Bloomer & Bloomer t/a Bloomer Constructions v Todbury Pty Ltd [1999] QSC 312
. . .JUSTICE-~.-...:...-
~ :37H7
State Reporting 8c 19/31 ~r\ Ie
Bureau
TRANSCRIPT OF PROCEEDINGS
Copyright in this transcript is vested in the Crown. Copies thereof must not be made
or sold without the written authority of the Director, State Reporting Bureau.
\
SUPREME COURT OF QUEENSLAND
CHAMBERS
DERRINGTON J
Writ No 11653 of 1998
No 12007 of 1998
WAYNE NORMAN BLOOMER and PAULINE BLOOMER
TRADING AS "BLOOMER CONSTRUCTIONS"
and
TODBURY PTY LTD ACN 010 478 038
BRISBANE
.. DATE 10/06/99
JUDGMENT
1
REVISED COPIES ISSUED
State Reporting Bureau
Date r(/ /
plaintiffs
Defendant
II FI 1111 r, The Law COllrl.~, GelJrge Street, Brishallc, Q. 41l()() TclcphlJlll': (07) J2.t7 4J()0 F:.:.:: (1l7) .12.t7 55.12
-- 1 of 9 --
L--______ .. _._. ___
100699 T4/ST5 M/T 4943/99 (Derrington J)
HIS HONOUR: This is an application by a plaintiff under
order 45 rule 1 of the Rules of the Supreme Court for a
review of an order made on 4 February 1999 by Williams J.
That hearing was in respect of an application by the
defendant for the setting aside of judgment obtained
summarily and the granting of leave to defend, both of which
were granted subject to a condition that the defendant
provide security, ultimately amounting to $500,000, to
answer the claim.
HIS HONOUR: The history of the matter is this. The
plaintiff's writ for $1.1 million was issued on 16 December
1998 and apparently served on that date. On 24 December
1998 the plaintiff obtained judgment in default of entry of
appearance. On the same date, 24 December 1998, the
plaintiff issued a second writ for $590,883 and on 5 January
1999 obtained judgment by default again.
Upon the defendant's applicatiQn on 8 January His Honour
Justice Williams set aside both default judgments on the
basis that there was a reasonable basis for defence. The
reason for the defendant's default in failing to enter an
appearance seems to have been that the defendant solicitor
was on vacation at that time.
On 18 January 1999 the plaintiff brought an application for
summary judgment and a Mareva injunction, again before
2 JUDGMENT
10
c
30
40
c
50
60
-- 2 of 9 --
100699 T4/ST5 M/T 4943/99 (Derrington J)
Williams J. That motion for the mareva injunction was
dismissed but the defendant was given conditional leave to
defend, conditional upon one half of the net proceeds of the
sale of the units that were the subject of the building
contract that formed the basis of the claim be held in a
trust account up to a sum of $500,000.
The defendant now seeks to have that order relating to
security which forms the basis of the condition of leave to
defend set aside on the basis of the appearance of new facts
which, it is said, were not reasonably available at the
time.
The order made by His Honour for security to the extent
indicated was no doubt based upon the fact that the
defendant was a proprietary company and Hi$ Honour formed
the view at the time that the plaintiff's case had a strong
chance of success.
One of the pieces of evidence before His Honour at that time
was an affidavit by a Mr Dawes, who deposed in clear terms
and, indeed, purported to quote the exact words used, to the
effect that Mr Romano, the principal agent of the defendant,
stated in his presence that the contract between the
defendant and the plaintiff was on a cost plus basis
completely.
The basis of the plaintiff's claim is that it was a cost
plus contract whereas the basis of the defence is that it
3 JUDGMENT
10
20
30
40
50
60
-- 3 of 9 --
100699 T05/AW16 M/T 4943/99 (Derrington J)
was a fixed price contract. As such Mr Dawes' evidence at
that time appeared strongly to support the plaintiff but
contradicted the defendant's case. Mr Dawes was an
independent person representing a building authority.
10
Mr Dawes was called at the hearing under subpoena to produce
certain material but was not cross-examined by learned
counsel, who appeared at that time for the defendant, in
respect to the statement contained in his affidavit.
The defendant has now produced an affidavit by Mr Dawes
saying that he did not know at the time, nor does he know
now, whether the reference to a cost plus contract by c
Mr Romano was in relation to the whole of the contract or
only to extras. That is a considerable resiling from the 30
clear evidence that was before His Honour and which no doubt
must have had a serious impact upon his opinion as to the
strength of the plaintiff's case.
There is one difficulty in that respect so far as the 40
evidenc~ that now appears before the Court is concerned and cthat is that presumably it would have been available at the
time, if learned counsel then appearing for the defendant
had chosen to cross-examine ~lr Dawes upon the point. There
is no" good reason why that should not have been done sinc~ 50
the allegation was that the words were spoken by Mr Romano
and there was no suggestion whatever that Mr Romano was not
available at the time to give evidence to the contrary.
60
4 JUDGMENT
-- 4 of 9 --
100699 T05/AW16 M/T 4943/99 (DerringtonJ)
Consequently the evidence cannot be said to be fresh
evidence within the technical meaning of that expression as
is used in respect of appeals; However it is not a
necessary feature of evidence that might be taken into
account in these proceedings for obvious reasons and yet on
the other hand it must be taken into account in respect of
the exercise of theCourt's discretion.
Much more serious material has been advanced by the
defendant relating to the plaintiff's claim and it is
important to note that it has not been contradicted in any
way by any evidence from the plaintiff's side. Perhaps the
most important evidence in that respect is that now that the
defendant's accountants have had the opportunity of having
10
20
discovery of and checking the documentary material 30
supporting the plaintiff's claim, they are able to depose to
the fact that there is a considerable shortage of
documentary material supporting the claim that has been
made.
Moreover there is evidence that was plainly not available at
the time, prima facie, demonstrating,
( i ) that material was claimed for by the
40
plaintiff that was, in fact, not delivered to 50
the job;
(i i) that workmen \t/hose hours were claimed for in
respect of the job were, in fact, not working
5 JUDGMENT
60
-- 5 of 9 --
100699
(iii)
T05/AW16 M/T 4943/99 . (Derrington J)
there all the time or at times for which some
of the claim has been made; and
that materials that are alleged to have been
used were just not used on this job but were
either used in the plaintiff's private
affairs or not provided at all for other
purposes.
These are very significant matters of course which, had they
been before His Honour at the time, might well have had a
considerable bearing upon his view of the strength of the
plaintiff's case.
There is also strong evidence advanced prima facie showing
that there are very substantial defects in the building
which might amount to a very serious deduction from the
plaintiff's claim.
It might be added parenthetically that the plaintiff ceased
to continue the work and that it was completed by the
defendant at its own cost in the sum of about $700,000. This
has to be taken into account to the extent that even if it
were a cost plus job the amount to which the plaintiff would
have been entitled would not include the additional work
done.
In respect of many of these nlatters the· absence of the
defendant's opportunity of adducing the evidence at the
6 JUDGMENT
10
30
40
50
60
-- 6 of 9 --
100699 T05/AW16 M/T 4943/99 (D~rrington J)
hearing before Williams J was no doubt substantially due to
a number of factors. In particular, the exigencies of the
situation led to this, namely that the matter was being
heard as a summary judgment application not long after the
issue of the writ when the matter was very new and the
opportunity for making more serious and detailed
observations was not possible. However, it must be observed
contrary to that, so far as the defects were concerned, for
example, Mr Romano himself was a builder and should have had
an ample opportunity to have at least presented to the Court
some prima facie evidence of serious defects that would have
amounted to a significant feature attending against the
plaintiff's claim.
Although one must take this into account, overall the
general picture is that much of the material that is now
produced showing very seriouS questions indeed as to the
strength of the plaintiff's claim, cannot be said to have
been reasonably available to the defendant at the time of
that hearing, having regard to the situation that existed at
that time.
That is not the end of the matter. There still remains the
issue of the desirability of the security to the plaintiff
in respect of its claim because of the status of the
defendant. It seems to have substantial property still
available to it. In so far as it has now reached the
position, in respect of sales of the various units
comprising the relevant property, that it has sold
7 JUDGMENT
10
20
30
40
:;0
6{)
-- 7 of 9 --
100699 T6/MLM14 M/T 4943/99 (Derrington J)
sufficient units to have paid off the financier. The
remaining sales will now be available to it without the need
to repay any security in that reSpect,so the defendant is
probably in a reasonably good financial position, providing
moneys are not in some way siphoned off for ulterior 10
purposes.
Having regard to the desirability of providing some security
to the plaintiff in these circumstances but also having
regard to the very serious alteration of the Court's view as
to the strength of the plaintiff's case, I am of the view
that if an undertaking were to be given by the defendant,
C ~
that it will not use moneys or other assets of the company, _'
other than in the ordinary course of the company'sbusiness,
I would set aside the condit~on of His Honour, on a 30
temporary basis. The parties will have liberty to reapply
in the near future when the report comes out of the
independent expert appointed by the Court to make an
cassessment of the value of the work that has been done.
40
The Court then will be in a better position to see from an c=
independent person what the true position of the plaintiff's
claim might be expected to be. In the meantime, having
regard to what appears to be the reasonable strength of the
defendant'~ case, it is probably desirable to avoid imposing 50
any fetter upon its ordinary use of its funds in its
business if the security for the plaintiff can be preserved
by the provision of an undertaking as I have described.
60
8 JUDGMENT
-- 8 of 9 --
100699 T6/MLM14 M/T 4943/99 (Derrington J)
The proposal which I present would also avoid the necessity
of expenditure of further moneys upon the provision of a
bank guarantee, which can be quite expensive and which might
entail the defendant in further loss through having to
provide security to support that and the provision of that
security might cause it some loss in the conduct of its
business. That loss might be difficult to prove, but if it
were capable of proof, and if the defendant were to succeed,
that might fall upon the plaintiff very heavily in that
respect.
In summary, the proposal that I make is designed to try to
reduce the possibility of loss to both sides so far as may
be reasonably open, at this E:tage, on a temporary basis
10
20
until such time as the Court is placed in a somewhat better 30
position to see from the report of the expert what. the
prospects are in respect of the plaintiff's claim.
HIS HONOUR: The order will be, in accordance with the terms
of the order which I have initialled.
9 JUDGMENT
40
50
60
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1999/312