Elesanar Constructions Pty Ltd v Thiess Contractors Pty Ltd [1999] QSC 5
IN THE SUPREME COURT
OF QUEENSLAND
II
No. 9673 of 1997
Brisbane
Before Justice Wilson
[;Elesanar Constructions P/L v Thiess Contractors P/L]
BETWEEN:
ELESANAR CONSTRUCTIONS PTY LTD (ACN 000 804 384)
AND:
THIESS CONTRACTORS PTY LIMITED (ACN 010 221 486)
REASONS FOR JUDGMENT - WILSON J.
Delivered the 22nd day of January 1999
Plaintiff
Defendant
CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS - subcontract -
summary judgment - whether there are triable issues - whether
plaintiff failing to notify defendant of dispute as required under
contract gives rise to estoppel - counter-claim - whether claim for
damages for defective work is a debt owing under the contract -
equitable set off - jurisdiction of District Court.
Counsel:
Solicitors:
Hearing Date:
District Court Act 1967 ss. 68, 77
Morgan & Son Ltd v. S Martin Johnson & Co Ltd [1949] 1 KB 107
Mr A. Abaza (sol.) for the plaintiff
Mr J. Sweeney for the defendant
Andrew P. Abaza for the plaintiff
Clayton Utz for the defendant
16 November 1998
[1999] QSC 5
-- 1 of 15 --
( ,. "
I
()\. J
"' ....
IN THE SUPREME COURT
OF QUEENSLAND
Brisbane
Before Justice Wilson
[Elesanar Constructions PIL v Thiess Contractors PIL]
BETWEEN:
No. 9673 of 1997
ELESANAR CONSTRUCTIONS PTY LTD (ACN 000 804 384)
Plaintiff
AND:
THIESS CONTRACTORS PTY LIMITED (ACN 010 221486)
Defendant
REASONS FOR JUDGMENT - WILSON J.
Delivered the 22nd day of January 1999
The plaintiff seeks against the defendant summary judgment for the sum claimed in the
writ together with interest and costs.
2 Bya specially endorsed writ issued on 27 October 1997 the plaintiff claimed $143,300.72
as the balance price of crushed rock and pavement gravel sold and delivered by it to the
defendant. In the particulars of claim the plaintiff alleged:-
"The Plaintiff sold and delivered to the Defendant crushed rock and pavement
gravel at the Defendant's request and pursuant to an agreement in writing made
the 3rd day of April 1993 between the Plaintiff and the Defendant for a project at
Cunningham Arterial Road, Harcourt Road and Rudd Street Interchanges,
Archerfield to the balance value of$143,300.72.
31.01.1994
31.02.1994
Particulars
Invoice
Invoice
$ 31,955.76
$ 46,690.84
-- 2 of 15 --
2 "
31.03.1994
30.04.1994
Invoice
Invoice
$ 61,145.24
$ 3,508.88
$ 143,300.72
The.Defendant has not paid to the Plaintiff the balance sum of$143,300.72."
3 On 3 November 1997 the defendant entered a conditional appearance. The judgment
summons was taken out on 30 October 1998 and returnable on 16 November 1998. During the
hearing on 16 November the defendant submitted to the jurisdiction of the court.
4 The defendant as head contractor entered a contract with the Queensland Department of
Transport in relation to a project at Cunningham Arterial Road, Harcourt Road and Rudd Street
Interchanges, Archerfield. Part of the work, namely the supply and delivery of crushed rock
pavement gravels, was subcontracted to the plaintiff trading as Reedy Creek Quarries.
5 The plaintiff contends that the subcontract was contained in a written document entitled
"Subcontract Agreement No. 18012". Clauses 1 - 3 of that Agreement were as follows:-
"1.
2.
The Subcontractor shall entirely at its own expense and assuming all risks
in any way connected therewith perform the work set out in Schedule A
(below) such work being part of a contract hereinafter called the 'Head
Contract' particulars of which are set out in Schedule B (below) to be
performed by the Contractor and shall supply all labour, equipment and
materials required therefor.
The Subcontractor shall perform such work to the complete satisfaction
of the Contractor and the Principal's Engineer or Architect, in accordance
with all the terms, provisions, conditions, plans and specifications of the
Head Contract so far as they may be applicable thereto and also in
accordance with the general conditions of acceptance of this Subcontract
as shown overleaf and any other special conditions as may be annexed
hereto.
3. As full consideration for the performance of such work the Contractor will
pay to the Subcontractor the amounts shown in Schedule C (below) with
such additions or reductions as may be subsequently agreed in writing."
Further, the general conditions of subcontract included the following:-
01
c
-- 3 of 15 --
3
"Only these General Conditions and the terms, provlsIOns, plans and
specifications of the Head Contract shall apply to this Subcontract unless
otherwise agreed and in the event of any conflict the conditions of the Subcontract
both general and special (if any) shall prevail. All plans and documents pertaining
to the Head Contract will be available for perusal at the Contractor's site office."
6 The defendant contends that the contract was partly in writing (constituted by the
subcontract agreement into which the head contract documents were incorporated) and partly oral.
7 Despite the formulation of the claim in the writ the plaintiff has not put the four invoices
into evidence. Instead, it presented argument by reference to progress certificate no. 19 dated
( 6 October 1994 issued by the defendant, a copy of which is exhibit "PNL3" to the affidavit of
Peter Neville Lyons filed on behalf of the defendant. (A copy of the exhibit is annexed to these
(\ reasons for judgment.)
\ )
8 Jill Ivory, the plaintiffs weigh bridge and dispatch clerk, deposed in paragraph 30 of her
affidavit sworn on 28 October 1998:-
"The total charged correctly by RCQ to Thiess under the Contract, and which
amounts I verify from the Company records prepared by me is as follows:
Total charged
Total paid
The balance owing is
$1,133,738.76
$ 990.438.04
$ 143,300.72"
9 Peter Neville Lyons, the defendant's civil engineering manager, responded to this in
paragraph 15 of his affidavit sworn on 16 November 1998 as foIlows:-
"As to paragraph 30 of Ms Ivory's affidavit I say that the contract value was
$1,045,105.35 and the value of work completed by the plaintiff under the
Subcontract was $978,052.11. Now produced and shown to me and marked
'PNL 3' is a copy of progress certificate 19 with provides a breakdown of these
amounts."
10 The plaintiffs argument is summarised in its written submissions as follows:-
\
-- 4 of 15 --
I
4 II
"8. Exhibit' PNL 3' , records an amount of $140,116.76 as owing by Thiess
to the Plaintiff. The Exhibit records on the second page 'Total Value of Work
Completed to Date' - $1,045,105.35 but there is a 'deduction' from that amount,
not explained or verified, of$3,068.76; another 'deduction' of $68,574.00; and
admitted sundries of$I,520.76 not added.
9. The calculation is:
Contract Valuel •
Add Sundries referred to
in 'PNL 3'
Add unspecified and unverified
deduction
Add unspecified and unverified
deduction
carried forward
Less Payments asserted to date
on 'PNL 3'
Sub Total
Less payment recorded by 'PNL 3'
Balance owing
$ 1,045,105.35
$ 1,520.76
$ 1,046,626.11
$ 3,068.76
$ 1,049,694.87
$ 68,574.00
1,118,268.87
$ 972,886.98
$ 145,381.89
$ 5,265.13 [sic - should be
$5,165.13]
$ 140,216.86 [sic - should be
$140,216.76]
c'
I
01
10. There are, the Plaintiff points out in fairness to Thiess, three Clerical errors
on the figures in 'PNL 3' nett in favour of Thiess, amounting to $220.37: C
Item 4 00.27¢
Item 5 00.18¢
Item 6 $ 526.31
Item 11: $ 306.39¢
Nett
adjustment $ 220.37
11. Allowing the nett adjustment of $220.37 to Thiess the difference between
the case for the Plaintiff and the case for Thiess amounts to $3,404.33 [sic -
should be $3,304.33] which is no ground to resist the application: and no ground
to hold the Plaintiff further out of its money.
Para 15 of Mr Lyons affidavit.
C;'
-- 5 of 15 --
5
12. The difference in amount is so small that it ought to be resolved in favour
of the Plaintiff by the weight of the evidence of the Plaintiff with reference to the
whole of the evidence and having regard to the following matters."
1I In my view the calculations in paragraph 9 of the plaintiff's written submissions involve
a wrong analysis of exhibit "PNL3". In the plaintiffs calculations $68,574.00 (shown on the
progress certificate as back charges) has been added back into the equation. This ought not to
have been done, because the amount was subtracted after, and not before, the figure of
$1,045,105.35 was reached. If the figure of $68,574.00 is subtracted from the plaintiffs balance
( of $140,216.86, there is the sum of $71,642.86 (or more correctly $71,642.76) owing by the
\
defendant to the plaintiff. That is the sum of the deductions shown on the progress certificate
($3,068.76 + $68,574.00 = $71,642.76).
12 The plaintiff makes an adjustment in favour of the defendant of$220.37. On that basis
the amount owing by the defendant would be $71,422.39.
13 This would suggest that the matters in issue are those which comprise the $3,068.76 and
the $68,574.00. However, the supporting documentation referred to (progress claim no. 15 and
letter dated 5 September 1994) is not before the court.
14 Also exhibited to Mr Lyons' affidavit is a draft defence and counter-claim.
15 The affidavit material and the oral argument concentrated on two issues - whether the
plaintiff was entitled to be paid for the use of certain body trucks and the amount for which the
plaintiff was entitled to be paid for the supply of stabilizing agent.
16 So far as the body trucks are concerned, the plaintiffs claim amounted to $23,587.10 as
particularised in a schedule to Ms Ivory's affidavit.
17 Material had to be delivered to a ABG511 paver used by the defendant. In order to ensure
that the material was discharged efficiently, consistently and without spillage, there had to be a
-- 6 of 15 --
6 II
certain relationship between the dimensions of the delivery vehicle and the paver. The body
trucks were used for this purpose. The plaintiff contends that it was entitled to extra payment for
the use of the body trucks while the defendant contends that it was not so entitled.
18 The subcontract was a schedule of rates contract. Schedule C to it provided an item as
follows: additional rate for cartage by eight-wheel body truck rate $0.30 (per tonne). The body
trucks fitted that description.
19 The defendant relies on clause 7 .1.2(b) of the specification to the head contract (which
was incorporated into the subcontract) to say that the plaintiff is not entitled to any additional
payment. It provided as follows:-
"Vehicles used for the delivery of the mix shall be of the open body truck type C.
equipped with adequate covers and capable of transporting and discharging the
mixture without segregation.
If discharging into the hopper of a paving machine, the vehicles shall be designed
or equipped with the capacity to efficiently discharge into the hopper consistently
and without spillage."
20 Mr Lyons has said that the $0.30 additional rate shown in the schedule to the subcontract
was for the supply of eight-wheeler body trucks for use in tight and confined spaces at the
direction of the defendant, and not in respect of the use of body trucks in conjunction with the
ABG511 paver. It is not clear to me whether this is put forward as the proper interpretation of C"
the schedule having regard to the matrix of facts in which the subcontract was made, or whether
it is put forward as an oral term of the agreement (the defendant's contention being that the
agreement was partly oral and partly in writing).
21 Be that as it may, the plaintiffs claim is not for an additional $0.30 per tonne, but for
actual amounts paid per tonne in excess of $4.40. These amounts vary between $055 and $2.10
per tonne.
-- 7 of 15 --
7 I
I
22 In the circumstances there is a triable issue with respect to the claim for the body trucks.
23 Presumably the balance of the plaintiffs claim ($119,713.62) is for extra payment for
cement.
24 The essence of the plaintiff s complaint is the alleged alteration of the cement content
from 4.2 per cent to 3.5 per cent. I have had difficulty understanding the basis of this claim.
Having regard to the calculation in paragraph 19 of Ms Ivory's affidavit, I take it that the
plaintiffs point is that, had the ordered cement content been 4.2 per cent rather than 3.5 per cent,
it would have been entitled to greater remuneration. This is illustrated as follows:-
$153.00 x 4.2 % = $6.43/t
$153.00 x 3.5 % = $5.36/t.
25 I notice that the deduction of $3,068.76 in progress certificate no. 19 is described as
"difference in cement costs between cement % invoiced & actual cement %. Details attached to
progress claim no. 15".
26 It was provided in schedule C to the subcontract that the plaintiff should be paid for .
stabilizing agent (cement) at $153.00 per tonne. The defendant says that the dispute is how to
measure the tonnage.
27 The subcontract was a schedule of rates· contract. The plaintiff tendered on the basis of
a cement content of 4.2 per cent: see Ms Ivory's affidavit paragraphs 7 - 9 and the document
headed "Addendum Specific Job Requirements" which is exhibit B to that affidavit.
28 The specification called for pavement material with a "characteristic value not less than"
the "ordered cement content". See specification clauses 7.2.1 and 8.2.2. The ordered cement
content could not be determined until after the tender had been let, because the specification
-- 8 of 15 --
8 "
provided that the stabilizing agent should be ordered by the engineer after tests had been carried
out on a preliminary sample of the paving material which the contractor intended to. use.
29 In her affidavit Ms Ivory deposed to cement being first added at 4.2 per cent "in
accordance with Thiess' direction Attachment B." This was a reference to the "Addendum
Specific Job Requirements" previously referred to. That was part of the specification upon which
the plaintiff tendered rather than a direction from Thiess. On 29 March 1993 Thiess gave a
direction that the cement content was to be 3.5 per cent. There was further testing carried out up
~',; until 22 April 1993 when the defendant advised that it wanted a characteristic value of 3.5 per \. ..
cent.
30 In these circumstances there is a triable issue as to whether the plaintiff was ever entitled C
to be paid for stabilizing agent at the rate of 4.2 per cent.
31 It was a term of the subcontract that the plaintiff would notify the defendant of any matter
in dispute under the subcontract within thirty days, failing which the plaintiff would be deemed
to have waived any claim arising therefrom: general condition 10. The defendant asserts that the
plaintiff failed to notify it of the dispute within that time and that the plaintiff has accordingly
waived its claim and is now estopped from advancing any claim it might otherwise have had. It
c
is not clear what detriment is relied upon in support of such an estoppel. On the evidence and C
submissions on this application, I am not prepared to find that the defendant has raised a triable
issue with respect to waiver or estoppel. Of course, the defendant may still be able to make out
either or both of these defences at trial.
32 The defendant has raised a counter-claim amounting to $81,214.00. In the draft pleading
it is alleged as follows:-
-- 9 of 15 --
( 33
9
"In breach of the tenn mentioned in paragraph 10 hereof, the Plaintiff failed to
provide material with a Characteristic Value not less than the ordered cement
content.
As a result of the Plaintiff s breach:
(a) some material which did not confonn with the specification was removed
and replaced at a cost of$35,620;
(b) the Defendant laid an additional 40mm of asphalt to overcome the
weakness in the sub-base in some areas at a cost of$35,814;
(c) the Defendant incurred engineering consulting fees in the sum of$5,280;
(d) the Defendant had moneys withheld pursuant to its head contract with
MRD due to the reduced level of service of material which fell below
specification requirements in the sum of $4,500."
By clause 8 of the general conditions of subcontract in the event of default on the part of
the plaintiff the defendant had the right at its discretion to use any moneys owing to the plaintiff
~\
( / for the purpose of paying any debts owing by the plaintiff in respect of the agreement. The
defendant asserts that it had used money owing to the plaintiff for the purpose of rectifying the
defective work (presumably that which is the subject of the counter-claim). Accordingly it claims
to set off against any sum which it may owe the plaintiff so much of the counter-claim as will be
necessary to extinguish that sum.
"-~j
34 I do not accept that a claim for damages for defective work is a "debt owing under the
contract". However, such a claim may be set off against the plaintiffs claim pursuant to the
principles in Morgan & Son Ltd v. S Martin Johnson & Co Ltd [l949.J 1 KB 107.
35 In summary, upon a proper analysis of progress certificate no. 19 and making the clerical
adjustment allowed by the plaintiff, the amount owing by the defendant to the plaintiff (if no
account is taken of the deduction and back charges) is $71,422.39. The defendant has a counter-
claim for $81,214.00. That counter-claim may also be set off against the claim pursuant to the
-- 10 of 15 --
10 "
principles of equitable set off. That in itself is enough to raise a triable issue to defeat the
application for summary judgment.
36 If it were necessary for me to decide this application by reference to the arguments about
payment for percentage cement content and the supply of body trucks, I would be prepared to find
that there are triable issues with respect to both.
37 In the circumstances the application for summary judgment is dismissed.
38 The question arises whether this action ought to be remitted to the District Court. By s. 68
of the District Court Act 1967 the District Court has jurisdiction in personal actions in which the
principal amount claimed does not exceed $250,000.00, even though the addition of interest
ell
would take the total amount above that sum. Pursuant to s. 77 of that Act, the action can be C·
remitted to the District Court. I.will hear the parties on whether this ought to occur in the present
case.
39 I will hear the parties also on the question of costs.
c
c'
-- 11 of 15 --
~~trad()r'5 Progress C.emii('~te
;~:Z4F4
'et?V'.I..J7CA/AL.
C<.,Int of Contro~
ApptOVt:d
,i
Conlrccl S 9r/3B?:.
C-~Pvr$CW.4L.-
-- Sc:hcdU:..
l,<mN.,.
I I
Annexure
pgr:licurars of Claim
~ ~e1eJljiQJt --- %
i'fe.1 AmQunt Pa~obll!!
Ie,.. pr6"t'klu~ p~)'m~m'"
Net PoO),r'I'I:,nl No. /9
//
P V/..2of 6()
._._ ..' ..'- __.__ ~. ____-...-1 ..._::;;::. .. _==...= ..__:::::: ____--=._::::::::..:5_=_._...- ...... ___ .. _ ... __ .. Do:. 6~ ~O. =.. 2«"
d. •. __ • __•... _._... _... DolO!
r:;~a
-- 12 of 15 --
Amoupt of Conlro.::
, "
ll)l~ OadlrCliian;
N9t Conlroc::t
A<'rIotIl,IBi
<:<:r.ifisd .•. _..•.....•.•...••.•.' •.... •.••. •
/
z
12
1.016 ;Ca,,">, ~cr
FOSCO( lW
A",h~Add QlD 41 C63
Av''<'cI1ia
T$I~pt.on"1071275 8500
rae,i..,il. (07) 275 aS17
POfliastof$ of Clc im
v¢lu~ Qf work compleJed 10 d'Qh3
1m;; Itetllnnan %
Mel AnlQuni Payabl'e
l.4;:'i>:O prwrous pOlimeni;
Ner P(]~moc:nt No.
/v
.tVO#5/OS.. 35
._ .• __.Ocle r;; /Q .~-.?!f
.' ~te
· ,
c
c
e}1
-- 13 of 15 --
~l1b~o.ntradQrl:s Prcg~$~· CeHificate
:.. ../-94GC" 3 c:JF ~
,-.)
Svbcollrroc:tor·, Prcgre~ CerU:'ccle NQ. -/_9~--------------
I,o\Qrb EI~ul'lld 10 ./7.. !;j'. ~_._____ Dotc._c:23-.L2 I ~
)..,oount of C~tracl
Eldro~ A~pr~
. . ~l
te$S Oed'tII:II¢~
Net CQDltCl<;~
AlZlounl
Porllc".lors -of Sub.:onlto¢~
Vol.¢, ¢I ~rk OQmpt.;tGd 10 d<Jte
Ne-! Amount Poyoble-
lQ~s pr~iO\J~ poymoms
Net Pcyment No.
1'(6K·""/~
FOBax 199
MharAal4CtD 41Qa
~"ri:io
T."'Fhan;' i071 ~7S ll.5C()
Fac:imila 107) 275 .a.s 17
(~\ ----::~~~:--T-----------..,l,----___r_--.__:;:::___:::___r~_....------
"') W.K'uI~
II..." Nco. Un4
______I-______~_h _______• __ .....-.I ......_-_ ..... - •• ·-.· .. -- .. --1----1
Jl!; 'C-:S
.Claim prepc:l!d bY .. ---.- .... ----.--..--.......-.-.-_ ... - .... -...... -- -.. .
Clll/lifi~ __ ....___ ._ ...... --- ---- ......- .... ..... ........ __...
-- 14 of 15 --
" ~
St :-c:ontr<2d'or's PfOgre~;CE;.riifi<ate
~~~ /~ ~ ..t:;£ aF~
lf1;"u C .... lrad<ll'i
Pt- .limil>a<l:
"'~N. Ol~ nl 4e4 '
Sub:on:raczorr~ Progre:~ Ce:ttlfj~lc No. --J!./:..-.-::S~"c........,....--~---------
""forks e-:cecuted ll> /~ g ._~ Da~ d23 ! 9 I ?~
1..16 lC.rq R«Id
?o~199
Arc~.rnol'" -ctO "I ()ll
Av,IIOIIQ
T.I~fl/'>o3~. ~ 27S 0500
fecsimlla 107) 27.5 6.517
P~r!iculors of Subcoo1ract P"r::iculars of Clo;r:'!
Amo.lr'll of c... ... Jr(xt / value QfW<Jr!o; completed ~ dole V-/ E>!Ir~ Appr<lved t..,~oi hllinlioo % .II
. J / ~-- Ntl AmO<Jnt ?g>,g~l~ /
/ - / I.r:~$ .D~duciion$ Lt=!..< ~iO'J~ pQ)'lJ1SM$
NCilt Conlr(JC1 $/ Not P<lYmellot No_ $V AmOb1l1
.smcdvle- I
c-esalFli<l~ I u..,;t Q...... ~ Unll Vo.VQ <IF work II.." 1':.... G......,I.nd ~
L//VO/Le: q' ~LL3"t/~/O 77~S ~ ~ /7J /9~
A~~Q ... Lr::-! WrS ..;'-
A/ /t'tll1Je
".- -
ci50B:j!1 c:!JO 6/7S .OHt:)E'#..4Y-'/??~?JT ( .......... _... _..
&4'3 0060 90' ~NO. C?OS4ztQ.:.A If ~,~ ~ -
(b/SO C:C>6~(Q_. __ 2:b'-!~~~& Wov:'_~~~ 'c7/ ._y -,--"' ... -"
~-6S6~ ~60i:7-". .. -?-;.V7-,£3-
~iL::JJb3S/ •.... ".0_-
0063S~~
:-, 63~ CO 6.1.'_9-« -... _----
.- h-.o.ruS"...3Z6 ~.----~-....--- ~_~&2 ._ .............
Q?~c£ _~6>91L... . _.,.._..._._--- -- -_ .......... --- -_._- ."'............ _--
eJO LZ~' O?S07-~ - '''-_,",,_0- .. . .
~o60Z0 'L')OS«2 _ _10 __ -
CO~/3S . '--7-'-=r---~ ---_ .... _............. _--1--.- ~-----.- .... --_._- ---_....-..._----
c:!)O /,fS 1--- -_.- .... - --
05"&05 -----_.... '" ....._._.. --_. .- .....--_. _.. .._-- --_.-.,-- .. _----I
......-. Ji..~L u../, ~F 'Work CoR'lplel=d fQ OO~I: $
ClQim pt'epcl r~d;-~ ted ". . .... "':"".. . _.._.___ ... :: ~,- _. .._ ._ ...__.. _... __..._.. _.. ._. ._ . ___. Cole O'.~ ( a .~._ '-' .7.(
Cerli ~4!CI •• ..... •• - •• - ••
C~
c
c
c
-- 15 of 15 --