Boral Bricks (Qld) Ltd v Director-General, Department of Main Roads [1999] QLC 221
[1999] QLC 221
Re: Claim for Compensation -
Resumption for Road purposes -
Acquisition of Land Act 1967 -
(A97-23).
Boral Bricks (Old) Ltd
v.
Director-General, Department of Main Roads
DECISION ON APPLICATION FOR COSTS
LAND COURT,
BRISBANE
4 June 1999
Consequent upon the hearing of the judgment in the above matter on 4 March
1999, the respondent made application for the awarding of costs in its favour. The
claimant resisted that application, claiming that, in the circumstances of the case, no
order for costs ought to be made. There were no appearances on the matter of costs
and, with the agreement of both parties, the matter of costs was determined on the
basis of separate submissions supplied and exchanged by the parties. Counsel for the
respondent was Mr GJ Gibson QC assisted by Mr RS Jones. Counsel for the claimant
was Mr NM Cooke QC assisted by Mr T Trotter.
History of the Claim:
Following resumption of the land on 16 October 1992, the respondent applied
to the Registrar of the Land Court on 21 May 1997, seeking an application under
section 25(1) of the Acquisition of Land Act for the matter to proceed to a hearing in
the Land Court. In response to an order from the Registrar, the claimant filed an
initial claim for an amount of $7,721,189.55 on 30 July 1997. The matter was
initially set down for hearing on 15 June 1998, but with the consent of the parties, the
hearing commenced on 14 September 1998.
Prior to the hearing the claimant sought an application on 7 September 1998
to amend the claim to an amount of $3,140,692.65, and at the hearing, by consent
with the respondent, further amended the claim to an amount of $3,101,736.81, and
-- 1 of 10 --
2
subsequently further amended to $2,955,521.17, including professional fees of
$22,000.
The amount contended by the respondent was initially for $540,000 (including
professional fees agreed at $22,000), and later amended at the hearing to:
Acquisition of land = $671,000.00
Sign = $ 20,500.00
Agreed disturbance = $100,121.72
TOTAL = $791,621.72
The finding of this Court on 4 March 1999 was for an amount of $827,031.72,
including the agreed professional fees of $22,000.
The Legislation:
The general powers of this Court in respect of the awarding of costs are to be
found in the provisions of section 41 (9) of the Land Act 1962 which states:
"The Court may make such order as it thinks fit as to the costs
of or incidental to any matter that it has jurisdiction to hear and
determine including, without limiting the generality of this subsection,
the costs of an adjournment or application made in a pending matter,
allowances to witnesses attending for the purpose of giving evidence
at the hearing and the costs of any survey of boundaries. "
Any costs are further directed under section 27 of the Acquisition of Land Act
1967 which states:
"27. Costs
(1) Subject to this section, the costs of and incidental to the hearing and
determination by the Land Court of a claim for compensation under
this Act shall be in the discretion of that court.
(2) If the amount of compensation as determined is the amount finally
claimed by the claimant in the proceedings or is nearer to that amount
than to the amount of the valuation finally put in evidence by the
constructing authority, costs (if any) shall be awarded to the claimant,
otherwise costs (if any) shall be awarded to the constructing
authority."
Decision:
Before considering the implications on costs in the findings, I look to the key
issues outlined by the parties. I am directed by the Crown Solicitor, for the
-- 2 of 10 --
3
respondent, to the history of the claim. The respondent notes that the most significant
changes in respect of the claim may be summarised mainly as follows:
• Under heading of "Disturbance" - deletion of $109,329.66 for loss of
income.
• Under heading of "Injurious Affection - abandonment of $4,913,012.61
for reduction in life of plant.
• Under heading of "Severance" - a new claim for loss of clay totalling
$785,861.
The respondent argued that the belated withdrawal of the loss of income
claimed and failure to advise the respondent of such amendments to the claim, until
almost the actual date of the hearing, resulted in certain costs being "thrown away"
for professional services and advice necessarily incurred by the respondent in order to
defend the claim, later abandoned. The respondent argues that those costs could have
been avoided but for, in his opinion, the unreasonable actions of the claimant. The
claimant contests that view claiming that, in its opinion, the purely responsive
approach by the respondent did not contribute to the early resolution of certain
matters being investigated by the claimant. The claimant argues that such matters are
therefore essential to fairly represent the cases of both parties, and should not be part
of any order by the Court for costs associated with the hearing.
It is the respondent's submission that costs should be awarded because:
• Objectively the respondent adopted the more appropriate methodology in
arriving at his estimate of the valuation.
• The claimant failed to lead certain evidence in respect of Bora!' s policy on
the future use of the claim materials, which might have had some bearing
upon the outcome.
• The methodology adopted by the claimant was contrary to well established
legal principles.
• The claims by the claimant were clearly excessive, thus requmng the
respondent to seek a determination by the Court.
• The claimant was unreasonable because of the nature of the way late
amendments to the quantums claimed were made.
-- 3 of 10 --
4
• The late amendments of the claimant should be seen in the perspective of
any advantage that might bring to the claimant in the event of seeking to
avoid costs in the matter.
Rowell Gill & Brown, solicitors for the claimant argue:
• It is not appropriate to consider costs by a simple issue-by-issue basis, and
the broad outcome of the case should be considered.
• There is an obligation upon the respondent to document his own case, and
to consider all aspects of the claimant's losses.
• The Court found that the clay had an in situ value, but merely preferred
the method of valuing the clay on a deferred value approach. The
claimant's methodology was not found to be unreasonable or
unsupportable.
• The respondent's expert witness contributed to the length of the hearing
by certain lack of clarity in his technical reports.
• The claimant's claims for severance contained an amount of $750,000 for
interest, not required to be decided by the Court.
• The respondent also amended his estimate of compensation as the case
progressed.
In the matter of the power vested in the Land Court in respect of the awarding
of costs, I note that they are established entirely by Legislation, but they are also fully
or completely discretionary in nature. However, it has been held that in exercising
that discretion this Court must do so in a judicially sound manner, and by reference to
relevant considerations. In this regard I note the findings of the Land Appeal Court in
Townsville City Council v. Moyses and Morris etc (1979) 6 QLCR 271, where the
Land Appeal Court said at page 273:
"The general rule, then, is that costs are in the discretion of the Court,
but of course the discretion must be exercised judicially, that is, by
reference to relevant considerations."
The general power to award costs was considered by the Full Court of the
Supreme Court of Queensland in Wyatt v. Albert Shire Council [1987] 1 QdR 486.
The Full Court also considered the scope of a section of Legislation which gave the
Local Government Court power to "make such order as it thinks fit as to the costs of
any proceedings before it", which it saw as essentially the same as the power
-- 4 of 10 --
5
conferred upon the Land Court, and which was described by the Full Court as
"complete" (page 488).
I am directed also to the need to examine the reasonableness of the conduct of
the parties in deciding whether or not to award costs in this matter. In that respect I
note the findings of the Land Appeal Court in Moyses (supra), where the Land Appeal
Court followed the guidance outlined in Middleton v. Freier and Others (1958) QdR
351, where Philp J, speaking for the Full Court, said at page 357:
"Where an unfettered discretion is given by statute or a rule no court
can by its decision impose conditions upon the free exercise of that
discretion by another court .. . ".
However, the Land Appeal Court in Moyses (supra) went on to explain the
nature of a judicial decision at p. 274:
"Second, where the Court is considering whether it should award costs
to an authority, it could be wrong to have regard merely to the amounts
of the claim and of the award and of the value put in evidence by the
authority. We would think that usually it would be more relevant to
enquire whether the conduct of the claimant, including his making of
an exorbitant claim, if he has made one, has been such as to force the
authority; unreasonably and unnecessarily, into litigation. "
In seeking therefore to exercise my discretion on this matter, I note that had
the respondent been wholly successful in its claim, it may have generally had an
expectation for costs to follow the decision. However, such a conclusion would
always be subject to the discretion of this Court. (See Moyses p. 278).
The matter of whether a party has won or lost in a compensation matter was
discussed in Minister for the Environment v. Florence (1980-81) 45 LORA 127,
where Wells J said at p.149:
"Upon an ordinary claim in the general jurisdiction it is,
generally speaking, obvious who has won and who has lost, and
correspondingly clear why costs usually follow the event. Upon a
claim for compensation for land compulsorily acquired, it is not,
generally speaking, appropriate to speak of one party as having won;
compensation is awarded to one who had already been given, by
statute, the right to receive it. It is therefore as just to say of the latter
sort of case that the claimant ought, in the absence of special
circumstances, to receive his reasonable costs of obtaining the
compensation that is, ex hypothesi, his due, as it is to say of the former
sort of case that prima facie costs follow the event in favour of the
party who has won. But costs are, as always, discretionary, and no
hard and fast rule will ever be allowed to occupy part of an area
-- 5 of 10 --
6
controlled by a discretion, however predictable the result of its
exercise may be in certain sorts of cases."
General guidance on costs in the matters of compensation were also reviewed
by the Land Appeal Court in Yalgan Investments Pty Ltd v. The Council of the Shire
of Albert (A94-94), 11 December 1997 (to be reported) at pages 3-5. In the Court
below in that matter the learned Member, in the circumstances of that case, found that
each party should bear its own costs of the appeal, arguing that the unusual
circumstances of the rezoning of the land had an impact upon the determination of the
highest and best use of the land. In his determination the Member was critical of each
of the valuation methods adopted by the parties, and finally adopted a method which
was a compromise of the two approaches.
On appeal of that decision the Land Appeal Court, having outlined the
principles influencing the awarding of costs, found that the claimant's application for
costs should be allowed in part. The decision on costs was rescinded, and the
respondent was directed to pay the costs associated with a part of the hearing, as fixed
by the taxing officer of the Supreme Court. Because both methods of valuation were
rejected, the Land Appeal Court found that the rights of the claimant to seek costs, as
its claim was nearest to the amount of compensation awarded, should not have been
denied.
In determining that partial costs should be awarded in that matter, the Land
Appeal Court drew support from two decisions of the Federal Court in Hughes v.
Western Australian Cricket Association (Inc)(1986) 8 ATPR 40-748, and also in
Dodds Family Investments Pty Ltd v. Lane Industries Pty Ltd (1993) 26 IPR 261, at
271-272. A review of the above decisions was analysed by the Land Appeal Court in
Kabale Holdings Pty Ltd v. Director-General, Department of Transport (A94-34), 15
October 1997, to be reported, at pages 33 and 34.
In the matter of Nadco Pty Ltd v. Chief Executive, Department of Transport
(AV96-05), 18 July 1997, unreported, the learned Member found costs against the
respondent on the basis that while the claimant was not "wholly successful", the facts
available supported that the claimant had not acted unreasonably in pursuing the
claim. The initial claim by the claimant amounted to $1,193,593.63, the respondent
contended for $483,500, and the Land Court found for compensation at $718,611.
On the final day of the hearing the claimant, with leave from the Court, and without
opposition from the respondent, amended the claim to $892,000.
-- 6 of 10 --
7
On appeal the Land Appeal Court rejected the claim by the constructing
authority for a re-assessment of the amount of compensation, but rescinded the
Member's direction in respect of the awarding of costs. The Land Appeal Court
found at page 10:
"A clear intention evident in section 27(2) is to discourage exorbitant
claims in compensation cases. It would not be unreasonable to
describe the claim to $1,193,593.63 as exorbitant since it exceeded the
sum arrived at by the Member by such a large amount. It remained the
claim until nearly all of the costs of the hearing had been incurred.
With hindsight it can be seen that the claimant was permitted the
substantial advantage of avoiding any possibility of an order for costs
against it by its late amendment; to add to that an order for costs in its
favour went far too far we think. In the result we conclude that the
Member's discretion on the matter of costs miscarried and that she
should have made no order as to costs."
That decision followed guidance found m Commissioner for Railways v.
Buckler [1996] 1 QdR 18 where McPherson JA said at p.23:
"Stated in general terms, what the court is now required to do in fixing
the incidence of costs under this rule is look to the final positions taken
up by the parties. In the case of the claimant, it is the quantum of
compensation last claimed. Theoretically at least, its amount might
not be known until the final address of counsel for the claimant. In
practice, however, s.24(2A) furnishes a disincentive against conduct
like that. It does so by restricting the right to amend a claim once it
has been filed in accordance with s.24(2A) of the Act. Thereafter an
amendment may be allowed; but on terms including payment of costs:
see s.24(3 ).
On the other hand, there seems to be no comparable restnct10n
preventing the constructing authority from deferring disclosure of its
final position until a late stage of the proceedings. It will be
discoverable only from "the amount of the valuation finally put in
evidence by the constructing authority", which means that it cannot
with confidence be known what the amount of it is until the
constructing authority closes its case."
In the current matter the final amounts led by the parties formed the basis of
any discretion on costs in the matter.
In the end, while it is the final amount claimed by the parties which is to form
the basis for comparisons under section 27(2) of the Act, any strategic advantage
gained by a party in delaying the adoption of a final claim, should be taken into
consideration when assessing whether costs should be awarded. Note the difference
-- 7 of 10 --
8
approach taken in Arcpoint Pty Ltd v. Director-General, Department of Transport,
(1992) 14 QLCR 115 .
However, in Buckler (supra) McPherson JA went on to explain that, in his
opinion, the words "outlining the amount of the valuation finally put in evidence by
the constructing authority refers to 'the constructing authority's assessment of the
compensation payable, which in the ordinary way will be contained in a valuation
report put in evidence in the proceedings'." (P.25). In the current matter the amount
of $791,621.72 previously discussed should be taken to represent the respondent's
final claim. In the current matter I also consider the "reasonableness" of the claims
submitted by the claimant. Initially, on the directions of the Registrar of the Land
Court, the claimant lodged an outline of its claim to a total of $7,721 ,189.55. That
was subsequently in a series of amendments reduced to $2,955,521.17. It was argued
during the hearing that some delays had occurred in bringing the matter to completion
by a reluctance to pursue the matter by the claimant. That was strenuously denied by
the claimant and not upheld by the Court. There was no evidence that the claimant
had not approached the matter in other than a serious attempt to assess the total loss to
the claimant. It was reasonable in such circumstances for both parties to fully
examine all aspects of the possible claim, including, if appropriate, any claim for
disturbance, injurious affection or severance.
That some of those claims were later not proceeded with by the claimant, does
not prove that the specialist technical advice for both parties was not necessary. In
those circumstances I believe it was proper for each party to bear their own costs in
preparing their respective cases, and I find no cause for costs to be awarded to either
party for expenditure "thrown away" by not proceeding to hear on all matters. Such
costs would appear to be reasonable costs associated with justifying the separate
positions of each party. Following further discussions it was also agreed between the
parties on disturbance items to a total of $100,121.72, thus reducing the length of the
hearing, a matter which should not be held to the disadvantage of either party.
A key issue between the parties was the preferred method of assessing any
residual value in the claim for material lost by the resumption. In the end the Court
favoured the method of deterred value, as proposed by the respondent. The decision
of the claimant not to elect to provide other evidence of any different policy in respect
of the use of the clay material, instead of that provided to the Court, influenced the
reliance of the Court in the method adopted for that purpose.
-- 8 of 10 --
9
In considering the prosecution of this matter I have found no evidence of
anything that could be construed as other than a very professional approach by both
parties. In considering whether there were any "special circumstances" existing in
this matter, I note the findings of the Land Appeal Court in WH Bowden v. Valuer-
General (1980-81) 7 QLCR 138, where in dealing with the matter of costs, the Land
Appeal Court said at p.146:
"We think, in dealing with questions of cost, that it is an important
consideration that there be ease of access to the Land Court and the
Land Appeal Court ..... Fear of an adverse order with respect to costs
may deter citizens with just complaints from resorting to the Courts;
that has in the past occurred, as will appear. It seems to us unjust to
adopt a restrained attitude towards awarding costs against citizens
without adopting an equally restrained attitude towards awarding costs
against the Valuer-General. That is not to say that, in a proper case,
the Land Court or the Land Appeal Court will not award costs against
either a citizen or an authority subject to the provisions of the statute
which governs the matters."
In the end I find that the total amount awarded by the Court ($827,031.72)
was considerably nearer to the final amount contended by the respondent
($791,621.72) than to the final amount claimed by the claimant ($2,955,521.17). On
that basis there is argument for an award of costs in favour of the respondent under
sections 27(1) and (2) of the Act. On the matter of whether there were any actions on
the part of the parties that may have led to an unnecessary extension of the litigation,
I find that, while the claimant acted in a reasonable manner in pursuing its claim, the
major variation between the parties would have invariably led to requiring the matter
to be resolved by the Court.
Because of a lack of any "special circumstances" which might otherwise upset
the usual rule that a successful party might expect an order for costs, I believe the
respondent has a reasonable expectation of an award of costs in this matter.
However, as noted earlier, in the matter of whether the respondent should be
compensated for professional costs "thrown away", I find that those additional costs
associated with preparing the respondent's case should be borne by the respondent.
In accordance therefore with directions found in the Legislation and
exercising judicial discretion afforded by precedents, I order that the claimant pay the
respondent's costs of and incidental to this appeal. The amount of such costs shall be
ascertained and fixed by the proper costs taxing officer of the Supreme Court of
-- 9 of 10 --
10
Queensland at Brisbane in accordance with the provisions of section 41 (9) of the
Land Act 1962.
(NG Divett)
Member of the Land Court
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1999/221