mining will not have any deleterious effect on any river or creek system. Chemicals will
not be used in the mining process. Due to low rainfall and the method of mining, erosion
will not be a problem provided the usual control measures are put in place. There are no
other environmental factors of significance, which may be adversely affected by the
operation, that have not been addressed in the EMOS.
By Section 35 of the Mineral Resources Regulations 1990, the applicant is required to
maintain the lease and access free of parthenium weed and any other weed declared
under the Rural Lands Protection Act 1985.
(k) Will the public right and interest be prejudiced?
No factors prejudicial to the public right and interest have been identified. It appears
there are no endangered flora or fauna within the application area. There are no public
utilities on or across the application area. There are no sites of historical interest or
aboriginal significance within the area. If any such sites are identified, the EMOS can be
amended to put forward specific site protection or site avoidance strategies.
(l) Has any good reason been shown for a refusal to grant the mining lease?
The economic viability of this project is a commercial decision of the applicant. When all
other aspects of the application and the matters referred to in s.269 are taken into account,
I am satisfied that the objects of s.2(a), (b), (c), (d), (e) and (g) will be attained if a mining
lease is granted for the term recommended for the following reasons:
♦ A small scale/low impact operation is planned.
♦ It is unlikely that the land applied for is of any interest to a large scale miner.
♦ The location of the proposed mining operation and the proposed method of mining is
unlikely to cause environmental or public interest concerns about safety.
♦ A realistic security deposit will be imposed to guard against financial failure of the
miner to ensure rehabilitation is completed.
-- 6 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 7
♦ The applicant appears to have sufficient experience in the industry to accurately
assess the potential of the project.
♦ There is a market for the product and the project will provide employment.
In my view, no good reason has been shown for a refusal to grant the lease application
(Carr –v- Simnovec, Pacminex –v- Aust Nephrite Jade Mines supra).
(m) Is the proposed mining lease operation an appropriate land use, taking into
consideration the current and prospective uses of the land?
The material indicates that the land is currently used for grazing purposes and appears, on
the evidence, to be suitable for no other use. In my view, there appears to be no risk of
significant conflict between the current land use, or any prospective land use and the
proposed mining operation. The land appears to be Class VII, and post mining will
return to Class VII. The proposed mining operation appears, on the evidence, an
appropriate land use, taking into account the current and prospective uses of the land.
A compensation agreement or determination of the Court will compensate the landowner
for any conflict or loss over land use (s.281). I note that a compensation agreement has
not been filed with the Registrar in accordance with s.279 of the Act.
GENERAL COMMENTS
This recommendation is based on an assessment of the information supplied. Should
there be any dispute over damage or loss, or should the miner depart from his plan of
operations or EMOS and cause loss or damage or interruption to the management of the
property not envisaged or not foreseen in the terms of the compensation agreement, the
parties are at liberty to apply to the Court for a determination or award of damages, and if
necessary, injunctive relief under the powers contained in s.363 (6). Any living quarters
erected on this lease must be regarded as temporary and removed at the conclusion of
mining.
-- 7 of 8 --
Warden’s Court of Queensland 1 September 2000
30205MLA.GEO 8
RECOMMENDATION:
Upon consideration of all the matters set forth in s.269 (4) of the Mineral Resources
Act 1989, I recommend that the mining lease be granted over the whole of the
application area for the purpose of mining for GOLD, LEAD ORE, SILVER ORE,
ZINC ORE, and for the establishment of infrastructure namely TREATMENT
PLANT, LIVING QUARTERS, ORE and OVERBURDEN STOCKPILE for a term
of 21 YEARS (s.270 (2)), subject to compensation being settled between the parties
or determined by this Court.
Dated at BRISBANE this 1 st day of September 2000.
F.W. WINDRIDGE
MINING WARDEN
2000
-- 8 of 8 --