Construction Diving Services Pty Ltd v Van Oord ACZ BV [1999] QSC 406
(
"
. ~1'1'\r 0 \
State Reporting Bureau
. TRANSCRIPT OF PROCEEDINGS
Copyright in this transcript is vested in the Crown. Copies thereof must not be made
or sold without the written authority of the Director, State Reporting Bureau.
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
MOYNIHAN J
No 8671 of 1999
CONSTRUCTION DIVING SERVICES (QLD) PTY LTD
(ACN 010 381 469)
and
VAN OORD ACZ BV (ARBN 051 409 440)
BRISBANE
' .. DATE 30/09/99
JUDGMENT
1
REVtSED COP1ES ISSUED
State Reporting Bureau
Date I ~ / J0/
Plaintiff
Respondent
II 1'1.11.1', TIle I.:I\V Courts. (;"111')..:<' St!'l:ct, Brisl':lut:, Q. 4(1111) Tdcphllill': (117) .1247 -1.1(,11 1-':1'(: (117) 32-17 5532
-- 1 of 5 --
300999 T2-3/LM23 M/T 6083/9'~ (Moynihan J)
HIS HONOUR: This is an appl~cation for an injunction to
restrain the respondent from having recourse to a bank
guarantee pending the determ:.nation of an arbitration
between the parties.
The bank guarantee is pursuant to a contract which provides
by clause 4.3.1 that there is no provision for retention
because the performance security is to remain in force
"during the entire program of the supply order II , in other
words, effectively while the contract remains unperformed,
or while the contract continues.
The· contract provides in clause 4.4 that the performance
security is valid for the period stipulated in the form of
Annexure 5. The form provides for an unconditional
guarantee payable on demand irrespective of the performance
or non-performance of the conract.
The form of the guarantee provides for its termination on
the date of issue of certificate of completion. The
evidence establishes that that has not occurred in this
case.
It is true that there has apparently been a certificate of
completion of the whole of the project but the construction
I give to the provisions of the contract and the guarantee
is that it means a certificate of completion in terms of the
contract which is in issue here.
2 JUDGMENT
10
(':
30
40
50
60
-- 2 of 5 --
i"
300999 T2-3/LM23 M/T 6083/9') (Moynihan J)
There was a certificate of cnmpletion in respect of that but
it was a condi tional certifil~ate and does not, in my view,
satisfy the terms of the con.':ract so as to discharge the
guarantee.
The argument for the applicant then becomes that there is a
prima facie case that the respondent had wrongfully
determined the contract, that it accepted the repudiation
and hence determined the contract so that the supply order
program which is referred to in the contractual terms I
mentioned earlier was no longer in place. Therefore it is
said the guarantee was not in force at the time that the
demand was made because the "entire program of supply order II
had itself been determined in the circumstances I have
mentioned.
The difficulty that I have with that submission is that it
seems to me that the combined effect of clause 4.3.1 and of
clause 4.4 and the form of Annexure 5 is to specifically
provide that the termination date is the date of the issue
of a certificate of completion, and for the reasons that I
have already mentioned that has not occurred.
It therefore seems to me that there is not a serious
question to be tried .. I should say that the helpful written
submissions canvass other issues and it may well be true
that this case is distinguishable from cases such as
Woodhall Limited and the Pipeline Authority (1979) 141 CLR
3 JUDGMENT
10
20
30
:.
40
50
60
-- 3 of 5 --
300999 T2-3/LM23 M/T 6083/9~J (Moynihan J)
443 and Burleigh Forest Estate Management Pty Ltd and Signa
Insurance Australia Limited [1992] QdR 54. But having
regard to the terms of the contractual provisions in this
case it seems to me that the point on which it turns is the
one which I have identified and I have already expressed my 10
conclusions in respect of that.
It therefore, on the view I take of the matter, is not
necessary to embark on a consideration of the balance of
convenience.
As to that, however, it is perhaps proper that I say that
there is an arbitration proceeding between the parties, the
respondent having successfully obtained a stay of an action
commenced by the applicant in order for that to be done.
The consequences of the bank guarantee having been called up
can of course be accommodated in the context of the
arbitration.
No doubt there will be some adverse consequences to the
applicant in the event that the guarantee is called up but
as I have already said on the view I take of the matter it
is unnecessary for me to determine the weight which they
should be given in respect of an injunction.
As I say I decline the application for an injunction.
4 JUDGMENT
20e\:
30
o
"40
CJ
50
60
-- 4 of 5 --
300999 T2-3/LM23 M/T 6083/9 1) (Moynihan J)
HIS HONOUR: The application having failed on the basis
which I have outlined it seeI1S to me that the applicant
ought to pay the respondent'G costs of the application.
10
20
(
I "
50
60
5 JUDGMENT
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1999/406