Blythe v Queensland Generation Co [1999] QSC 92
Ie
IN THE SUPREME COURT
OF QUEENSLAND
No. 754 of 1995
Brisbane
Before Wilson J
[Blythe v Queensland Generation Corporation]
BETWEEN:
AND:
CATCHWORDS:
Counsel:
Solicitors:
Hearing Date:
ERIC JOHN BLYTHE
Plaintiff
QUEENSLAND GENERATION CORPORATION
Defendant
I JUDGMENT _ WILSON 1.
Judgment delivered 27 April 1999
PRACTICE - striking out action for want of prosecution - injury
sustained 1992 - writ issued 1995 - writ not served for almost 12
months - 2Yz years delay in delivery of statement of claim - no
evidence of prejudice to defendant - possibility of action for
negligence against solicitors.
Birkett v Jones [1978] AC 297
Bruce Pie & Sons Pty Ltd v Mainwaring [1987] 1 Qd.R. 304
Dempsey v Dorber [1990] 1 Qd R 418
Tricon Industries Pty Ltd v Abel Lemon & Company Pty Ltd (No.2)
[1998] 2 Qd R 551
Mr M 0' Sullivan for the applicant/defendant
Mr H Zillman for the respondent/plaintiff
Crown Solicitor for the applicant/defendant
William R Wilson & Associates for the respondent/plaintiff
19 April 1999
-- 1 of 5 --
IN THE SupRE!v1E COURT
OF QUEENSLAND
No. 754 of 1995
Brisbane
Before Wilson J
[Blythe v Queensland Generation Corporation]
BETWEEN:
ERIC JOHN BLYTHE
Plaintiff
i (.
r
AND:
QUEENSLAND GENERATION CORPORATION
(.- -
Defendant
I JUPG!v1ENT - WILSON 1.
Judgment delivered 27 April 1999
1 This is an application by the defendant to strike out the plaintiff's action for want of
( prosecution or alternatively to dismiss the action.
2 By the writ issued on 4 May 1995 the plaintiff claimed damages for negligence and/or
breach of duty and/or breach of contract of employment and/or breach of statutory duty. No
other particulars were given.
3 The writ was not served for almost twelve months. It was served on the Workers'
Compensation Board of Queensland on 24 April 1996 and on the defendant two days later.
4 It was not until 17 February 1999 that the statement of claim was delivered. It contains
the following allegations (inter alia). The plaintiff was in the employ of the defendant from 20
April 1968. At all material times he was working as a "generation planning engineer." On 4 May
1992, whilst performing his duties, which included public relations and engineering planning work
-- 2 of 5 --
5
6
7
8
, .l
2
and the conduct of project approval for the Tully-Millstream Hydro-Electric Project, he suffered
an injury, namely a major depressive illness. He was compelled to take extended sick leave. He
obtained medical and psychiatric treatment, and was subsequently retired on medical grounds.
On receipt ofthe statement of claim the defendant's solicitors briefed counsel and sought
a short extension of time in which to deliver a defence. Then they advised the plaintiffs solicitors
that the defence was ready, but that they wanted an explanation for the plaintiffs delay in
prosecuting the action. An explanation was not given. The plaintiff s solicitors threatened to enter
interlocutory judgment. The defence was delivered on 29 March 1999. This application was filed
on 1 April 1999.
FroIh the defence it is clear that both liability and quantum are in issue. The pleading (
\
consists largely of denials and non admissions, and an allegation that the action is barred by the
Limitation of Actions Act.
The principles applicable to an application such as this were enunciated by the House of
Lords in Birkett v James [1978] AC 297. At P 318 Lord Diplock said that the power to dismiss
an action for want of prosecution should be exercised only where the court is satisfied either: ,: .,.J
"(1) that the default has been intentional and contumelious, e.g., disobedience to a
peremptory order of the Court or conduct amounting to an abuse of process of the
Court; or
(2) (a) that there has been inordinate and inexcusable delay on the part of the
plaintiff or his lawyers; and
(b) that such delay will give rise to a substantial risk that it is not possible to
have a fair trial of the issues in the action or is such as is likely to cause or
to have caused serious prejudice to the defendants either as between
themselves and the plaintiff or between each other or between them and
a third party."
This was adopted by the Full Court of the Supreme Court of Queensland: see Bruce Pie & Sons
Pty Ltd v Mainwaring [1987] 1 Qd. R. 304 and Dempsey v Dorber [1990] 1 Qd. R. 418.
More recently the continued application of these principles has been questioned by the
-- 3 of 5 --
9
3
majority of the Court of Appeal in Tricon Industries Pty Ltd v Abel Lemon & Company Pty Ltd
(No.2) [1998] 2 Qd. R. 551. That case concerned a fire in an industrial building in December
1982. The action was begun at the end of 1983. There was substantial delay in its prosecution
from the end of 1986 to mid 1996. The Court of Appeal upheld the primary judge's decision to
strike out the action relying on the second limb in Birkett v James. At p. 555 Pincus JA (with
whom McPherson JA agreed) said:-
"In a time when complaints of delay in the disposition of legal proceedings are
legion, one may question whether principles which can encourage delay and which
have been said to have failed in their country of origin should continue to be
applied in this State."
However, the court was not asked to overrule the application of the Birkett v James doctrine, and
in any event, the delay was such that the case fell within that doctrine.
In the present case it seems that the plaintiff's advisers were proceeding with the
I
preparation of is case over most of the period of delay which is in question, but that they failed
to communicate with the defendant's solicitors to this effect. From March 1996 to February 1997
they were carrying out investigations including obtaining a copy of the relevant file of the
( . Workers' Compensation Board of Queensland (which contained medical reports obtained by the
Board in 1994) and medical reports. In March and May 1997 the defendant's solicitor inquired
as to the plaintiff's intentions with respect to the action, but no response was given. In July 1997
the plaintiff was hospitalized for a depressive illness. Further medical evidence was obtained in
November 1997. There appears to have been a period of inactivity until about September of 1998.
Then further work was carried out including a conference with counsel and obtaining further
medical reports. Notice of intention to proceed was given on 7 January 1999.
10 The statement of claim ought to have been delivered by mid June 1996. The defendant has
cause to be critical of the delay of more than 2Y2 years. However, I do not consider the delay to
-- 4 of 5 --
.. , ,
4
have been so long that it was inordinate. Nor do I consider that it was inexcusable given the
nature of the plaintiff's injury, the investigations which were being carried out and his
hospitalization in July 1997.
11 The defendant bears the onus of establishing that the delay is such that there is a
substantial risk that it is not possible to have a fair trial of the issues or such that it is likely to
cause or to have caused serious prejudice to it either as between it and the plaintiff or between
it and a third party. The defendant led no evidence of prejudice. It asked the court to infer that
the passage of time would have had a detrimental effect on the recollections of witnesses, but it
did not condescend to any particulars of the witnesses whose recollections might be so affected
or even of the type of evidence in question. I am not prepared to draw an inference of serious
prejudice on the facts of this case, particularly given that the Workers' Compensation Board had
obtained medical reports about the plaintiff's condition as early as 1994.
12 The defendant's counsel asked me to take into account in support of the application that
the plaintiff may have available an action for negligence against his solicitors. That is not a factor
which can be given any significant weight on the material before me. It seems that they were <~ I
relatively diligent in investigating his claim but I cannot express any concluded view on whether
he may have a viable cause of action against them.
13 ' In all the circumstances I dismiss the defendant's application.
14 I direct the plaintiff to file and serve a statement ofloss and damage by 4 pm on Friday,
21 May 1999.
15 I order the applicant/defendant to pay the respondent/plaintiff's costs of and incidental to
the application to be taxed.
--------- ---
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1999/092