Cox v Chief Executive, Department of Natural Resources [1998] QLC 141
LAND COURT,
BRISBANE
17 November 1998
Re: Claims for Compensation -
Resumption for Burdekin River Irrigation Project -
Acquisition of Land Act 1967.
Cecil Arthur Cox, Valarie Mary Cox and Lex Howard Cox
v.
Chief Executive, Department of Natural Resources
(A96-25)
Cecil Arthur Cox
v.
Chief Executive, Department of Natural Resources
(A96-26)
Lex Howard Cox
v.
Chief Executive, Department of Natural Resources
(A96-27)
Valarie Mary Cox
v.
Chief Executive, Department of Natural Resources
(A96-29)
James Cyril Cox
v.
Chief Executive, Department of Natural Resources
(A96-28)
(Hearing at Townsville)
J U D G M E N T
Introduction
These matters involve claims for compensation in respect of five (5) parcels of land
held by members of the Cox family and situated to the south of the Bruce Highway between
Giru and Ayr, in the Burdekin District. The lands were resumed under the provisions of the
Acquisition of Land Act 1967 for the purposes of the Burdekin River Irrigation Project (the
Burdekin scheme).
[1998] QLC 141
-- 1 of 78 --
2
The first claim is for the taking of land owned by Mr Cecil Cox, his wife Mrs Valarie
Cox and their son Mr Lex Cox, described as Lot 44 on Plan GS7, Parish of Jarvisfield (Lot
44), containing an area of 1817.577 hectares. It was resumed on 22 December 1990.
The second claim is for the taking of land owned by Mr Cecil Cox, described as Lot
42 on Plan GS 148, Parish of Selkirk (Lot 42), containing an area of 1,328.178 hectares. It
was resumed on 18 December 1992.
The third claim is for the taking of land owned by Mrs Valarie Cox, described as Lot
43 on Plan GS148, Parish of Selkirk (Lot 43), containing an area of 1,328.178 hectares. It
was also resumed on 18 December 1992.
The fourth claim is for the taking of land owned by Mr Lex Cox, described as Lot 5
on Plan GS149, Parish of Barratta (Lot 5), containing an area of 1,781.831 hectares. It was
resumed on 5 November 1993.
The fifth claim is for the taking of part of land owned by Mr James Cox, the son of Mr
Vivian Henry Cox and the nephew of Mr Cecil Cox, originally described as Lot 15 on Plan
GS37, Parish of Jarvisfield, containing an area of 610.569 hectares. It was resurveyed as Lots
1 and 15 on Plan 814658 on 22 May 1991 and Lot 1, containing an area of 344.5 hectares was
resumed on 7 September 1991. Lot 15, containing an area of 266.0695 hectares, was retained
by Mr Cox. Plan 814658 was registered on 7 April 1992. However, despite the fact that Lot
15 is now the description of the retained land, throughout the hearing of these cases, the
resumed land was referred to as “Lot 15”, no doubt as a shortened version of the more correct
reference “the land resumed from the original Lot 15 on Plan GS37”. To avoid confusion, I
will continue to refer to the resumed land as “Lot 15”.
These matters were heard in Townsville in March and April 1998. The claimants
were represented by Mr RM Needham and Mr RS Litster. The respondent was represented by
Mr NM Cooke QC and Mr RS Jones.
The Claims
The original claims for compensation for Lots 44, 42, 43 and 5 were dated 17 March
1995, for the following amounts:
Lot 44 $ 4,960,000
Lot 42 $ 3,349,000
Lot 43 $ 3,349,000
Lot 5 $ 4,324,000
The original claim for Lot 15 was dated 31 July 1992, for an amount of $742,000.
On the first day of hearing, 16 March 1998, the claims were amended as follows:
-- 2 of 78 --
3
Lot 44 $ 2,595,334
Lot 42 and Lot 43 $ 4,202,855
Lot 5 $ 3,032,971
Lot 15 $ 721,348
The claim in respect of Lot 15 was again amended on 27 March 1998, to accord with
the altered valuation of the claimants’ valuer, Mr Eales, to $699,400.
The respondent contended for compensation in the following amounts:
Lot 44 $ 1,450,100
Lot 42 $ 691,840
Lot 43 $ 744,180
Lot 5 $ 939,600
Lot 15 $ 372,750
The difference between the parties stems from the approach which they adopted to the
highest and best use of the land and the extent to which each of the parcels had potential as
irrigable arable land. Before proceeding to consider each of those different approaches, I will
outline the background to these cases.
Background
The resumed land originally formed part of a cattle grazing property, which has been
owned by members of the Cox family for four generations, since 1887. Towards the end of
1974, the then joint owners of the property, Cecil Arthur Cox and his brother, Vivian Henry
Cox, commenced negotiations with a view to partitioning the land. In November 1977, the
property was partitioned and certain parcels, including Lots 44, 42, 43 and 5, were transferred
to Cecil Arthur Cox and members of his family. Mr Cecil Cox held Lot 44 jointly with his
wife, Mrs Valarie Cox, and their son Mr Lex Howard Cox; Mr Cecil Cox held Lot 42 by
himself; Lot 43 was held by Mrs Cox; while Lot 5 was held by Mr Lex Cox. The balance of
the property was transferred to Mr Vivian Henry Cox and his family, including his sons
Geoffrey, David and James, and was held by them in various ownerships, with the land from
which Lot 15 was resumed being owned by James.
Up until the time of the redistribution of ownership of the land, the property had been
used for grazing cattle, but members of the family realised that the land had potential for
growing sugar cane and set about developing parts of it for agriculture. However, the balance
of the property continued to be used for grazing cattle.
At that time, most of the cane in the Burdekin district was grown on light levee soils
in the Burdekin delta area, as the heavy cracking clays, or Barratta clays, of which the Cox
lands largely consisted, were not regarded as suitable for cane growing. However, at the time
-- 3 of 78 --
4
of transfer of the lands to the various family members, it was intended to progressively
develop those lands for agriculture.
In addition to the subject lands, Mr Cecil Cox and Mr Vivian Cox also owned a cane
farm of approximately 100 hectares in the Kalamia area, known as “Millview”. In June 1973
that property was transferred to Mr Cecil Cox, Mrs Valarie Cox, and Mr Lex Cox. It
continued to be leased to various tenants until 1978, when Mr Lex Cox took over its
management and operated it in partnership with his parents.
It became apparent to Mr Lex Cox that the subject lands were superior to “Millview”
for the growing of sugar cane. The land in the Kalamia area was broken in nature and of
poorer soil quality, the light sandy soils required more water and were, therefore, less
economic to farm than the Barratta clays.
At the time of the redistribution of the Cox lands to the various family members, Lot
574, Parish of Jarvisfield (Lot 574), of 64.75 hectares, which adjoined Lot 44 to the east, and
situated within the North Burdekin Water Board area, was transferred to Mrs Valarie Cox. At
that time it was leased to a rice grower.
The owners of “Millview” intended to transfer their cane farming operations to Lot
574 and then onto Lot 44. However, they faced a number of difficulties. The cane land on
“Millview” was assigned to the Kalamia Mill, while Lot 574 and the subject lands, although
having no assignments, were in the Pioneer Mill area and the Invicta Mill area. At that time,
peaks and assignments attached to the lands to which they were granted and could not be
substituted and transferred as of right. Furthermore, the Regulation of Sugar Cane Prices Act
prevented transfers between mill areas, except in extreme circumstances.
In 1986 the regulation of peaks and assignments was freed-up to some extent, so that
peak and assignment could be purchased independently of land. By the end of 1987, they had
purchased 2,000 tonnes of peak and approximately 20.4 hectares of assignment and relocated
it to Lot 574. However, their 1989 application to substitute part of the “Millview”
assignment to Lot 44 was not approved, but in that same year the sugar industry was further
deregulated to allow roaming between mill areas. This enabled them to plant part of the
“Millview” assignment on Lot 44 in September 1989. By the time of the resumption of Lot
44 in December 1990, approximately 20 hectares of it were planted up to sugar cane.
In March 1988, the owners applied to the Water Resources Commission (WRC), the
predecessor of the Department of Natural Resources (DNR), for an irrigation bore licence to
grow cane on Lot 44. That application was granted in accordance with the WRC groundwater
allocation policy for 0.25 megalitres per hectare, with an entitlement of 454 megalitres.
Their intention had been to use Lot 44 for the peak and assignment which they had purchased,
-- 4 of 78 --
5
but which circumstances had made it more appropriate to locate on Lot 574. In addition, part
of Lot 574 had been leased to a neighbour for cane growing.
During this period, the family of Mr Vivian Cox had also been active in the
development of their land for cane farming and in planning the means by which irrigation
water could be obtained. It was clear that the progress of the development of all of the Cox
land for sugar cane growing was dependent upon the availability of irrigation water.
All this development took place under the threat of resumption. From the time of
publication of an Order in Council on 12 April 1980, the subject lands had been included
within the Burdekin River Irrigation Area (BRIA) and therefore likely to be resumed. The
lands owned by Mr Vivian Cox and his family were similarly affected and on 5 May 1990
and subsequently, over 3,700 hectares of land owned by Mr Vivian Cox was resumed.
Claims for compensation for approximately $10.4 million were heard by the Land Court and
on 17 July 1995, judgment was delivered in the matter of VH Cox v. Water Resources
Commission (not yet reported), determining compensation at $4,960,400. Both parties
appealed to the Land Appeal Court and on 21 August 1997, that Court delivered a judgment
in the matter of Water Resources Commission v. VH Cox (not yet reported), determining
compensation at $4,300,400. The judgments of the Land Court and Land Appeal Court will
be referred to as “the Davco decision”.
“Davco” is derived from the name given to a private irrigation project called the
Davco Irrigation Project (the Davco project), devised by Mr David Cox (the son of Vivian
Henry Cox), for the development of the Cox family lands as irrigated cane land. The
Burdekin scheme prevented the Davco project from proceeding as planned. The whole matter
was discussed in detail in the Davco decision and that degree of detail need not be repeated
here. However, because of the importance of the Davco case to the present cases, it is
necessary to briefly outline the main features of the Davco project.
The Davco Project
Essentially the Davco project was a private irrigation scheme devised by Mr David
Cox for the growing of sugar cane on his own land, that of his family and the land of
neighbouring farmers. The project commenced in 1977 and was modified over the years with
changes in circumstances. It involved the conjunctive use of water resources, a series of
drains which exploited the natural drainage of the land in such a way as to utilise run-off
water and tail water from irrigation, together with water pumped from the Burdekin River to
recharge underground water supplies.
-- 5 of 78 --
6
It was described by David Cox in the Davco case as “... a carefully planned privately
funded self-sufficient integrated system of water harvesting, storage and distribution with
infrastructure to legally harness, store and reticulate water from the Burdekin River, the
underground aquifer, natural rainfall and topographical runoff for use on lands owned by the
Cox family and others. The project comprises a system of conduits, channels, drains, pipes,
culverts, pumps and storage cells to distribute the water to and over the lands. The project
was designed by me with sufficient capacity to supply peak irrigation requirements to the
whole of the land for the growing of sugar cane on that land.”
Support and financial assistance for the project were provided by members of the Cox
family, but it was largely financed by developing, subdividing and selling part of their land.
During 1978 and 1979, development work proceeded on the Davco main channel, preliminary
work on the pump stations and pipe systems were carried out, consents obtained and a licence
to pump 1,200 megalitres per annum from the Burdekin River was granted.
However, with the announcement of the Burdekin scheme in April 1980, the Cox
family was prevented from proceeding with the development of their land by financing that
development by the subdivision and sale of part of it. However, development continued on
the Davco main channel, because David Cox was not convinced that the Burdekin scheme
would proceed. As explained in the Davco decision, he spent a considerable amount of time
and effort trying to limit the impact of the Burdekin scheme on his farm and his project.
The Davco project plan was continually modified as circumstances changed. With the
announcement of the Burdekin scheme and the inclusion of his land, that of his family, and
that of all potential beneficiaries of the Davco project in the BRIA, subdivision of any of
those lands would be allowed only with the approval of the WRC. Such approval would be
unlikely, as the land was required for the Burdekin scheme. In addition, from the time of that
announcement, the lands of all potential users of water from the Davco project, including the
subject lands, were under threat of resumption.
Development of the Davco project in a modified form continued from 1984 to 1986,
but it was realised that the construction of the Burdekin Dam and the supply of channel water
to the BRIA, was going to profoundly affect the project.
At least part of the subject land, Lot 44 and Lot 15, were to be included in the Davco
project. Mr Lex Cox explained that his cousin, David Cox, had approached his father and
himself in 1977, suggesting that he (David) would be financing the project by selling property
as he went and that Cecil and Lex Cox should pay him in land, rather than money. He said
that David believed there was sufficient water for the Davco project to extend right through to
the Bruce Highway. However, they all realised that the benefit would not accrue to the
-- 6 of 78 --
7
subject land for some time, so David opted to take a loan of funds to offset his development
costs. Loans were made by Cecil Cox to David Cox from 1977 and have all been repaid.
The Resumed Lands
At the various dates of resumption, the whole of the resumed land, with the exception
of part of Lot 44 and Lot 15, was being used for the grazing of cattle by the Kalamia Plains
Pastoral Company, a partnership comprising Vivian Henry Cox and his son, Geoffrey Cox,
which ran cattle over an aggregation of family lands, a large proportion of which was resumed
for the purposes of the Burdekin scheme.
Mr Geoffrey Cox explained that they used Lot 44 for breeding, whilst Lots 42 and 43
were used for growing steers and Lot 5 was used for fattening bullocks. He regarded Lot 44,
which comprised heavy Barratta clays, as being very similar to the lands of Vivian Henry
Cox, which were the subject of the Davco case. Lots 42 and 43 comprised soils ranging from
heavy clays suitable for agriculture, through to river silts and creek overflows, which were
better drained. Lot 5 comprised areas of heavy clay soils, but the balance of it was what Mr
Cox described as “broken sandier and siltier creek banks, well drained and suitable for
fattening bullocks”. Para grass was successfully introduced into the reliable swamps on Lots
42, 43 and 5, but was not successful on Lot 44. Three stockwater dams were constructed on
Lot 5, but only one was really successful.
There was little dispute between the valuers for the parties about the description of the
resumed lands. Where there were significant differences, I have so indicated in the following
discussion of each of the lots. There was also very little difference between the soils experts
as to the areas of land on each lot suitable for development for furrow irrigation of sugar cane.
Where they have differed, I have adopted the greater area.
Lot 44 comprises level to gently undulating forest country, which in its original state
was moderately timbered with poplar gum, Moreton Bay ash and tea-tree. The soils are
predominantly Barratta clays, with smaller areas of clay loams and some sandy loams. Some
1470 hectares were considered to be suitable for development for furrow irrigation of sugar
cane.
At the date of resumption (22 December 1990), approximately 45 hectares had been
cleared to cultivation, 20 hectares of which was growing irrigated sugar cane. Approximately
575 hectares had been cleared and burnt and was carrying light regrowth, while a further 20
hectares (according to the respondent’s valuer) had been pulled, but was carrying regrowth.
-- 7 of 78 --
8
An equipped irrigation bore with electricity connected, was situated near the southern
boundary, with a waterworks licence with a nominal allocation of 454 megalitres to supply
Lot 44. There was also a small earth dam.
Lot 44 is situated about 15 kms south-west of Ayr, with access at the date of
resumption by means of the formed gravel Sexton Road. There was a mill tramline siding
approximately 2.5kms from the property boundary on Sexton Road. A tramline easement had
been granted to the Pioneer Mill on land immediately to the south.
Lot 42 is level to gently undulating forest country, broken by a number of
watercourses, with seasonally flood prone frontage to Barratta Creek on the east. It was
originally timbered with poplar gum, Moreton Bay ash and tea-tree. The main soil types are
Barratta clays, with areas of clay loam and areas of sandy loam. Some 961 hectares were
considered to be suitable for furrow irrigation of sugar cane.
At the date of resumption (18 December 1992), about 41 hectares had been pulled,
carrying moderate to heavy regrowth, with a further 15 hectares cleared to grass.
A waterworks licence with a nominal allocation of 332 megalitres had been granted to
supply Lot 42, but had not been acted upon and there were no irrigation bores on Lot 42 at the
date of resumption. Stock water consisted of three excavations or small earth dams.
Lot 42 is situated about 28 kms west of Ayr, with access at the date of resumption by
means of 2 kms of formed gravel road, or track, to the Bruce Highway. A mill tramline was
located 6 kms from the north-west corner.
Lot 43 is level to gently undulating/sloping forest country, broken by a number of
watercourses, with seasonal flood-prone frontage to Barratta Creek. It was originally
timbered with poplar gum, Moreton Bay ash and tea-tree. The main soil types are Barratta
clays and clay loams, with some sandy loam. Some 1019 hectares were considered to be
suitable for furrow irrigation of sugar cane.
At the date of resumption (18 December 1992), approximately 159 hectares had been
pulled, with moderate to heavy regrowth and 6 hectares had been cleared to grass.
An application for a waterworks licence had been made in July 1990, but it does not
seem to have been granted or refused. In accordance with the respondent’s groundwater
allocation policy of 0.25 megalitres per hectare, Lot 43 would have been entitled to a nominal
allocation of 332 megalitres per annum. Stock water consisted of two dams/excavations and
one equipped bore, licensed for stock water.
-- 8 of 78 --
9
Lot 43 is situated about 30 kms west of Ayr, with access at the date of resumption to
the Bruce Highway by means of 4 kms of bush track. A mill tramline was located about 4
kms from the south-west corner.
Lot 5 is level to gently undulating to gently sloping forest country, broken by a
number of watercourses, with seasonal flood-prone frontage to Barratta Creek on the east. It
was originally timbered with poplar gum, Moreton Bay ash, tea-tree and some beefwood.
Soil types vary from Barratta clays to clay loams, to loamy sands and sandy loams, some
alluvial soils and swampy areas. It was considered by all relevant witnesses to be good
grazing and fattening country. Some 1259 hectares were considered to be suitable for furrow
irrigation of sugar cane.
At the date of resumption (5 November 1993), about 78 hectares had been pulled and,
according to the respondent’s valuer, part stick-raked and burnt with moderate to heavy
regrowth, while the claimants’ valuer said it had light regrowth.
An application for a waterworks licence to irrigate sugar cane had been made in July
1990, but it seems this had been neither granted nor refused. In accordance with the
groundwater allocation policy of 0.25 megalitres per hectare, Lot 5 would have been entitled
to a nominal allocation of 445 megalitres per annum. Stock water consisted of a concrete
well and three earth dams.
Lot 5 is situated about 32 kms south-west of Ayr, with access at the date of
resumption by means of 7 kms of bush track to the Bruce Highway, or about 1.5 kms of track
to Up-River Road to the west.
Lot 15 comprises generally level, lightly to moderately timbered forest country,
originally timbered with poplar gum, Moreton Bay ash and tea-tree, particularly in a flood-
prone area to the north-east. The soils are predominantly Barratta clays and clay loams.
Some 311 hectares were considered to be suitable for furrow irrigation of sugar cane. At the
date of resumption (7 September 1991), approximately 256 hectares had been cleared, stick-
raked and burnt, with light regrowth (according to the claimants’ valuer) or pushed, stacked
and burnt (according to the respondent’s valuer).
Lot 15 was subject to two easements in favour of the Ayr (later Burdekin) Shire
Council for water storage conservation diversion and ancillary purposes. These easements are
in the south-eastern corner of the resumed land, but neither valuer has mentioned them as
affecting its value.
-- 9 of 78 --
10
At the date of resumption, there was an irrigation bore on the unresumed part of Lot
15, the waterworks licence for which provided for a nominal allocation of 153 megalitres per
annum. However, it seems to be agreed that only 87 megalitres of this is attributable to the
resumed land, while the balance 66 megalitres is attributable to the unresumed part.
A Water Board channel is constructed in the north-east corner of Lot 15, but no
irrigation water is available, as the subject land is outside the Water Board area. Stock water
supplies were permitted, but the Board bylaws prevented irrigation supplies being available to
the subject land.
An area of 122.8 hectares of the resumed land had been leased to an adjoining owner,
Mr G.O. Poli, from 14 May 1990 to 31 December 1994, for the purpose of growing sugar
cane. The lease was terminated by the resumption, but it seems that Mr Poli arranged to grow
cane on part of the retained land, which he subsequently purchased. There was evidence that
as a temporary measure, Mr Poli was permitted to use NBWB water.
There was also a stockwater bore on the resumed land and a small dam.
Lot 15 is situated about 12 kms south-west of Brandon and about 18 kms south-west
of Ayr. Access at the date of resumption was by means of about 2 kms of gravel and bush
track to a bitumen road. A mill tramline was located about 1.5 kms away.
The Effect of the Burdekin Scheme
In these cases, as in the Davco case, there was no dispute between the parties that any
effect that the Burdekin scheme had on the value of the claimants’ lands must be disregarded
in determining compensation, in accordance with the principles in Pointe Gourde Quarrying
and Transport Co Ltd v. Sub-Intendent of Crown Lands [1947] AC 565 and Melwood Units
Pty Ltd v. Commissioner of Main Roads [1979] AC 426.
As in the Davco case, that gave the whole proceedings a sense of unreality, because
much of the evidence and argument was directed not at what has happened, but what would
have happened if there had not been a Burdekin Dam and the resulting Burdekin scheme.
In the Davco case, the claimants contended that the value of the resumed land had
been depreciated by the Burdekin scheme, while the respondent contended that the scheme
had enhanced its value. The Court found that the proclamation of the Davco land as part of
the BRIA in 1980 had prevented the Cox family from financing the development of their land
by the subdivision and sale of part of it. The Court also found that the evidence did not
establish that the Davco project would have been successful, nor did it prove that it would
not. There was simply too much doubt about its technical feasibility and its financial
viability. The best that could be said was that it might have been successful.
-- 10 of 78 --
11
Therefore, the Court could not make any finding as to how far the Davco project
would have progressed by the date of resumption, if there had been no Burdekin scheme. It
found that it could not be said that, but for the Burdekin scheme, the Davco project would
have been completed.
In that case, the claimant contended that the Court must find that at the date of
resumption the resumed land would have had irrigation water provided by the Davco project.
The claimant relied for that contention on the decision of Hardie J. of the Land and Valuation
Court of New South Wales in Woollams v. The Minister (1957) 2 LGRA 338, which
concerned compensation payable for land resumed for the construction of the Warragamba
Dam. In that case, Hardie J. assumed that if it had not been for the announcement of that
scheme, the amenities and economic and social conditions in the area would have improved
and not deteriorated in the period between the decision of the resuming authority to proceed
with the dam project and the date of resumption.
In the Davco case, the Land Court rejected the proposition that the principle in
Woollams could be extended to include the assumption of the successful completion of a
private irrigation scheme. The Land Appeal Court upheld that finding and went on to state at
page 7 of its judgment:
“ These are, however, different times, and we see no justification for extending such
an assumption-making process to a case concerned with the sugar industry in
Queensland from April 1980 to May 1990, and more particularly with the possible
completion of the private irrigation scheme undertaken by people unable to finance it
from their own resources and dependent upon the approval of regulatory authorities.
Such a process is no proper substitute for evidence from which reasonable inferences
may be drawn. ”
However, the Land Court did assume that there would have been an expansion in the
sugar industry, a tramway would have been constructed and the values of irrigated cane land
and land with that potential, would have increased in value.
The Land Appeal Court endorsed the approach of the Land Court in finding that part
of the resumed land which was suitable for cane growing could be irrigated in accordance
with the then existing WRC groundwater allocation policy of 0.25 megalitres per hectare and
that such land would be selling for prices higher than were being achieved for irrigated land at
the BRIA auction sales at the date of resumption.
It also endorsed the finding of the Land Court that a prudent purchaser would have
paid something extra for the remaining land which was suitable for the growing of cane,
because of the possibility that the Davco project would have provided irrigation water to that
land at some time in the future.
-- 11 of 78 --
12
After re-examining the evidence, the Land Appeal Court affirmed the value of $6,000
per hectare determined by the Land Court for irrigable arable land. However, while agreeing
that the evidence supported the Land Court’s finding that a hypothetical prudent purchaser
would have paid some premium for dry arable land with potential for sugar cane growing for
the benefit that might flow from the Davco project, the Land Appeal Court was persuaded
that the assessment of $2,000 per hectare by the Land Court was more generous than justified
on the evidence. It considered that $1,700 per hectare was more appropriate.
The Land Court’s determination of $400 per hectare for the grazing land was not
challenged on appeal.
In the present cases, both the parties relied on the Davco decision, as endorsed and
amended by the Land Appeal Court. However, counsel for the claimants, argued that while it
was not possible for the Court to find the extent to which the Davco project would have
progressed at the date of resumption if it had not been for the Burdekin scheme, it was open
to the Court to find that it would have progressed further than it had actually done at that date.
I have no difficulty in coming to that conclusion. However, I cannot see how that
much assists the claimants. The same uncertainties remain as to the technical feasibility or
financial viability of the Davco project. In the Davco case, the Court was unable to assume
that the Davco project would have been providing water to the resumed land at the date of
resumption. In these cases, the subject lands are, with the exception of Lot 15, further
removed, so there is even less likelihood of them being supplied with irrigation water.
It was submitted that I should find that, but for the Burdekin scheme, more of the
Davco lands would have been subdivided and developed, and/or further channels would have
been dug to service those lands, and/or an above ground storage would have been built. For
the reasons already discussed, I cannot make such specific findings. I can only find on the
evidence before me that it is likely that the Davco project would have been further advanced
than it was at the dates of resumption.
However, there is another aspect of this argument which must be considered and that
relates to the respondent’s groundwater allocation policy. The evidence in this regard, like so
many other aspects of these cases, involved a large degree of conjecture on the part of the
witnesses. Of course, no one can be certain just what would have happened if the Burdekin
scheme had not been announced in early 1980 and the Burdekin Dam had not been built. The
witnesses on each side had different views. The role of the Court, as I see it, is to consider
the evidence upon which those views were based and to decide what is most likely to have
happened.
-- 12 of 78 --
13
Groundwater Allocation Policy
At the date of resumption of the subject lands, the WRC had a policy of granting
waterworks licences for sub-artesian bores for irrigation purposes on the basis of 0.25
megalitres per hectare per annum, for the area in which the subject lands are located. That
groundwater allocation policy has continued.
Mr ML Leach, who was employed at the relevant time by the WRC as Senior
Hydrologist, Northern Region, based at Ayr, gave evidence for the respondent. He explained
that the subject lands are situated in a sub-artesian bore locality where a licence is required for
construction of a sub-artesian bore for purposes of irrigation. For the sub-areas 600 and 700
in which they are situated, the WRC allocation policy was 1 bore for each 800 hectares or part
thereof, and a nominal allocation of 0.25 megalitres per hectare per annum.
Mr Leach was unable to trace the source of that allocation policy. He said that it was
in existence when he arrived in the Burdekin district in 1987, and he felt that it was related to
rainfall infiltration of 25 millimetres per annum.
Mr Leach provided the following summary of the entitlement of each of the subject
lands:
Lot 44 - Entitlement 454 megalitres; licence granted and bore constructed;
Lot 42 - Entitlement 332 megalitres; licence granted, but no bore constructed; Lot
43 - Potential entitlement 332 megalitres; application for licence, but no bore constructed;
Lot 5 - Potential entitlement 445 megalitres; application for licence, but no
bore constructed.
Lot 15 - Entitlement 87 megalitres; application for licence, but no bore constructed
on resumed land.
Mr Leach went on to explain that if the claimants had applied for additional allocation
over and above 0.25 megalitres per hectare per annum, under the provisions of section
4.18(1)(b) of the Water Resources Act 1989, the Chief Executive must have caused inquiry to
be made into:
the availability and sufficiency of groundwater to satisfy the requirements of
existing licensees and the applicant;
the effect the granting of the licence would have on others; and
any other matters the Chief Executive thinks fit.
In Mr Leach’s opinion, the Chief Executive’s foremost responsibility was to preserve
the right of existing licensees and as far as practicable, to maintain equity in the management
of the groundwater resource when granting, modifying or refusing applications for additional
bores.
-- 13 of 78 --
14
Mr Leach had examined the results of Departmental investigation drilling prior to
1987. Since that date he had personally overseen such investigation. His evidence provided
an insight as to what his attitude would have been as the officer responsible for implementing
the groundwater allocation policy in the Burdekin district.
Mr Leach was of the opinion that the Department must take into account the fact that
underground water may not become available for several years after rainfall, depending on the
permeability of the aquifer and the water table gradient. It may undergo changes in chemistry
as it permeates through the aquifer.
He advanced the following propositions:
Because of the extensive clay blanket of the Burdekin Plain, the downward
percolation of rainfall is impeded and the full response may not be observed for up to eight to
twelve months. Most of the recharge is derived from rainfall and only a little more than 2.5%
of average rainfall may reach the aquifer. Some recharge can occur as seepage from beds or
banks of rivers, but because the Burdekin River is incised below the level of the plain, only
limited recharge may reach the aquifer as seepage during periods of high river flow. Water
levels east of the Barratta Creek show only minor water level response following rainfall; it
has a thin bed of clayey sand overlying clay which would severely impede recharge and only
limited recharge could occur. The long-term average recharge from rainfall is a little over 25
millimetres per year, equivalent to an extraction rate of 0.25 megalitres per hectare per year.
Mr Leach explained that departmental monitoring had shown that water quality had
degraded in some areas due to over-use of ground water. There had been a problem in the
Mona Park area in the late-1970s into the 1980s and in the Giru area in 1987, following
which, as a temporary arrangement, farmers were allowed to grow cane in the Horseshoe
Lagoon area, which also resulted in groundwater quality problems, and in the Red Lily area.
Those problems will be resolved with the introduction of BRIA water. However, it seems to
be accepted that water quality beneath the subject lands is generally satisfactory, except for
the south-east corner of Lot 15, where it is marginal for irrigation. To the north of the subject
lands the salt water wedge is located in the vicinity of the Bruce Highway, with the potential
for salt water intrusion with any lowering of the water table.
Mr Leach’s conclusions regarding water availability were that:
groundwater is of limited quantity due to limited recharge;
the allocation policy of 0.25 megalitres per hectare per year attempts to balance
licensed extraction with long-term recharge, to protect the rights of existing users
and maintain groundwater levels and quality;
the natural groundwater resource was unable to sustain any further extraction
without lowering water tables during dry years and causing further deterioration of
water quality.
-- 14 of 78 --
15
Water quality problems had occurred in the Mona Park, Giru, Horseshoe Lagoon
and Red Lily areas as a result of overpumping and will be resolved only with BRIA
water.
In 1983, the WRC had commissioned Australian Groundwater Consultants Pty Ltd
(AGC) to study the groundwater resources in the Mona Park/Barratta Creek area. The WRC
had received an application for extraction of groundwater for irrigated farming (perhaps by
members of the Cox family) and was concerned that if it was granted, other applications
would follow.
It seems that the officers of the WRC felt that the AGC report confirmed the
Department’s groundwater allocation policy of 0.25 megalitres per hectare per annum.
However, the AGC report was not an assessment of the safe yield of the aquifer, or of the rate
at which pumping could safely be permitted.
AGC was given various options by the WRC for the extraction of groundwater and
asked to report on the probable consequences of adopting each of those options.
Its conclusions relevantly were:
that extraction from areas “A” (where the Davco lands are situated) and “B” (where
the subject lands are situated) together, according to the policy of 0.25 megalitres
per hectare per year, would have only moderate effect on groundwater levels in
then present irrigation areas (Mona Park) and at the coast; it was unlikely to have a
detrimental effect on then current users;
that an extraction of 2 megalitres per hectare per year over areas “A” and “B”,
although unlikely to cause an ingress of salt water intrusion, would have a
detrimental effect upon the then present irrigation by decreasing water levels in
those areas;
that full extraction (8 megalitres per hectare per year) from either or both areas “A”
and “B” simultaneously, could not be sustained for more than twelve months
without having a dramatic effect upon water levels in then present irrigation areas.
Salt water intrusion problems would be caused by these pumping rates after five
years.
According to Mr Leach, an earlier report by Coffey and Hollingsworth Pty Ltd on the
possibility of additional availability, also concurred with an assessment made by the
Department. However, the 1975 report by Coffey and Hollingsworth Pty Ltd did not address
the question of a groundwater allocation policy of 0.25 megalitres per hectare, but was
concerned with other matters. In Mr Leach’s opinion it would have been inappropriate to
have granted more than 0.25 megalitres per hectare because there was poor quality
groundwater to the south and east of the subject lands, while to the north and north-east, salt
water intrusion would have occurred if additional allocations in excess of 0.25 megalitres per
hectare had been granted.
-- 15 of 78 --
16
According to Mr Leach, further and ongoing studies by the DNR of the effect of
irrigation from the Burdekin scheme on groundwater are continuing. They have shown that
while there may be minor accessions of between 50 and 75 millimetres per year to the
groundwater storage resulting from the deep percolation of irrigation waters from the scheme,
there will also be additions of salts to the groundwater storage. He thought that some
additional use of this enhanced groundwater may then be possible in areas of suitable and
stable groundwater quality, such as adjacent to Barratta Creek. However, he warned that
without prudent management of existing salinity levels during this period of transition, it
would not eventuate.
In Mr Leach’s opinion, the WRC allocation policy was appropriate to control the
effects on other licensees. Although the full entitlement of 0.25 megalitres per hectare per
year had not been sought in respect of all of the subject lands, he thought that it was likely to
have been granted, as it would have had little effect on existing licensees.
The Polletti Line - The Polletti Line takes its name from a line of bores drilled in the
early 1970s from the Red Lily area in the east to the Haughton River in the west, which ran
along the southern boundaries of Lots 42 and 44. It seems that the WRC considered that it
was unsafe to grant groundwater pumping licences for irrigation purposes north of the Polletti
Line. However, it seemed to be accepted that irrigation bores located close to the southern
boundaries of Lots 42 and 44 could be used to supply irrigation water to those lots.
Quite contrary to that policy, however, in February 1980 a waterworks licence was
issued to the Hoeys equivalent to 6 megalitres per hectare per annum, in respect of their land
situated to the north of Lot 44 and therefore well north of the Polletti Line.
Much of the claimants’ case was directed at endeavouring to demonstrate that the
respondent’s groundwater allocation policy was far too conservative and that, if there had
been no Burdekin scheme, it would have been changed to allow groundwater extraction at the
rate of 2 megalitres per hectare per annum.
However, before considering the evidence of the various experts in relation to the
water resources available in the aquifer beneath the subject lands, it is necessary to deal with
some other matters.
The North Burdekin Water Board (NBWB)
The subject lands are all outside the NBWB area, but it abuts the northern and part of
its eastern boundary of Lot 15, and the eastern boundary of Lot 44. Part of the claimants’
-- 16 of 78 --
17
case was that without the Burdekin Dam, there would have been an expansion of the NBWB
area to include at least part of those lands. It is therefore necessary to consider the validity of
that proposition.
The NBWB was established in 1965 as the result of pressure by farmers for the
establishment of water conservation measures and improvement to the availability of
groundwater in the area. The Board consisted of eight members, comprising two cane
growers’ representatives from each of the Kalamia and Pioneer Mill areas, a representative
from each of those mills, a representative of the Burdekin Shire Council and a representative
from the then Irrigation and Water Supply Commission (the predecessor of the WRC). The
Board’s operations were financed by levies on farmers and mill owners and by way of
Government grants and subsidies.
The original charter of the Board was to improve the replenishment of underground
water supplies in the Board’s area, so as to ensure the continued availability of water to
existing farms and to enable expansion of cane farming operations. The Board’s area is in
respect of a locality referred to as “the delta”, on the north side of the Burdekin River, running
north from near Mount Kelly. That area comprised most of the cane growing lands north of
the river prior to the Burdekin scheme and it seems that the NBWB area was intended to
include those lands with cane assignments.
There is also a South Burdekin Water Board (SBWB), south of the Burdekin River,
but apart from the fact that some of the sales used by the valuer for the claimants are in that
area, the SBWB has no relevance to these cases.
In keeping with its charter, the NBWB developed and carried out many separate
schemes and was very successful in improving the availability of underground water to allow
for considerable expansion of cane growing within its area. The Board pumped water from
the Burdekin River directly into natural and artificial recharge areas in order to recharge the
aquifer. Although there is a variety of soils in the delta area, the majority of the area
comprises highly permeable alluvial soils. Prior to the availability of BRIA water, irrigation
in the NBWB area was mainly by pumping from underground supplies.
The construction of the Burdekin Dam gave the Board a year round pumping capacity.
However, before the construction of the dam, supplies of water for recharge purposes were
obtained by pumping from the Burdekin River while it was running. To extend the period
during which water could be pumped from the river, the Board constructed sand dams to
retain water, allowing pumping to continue long after the river had stopped flowing. Despite
these measures, the amount of water available to the Board for recharge purposes was limited
and this in turn limited the amount of expansion of irrigation in its area.
-- 17 of 78 --
18
In July 1974, during a period of expansion in the sugar industry, the Board extended
its area to include Portion 40V, Portion 27, Portion 564 and other lands which were
immediately to the north of Lot 15 and to the east of Lot 44. However, there is evidence that
those lands were included, not as part of a general expansion of the NBWB area, but because
they were assigned lands which were inadvertently omitted from the Board’s area in the first
place.
Evidence relating to the NBWB was given by Mr FG Kelly, who was called by the
claimants. Mr Kelly had been farming in the Burdekin District for more than 50 years and
had been a member of the NBWB for about 12 years, between 1977 and 1989. He explained
that during his time on the Board, there were several schemes which would have the effect of
improving the availability of underground water in the general vicinity of the eastern
boundary of Lot 44. In particular, he referred to the “Waterview Scheme”, where a number of
alternatives were considered, the basic intention of which was to introduce water into the
aquifer to improve the availability of water to farmers who were running short of
underground water. Eventually, the only scheme that proceeded was the pumping of water
into “The Sandpit” located on Portion 55. However, that scheme was implemented only three
or four years ago, after the construction of the Burdekin Dam, when the Board’s water
availability difficulties had been solved.
There was also the “Red Lily Scheme”, which involved the pumping or diverting of
water from Sheep Station Creek into Red Lily Lagoon and then by means of an open channel,
thereby allowing approximately six growers in Portion 40V to augment their underground
supplies by use of surface water from the channel. That scheme was implemented in late
1988, again after construction of the Burdekin Dam.
However, prior to the implementation of the Red Lily scheme, there was a temporary
arrangement for water to be pumped from Sheep Station Creek into Red Lily Lagoon. That
scheme was further extended by the construction of an open channel from Red Lily Lagoon to
Corica Road, where it joined an agricultural drain which had been constructed by the
Burdekin Shire Council. That allowed, as Mr Kelly put it, “a considerable additional number
of farmers to access the water...” Mr Kelly stated that while he was a member of the Board,
there was an emphasis on pushing water into the northern areas to recharge the aquifer in that
location.
Mr Kelly explained that farmers in the NBWB paid for water on the basis of the crop
produced, rather than the quantity of water used, which was the basis of payment for water in
the BRIA. It was an offence for water from the NBWB area to be used on land outside that
area.
-- 18 of 78 --
19
In Mr Kelly’s opinion, if there had been no Burdekin Dam, with the expansion of the
sugar industry, the NBWB would have actively promoted the extension of its area to include
land that was suitable for cane growing outside its designated area. That had happened in
1974 with the inclusion of Portion 40V and other lands. He acknowledged that initially
expansion would have taken place on suitable lands within the NBWB area, but the
expansion in the late-1980s and early-1990s would have required development of lands
outside the Board’s area. He believed that the sugar industry, both millers and growers,
would have taken steps to ensure the expansion of the industry in the Burdekin was not
hindered or halted by the lack of water. Since the NBWB could not expand its area to the
north towards the sea, the only way it could expand was to the west, to include Lots 44 and
15.
The thrust of Mr Kelly’s evidence was that if there had been no Burdekin Dam,
additional water would have been obtained from somewhere; for example, if the Board’s
pumps had been increased in size, they could have pumped more water from the Burdekin
while the river was running. It was apparent that Mr Kelly had great faith in the “Waterview
Scheme”, which he described as a “marvellous replenishment scheme”, to have significantly
improved the availability of water in the northern part of the Board’s area and to other lands,
such as Lots 44 and 15, located immediately adjacent.
Mr Kelly was the only witness called by the claimants who gave evidence directly
related to the possible expansion of the NBWB area, if there had been no Burdekin scheme.
However, despite his optimism, his evidence showed that there was not an over-abundance of
water in the area and there had been water quality problems. The Board was continually
seeking ways to improve its water supply. If additional water was obtained, the Board would
have applied it to those areas of potential cane land within the NBWB area, before the area
was expanded to include outside lands. The 1974 expansion of its area provides no precedent
for further expansion. I accept that it was necessary to include cane land which had been
inadvertently omitted.
In my view, the evidence has not demonstrated that there was much likelihood of
expansion of the NBWB area to include parts of Lots 44 and 5. Therefore, it is not likely that
a prudent purchaser would pay more for that possibility. The best that can be said is that Lot
44 in particular, is well situated to benefit from recharge from percolated irrigation water
from the NBWB area.
The Agricultural Drain
-- 19 of 78 --
20
The agricultural drain referred to previously had been constructed by the Burdekin
Shire Council to carry away storm water and irrigation runoff water from the farms in Portion
40V, which at that time were used for cane farming and rice growing. Prior to the
construction of the drain, two of the farmers had sought permission from the then-owners of
Lot 44, Cecil and Vivian Cox, to construct drains into Lot 44 to carry their irrigation runoff
waters. However, those drains proved to be insufficient to carry away the quantity of water.
Therefore, it was necessary for the Council to construct the agricultural drain, which also
served to carry stormwater runoff in times of heavy rainfall. The drain was dug through a
ridge to a depth of about 2 metres on the western boundary of Lot 574, into Lot 44 for some
distance and then turned at right angles and into the Hoey’s Lot 27, which was generally
regarded as a very good recharge area, and from there to Collinsons Lagoon.
The agricultural drain followed the western boundary of the NBWB area, except for
the diversion into Lot 44. It had originally been intended to truncate the most easterly corner
of Lot 44 and sever a triangular area. However, as the Coxes intended to grow cane on Lot
44, they persuaded the Council to alter the drain to extend into Lot 44 and then turn at right
angles, leaving the severed area rectangular in shape, which was much more satisfactory for
cane growing. It could also be attached to their cane land on the adjoining Lot 574. They
hoped that an easement through Lot 44 would make it easier for them to get the land
transferred into the NBWB area. However, it seems that no easement was ever arranged over
the area occupied by the drain.
All lands served by the agricultural drain were in the NBWB area and many at that
time were growing rice. Since farmers in the Board area paid an annual levy based on crop
production and not on quantity of water used, there was no great incentive to use water
efficiently. As a result, there was always a large quantity of runoff irrigation water in dry
times when farmers found it necessary to irrigate. In wet times, the drain carried runoff
rainwater. Mr Lex Cox estimated that the runoff tailwater could be as high as 20% of
irrigation water applied.
In July 1989 the Coxes approached the Council for permission to divert waters from
the drain which ran through their property, Lot 44. In September 1989 they were granted
permission to construct an open earth channel to divert water “to a private dam for irrigation
purposes”, subject to certain conditions. Mr Lex Cox explained this would have taken all the
water in the drain, not just the overflow, so that very little would have got through to the
Hoey’s Lot 27. However, he contended that the water from the agricultural drain was not
used by the Hoeys and it was not at that time used for recharge purposes. That came later,
when the NBWB started using it as a recharge drain, with BRIA channel water.
-- 20 of 78 --
21
Mr Lex Cox explained that they had intended that “the dam” be a channel or trench,
rather than a conventional dam. However, because of the uncertainty of resumption hanging
over their lands, they did not proceed with the proposal to divert water from the agricultural
drain. Since then, in the development of Lot 80 (an area from Lot 44 developed for cane
growing with the approval of the respondent), Mr Cox has constructed a trench for recycling
purposes. This trench extends for approximately 3.1 kms and is approximately 3 metres
wide. According to Mr Cox, it is similar to the diversion trench which was proposed in 1989
and which he believed could have held at least 10 megalitres of water. That water, together
with the water that they were able to pump from their irrigation bore would, he believed, have
allowed the claimants to irrigate approximately 100 hectares of cane on Lot 44. In other
words, water from the agricultural drain would have allowed them to irrigate an additional 50
hectares of land.
Mr Cox explained it in this way: the 10 megalitres in the trench/dam would allow
him to start irrigating the same day as his neighbours and not have to wait until the
agricultural drain picked up their tail water. That would allow him an additional 24 hours of
pumping, which could continue as the drain would by then be picking up tail water. The
drain would also catch tail water from their own 1 kilometre long drills, as he envisaged
developing an area 1km x 1km.
Mr Cox further explained that once the Burdekin scheme was providing water, the
NBWB saw the benefit of using the agricultural drain as a channel. He believed that it would
have done so even if there had been no Burdekin Dam, because expansion was coming.
Before proceeding further, it is necessary to consider briefly the recent history of cane
growing in the area to the north of the Burdekin River.
Cane Growing in the Burdekin
Prior to the construction of the Burdekin Dam, the growing of sugar cane in the
vicinity of the subject lands had been largely confined to the alluvial soils of the NBWB area,
where cane was irrigated from pumping from underground supplies. However, cane was
successfully grown in other areas, notably in the Clare and Giru areas. In the Mona Park area
near Clare, immediately to the south of the Davco lands, cane had been grown since the early
1960s, largely irrigated from underground supplies. It seems that the then IWSC permitted
pumping at the rate required for successful irrigation of sugar cane, about 8 megalitres per
hectare per annum. However, the quality of groundwater deteriorated, because of increasing
salinity from over-pumping.
-- 21 of 78 --
22
Similar problems were experienced in other areas. In the Red Lily Lagoon area
increasing salinity caused the NBWB to investigate several possible solutions. There is
evidence that the salt problems in that area may have been caused by leaching of salt from
the bedrock near Mount Kelly, rather than from over-pumping.
In the Giru area to the north-west of the subject lands, increasing salinity forced the
temporary transfer of some assignments to the Horseshoe Lagoon area, immediately to the
north-west of Lot 42. It seems that in 1988, farmers were allowed to temporarily transfer
assignment and were given licences to pump groundwater. Again, salinity problems arose.
That area is north of the Polletti line and such pumping was always likely to have an adverse
effect on the aquifer in the Horseshoe Lagoon area. There was also a suggestion that the
problems which arose in that area were the result of illegal use of water by farmers, as they
were alleged to be far exceeding their licensed water allocations.
These examples of declining groundwater quality, largely the result of over-pumping,
were used by witnesses for the respondent to demonstrate that the groundwater allocation
policy of 0.25 megalitres per hectare was appropriate, as it was a pumping rate which was
considered to be safe. That policy was in effect at the date of resumption of the subject lands
and remained in effect at the date of hearing of these matters. The claimants, as mentioned
previously, considered that the policy was far too conservative and contended that a safe
extraction rate from the aquifer would have been 2 megalitres per hectare per annum, if there
had been no Burdekin scheme. That issue will be considered in detail later in this judgment.
The Approach of the Valuers
Mr GW Eales, a registered valuer in private practice, gave evidence for the claimants,
while Mr RJ Moloney, a registered valuer employed by the Department of Natural Resources,
gave evidence for the respondent. Both valuers made their valuations on the hypothesis that
the Burdekin scheme was not in existence at the dates of resumption of the subject lands.
However, their approaches differed considerably, depending on how they envisaged
what the circumstances would have been at the various dates of resumption, if there had been
no announcement of the Burdekin scheme in 1980, which effectively put an end to the private
development of lands in the BRIA area.
Mr Eales took what might be termed an optimistic view of what would have been the
progress in the area. In his view, the sugar industry would have expanded in line with the
expansion in other areas in Queensland; there would have been considerable political and
local pressure for development of further areas of irrigated cane land with water being made
-- 22 of 78 --
23
available from various sources; and the market for irrigated cane land would have increased
considerably.
Mr Moloney was much less optimistic about what progress would have occurred in
the area in the absence of the Burdekin Dam and that was reflected in his approach to his
valuations. It was clear that he did not think there was any prospect of worthwhile irrigation
supplies from any other source and, in those circumstances, the situation would remain much
as it had been at the date of the announcement of the Burdekin scheme.
The valuers’ approaches were very similar to those which they had adopted in the
Davco case. The Davco decision chartered a course somewhere between the optimism of Mr
Eales and the pessimism of Mr Moloney. Although each of them claimed to accept that
decision, it seems that they did so reluctantly and sought opportunities to depart from the
findings of the Court when they felt that they could, to further return to something like their
original positions.
Be that as it may, they both agreed that the key to any progress in the Burdekin area
between 1980 and the dates of resumption would depend upon the availability of irrigation
water from whatever source, be it from the Davco scheme, the NBWB, the groundwater
aquifer, or perhaps some other scheme. Mr Eales’ valuations proceeded on the basis that a
hypothetical prudent purchaser as envisaged by the High Court in Spencer v. The
Commonwealth (1907) 5 CLR 418, would have taken into account the likelihood of obtaining
supplies of irrigation water significantly greater than permitted by the respondents’
groundwater allocation policy. Needless to say, Mr Eales’ assessment of the prospects of
success was optimistic. This was reflected in the price which he felt such a hypothetical
prudent purchaser would be prepared to pay for each of the subject lands at the respective
dates of resumption.
The Davco project has been discussed in detail in the Davco decision and the Court’s
findings of the prospects of success of that project are set out therein. In the present cases,
and central to Mr Eales’ valuations, is the reasoning that in the absence of the Burdekin
scheme, the WRC would have been persuaded to change its groundwater allocation policy
from that which existed at the date of announcement of the Burdekin scheme of 0.25
megalitres per hectare. His valuations were based on what Mr Eales considered that a
hypothetical prudent purchaser would have paid for the potential for a change of policy by the
WRC, or on appeal, by the Land Court.
Mr Eales’ assumptions of the likelihood of a change of policy were, in turn, based on
the opinions of hydro-geologists, Mr DR Woolley and Mr NP Merrick, who gave evidence
for the claimants. They had been requested to assess the extent to which groundwater could
-- 23 of 78 --
24
reasonably be developed by the claimants for irrigation of sugar cane on their properties, if
there had been no Burdekin scheme. Mr Woolley did so by making an objective assessment
based on a study of various reports, including the AGC report, and information from official
sources, such as DNR and the Bureau of Meteorology. On the other hand, Mr Merrick
personally conceptualised, designed and ran a computer-based numerical groundwater model
of the area.
Mr Moloney’s valuations were based on the opinions of the respondent’s experts that,
in the absence of the Burdekin Dam, there would have been no prospect of altering the
respondent’s water allocation policy of 0.25 megalitres per hectare per annum and no
prospects of the resumed lands gaining irrigation supplies from any other source. Evidence
for the respondent was given by hydro-geologists, Mr JR Hillier and Dr RS Evans, as well as
by Mr Leach.
Because the opinions of these experts were so fundamental to the valuation
approaches taken by the respective valuers, it is necessary to consider the water evidence in
some detail to assess the soundness of the foundations for the approaches taken by the
valuers.
The Water Evidence
Evidence of the safe extraction rate from the aquifer beneath the subject lands was
given by both Mr Woolley and Mr Merrick.
Mr Woolley’s Evidence
Mr Woolley produced a detailed report, the objective of which was two-fold:
to examine the groundwater yielding potential of the alluvial deposits in the
Burdekin Valley; and
to make an assessment of the extent to which groundwater could reasonably have
been developed for the irrigation of sugar cane on the claimants’ properties.
The AGC report had estimated recharge from rainfall at 2.5%, or 25 millimetres for an
average year. However, Mr Woolley warned that this is only a guide and might not be
realised for the whole valley. He regarded it as a reasonable broad estimate to use over the
area of his study.
In considering the proportion of irrigation water which infiltrates to ground water
storage, Mr Woolley concluded that an average of 20% seemed conservative and could be
adopted as a reasonable estimate. It seems that the figure of 20% for deep furrow recharge
was based on an article by Raine and Bakker entitled “Increased Furrow Irrigation Efficiency
Through Better Design and Management of Cane Fields”, published in 1996.
-- 24 of 78 --
25
Mr Woolley felt that the Barratta Creek and Haughton River systems are important
sources of recharge to the alluvial aquifers. Although the Haughton River drains a larger
catchment than Barratta Creek, Mr Woolley pointed out that for much of its course it
traverses very thin alluvium near the western edge of the alluvial filled valley and the
proportion of its flow which enters the aquifers is uncertain. In support of his contention that
recharge from the Barratta and the Haughton is substantial, Mr Woolley referred to the AGC
report, which estimated the recharge attributed to rivers and streams during the wet summer
year 1973-74 and the average summer year 1978-79, in a defined study area of about 600
square kilometres, as 274,000 megalitres and 159,700 megalitres respectively. However, he
noted that those figures appear to include recharge from rainfall infiltration. If the AGC
estimates for rainfall infiltration of 25 millimetres, or 0.25 megalitres per hectare per year, or
about 15,000 megalitres (60,000 hectares x average rainfall recharge of 25 millimetres) over
the whole study area are subtracted, then recharge attributed to infiltration from rivers is
approximately 260,000 and 145,000 megalitres respectively. Mr Woolley subsequently
amended the latter figure to 140,000 megalitres as being more appropriate for an average
year.
From an assessment of material contained in the AGC report, Mr Woolley concluded
that it would be reasonable to assume that substantially more than half of the recharge was the
result of infiltration from Barratta Creek and the Haughton River, suggesting a total recharge
from these two sources in the order of 100,000 megalitres during an average year. That figure
was for joint recharge, because Mr Woolley knew of no quantitative way of apportioning it.
Although the Barratta has a smaller flow, Mr Woolley thought that a greater proportion of its
flow goes to recharge.
Mr Woolley felt that his conclusion was supported by the salinity data contained in the
AGC report, which showed a consistent area of lowest salinity along or close to Barratta
Creek, suggesting that it is an important source of recharge. He gained further support from
the Value Engineering Study carried out by the WRC in 1987, Figure 1 of which showed
groundwater flowing from the west in the vicinity of a steep water table gradient area along
the southern part of Barratta Creek. He also drew support from DPI salinity diagrams, which
showed low salinity along Barratta Creek, similar to that of the 1983 AGC report, which he
considered to be the result of recharge from the Barratta Creek system.
Because of insufficient data, the extent of discharge by groundwater pumpage could
not be quantified precisely. Therefore, Mr Woolley made an estimate based on crop areas
determined from satellite imagery. He concluded that the amount of groundwater being
-- 25 of 78 --
26
pumped for irrigation exceeded the authorised amount by a factor of more than two. He felt
that his conclusion was confirmed by anecdotal evidence.
Mr Woolley also had regard to the interface of the fresh groundwater with highly
saline sea water, the Salt Water Interface (SWI). After examining the data from a number of
bores, he concluded that the natural position of the SWI seemed to be in the area between the
railway line and the Townsville Road. Although pumping in the vicinity of Lot 67 (the
Horseshoe Lagoon area to the north-west of Lot 42) may have caused some southerly
movement of the SWI, there had been little or no movement since 1970. He also concluded
that pumping from locations further up-gradient in the aquifer had contributed to the southern
migration of the SWI.
Based on similar bore data, Mr Woolley concluded that the salinity encountered in the
Red Lily area was consistent with the drainage of water from the bedrock into the alluvial
aquifer, modified to some extent by pumping. There did not appear to be any long-term trend
to increasing size of, or salinity within, the area affected. While he was of the opinion that
the presence of the saline water source should not prevent the use of groundwater for
irrigation on Lot 44, it would have a bearing on the location of bores.
He thought that there was little doubt that over-pumping exacerbated the problem at
Red Lily. Excessive pumping had led to salinity problems at Mona Park, but he understood
that the pumping rate in that area was 5 or 6 megalitres per hectare. He thought that there had
been a similar pumping rate at Horseshoe Lagoon, where farmers had been allowed to transfer
cane growing, following the groundwater problems at Giru.
Mr Woolley arrived at the conclusion that a safe extraction rate of 2 megalitres per
hectare per year could be maintained, based on
analogy with previous conclusions about the capacity of the aquifer in the Mona
Park area;
the position of the subject lands in relation to favourable recharge conditions along
Barratta Creek, which he assessed as being in the order of 100,000 megalitres per
year;
analysis of the 1983 AGC report, which indicated that in this part of the aquifer a
withdrawal of 2 megalitres per hectare per year would not cause saline water
intrusion problems; no allowance had been made in the AGC report for deep
drainage of irrigation water, which he estimated is likely to have been at least 20%.
In respect of Lot 15, Mr Woolley felt that it was unlikely that irrigation from
groundwater pumping could be maintained close to Mt Kelly, as the water would be too
saline. However, cane had been grown to the north and east of Lot 15 for many years and he
thought that groundwater from the northern half could be used.
-- 26 of 78 --
27
Mr Woolley was criticised by the respondent for not making a quantitative
assessment. However, he said that his contribution was descriptive rather than numeric. He
had left that to Mr Merrick. Mr Woolley conceded that he relied heavily on the AGC report,
but that as that report had made no distinction between rain water and river water recharge, he
had to make a calculation to apportion the extent of river water recharge by subtracting the
volume of infiltration from rainfall.
Mr Merrick’s Computer Model
Mr Merrick, who is a Senior Lecturer at the National Centre for Groundwater
Management at the University of Technology, Sydney, developed a groundwater model for
part of the Burdekin Valley, the objective of which was to assess the extent to which
groundwater could reasonably be developed for the irrigation of sugar cane on the subject
lands. That involved a computer simulation of the real system.
He explained that a groundwater model provides a mechanism to gain a better
understanding of how groundwater will respond to a number of simultaneous processes which
often defy intuitive analysis. Models can enable predictions to be made about aquifer
behaviour under alternative development schemes.
Mr Merrick explained that in this case, he developed a numerical model which
attempted to simulate some complex interactive processes. In order to determine parameters
for development of the model, he first made a critical analysis of all the raw data collected in
the study area. In conceptualising the model, he had regard to at least five earlier studies. He
explained that models are set up for a particular time scale as well as for a particular spatial
scale. In this case, it was a long-term regional model.
Mr Merrick’s model was set to start in January 1971 and proceed in monthly steps
until December 1988, the dates chosen to address a full climatic cycle and because the model
aimed to replicate pre-Burdekin scheme conditions.
After analysing data from a number of bore hydrographs to gauge the interaction
between stream peaks and groundwater level peaks, Mr Merrick concluded that the
qualitative analysis suggested that the bed of Barratta Creek has a lower leakage characteristic
than the Burdekin or the Haughton. However, he thought that substantial volumes of water
could still enter the aquifer from Barratta Creek, because of its higher propensity for flooding
and greater exposure to the aquifer.
Mr Merrick concluded that there was a clear correlation between residual rainfall mass
and the behaviour of groundwater in each of the bores. That suggested that an important
mechanism in the aquifer system is rainfall, or stream recharge correlated to rainfall. There
-- 27 of 78 --
28
was the same behaviour in the 44 bores looked at, which were either on, or close to, the
subject lands.
After having made the residual mass comparison with all hydrographs, Mr Merrick
was certain that recharge was occurring from either rainfall or streams. He then undertook a
comparison of stream hydrographs with bore hydrographs to determine whether stream
recharge was significant, or whether rainfall recharge was the sole mechanism. The
hydrographs showed there was a decrease in the stream signature with distance from the
stream.
Mr Merrick explained that the data used in the model included assumptions which he
made in the absence of firm data, such as for groundwater use. Groundwater usage being one
of the major stresses on a system, was vital to the model. He calculated the areas of the crops
that were growing in the study area from three published reports. He adopted a similar
approach to that adopted by Seccombe and Arunakumaren (1990) to estimate usage on the
basis of crop areas determined by satellite imagery. He estimated usage to range from about
50,000 megalitres to 180,000 megalitres in any one year, with median about 100,000
megalitres and average about 110,000 megalitres.
The model calibration suggested that streams were the most important source of
recharge and that it was almost balanced by net abstraction of groundwater from bores.
Averaged over the 18 years of the simulation period, recharge to the aquifer from streams was
estimated to have been about 115,000 megalitres per year and from rainfall about 36,000
megalitres per year. Allowing for infiltration to the aquifer of irrigation water, net
groundwater usage was estimated to have averaged about 110,000 megalitres per year, with
about 35,000 megalitres per year discharged by evapo-transpiration and outflow to the sea.
Over the simulation period, the model showed that there was a net gain in the aquifer storage
of about 8,000 megalitres per year.
Mr Merrick said that all three streams that are represented in the model are an
important source of recharge. In order of importance, he would rank them as Barratta Creek
first, Haughton River second, and Burdekin River third.
Mr Merrick pointed out that the records of groundwater use in the area are very poor.
He was unable to achieve calibration of the model against key bore hydrographs with
estimates of groundwater usage based on metered use, or on estimates based on fully efficient
irrigation. From those bore hydrographs, he concluded that actual groundwater usage was
much higher than might otherwise have been expected in the early 1970s, probably due to
inefficiency, and about 20% to 30% higher than might otherwise have been expected in the
mid-to-late 1980s, probably due to expansion of cane farming. He concluded that during the
-- 28 of 78 --
29
period 1971 to 1973, farmers applied about 2 times the amount of water needed to irrigate
crops efficiently.
The calibrated groundwater usage is shown in Figure 31 of Mr Merrick’s report for
each of the 18 years, with median and average usage about 150,000 megalitres per year. He
assumed net usage would be about 20% lower to account for deep drainage to the aquifer
after irrigation, based on the percentage in the article by Raine and Bakker.
Having achieved calibration, Mr Merrick’s model was run in a transient mode to
predict how the aquifer would have responded from 1971 to 1988 for a hypothetical usage
scenario. That scenario was that all the Cox land and all the land south of the Polletti Line,
had a given allocation of 2 megalitres per hectare. Existing licensed allocations both north
and south of the Polletti Line were taken into account; for those south of the Polletti Line,
only if the actual allocation was greater than 2 megalitres per hectare. Seasonally adjusted
crop requirements for groundwater in the NBWB area were also assumed to be active.
Mr Merrick explained that for that particular scenario, the model results showed that
the one metre groundwater level contour would have moved about 8 kilometres northward,
thus, in his view, “obviating the threat of saline intrusion;” water levels would have been
generally half a metre higher between the highway and the railway line; and two metres
higher at Mona Park. They also showed that there would have been no decline in
groundwater levels north of the Polletti Line. The maximum decline in level would have
been about two metres in the south-west, where there had been no historical abstraction.
Those somewhat surprising results could be explained because the scenario on which
the model was run resulted in less water being extracted from the aquifer than had actually
been extracted, because of significant unauthorised over-use by farmers.
Mr Hillier’s Evidence
Mr RJ Hillier, Principal Hydrologist, Water Assessment and Planning, Resource
Services Centre, DNR, gave evidence for the respondent. Mr Hillier prepared reports on the
hydrogeology of the subject lands and on groundwater modelling. His study area and the
model area were bounded by the Haughton River to the west, the Burdekin River upstream of
Mount Kelly and Sheep Station Creek to the east, the Coral Sea to the north and to the south,
by a line from Clare to the Haughton River.
Mr Hillier’s Hydrogeology Report
Mr Hillier explained that the purpose of the report was to describe the nature and
occurrence of groundwater in the area and for that purpose an analysis of the aquifer system
and the groundwater quality and quantity had been undertaken.
-- 29 of 78 --
30
He acknowledged that there was a possibility that the Burdekin and Haughton Rivers
and Barratta Creek provide some recharge to the aquifers, due to the apparent presence of
groundwater mounds beneath those drainage lines. However, he pointed out that flows from
Barratta Creek are seasonal and groundwater movement from the Burdekin River is restricted
by a basement ridge marginal to its banks and underlying its bed, and from the Haughton by
low transmissivities.
Mr Hillier said that the Haughton River was always regarded as hydrologically
separate from the Burdekin system, because of the existence of a deep underlying layer of
clay. He thought that Barratta Creek was similar, but being a smaller watercourse had very
limited access to aquifer sands and gravels. Originally Mr Hillier thought there was no
connection between the Haughton and the main aquifer, but after looking at the 1993 report
by Arunakumaren, he accepted there was some connection, although limited.
Mr Hillier went on to explain that north of the subject lands in the vicinity of the
railway line, groundwater levels approach sea level and often fell below it, which gave rise to
major concern over the position of the SWI, which can adversely affect the quality of bore
water. To prevent the salt water boundary from advancing landward, he contended that
groundwater levels must remain above sea level.
Mr Hillier referred to the vulnerability of fresh water resources to sea water
inundation. There was a depression of fresh water levels to the north-west of Lot 42
(Horseshoe Lagoon), with values up to 3 metres below sea level caused by pumping, which
he considered to be extremely vulnerable to sea water intrusion from the north. It was
essential that fresh water head levels do not fall below a point that could cause any threat of
salt water intrusion from the sea.
Mr Hillier explained that DNR monitors groundwater quality on a regular basis to
detect any areas that may be experiencing deterioration of groundwater quality. An
observation of conductivity in the area between June and July 1997 showed that values
ranged from fresh to very saline. Within the subject lands, water quality was slightly better
on the east side of Barratta Creek than on the west side.
Mr Hillier explained that past management practices adopted by DNR have accepted
that the average annual recharge is a little over 25 millimetres per year in the Haughton-
Burdekin alluvial plain, based on the 1983 AGC report. He referred to those AGC
conclusions which, he said, recommended that the area containing the subject lands should be
allocated extraction rates of 0.25 megalitres per hectare per year to prevent encroachment of
the northern sea water boundary. However, as mentioned previously, the AGC report made
-- 30 of 78 --
31
no such recommendation, simply concluding that the current policy would have only a minor
effect on water levels.
Mr Hillier also said that in its final assessment, AGC stated that an increased
extraction rate of 2 megalitres per hectare per year may not cause immediate sea water
encroachment, but would have a detrimental effect upon present irrigation by reducing
surrounding groundwater levels. However, as mentioned previously, the AGC report made
no allowance for infiltration of irrigation water.
Mr Hillier commented that the AGC report concentrated on land further inland than
the subject land and its model was based on water levels from 1978 to 1982. He confirmed
that the AGC report was not the genesis of the 0.25 megalitres per hectare per year policy,
saying that the policy pre-dated that report. He stated that in addition, a 1981 Departmental
report and an independent study by Coffey and Hollingsworth in 1975, concluded that
allocations (at the time 204 megalitres per 800 hectares) should not be increased in any area
north of the Polletti Line, because of concerns about salt intrusion. He went on to say that
since then, numerous other bore holes have been drilled, and water level variations and
quality changes in the coastal area tend to support those assessments.
In summary, Mr Hillier emphasised that the aquifer sediments in the BRIA are
covered by a blanket of clays and silts deposited from floods of the Burdekin and Haughton
Rivers, which impede the downward percolation of rainfall to the aquifer system. Strata log
descriptions often over-simplify the aquifers and do not always indicate the proportion of
clays in the sediments, which can lead to an over-approximation of specific yield values.
North of the subject lands, groundwater levels have been drawn down below mean sea level,
resulting in sea water intrusion into the main aquifers. Corrected saline water levels indicate
that the potential for further intrusion may be greater than initially perceived. Apart from the
area intruded by salt water, groundwater quality is generally quite good. However,
groundwater levels show long-term decreases during periods of below-average rainfall,
leading to the conclusion that because of the limited volume of recharge and the threat of
seawater intrusion, the management practices adopted by the DNR and based on independent
consultants’ analyses, of issuing allocation at a rate of 25 millimetres per hectare per year,
were appropriate.
The DNR Groundwater Model
Mr Hillier also prepared a report on the development of a groundwater model of the
BRIA, bounded by the Burdekin and the Haughton Rivers. The objective of the study was to
investigate groundwater supplies and to develop a computer-based model which could be
-- 31 of 78 --
32
used to simulate groundwater conditions in the area of the subject land. The model was
developed to investigate the impact of different combinations of water supplies on
groundwater levels.
Mr Hillier said that he conceptualised the model personally to a large extent, but did
have several other people assisting him in its construction. Despite the submission by the
claimants that he had little to do with the model, I accept that he supervised and guided the
project.
Mr Hillier explained that model calibration started in 1981 and went to 1987, the
period being chosen because crop-cover data was not reliable back past 1981. The model was
verified in the period 1988 and 1989.
Mr Hillier, like Mr Merrick, noted the lack of complete groundwater use records in
the model area. He also calculated the areas of crops growing in the study area in order to
estimate groundwater usage. He considered that the correct estimation of groundwater
withdrawals was a critical step in model development.
From crop coverage maps compiled by Departmental staff in about 1988 for the years
1981 to 1985 and 1986 to 1987, and 1988 satellite imagery of vegetation in the model area,
the irrigation use from groundwater for crops in the area was simulated.
The water balance of the model simulation showed the average annual rainfall
recharge to be 25,607 megalitres over the model area of 88,975 hectares, estimated to be 29
millimetres per year. Further water balance calculations showed that groundwater was
leaving through parts of the Burdekin and Haughton Rivers from the model area. The
resultant average recharge from the Burdekin and Haughton Rivers was estimated to be 600
megalitres and 500 megalitres.
One of the major differences between Mr Merrick’s model and the DNR model was
that the latter did not recognise that there was any recharge from Barratta Creek. Mr Hillier
explained that at the conceptualisation stage there was no water provided into the model
through Barratta Creek except by rainfall, because it did not show up in any of the water level
contours, so it was impossible to calibrate it.
The model was run to provide for extraction at the rate of 2 megalitres per hectare
over all the land south of the Polletti Line, or if the existing allocation was over 2 megalitres
per hectare, at that rate. It was found there was an unrealistically high usage. It was then run
at 2 megalitres per hectare over the whole of the subject land and that was also found to be
excessive.
It was then run to provide for additional groundwater extraction of 2 megalitres per
hectare from south of the Polletti Line in the subject lands. The additional groundwater
-- 32 of 78 --
33
extraction was estimated to be 6,403 megalitres per year. It showed that groundwater quality
was deteriorating in the area north of the subject lands.
Mr Hillier drew the following conclusions from the groundwater model:
the additional extraction from the subject lands caused the water level to drop below -1.0
metres AHD. As a freshwater head of between +0.5 and +1.0 metres was required to balance
the salt water, a fall to -1.0AHD would cause movement of salt water into the aquifer. Such
ingress of salinity would not be acceptable, and use from the aquifer at the suggested rate
would not be sustainable.
Mr Hillier had also produced a water balance for the Haughton-Barratta area using the
AGC study. This showed that recharge from the Haughton, the Burdekin and the Barratta was
66,000 megalitres. From the contours on Figure 15 of the AGC report, he concluded that the
majority of recharge is from the NBWB area. Recharge from the Burdekin and from the
Haughton was limited, with virtually no recharge from Barratta Creek. When the DNR
parameters were applied, recharge from streams fell to 26,800 megalitres.
From water levels in bores in 1978-79, Mr Hillier concluded that there was direct
infiltration across the area and assumed that rainfall was the predominant recharge. While
there was some recharge from the Haughton, there was no evidence of any movement of
water from Barratta Creek. He said that the 1975 Coffey and Hollingsworth report supported
that conclusion.
The main differences between Messrs Woolley and Merrick on the one hand and Mr
Hillier on the other are:
(1) the stream recharge, and
(2) the amount of water used.
According to Mr Hillier there is no evidence that Barratta Creek is the source of recharge. He
said that if more groundwater usage was assumed, there must be more recharge, but it could
come from rainfall.
Mr Hillier was prepared to accept that each of the streams was providing some
recharge due to the presence of the groundwater mounds, but only in the downstream area
towards the railway line. He asserted that there was no evidence of any possibility of Barratta
Creek providing significant amounts of recharge upstream of the highway. In Mr Hillier’s
opinion, Mr Woolley got the hydrogeology wrong.
Mr Hillier thought that Mr Merrick had over-estimated the thickness of the aquifer,
that his hydraulic conductivity values were too high, but that his storativity values seemed
acceptable.
-- 33 of 78 --
34
The crop areas used in the DNR exercise, particularly for sugar cane, are significantly
less than those used by Mr Merrick, being only about one-third of the sugar cane area that he
showed. It emerged in evidence that the satellite imagery of crop areas was produced from
office assessment only, with no ground verification. Mangoes were a comparatively new crop
in the Burdekin, but were grown in commercial quantities by June 1988. Mr Merrick’s crop
areas did not include mangoes.
The Evidence of Doctor Evans
Doctor RS Evans, employed by the consulting engineering company, Sinclair Knight
Merz as Principal Hydrogeologist, gave evidence for the respondent. He had been requested
to review all the data and, in particular, to provide comment on the reports of the claimants’
witnesses. He had produced a report, the stated purpose of which was to provide an
assessment of the technical and management veracity of the reports prepared by Mr Woolley
and Mr Merrick.
Dr Evans’ Comment on the Report of Mr Woolley - Doctor Evans concluded that Mr
Woolley had significantly over-estimated the groundwater resources; that his conclusions
were not consistent with the available data. He thought that Mr Woolley failed to emphasise
the main difference between the Burdekin delta sediments which rainfall can readily percolate
to recharge the aquifer, and the sediments deposited in the Barratta/Haughton area, where the
“universal” clay layer severely restricted recharge. However, under cross-examination Doctor
Evans agreed that the clay layer was not universal, as there are areas where the clay was not
present and recharge was potentially greater.
Doctor Evans noted that Mr Woolley had accepted as reasonable a 20% average return
of irrigation water to the aquifer, while he felt that for the cracking clays of the Barratta area,
an average recharge would not exceed 10%. However, he conceded that he was not aware of
the areas of different soils, his discussions with Mr Hillier and his staff had led him to
understand that a substantial proportion of the area consisted of cracking clays.
Doctor Evans contended that Mr Woolley grossly over-estimated the volume of
recharge from the Haughton River and Barratta Creek; most of his figures came from the
1983 AGC report, adjusted to exclude infiltration from rainfall; he failed to take into
consideration the fact that as the period from 1971 to 1978 was a very wet period, the
recharge from rainfall would also be much above average.
Doctor Evans went on to say the figures in the AGC report show that a significant part
of the recharge came from the delta area. Once that influence was removed, most of the area
-- 34 of 78 --
35
had restricted recharge and Mr Woolley’s assertion that the recharge from the Haughton and
Barratta is 100,000 megalitres per annum is without foundation. While Doctor Evans
conceded that the contours indicate some small recharge from the Haughton, he thought that
the extensive clay layers restrict its extent.
He dismissed Mr Woolley’s opinion that the excellent quality of water near Barratta
Creek was proof of good recharge from the creek; he agreed that it indicated recharge in the
vicinity, but it did not quantify volumes. However, Doctor Evans conceded that the excellent
quality water near Barratta Creek extended over a large area.
Doctor Evans asserted that Mr Woolley’s estimate of groundwater use was
excessively high, but left it to Mr Leach to deal with that aspect .
Doctor Evans made the general statement that the subject land had poor quality water
all around it, but he had not looked at the raw data. He relied on Mr Hillier’s report for his
assertion that groundwater quality was deteriorating in the area north of the subject land. He
attributed the deterioration in groundwater quality to pumping , if the bores are located too
close to the SWI.
Doctor Evans disputed Mr Woolley’s conclusions regarding groundwater salinity, on
the basis that water quality monitoring by DNR showed deterioration of water quality over
time and any lowering of the water table below sea level would induce the flow of salt water
into the aquifer. He alleged that Mr Woolley tried to justify his case for increasing
groundwater allocations by comparing water levels in various bores. In his opinion,
comparison of trends between bores means little.
He asserted that recharge from Barratta Creek has been shown to be quite limited, the
Barratta having an annual flow over the period since records began in 1975, of only 118,000
megalitres. He reasoned that if 1% resulted in recharge, this would be about 1200 megalitres
per annum, nowhere near Mr Woolley’s estimate of 100,000 megalitres.
He also took issue with Mr Woolley’s reliance on the AGC report to support his
proposal that allocations could have been increased to 2 megalitres per hectare, pointing out
that the AGC investigation was carried out in 1982 when water levels were still high from the
extremely wet period in the 1970s. In the dry periods of the 1980s and 1990s, water levels
were much lower and a further decline of 3 metres would have resulted in water levels well
below sea level. Such a drop in water levels so close to the SWI would be unacceptable and
not be sustainable.
However, Mr Woolley had pointed out there had been no allowance for infiltration
under irrigated land in the AGC study and that there would have been probably more than
-- 35 of 78 --
36
20% infiltration to groundwater. In his opinion that would have made a substantial difference
to the impact of groundwater pumpage.
In summary, Doctor Evans’ criticisms of Mr Woolley’s report were:
the whole of the Barratta aquifer is overlain by a thick clay layer which severely
restricts rainfall infiltration for aquifer recharge;
both Barratta Creek and the Haughton River are underlain by significant clay
thicknesses which restrict infiltration of stream flow;
groundwater usage has been grossly over-estimated;
the threat of salt water intrusion is a very real limitation on the long-term
sustainable yield of the system;
the work carried out by AGC was at the end of a very wet period and some of its
results are not applicable when dry season water levels are considered;
in this area, the groundwater resources must be managed in a cautious manner;
fresh water levels need to be maintained at between 0.5 and 1.0 metre above sea
level just to balance the salt water and any additional use which will have an effect
of increasing the risk of salt water intrusion must be restricted.
Doctor Evans’ Comments on Mr Merrick’s Report - Dr Evans thought that Mr
Merrick’s model appeared to be deficient because:
it was calibrated over the 18 year period, but not verified outside that period and so
failed to prove the model’s accuracy and reliability;
hydraulic conductivity, a key model parameter, was generally significantly greater
than those in the aquifer material;
the model was developed based on uniform rainfall recharge and uniform
conductance along the rivers and on that basis it contained errors;
the model was developed based on doubtful data, as the groundwater extraction
used in the model was unrealistically high;
errors associated with estimating groundwater extraction, rainfall recharge, stream
recharge and initial conditions were present in the model.
He rejected Mr Merrick’s conclusions as not acceptable. He thought that the
developed model was a poor representation of the groundwater system of the BRIA. He was
critical of the fact that the model area extended into the NBWB area, where groundwater is
replenished by an artificial recharge scheme and where the deltaic soils are much more
permeable. However, he had to agree that good modelling required the model area boundaries
-- 36 of 78 --
37
to be located away from the area being examined and that necessitated including the NBWB
area in this case.
Doctor Evans thought that Mr Merrick’s estimate of groundwater usage was
unrealistically high. He felt that surface water irrigation areas, and areas irrigated from flood
harvesting, were included as groundwater, in addition to the delta area with its artificial
recharge scheme. He also commented that Mr Merrick had not attributed any area to
mangoes.
He contended that Mr Merrick compounded the already over-estimates to ensure
calibration, by altering the usage estimates to allow for irrigation inefficiencies, which he
considered to be completely unrealistic, especially on heavy Barratta clays where, at 2.5
inefficiency, paddocks would be flooded. Although some water recharges, he thought it was
a small percentage and the majority would be lost to evaporation and runoff. Inefficiency to
the extent of 2.5 was very unlikely in Doctor Evans’ experience. He concluded that
“Changing water usage in order to obtain a calibrated model has resulted in unrealistic values
which have been needed to allow other parameters to also remain at quite unrealistic values”.
Doctor Evans was critical of the model’s use of a uniform net recharge factor of 2.5%
of rainfall. The DNR model indicated an average rainfall recharge of 29 millimetres. He was
also critical that the conductance values used in the model were consistent with artificial
recharge trials in the delta, an area quite unrepresentative of the area in which they have been
applied. He criticised the fact that groundwater extraction was adjusted, along with other
parameters, in the model calibration. He said this was not an acceptable procedure in
groundwater model development. However, he conceded that in other cases that he had been
involved with, there had been some indication of groundwater use, whereas here they had to
be estimated.
He concluded his criticism of Mr Merrick’s modelling by setting out several key
issues which led him to the conclusion that the model was not a realistic representation of the
aquifer system:
there is no top clay layer in his model;
the model made no provision for the spatial variation of recharge;
the values used for groundwater usage and stream recharge were quite unrealistic;
the calibrated parameters did not generally agree with the hydrogeological
characteristics of the area;
the procedure used for model calibration was not acceptable, as both input and
model parameters had been varied during calibration;
the model had not been validated.
Doctor Evans endorsed the DNR policy of groundwater management of 0.25
megalitres per hectare per year, which he felt would ensure no long-term over-development of
-- 37 of 78 --
38
the groundwater resource. However, he was not able to refer to any reports which justified
that policy, apart from Mr Hillier’s report, which showed that sea water intrusion was
gradually occurring under the current pumping regime. However, if Mr Woolley and Mr
Merrick were correct, pumping may well have exceeded authorised use.
Doctor Evans agreed that good groundwater management was about equitably sharing
between conflicting requirements. While he considered that the policy limiting allocations to
0.25 megalitres per hectare per year was appropriate, he would not argue that it could not be
increased; but to suggest that it could be increased to 2 megalitres per hectare, was not
consistent with the data. Clawing back over-allocated resources was a major problem. In his
opinion, it was far more prudent to gradually increase allocations and observe how the
groundwater resource responded so that a more prudent and cautious approach can be
developed.
He concluded that the weight of technical data and evidence supported the view that
the current allocation policy of 0.25 megalitres per hectare per year was a prudent approach.
To suggest that it could be increased to 2 megalitres per hectare per year was, in his opinion,
grossly excessive and clearly not sustainable.
Under cross-examination, Doctor Evans admitted that in hindsight it probably would
have been desirable to include Barratta Creek as a recharge source in the DNR model,
provided that realistic conductance values and realistic flow figures were used. However, he
thought that Barratta Creek would not have been a significant source of recharge and that
leaving it out did not detract from the model. The DNR model calculated the total inflow into
the aquifer, even though it did not attribute any recharge to Barratta Creek.
Mr Leach’s Comments on Mr Woolley’s Report
Mr Leach also thought that Mr Woolley’s estimate of groundwater use was high. He
said that Mr Woolley seemed to rely on the report of Seccombe and Arunakumaren (1990),
for the areas that were irrigated; but the cultivated areas in the Seccombe and Arunakumaren
Report (pre-1985 and post-1985), were mostly in areas marginal to the study area, with little
use of the central area. Most of the cultivated area for sugar cane was in the NBWB area,
where groundwater was supplanted by artificial recharge and there were no authorised
volumes.
Mr Leach thought that the groundwater use adopted by Mr Woolley of 8 megalitres
per hectare could not be correct. In the Seccombe and Arunakumaren 1990 study, the
maximum groundwater use was 56,000 megalitres in 1992 (a dry year) and the minimum use
about 26,000 megalitres in 1989 (a wet year). However, Mr Leach agreed that the average
-- 38 of 78 --
39
use could be about 42,000 megalitres per year. If that was divided by the average of Mr
Woolley’s irrigated area of 8,000 hectares, the result is an average use of 5.25 megalitres per
hectare. But that covers part of the NBWB area, which further complicates matters.
Findings in relation to the water evidence.
It was contended by the claimants that they were able to demonstrate that, in the
absence of the Burdekin Dam, they would have been able to produce evidence which would
have persuaded the respondent to modify his policy of restricting groundwater allocations in
this area to 0.25 megalitres per hectare per year. In the event that the respondent refused to
grant additional entitlement to a landowner who had applied for a waterworks license, that
landowner could appeal to the Land Court. The inference was, that the Court would have
been persuaded to overturn the respondent’s decision and grant the additional entitlement.
The evidence of Mr Woolley and Mr Merrick was directed towards establishing that a
safe pumping rate for the aquifer would be 2 megalitres per hectare per year. The evidence of
Mr Hillier, Doctor Evans and Mr Leach was directed towards showing that it would not, and
that the policy of 0.25 megalitres per hectare per year would not have been, and should not
be, altered.
The claimants’ arguments therefore differ from those advanced in the Davco case,
where it was sought to establish that there was sufficient unsaturated material in the aquifer to
sustain artificial recharge and that sufficient quantities of water could be pumped from the
Burdekin River, artificially recharged into the aquifer and later extracted, to enable the
irrigation of sugar cane on the Davco lands.
Although the arguments are different, there are findings in the Davco case which are
pertinent to the subject lands, particularly to Lot 44 and Lot 15. However, quite apart from
the Davco decision, in these cases the claimants have endeavoured to demonstrate that, in the
absence of the Burdekin Dam, there was sufficient groundwater in the aquifer to justify a
pumping rate of 2 megalitres per hectare per annum for each of the subject lands.
The claimants’ argument proceeds on the basis that if there was sufficient water to
allow pumping at that rate without the risk of affecting groundwater quality or the rights of
other landowners, then it would be unreasonable for the respondent to refuse to allow such
allocations, and any such decision would be reviewed by the Land Court.
It seems to me that this argument should be considered at two levels:
First, whether the respondent (or on appeal the Land Court) would have been persuaded to
grant additional entitlement in the period between the announcement of the Burdekin scheme
and the dates of resumption of the subject lands; and/or
-- 39 of 78 --
40
Second, whether a hypothetical prudent purchaser would have been prepared to pay a
premium for the subject lands for the prospects that in the future, the respondent (or on appeal
the Land Court) would have been persuaded to grant additional entitlement.
The first proposition is an extension of the Woollams principle, while the second,
although differently based, is somewhat analogous to the finding in the Davco case in relation
to the value of dry arable land with potential for irrigation from the Davco project.
The Likely Attitude of the Respondent
The respondent’s witnesses left no doubt that their attitude was that there would have
been no relaxation of the allocation policy. Essentially that was based on their opinions that
extraction of groundwater must be balanced by recharge, the present policy of 0.25 megalitres
per hectare per year being directly related to average annual infiltration of rainfall of 25
millimetres per year.
Where extraction has exceeded that rate, such as at Mona Park, Giru, Horseshoe
Lagoon and perhaps Red Lily, there has been a deterioration in groundwater quality. Once
water quality has been affected, it is very difficult to correct, the solution in each of those
cases being dependent upon the supply of channel water from the Burdekin scheme.
Therefore, in the absence of the Burdekin scheme, I have no doubt that the attitude of
the respondent would have been cautious and conservative. In normal circumstances, it was
argued, it would have been most unlikely that the respondent would have changed that policy
at any time in the forseeable future. That leaves unexplained the departure from that policy
by the granting of a licence to Hoey with an allocation of 802 megalitres for 132 hectares, or
over 6 megalitres per hectare in February 1980, and the later renewal of that licence. Mr
Leach could only suggest that the land is in a different sub-area. He could offer no other
explanation. However, the Hoey land is north of Lot 44, north of the Polletti line and closer
to the SWI.
The claimants argue that if there had been no Burdekin scheme, the circumstances
would have been far from normal. The Court found in the Davco decision that, in the absence
of the Burdekin scheme, there would have been some expansion in the sugar cane industry,
although not to the extent that occurred after the construction of the Burdekin Dam. It was
also found that in such circumstances, land which was suitable for cane growing and which
had access to irrigation water, would have commanded premium prices, certainly higher than
those being achieved at the BRIA auction sales.
-- 40 of 78 --
41
Once the suitable land within the NBWB had been exhausted, the only possible
direction for cane expansion would be west, onto the subject lands. There could be no
expansion to the north-west, because of the danger of salt water intrusion from the sea. Those
circumstances would have placed enormous local and political pressure on the respondent to
relax his groundwater allocation policy, or at least to review it.
The argument proceeds that faced with the evidence presented by Messrs Woolley and
Merrick, and the precedent of the Hoey allocation, the respondent would have good reason to
allow groundwater pumping to at least 2 megalitres per hectare per year. However, it could
equally be expected that the respondent would also have received advice of the type presented
in evidence by Mr Hillier, Doctor Evans and Mr Leach. Faced with that conflicting evidence,
I have no doubt that the respondent would have continued to adopt a cautious and
conservative approach.
In the circumstances of these cases, there can be no conclusive evidence of what
would have happened if the Burdekin Dam had not been built. Nor is it possible to resolve all
the differences between the water experts for the claimants and the respondent. It is a matter
of weighing that lengthy and complicated evidence and deciding as best I can, on the balance
of probabilities, what was likely to have happened.
If a landowner had appealed to the Land Court against the respondent’s decision on
his application for a waterworks licence, then there is no doubt that the Court would also have
taken a careful and conservative approach.
That being so, it is highly unlikely that the respondent or the Court would have
approved a pumping rate of 2 megalitres per hectare per year, or four times the prevailing
allocation policy, by the dates of resumption. Instead, it is much more likely that the
respondent would have adopted what was agreed to be good resource management practice by
proceeding slowly and monitoring the results of any increase in pumping rates.
In making this finding, I pay no regard to the evidence that the respondent has not in
fact altered the policy, notwithstanding the introduction of Burdekin scheme channel water to
the area. Mr Leach seemed to rely on that fact as part of his argument that there should be no
increase in groundwater pumping rates. However, with the introduction of Burdekin scheme
channel water, there was no need for the respondent to alter his policy, as irrigation water was
available from the BRIA channels, rather than groundwater. Mr Leach was prepared to admit
that the rate of groundwater pumping will have to be addressed in the future, as there is
evidence that the water table is rising as a result of percolation of irrigation water from the
Burdekin scheme.
-- 41 of 78 --
42
The claimants’ witnesses were criticised for their reliance on various aspects of the
AGC report for the assumptions which they made. However, the respondent’s witnesses also
relied on that report, but departed from it where they thought it necessary. There is no doubt
that the AGC report played an important part in these cases. That is not surprising, as it is
one of the few studies dealing with the water resources of the aquifer in the area. However,
as pointed out previously, the AGC findings did not give unqualified support to extraction at
the rate of 2 megalitres per hectare per annum. Neither did it give such support to the
allocation policy of 0.25 megalitres per hectare per annum.
Having regard to the whole of the evidence, the respondent has not persuaded me that
the groundwater allocation policy should not have been cautiously increased. The
respondent’s witnesses steadfastly refused to admit that there was any possibility of any
increase in groundwater allocations. They seemed to have great difficulty in accepting that if
there had been no Burdekin scheme, there would have been very little progress in the
Burdekin district.
Only Dr Evans, the only “outsider” amongst the respondent’s witnesses, was prepared
to admit that the allocation policy was somewhat arbitrary and could have been increased at
least to some extent. Although he was critical of much of the evidence of Mr Woolley and
Mr Merrick, he was prepared to concede that some of those matters criticised could be
explained. Of those that remained, many seemed to me to be influenced by the views of the
respondent’s witnesses, which is not surprising, as DNR was the source of much of Dr Evans’
information.
I think that it can reasonably be assumed that by the date of resumption of the first of
the subject lands in December 1990, the respondent, or the Land Court, would have increased
the allocation rate south of the Polletti Line to 0.5 megalitres per hectare per year. It is not
likely that this would have increased further by the date of resumption of the last of the
subject lands, as the respondent would still have been monitoring the effect of the increased
pumping rate.
The Likely Approach of a Hypothetical Prudent Purchaser
The question remains as to whether a hypothetical prudent purchaser of the subject
lands at the various dates of resumption would have been prepared to pay an additional
amount for dry arable land for the possibility that the respondent would further alter his
groundwater allocation policy.
It must be assumed that such a hypothetical purchaser would “... be cognizant of all
circumstances which might affect its value, either advantageously or prejudicially, ... the then
-- 42 of 78 --
43
present demand for land, and the likelihood as then appearing to persons best capable of
forming an opinion, of a rise or fall for what reason soever in the amount which one would
otherwise be willing to fix as the value of the property”. (Isaacs J in Spencer v. The
Commonwealth (1907) 5 CLR 418 at 441.)
If one makes that assumption, such a purchaser would have been armed with the
knowledge of the type of evidence given by Messrs Woolley and Merrick and the contrary
views of Mr Hillier, Doctor Evans and Mr Leach. In such circumstances, I think that the
hypothetical purchaser would have come to the following conclusions:
there is simply too much doubt about the capacity of the aquifer to sustain pumping
at the rate of 2 megalitres per hectare per year;
there will be irrigation of at least part of the subject lands and other lands at the rate
of 0.5 megalitres per hectare per year;
there is likely to be at least partial success of the Davco scheme which will be
irrigating lands to the south of Lot 44;
in the longer-term, there will be recharge of the aquifer from infiltration of those
irrigation waters at the rate of between 10% and 20%;
therefore, there is the likelihood of greater recharge to the aquifer than at the dates
of resumption;
the extraction rate of 0.5 megalitres per hectare will itself be proven to be
conservative;
in those circumstances, there is the likelihood that the respondent (or the Land
Court) would increase the allocation further;
however, the likelihood of that allocation being increased more than 1.0 megalitre
per hectare per year was remote.
On that reasoning, I think that a hypothetical prudent purchaser would have been
prepared to pay something extra for dry arable land suitable for cane growing for the
possibility that, in the not too distant future, the allocation would be increased from 0.5
megalitres per hectare per year to 1.0 megalitre per hectare per year.
The amount of that additional payment will be discussed later in this judgment.
The Soils Evidence
-- 43 of 78 --
44
Evidence regarding soils and land suitability was given by Mr GA MacGregor of
MacGregor and Associates, Agricultural and Irrigation Consultants of Bowen, for the
claimants and by Mr JI McClurg, a self-employed agricultural consultant of Mackay, for the
respondent.
There is little disagreement between the soils experts about the areas of each of the
subject lands that are suitable for furrow irrigation of sugar cane. This is not surprising, as
they have both used the same soils suitability maps. Where they differed, I have adopted the
greater area, sometimes that of Mr MacGregor and sometimes that of Mr McClurg.
The real difference between them is in respect of the suitability of the soils for trickle
irrigation of horticultural crops. Mr MacGregor was of the opinion that all land suitable for
furrow irrigation of sugar cane would also be suitable for trickle irrigation of horticultural
crops. His opinion was largely based on his first-hand knowledge of the experience of the
Rapisarda Farming Company, which grew horticultural crops on Barratta clays, and of
farmers who were growing such crops on cracking clays in the Bowen district.
On the other hand, Mr McClurg was of the view that only relatively small areas of the
subject lands would be suitable for trickle irrigation of horticultural crops. He thought that
Barratta clays were totally unsuitable, because of wetness, leading to the increased possibility
of disease and trafficability difficulties. His opinion was based largely on his knowledge that
the Rapisarda Farming Company had abandoned its horticultural activities on Lot 240, which
at the date of the hearing was all under cane. He was also aware that a Mr Quinn had
attempted to grow horticultural crops on Barratta clays in 1995, but had to abandon the
venture with severe losses.
Both matters were clarified. It was established that the Rapisarda Farming Company
had successfully grown horticultural crops on Barratta clays on Lot 240 for about five of the
last ten years, but in 1998 the land was all under cane. It seems that there were difficulties in
using Barratta clays for horticulture. It could be successful, provided crops were planted after
one wet season and harvested before the next wet season.
It also seems that Mr Quinn abandoned his operations, not because of any fault in
Barratta clays, but because of an insect-borne disease. Mr MacGregor had first-hand
knowledge of this, while Mr McClurg was not aware of it.
Trickle irrigation of vegetable and rockmelon crops was well established in the
Burdekin District by the late-1980s. In Mr MacGregor’s opinion, Classes 1 to 3 soils would
be suitable for trickle irrigation of vegetable crops, as well as for furrow irrigation of sugar
cane. While DPI land suitability maps showed land suitable for rice, maize, mangoes and
capsicums, Mr MacGregor believed the best use of the land was for sugar cane and
-- 44 of 78 --
45
horticultural vegetable crops. He thought that the land suitable for sugar cane would also be
suitable for horticulture.
Mr MacGregor believed that in the period 1990 to 1993, there would have been
interest in the use of 250 hectares of the subject lands for horticultural crops. That opinion
seemed to be based on the fact that in the early 1990s, there was an expansion in the melon
market, melons being grown on whatever land was available. He noted that the Brandon
airstrip was located nearby and could be used for aerial spraying and fertilising. He thought
that rockmelons would be the major, but not the only crop. Using an average water
requirement of 2.5 megalitres per hectare for the 250 hectares of horticultural crops, the total
requirement would be 625 megalitres per year.
He thought that the 250 hectares of horticultural crops could be grown on Lot 5 and
Lot 44, 125 hectares on each, because they had the best access. The balance of the annual
water allocation would be used for sugar cane production.
Mr MacGregor had direct experience with trickle irrigation on Barratta clays, having
established a computer irrigation system for the Rapisarda Farming Company, which grows
small crops. However, he admitted that apart from that company he did not know of any
other growers of small crops using trickle irrigation on Barratta clays. He thought that
Barratta clays were very similar to the Bowen and Gumlu clays.
Mr McClurg thought it would be difficult to locate a large enough area with suitable
soils for horticultural crops on Lot 5. He agreed there was plenty of suitable soil, but all in
small areas. That made it more difficult and more expensive for horticulture and therefore
less attractive.
Mr McClurg’s evaluation consisted of two possible agricultural uses: the
irrigation of a range of crops where an allocation of high quality irrigation water was
available; and rain fed cropping, where no irrigation was available.
Mr McClurg was convinced that the soils in the Bowen area are not the same as soils
on the subject lands. The Bowen clay is not as heavy as Barratta clays. Bowen soils have
different soil physical features, horticultural crops being grown mostly on alluvial soils which
have different land forms and parent materials. In the Gumlu and Guthalungra areas, the soils
used for horticulture are not heavy clays, but mostly creek flats, with some 1Ug, which were
more permeable and had less wetness problems than 2Ug. Those soil types are not
comparable with the Barratta clays and Oakey soils in the BRIA.
-- 45 of 78 --
46
Mr McClurg based his opinion on DPI soil surveys in which he had played a part. A
field study in 1989 or 1990 by the relevant experts from Bowen and the Burdekin, including
himself, had arrived at a general consensus of opinion that they were different soils.
It seems that it is difficult but not impossible to grow horticultural crops on Barratta
clays. However, because of those difficulties and the lack of evidence of widespread use of
such lands for horticulture, it is difficult to see why they should be used for trickle irrigation
of horticultural crops instead of furrow irrigation of sugar cane. Indeed, there is evidence that
most of the horticultural crops in the Burdekin are grown on well-drained levee soils.
However, Mr MacGregor did not suggest that the whole of the potential cane growing
land would have potential for horticulture. He limited it to only 250 hectares. He felt that
125 hectares on each of Lot 44 and Lot 5 would be suitable, because of their superior access.
However, the 125 hectares he identified on Lot 44 is all Barratta clays. While both soils
experts agree there is at least 125 hectares of suitable soils on Lot 5, it is in scattered,
relatively small areas, making it expensive to establish the spray lines and other infrastructure
necessary for trickle irrigation. It would seem that such a venture would not be attractive to
farmers.
Therefore, I have come to the conclusion that the evidence has not established that
there is a higher and better use for any of the subject lands for trickle irrigation of
horticulture. Certainly there is no reason why a potential prudent purchaser would envisage
that 125 hectares on each of Lot 44 and Lot 5 would have potential for trickle irrigation of
horticultural crops, taking into account the risks and costs of establishment. It is most
unlikely that such a purchaser would take any such potential into account in deciding what to
pay for Lots 44 and 5.
Therefore, I find that the highest and best use of those areas is for cane land, either
irrigated or potential, depending on whether water is available, or potentially available.
The Valuation Evidence
Both valuers, Mr Eales for the claimants and Mr Moloney for the respondent, relied
on sales of comparable properties and on comparisons with previous Court decisions
(including the Davco decision) for the valuations of the various categories of land. However,
as pointed out previously, their approaches differed according to the information obtained
from the water and soils experts acting for each party. Although they both relied upon
findings in the Davco decision, Mr Eales did so more heavily than Mr Moloney, who
-- 46 of 78 --
47
preferred to revert to the findings in the earlier decision of the Land Court in Fabrellas v. The
Commissioner of Water Resources (A91-21) Land Court, 11 December 1991 (not reported).
Mr Eales’ Reasoning
Mr Eales reasoned that the subject lands were located in an area of the Burdekin
immediately adjacent to existing agricultural areas which were used for the growing of sugar
cane, with good quality soils, proven underground water supply, close proximity to mill
tramlines, with 3-phase power and good access. He contended that prior to the Burdekin
scheme, the owners of properties in the area had a general expectation that water would
become available hand-in-hand with the future expansion of the sugar industry. Therefore, a
prudent purchaser would pay a premium price for the subject lands, not only for the lands
which could be irrigated with their present entitlement, but for lands with irrigation potential,
with irrigation water from the Davco scheme and other sources being available in the future.
According to Mr Eales, if there had not been a Burdekin scheme, there would have
been the prospect of water from a number of sources, namely:
replenishment of underground supplies by a water board type scheme or the Davco
project;
expansion of the NBWB area;
proving up of existing underground supplies;
direct open water pumping from a water board channel;
the Burdekin Dam as outlined in the 1952 Kemp Report;
a development such as the Majors Creek Dam, which was one of the alternatives
outlined in the “Caneland Expansion Study” undertaken by McIntyre & Associates
and James Cook University, for the Haughton Sugar Co Ltd in 1975.
All those possible sources of water would have affected the value of potential irrigable arable
land in accordance with the Davco decision, which affirmed the principle that land that had
potential to obtain irrigation water had a higher value than dry arable land and grazing land.
Based on the advice of Mr Woolley and Mr Merrick, Mr Eales concluded that in the
absence of the Burdekin Dam, the WRC allocation of 0.25 megalitres per hectare could have
been supplemented by a further 1.75 megalitres per hectare potentially available, a total of 2
megalitres per hectare.
Mr Eales was confident that even without the Burdekin scheme there would have been
expansion of the sugar industry in the area. He said that prior to the scheme, studies had been
commissioned by the sugar mill proprietors to investigate the possibility of future expansion
within the Burdekin area. A study was carried out for the Haughton Sugar Company Limited
in May 1975, which set out a proposed development plan from 1974 to 1995, with a planned
expansion of available area for sugar cane. There were similar reports commissioned by
-- 47 of 78 --
48
Pioneer Sugar Mills Ltd for the Pioneer and Inkerman Mills in June 1976, and by CSR in
1988.
According to Mr Eales, the industry was being pressured to increase production
because of the world’s sugar shortage. With modern machinery and more efficient farming
practices, farmers were seeking to expand. The government would also have been pressured.
The process of deregulation of the sugar industry, which occurred in 1991 and 1992, was
known about in 1990, and would have put further pressure on the industry to expand.
Mr Eales relied on the following findings in the Davco decision: the cane industry
would have expanded in the area; the land that had an irrigation supply would have achieved
sale prices higher than those achieved at BRIA auction sales at the date of resumption; the
determination of the value of irrigable land at $6,000 per hectare; and the determination of the
value of dry arable land with potential for irrigation at $1700 per hectare.
He pointed out that the value of that latter category was based on the possibility of the
ultimate success of the Davco project, not from the potential for proving up existing irrigation
supplies, which he regarded as a further potential. It depended upon the opinions of Mr
Woolley and Mr Merrick being accepted by DNR or, on appeal, by the Land Court. Mr Eales
was of the opinion that potential from that source was “much higher” than the potential found
in the Davco decision.
In respect of Lots 44 and 5, he relied on Mr MacGregor’s opinion that 125 hectares on
each of those lots had potential for trickle irrigation of horticultural crops. As trickle
irrigation of horticultural crops required only 2.5 megalitres per hectare, rather than the 8
megalitres required by sugar cane, the additional water increased the area of dry arable land
with potential for sugar cane on each of those lots.
Furthermore, he considered that the potential from the drain/dam water from the
agricultural drain also provided an immediate potential for a further 50 hectares of irrigable
arable land on Lot 44.
Mr Eales reasoned that in addition to being encouraged by the prospect of ultimate
success of the Davco project, a potential prudent purchaser of Lot 44 and Lot 5 “would have
been very confident” that the NBWB would have expanded its area to include part of those
lots, or at the very least, the replenishment of the underground supplies from the NBWB area,
would have been available to those two lots.
Mr Moloney’s Reasoning
Although acknowledging that the Land Appeal Court had determined a value of
$6,000 per hectare for irrigable arable land, Mr Moloney adopted that value (adjusted for the
-- 48 of 78 --
49
state of development) only for the irrigable arable lands on Lot 44 and Lot 15. For such land
on Lots 42, 43 and 5, he applied values of $3,700 per hectare for irrigable arable soils with
development and $3,500 per hectare for irrigable arable soils with no development, those
values being derived from his sales of irrigable arable lands and from the determination of the
Land Court in Fabrellas.
For the values which he applied to dry arable and grazing lands, Mr Moloney relied
upon three sales in his Sales Schedule No 2, comprising grazing and dry arable sales. He also
relied on his apportionment of the Land Court determination in Fabrellas. He applied values
of $750 per hectare for dry arable land with development and $550 per hectare for dry arable
land with no development; for the grazing lands with no development he applied $330 per
hectare and $530 per hectare for grazing lands with development.
The Valuations
It is necessary to explain how Mr Eales and Mr Moloney arrived at such
different valuations for each of the subject lands. Their tasks were difficult enough, as they
were making retrospective valuations, but they were further complicated by the requirement
that the land must be valued on the hypothesis that the Burdekin Dam had not been built. In
that exercise they relied substantially on the opinions of the various experts, but it was the
responsibility of the valuers to investigate what evidence was available and to apply it.
First, I will set out the means by which Mr Eales and Mr Moloney arrived at their
valuations of each of the subject lots and then examine the sales evidence which they used as
a basis for those valuations.
Lot 44
Mr Eales valued Lot 44 as fully economically developed and then deducted the cost of
bringing the land to that state.
56.8ha of irrigable/arable @ $6,000/ha = $ 340,800
50.0ha of dry arable (with dam) potential
@ $3,000/ha = $ 150,000
483.5ha of dry arable with underground
potential @ $3,000/ha = $1,450,500
713.93ha of dry arable with potential
@ $1700/ha = $1,213,681
513.35ha of grazing @ $400/ha = $ 205,340
Total = $3,360,321
-- 49 of 78 --
50
Less Timber treatment
11.8ha desuckering, stickpicking, knifing
and laser-levelling @ $800/ha = $ 9,440
558.2ha desuckering, stickpicking, knifing
and levelling @ $500/ha = $279,100
689.23ha clearing, stickpicking, knifing
and levelling @ $700/ha = $482,461 $ 771,001
Total value of land $2,589,320
Forty-five hectares of the land had been cleared to cultivation and of that, 25 hectares
were under irrigated cane at the date of resumption. 570 hectares had been cleared to
cultivation, with light regrowth.
Mr Eales reasoned that Lot 44 had a water entitlement of 454.4 megalitres which, at 8
megalitres per hectare, would irrigate 56.8 hectares, to which he applied $6,000 per hectare,
as found in the Davco decision. He considered that a further 50 hectares could be irrigated
from the drain/dam, which he valued at half the rate applied to the irrigable arable land. As I
understand his evidence, that allowed for both what he considered to be the risk of
implementing the system and its cost of construction. He felt that it was a low level risk.
He then assumed that the whole area of 1,817.58 hectares was eligible for an
additional 1.75 megalitres per hectare, or 3,180.75 megalitres. However, Mr Eales reasoned
that as Mr MacGregor had identified 125 hectares of Lot 44 as having potential for
horticultural crops, at 2.5 megalitres per hectare for trickle irrigation, 312.5 megalitres would
be required, leaving 2,868.25 megalitres for the irrigation of sugar cane. At 8 megalitres per
hectare, that would irrigate 358.5 hectares. Therefore, the total dry arable land with potential
for irrigation from additional groundwater allocation was 483.5ha, to which he applied $3,000
per hectare. He reasoned that a potential prudent purchaser would have been “very confident”
of obtaining additional water; the rate of $3,000 per hectare, or 50% of the irrigable arable
rate, was adopted to take into account the risk of persuading WRC, or on appeal, the Land
Court. He further reasoned that another 713.93 hectares of dry arable land had irrigation
potential, from a combination of the Davco and NBWB schemes. He thought there was less
potential from the Davco project for Lot 44 than there was for the lands which were the
subject of the Davco decision, but more potential from the NBWB.
If the Court was to reject these arguments and find that there was no further potential
for irrigation, then in Mr Eales’ opinion, cleared dry arable land on Lot 44 would have a value
of $1400 per hectare. In such a scenario, the total dry arable area would be 1247.43 hectares.
Mr Eales’ grazing value of $400 per hectare was derived from the sales and from the
Davco decision. He felt that the grazing area included land with potential for growing cane in
-- 50 of 78 --
51
the future, but the possibility of a prudent purchaser paying more than grazing value was too
remote.
The allowances made by Mr Eales for timber treatment required to bring the land on
each of the lots to full economic development are in line with those adopted in the Davco
decision:
clearing, stickpicking, ripping and laser-levelling to cultivation $1,000 per hectare;
clearing, stickpicking, ripping and levelling to dry/arable standard $700 per
hectare;
desuckering, stickpicking, ripping and levelling to dry/arable standard $500 per
hectare;
clearing $200 per hectare.
He claimed that these costs were supported by figures supplied by an earthmoving and
treeclearing contractor at Ayr.
Mr Moloney valued Lot 44 quite differently. Instead of valuing the land as fully
economically developed, he valued each category of land as it was developed at the date of
resumption.
Land (valued as treated, fenced and watered)
(a) Irrigable/arable
45 ha irrigable coastal forest soils, cleared to cultivation
@ $6,000/ha including development; (exclusive of any
added value of the sugar cane assignment, sugar cane
stools or crop which remained the property of the
dispossessed owner) $ 270,000
12 ha irrigable coastal forest soils @ $5,300/ha including
development (timber pulled with parts formerly
tordoned) $ 63,600
(b) Dry arable lands: lands with some form of arability
in rainfed conditions
479 ha coastal forest soils $900/ha including timber
treatment (timber pulled with parts formerly tordoned) $ 431,100
707ha coastal forest soils @ $600/ha with no
timber treatment $ 424,200
(c) Grazing: lands suited to grazing only in rainfed
conditions
84ha coastal forest soils @ $700/ha including timber
treatment (pulled with parts formerly tordoned) $ 58,800
20ha coastal forest soils @ $700/ha including timber
treatment (pushed now carrying regrowth) $ 14,000
471ha coastal forest soils with no timber
treatment @ $400/ha $ 188,400
Total Land and Development $1,450,100
-- 51 of 78 --
52
For the 57 hectares which could be irrigated from the licensed irrigation bore, he
valued 45 hectares already developed to cultivation at $6,000 per hectare, in accordance with
the Davco decision, and to the remaining 12 hectares which were developed to a lesser
standard, he applied $5,300 per hectare.
Mr Moloney rejected completely Mr Eales’ proposition that there was any potential
for irrigation from any other source, be it from the drain/dam, the Davco scheme, increased
groundwater allocation, the expansion of the NBWB area, or
any other possible project.
Relying on Mr McClurg’s soils suitability report, he concluded that there were 1,186
hectares of dry arable land, suitable for cultivation in rainfed conditions. He reasoned that in
Fabrellas, the Land Court determined the value of dry arable land at $550 per hectare,
excluding development, and at $1241 per hectare, cleared to cultivation. In comparing the
dry arable land on Lot 44 with that on the Fabrellas land, he concluded that the remaining
479 hectares of cleared land, which had been pulled, with parts formerly tordoned, should be
valued at $900 per hectare, while the 707 hectares of dry arable land, with no timber
treatment, should be valued at $600 per hectare.
For the grazing lands, he adopted $700 per hectare for the 84 hectares, which have
been pulled, with parts formerly tordoned (the same as for Fabrellas), while the remaining
471 hectares of grazing land, with no timber treatment, he valued at $400 per hectare.
Lot 15
Mr Eales valued Lot 15 as follows:
11.0 ha of irrigable/arable @ $6000/ha $ 66,000
75.12 ha of arable with underground potential
@ $3000/ha $ 225,360
224.58ha of grazing with potential @ $2500/ha $ 561,450
33.8ha of grazing @ $400/ha $ 13,520
Total $ 866,330
Less
Timber treatment
11.0ha desuckering, stickpicking, knifing and laser
levelling @ $800/ha $ 8,800
244.0ha desuckering, stickpicking, knifing
and levelling @ $500/ha $ 122,000
56.58ha cleared, stickpicking, knifing and
levelling @ $700/ha $ 39,606 $170,406
Total Value of Land $695,924
(Adopt $695,900)
Mr Eales reasoned that the 87 megalitre allocation attributed to the resumed area,
would irrigate 11 hectares of cane land, to which he applied $6,000 per hectare, directly from
-- 52 of 78 --
53
the Davco decision. On the basis that the whole area of 344.5 hectares would have had the
potential for an allocation of 2 megalitres per hectare, or 689 megalitres, less the 87
megalitres, would leave a net of 602 megalitres available. At 8 megalitres per hectare, that
would irrigate an additional 75.12 hectares (actually 75.25 hectares).
In applying a value to that land, Mr Eales reasoned that in addition to its potential
from the ultimate success of the Davco project, that area had immediate potential for the
proving up of existing underground supplies (as proved by Messrs Woolley and Merrick) and
that DNR, or the Land Court on appeal, would be persuaded to increase the water allocation
to 2 megalitres per hectare. In his opinion, the immediate potential for irrigation of that area
was much higher than the potential found in the Davco case. Therefore, he applied $3,000
per hectare to the 75.12 ha with irrigation potential.
He also reasoned that in the absence of the Burdekin Dam, any prudent purchaser
would have been very confident that the NBWB area would have expanded to include all of
Lot 15. Therefore, he felt that the potential was greater than in the Davco case, so he applied
$2,500 per hectare to 224.58 hectares.
To the 33.8 hectares of grazing land he applied $400 per hectare.
The allowances for timber treatment were the same as adopted for Lot 44.
Mr Moloney adopted a different approach. His valuation proceeded as follows:
Land (including development)
(a) Arable
11ha irrigable/arable forest soils partially developed
by pushing, stacking and burning @ $5400/ha $ 59,400
58ha dry arable potential partially developed by
pushing, stacking and burning @ $1,575/ha $ 91,350
14ha dry arable potential forest soils (with
no development) @ $1175/ha $ 16,450
Total 83ha $ 167,200
(b) Non-arable
187ha forest soils suited to grazing only partially
developed by pushing, stacking and burning @ $900/ha $ 168,300
74.5ha forest soils (with no development) @ $500/ha $ 37,250
Total 261.5ha $ 205,550
Total Land and Development 344.5ha $ 372,750
His reasoning for the valuation of the 11 hectares of irrigable arable land was the same
as that of Mr Eales, except that he allowed $600 per hectare to bring that land to full
development. For the 58 hectares of partially developed dry arable land with potential for
irrigation, he adopted the finding in the Davco decision of $1700 per hectare which adjusted
-- 53 of 78 --
54
for state of development and size, came to $1,575 per hectare, while he adopted $1175 for the
187 hectares of partially developed grazing land and $500 per hectare for the 74.5 hectares of
grazing land with no development.
Lot 42 and Lot 43
Mr Eales considered that Lots 42 and 43 were better grazing country than Lot 44
(which he regarded as similar to the lands in the Davco case). They had been used for
growing cattle, whereas Lot 44 had been used for breeding only. He realised that there was
no potential in those lots for irrigation from the Davco project or from expansion of the
NBWB area, but considered there was potential from increased allocations of underground
water and from other possible schemes. His valuation proceeded as follows:
83.0 ha of irrigable/arable @ $8000/ha $ 664,000
581.0ha of arable with underground potential
@ $4000/ha $2,324,000
1200.0ha of dry arable with potential @ $1650/ha $1,980,000
792.35ha of grazing @ $650/ha $ 515,027
Total $5,483,027
Less
Timber Treatment
83.0ha desuckering, stickpicking knifing and
laser-levelling @ $800/ha $ 66,400
112.0ha desuckering, stickpicking knifing
and levelling @ $500/ha $ 56,000
1669.0ha clearing, stickpicking, ripping
and levelling @ $700/ha $1,168,300 $1,290,700
Total Value of Land $4,192,327
Mr Eales reasoned that Lots 42 and 43 would have a water entitlement of 664
megalitres, which at 8 megalitres per hectare would irrigate 83 hectares of cane land. Having
regard to the Davco determination of $6,000 per hectare for irrigable arable land, he adopted
$8,000 per hectare to make allowance for what he considered to be the increase in values
between the dates of resumption.
He further reasoned that the value for dry arable land with potential for irrigation
would increase by the same percentage and, as the Court had adopted $1700 per hectare, dry
arable land with potential should be valued at $2,250 per hectare, if Lots 42 and 43 had
potential similar to that of the lands in the Davco case. However, Mr Eales realised that there
was no potential from the Davco scheme for lots 42 and 43. He contended that their potential
-- 54 of 78 --
55
arose from the possibility of development of the Majors Creek Dam and other possible
schemes.
There was also the immediate potential from the proving up of the existing
underground supplies, as explained earlier. In his opinion, the immediate potential to irrigate
up to an additional 581 hectares from that source was much greater than the potential found in
the Davco case, so he applied $4,000 per hectare.
However, he reasoned that the location of the lots would lessen that potential for dry
arable lands which did not have that immediate underground potential. Therefore, he adopted
$1650 per hectare for dry arable land with potential from other sources.
He assessed the grazing values by comparison with his sales evidence at $650 per
hectare. His allowances for timber treatment were the same as for Lot 44.
Mr Moloney valued Lot 42 and Lot 43 as follows:
Lot 42 -
Land (valued as treated, fenced and watered).
(a) Potential irrigable arable
26 ha potential irrigable arable forest soils
@ $3700 per hectare including development
(pulled with moderate to heavy regrowth) $ 96,200
16ha potential irrigable uncleared arable forest
soils @ $3500 per hectare $ 56,000
(b) Dry arable lands: lands with some form of arability
in rainfed conditions
483ha uncleared dry arable forest soils @ $550/ha $ 265,650
(c) Grazing:lands suited to grazing only in rainfed conditions
15ha of forest grazing soils @ $730/ha
including development (cleared to grass) $ 10,950
15ha of forest grazing soils @ $530/ha
including development (pulled with moderate to heavy
regrowth) $ 7,950
773ha uncleared forest grazing soils @ $330/ha $ 255,090
Total Land & Development $ 691,840
Lot 43 -
Land (valued as treated fenced and watered)
(a) Potential irrigable arable
42ha potential irrigable arable forest soils @ $3700/ha
including development (pulled with moderate to heavy
regrowth) $ 155,400
(b) Dry arable lands: lands with some form of arability
in rainfed conditions
109ha dry arable forest soils @ $750/ha including
-- 55 of 78 --
56
development (pulled with moderate to heavy regrowth) $ 81,750
521ha of uncleared dry arable forest soils @ $550/ha $ 286,550
c. Grazing: lands suited to grazing only in rainfed conditions
6ha forest grazing soils @ $730/ha including development
(cleared to grass) $ 4,380
8ha forest grazing soils @ $530/ha including development
(pulled with moderate to heavy regrowth) $ 4,240
642ha uncleared forest grazing @ $330/ha $ 211,860
Total Land & Development $ 744,180
Mr Moloney reasoned that the water entitlements of Lots 42 and 43 would irrigate 42
hectares on each of them, which in accordance with his apportionment of the determination in
the Fabrellas case, he valued at $3,700 per hectare for the areas that were cleared, but with
regrowth, and $3,500 per hectare for the uncleared area on Lot 42. The dry arable land was
valued at $730 per hectare for the cleared areas and $530 per hectare for the uncleared areas.
The grazing lands he valued at $330 per hectare if uncleared, $530 per hectare if
cleared with regrowth, and $730 per hectare if cleared to grass.
Lot 5
Mr Eales valued Lot 5 as follows:
55.7ha of irrigable/arable at $8,000/ha $ 445,600
475.7ha of arable with underground potential @ $4000/ha $1,902,800
727.81ha of dry arable with potential @ $1650/ha $1,200,886
522.621ha of grazing @ $700/ha $ 365,835
Total $3,915,121
Less
Timber treatment
55.7ha desuckering, stickpicking, knifing
and levelling @ $800/ha $ 44,560
19.3ha desuckering, stickpicking, knifing
and levelling @ $500/ha $ 9,650
1184.2ha clearing, stickpicking, knifing
and levelling @ $700/ha $ 828,940 $ 883,150
Total Value of Land $3,031,971
From the water entitlements for Lot 5 of 445.5 megalitres, Mr Eales concluded that
55.7ha could be irrigated. On the same reasoning that he adopted in respect of such land on
Lots 42 and 43, he applied $8,000 per hectare. Similarly, as he did for the same categories of
land on Lots 42 and 43, for the 475.7 hectares of dry arable with underground potential, he
applied $4,000 per hectare and for the 727.81 hectares of dry arable with potential, he adopted
$1650 per hectare. For the 522.621 hectares of grazing land, he adopted $700 per hectare, as
Lot 5 was fattening country.
-- 56 of 78 --
57
His allowances for timber treatment were the same as those adopted for Lot 44, with
slight variations.
Mr Moloney valued Lot 5 as follows:
Land (valued as treated fenced and watered)
(a) Potential irrigable arable
56ha potential irrigable arable forest soils
@ $3700/ha including development (pulled
with moderate to heavy regrowth) $ 207,200
(b) Dry arable lands: lands with some form of
arability in rainfed conditions
5ha of (cleared to grass) dry arable forest soils @950/ha $ 4,750
12ha dry arable forest soils @ $750/ha including
development (pulled with moderate to heavy regrowth) $ 9,000
694ha of uncleared dry arable forest soils @ $550/ha $ 381,700
(c) Grazing: lands suited to grazing only in rainfed conditions
10ha of forest grazing soils @ $530/ha including
development (pulled with moderate to heavy regrowth) $ 5,300
1005ha of uncleared forest grazing soils @ $330/ha $ 331,650
Total Land & Development $ 939,600
Essentially, Mr Moloney adopted the same reasoning in applying values to the various
categories of land as he had for Lots 42 and 43, making allowances for differences in the state
of development for similar land on Lot 5. He agreed with Mr Eales that the water entitlement
for Lot 5 would irrigate 56 hectares, to which he applied $3,700 per hectare.
The figures which he adopted for dry arable land and for grazing land were the same
as for Lots 42 and 43, adjusted for the state of development.
The Sales Evidence
Irrigable/Arable Land
The Davco decision determined a value of $6,000 per hectare for irrigable arable land.
Both valuers adopted that rate per hectare for the irrigable arable land on Lots 44 and 15.
However, they departed from that rate per hectare for the irrigable arable lands on Lots 42, 43
and 5. Mr Eales adopted $8,000 per hectare for what he contended was an increase in value
between the dates of resumption of the Davco lands (effectively 5 May 1990) and the dates of
-- 57 of 78 --
58
resumption of Lots 42, 43 and 5 (18 December 1992 and 5 November 1993). Mr Moloney
adopted only $3,000 to $3,700 per hectare, depending on the state of development.
Mr Eales’ basis for the irrigable arable lands comprised a mixture of sales of irrigated
farms inside the Water Board areas and outside those areas, plus sales of BRIA lands. His
first schedule of cane farm sales contained the details of 13 sales of farms ranging in area
between 35.21 hectares and 69.76 hectares, which sold between May 1992 and December
1993, which he analysed to show values ranging from $7,941 per hectare to $12,245 per
hectare on what he termed “watered/cleared level to cultivation”. Each of those sales was
supplied with water from the NBWB or the SBWB.
His second schedule of sales contained the details of sales of 18 farms in the Mulgrave
and Northcote areas, which sold between January 1988 and November 1991, which he
analysed on a similar basis to show values ranging from $3,480 per hectare to $10,166 per
hectare. It was the same schedule of sales which he relied on in the Davco case and the
details of which were discussed in the Davco decision (particularly by the Land Appeal
Court) in arriving at $6,000 per hectare for irrigable arable land.
On the other hand, Mr Moloney relied principally upon Land Court determinations in
previous Burdekin scheme resumptions, particularly that of Fabrellas. He had also relied on
those Land Court determinations in the Davco case.
For the reasons set out in the Davco decision, the Land Court preferred the sales
evidence of Mr Eales, particularly of the combined sale, referred to as Sale No. 10/10A, from
Haselton to Roncato, to Mr Moloney’s evidence of the value of irrigable arable land,
determining the value of such land at $6,000 per hectare, watered and cleared level to
cultivation.
Mr Eales explained that he had included his first schedule of cane farm sales to
demonstrate the increase in value of irrigable arable land disclosed by those sales, compared
with the sales in his second schedule. In particular, he compared the sale from Haselton to
Roncato (Sale 10/10A on Schedule 2) of 335.826 hectares in July 1990 for $3.1 million,
which analysed to show $7,605.00 per hectare, with the sale from Watt to Davey (Sale 1 on
Schedule 1) of 57.162 hectares in April 1993, for $700,000, which analysed to show $12,245
per hectare. Both sales were analysed as watered and cleared level to cultivation. He
reasoned that as the Davco decision had determined the value of irrigable arable land at
$6,000 per hectare as at May 1990, principally on the basis of Sale 10/10A, then Schedule 1
and particularly Sale 1 on that schedule, indicated an increase of 33% by late 1993.
Mr Moloney accepted Mr Eales’ analyses of the sales in his second schedule, but he
thought there were sales closer to Lots 42, 43 and 5, which were more relevant, as most of the
-- 58 of 78 --
59
18 sales were in the old Clare irrigation area and had been developed and farmed for many
years. He did not accept that they were appropriate as a basis of valuation, a criticism he had
also expressed in the Davco case.
He disagreed with Mr Eales’ analyses of the 13 sales on Schedule 1, and although his
analyses of Sales 2 to 13 were generally at lower rates per hectare than Mr Eales’ figures,
overall the differences were not significant, as his analyses of those sales ranged from $6,890
to $9,889. However, he differed markedly in his analysis of Sale 1, Watt to Davey, which he
analysed to show $9,796 per hectare. After making further investigations, Mr Eales conceded
that he had erred in the analysis of that sale by underestimating the value of the structural
improvements. His re-analysis showed $10,820 per hectare. However, he still maintained
that the revised analysis supported his proposition that there had been an increase in value of
33% between the date of resumption of the lands in the Davco case and the dates of
resumption of Lots 42, 43 and 5.
Mr Moloney rejected that contention. In his opinion there had been no increase in
value. He thought the conclusion drawn by Mr Eales was not correct. Because of the
differences between the two sale properties relied on by Mr Eales, Mr Moloney felt that they
were simply not comparable. While conceding that they both draw water from the river and
have riverfront soils, he asserted that there the comparison ended, drawing attention to the
differences in their situation, size and sale price. He felt that they were at different ends of
the market spectrum. He questioned whether Sale 1 was supplied with water by the NBWB,
or had a river pumping licence.
I cannot accept that Mr Eales has demonstrated that there has been an increase of
33% in the value of irrigable arable lands between May 1990 and December 1993. Quite
apart from any errors which he made in his analyses of the sales in his second schedule and
the criticisms made by Mr Moloney, a comparison of his derived values from the sales on his
first schedule with those derived from the sales on his second schedule, indicates that there
were several sales on Schedule I which showed values between $8,000 and $10,000 per
hectare, the upper range of the values derived from the sales on his second schedule. It is
very difficult to prove an increase in values by comparing the values derived from sales of
farms such as Sales 10/10A and Sale 1, which differ in so many respects. More convincing
evidence would have to be provided, such as the sale and resale of the same property over the
relevant period.
Mr Eales had a second limb of reasoning for his contention that there had been an
increase of 33% in the value of irrigable arable land. For this he relied on the increase in
-- 59 of 78 --
60
the WRC auction sales between 1990 and 1993, particularly the higher prices paid in late
1993.
Both valuers agreed that there had been little or no increase in prices between Auction
1 in early 1988 to Auction 8 in late 1991, when a number of lots were passed in. More lots
were passed in at Auction 9 in June 1992. Mr Moloney explained that they were passed in
because of low returns following a cyclone and floods, at a time when there was a lack of
both money and confidence in the BRIA farms. This was followed by a good harvest from
BRIA lands in 1992. Delta farmers became interested when they realised that BRIA farms
grew good cane and development costs were not as high as they had thought. That was
followed by a ballot in November 1992, followed by higher prices achieved in Auctions 11,
12 and 13 in late 1993/early 1994. Mr Moloney felt that this increase in prices was assisted
by the various incentives which were offered by the Department to purchasers of BRIA lands
at those later auction sales, which he thought made a big difference to the prices achieved.
For those reasons, he was of the opinion that the conclusion could not be drawn that the
prices achieved at those auction sales supported an increase of 33% in the value of
irrigable arable land between 1990 and 1993.
I accept Mr Moloney’s explanation of the reasons for the increase in the auction
prices. However, it must be remembered that the Davco decision found that the price of
irrigable arable land was depressed by the number of BRIA auction blocks coming onto the
market. That, combined with the financial incentives offered by the WRC in the latter part of
that period, lead me to conclude that those auction sales do not support Mr Eales’ contention.
Therefore, I find that there is no evidence to support any increase in value for the
irrigable arable lands on Lots 42, 43 and 5, over the $6,000 per hectare found by the Land
Court and affirmed by the Land Appeal Court in the Davco decision.
However, Mr Moloney was of the opinion that a lower value should be applied. He
applied values of $3,700 per hectare for irrigable arable lands with development and $3,500
per hectare for such land with no development. Those values were derived from his sales of
irrigable arable lands and also from the determination of the Land Court in Fabrellas.
Mr Moloney relied on eight sales of irrigable arable lands between September 1991
and June 1994, with areas ranging from 41.8 hectares to 213.9 hectares and which, when
analysed by excluding the value of improvements and timber treatment, showed values
ranging from $1,924 per hectare to $5,016 per hectare.
In addition, as he did in the Davco case, Mr Moloney relied on his apportionment of
the Land Court determination in Fabrellas, as explained in the Land Court Davco decision at
page 75. The Land Court preferred to rely on recent sales evidence as a basis of valuation
-- 60 of 78 --
61
(page 92) and that approach was confirmed by the Land Appeal Court at page 15 of its
judgment.
Mr Moloney was of the opinion that the value for irrigable arable land found by the
Davco decision should not be applied for such lands on Lots 42, 43 and 5, for several reasons:
they were further removed from developed areas; they had different access; they had different
levels of development (e.g. no irrigation bores); and they were in a different area.
I cannot accept Mr Moloney’s proposition.
Lots 42, 43 and 5 adjoin the Davco lands to the west, being separated only by Barratta
Creek. The evidence indicates that the irrigable arable lands on those lots are at least equal in
quality to that of the lands the subject of the Davco case, and adjustments can be made for
different levels of development and other differences. The determination of the Land Appeal
Court of the value of irrigable arable lands at $6,000 per hectare must be the starting point for
the determination of the values of similar lands, unless the sales evidence indicates that it
should be departed from. I have found that Mr Eales has not demonstrated that there was an
increase in that rate per hectare so far as these three lots are concerned. It remains to consider
whether the sales produced by Mr Moloney show that the rate per hectare should be lower
than that found in the Davco case.
Three of Mr Moloney’s sales (Sales 1, 2 and 3) are situated in the vicinity of the
Fabrellas land, to the south of the three subject lots which are much closer to the Bruce
Highway. The other five sales are similarly, or even better situated than the subject lands.
There is evidence to the effect that at least three or four of Mr Moloney’s sales were of
retention areas and would therefore be competing on a market which was depressed by BRIA
auction sales. However, having regard to the position of all eight sales, they would all to some
extent be competing with the auction sales being held at the relevant dates. That, combined
with the fact that the sales from early 1993 (Sales 3 to 8) would not have been offered the
financial incentives which were available to BRIA auction purchasers, could well have
influenced the prices paid.
The claimants also argue that, but for the Burdekin scheme, none of Mr Moloney’s
sales would have been irrigated, as they are all supplied by BRIA channel water. In my
opinion, that aspect alone renders all Mr Moloney’s sales inappropriate as a basis, because it
is the scheme itself which gives the land its irrigable arable value. Whatever criticism can be
levelled at Mr Eales’ sales upon which the Davco decision for irrigable arable land was based,
they were irrigated farms prior to the introduction of the Burdekin scheme.
-- 61 of 78 --
62
Therefore, I find that the Davco determination of $6,000 per hectare for the value of
irrigable arable land should apply also to Lots 42, 43 and 5, with any necessary adjustments
for state of development or other differences.
The Areas of Irrigable Arable Land and Land with that Potential
There is no dispute in these cases as to the areas of land on each lot that could have
been irrigated in accordance with their groundwater entitlements based on then existing WRC
allocation policy. Those areas were determined on the basis that sugarcane requires irrigation
water at the rate of 8 megalitres per hectare per annum. There is no dispute that those areas
should be valued as irrigable arable land.
In these cases I have found that during the period between April 1980 to 22 December
1990, the WRC allocation policy would have been changed if there had been no Burdekin
scheme, and water entitlements of the subject lands would be 0.5 megalitres per hectare per
annum. That finding of fact means that twice the area should be valued as irrigable arable
land.
Mr Eales thought that Mr Woolley and Mr Merrick had proved up groundwater
resources sufficient to convince a prudent purchaser to believe that at some time in the future
water entitlements would be at the rate of 2 megalitres per hectare per annum. He reasoned
that because those entitlements would be granted in the future, a prudent purchaser would be
prepared to pay only half the irrigable arable rate, or $3000 per hectare.
As pointed out earlier, I think that the evidence indicates that it would be sound
management practice to increase groundwater entitlements gradually, monitoring the effects
of any increase for some time before further increases were made. I have also concluded that
based on the evidence of the various experts, groundwater extraction at the rate of 2
megalitres per hectare could not be sustained, but extraction at the rate of 1 megalitre per
hectare might well be, after a reasonable period of monitoring each progressive increase.
Therefore, I do not accept Mr Eales approach.
On the other hand, Mr Moloney did not accept that, in the absence of the Burdekin
scheme, there would have been any increase in groundwater entitlements. As already
discussed, I think that the evidence indicates otherwise.
It was argued by the claimants that the reason for WRC officers refusing to consider
any allocation in excess of 0.25 megalitres per hectare for the subject lands after April 1980,
was related to the cost of resuming irrigable arable land. The claimants suggest that the
reason that the Hoey land was not resumed was because of the expense of resuming land with
a water entitlement of 6 megalitres per hectare per annum.
-- 62 of 78 --
63
While the evidence did not go so far as to warrant drawing that inference, it certainly
can be said that once it had been decided to resume the Cox lands, it would have been
irresponsible for the respondent to have granted any additional water allocation to those lands.
However, the fact that he did not do so, seems to have influenced the thinking of at least some
of the respondent’s witnesses.
The Value of the Dry Arable Land with Irrigation Potential
With the exception of the dry arable land on Lot 15, Mr Moloney did not accept that
such land on the other four lots had any potential for irrigation. Accordingly, he valued the
dry arable land on Lots 5, 42, 43 and 44 at values which reflected no potential for irrigation.
On the other hand, Mr Eales valued the dry arable land on the various lots, depending
on what he considered to be likelihood and immediacy of that potential:
On Lot 44 at $3000 for the 483.5 hectares with potential from additional
groundwater allocations, and $1700 per hectare for the 713.93 hectares with
potential from a combination of the ultimate success of the Davco project and from
future expansion of the NBWB area;
On Lot 15 at $3000 for the 75.12 hectares with potential from additional
groundwater allocations, and $2500 with potential from future expansion of the
NBWB area;
On Lots 42 and 43 at $4000 for the 581 hectares with potential from additional
groundwater allocations; and $1650 for the 1200 hectares with potential from
“other schemes”.
On Lot 5 at $4000 for the 475.7 hectares with potential from additional
groundwater allocations; and $1650 for the 727.81 hectares with potential from
“other schemes”.
Apart from the potential for future increase from groundwater sources to a total of 1
megalitre per hectare, and from the Davco project in the case or Lot 15, I have rejected the
possibility of irrigation water being available to the subject lands from any other source. The
other possible sources of water, apart from the Davco project and the NBWB, were the
Burdekin Dam, as proposed by the 1952 Kemp Report, and the Majors Creek Dam, as
proposed in the 1975 Caneland Expansion Study. While Mr Eales raised those proposals as
examples of the various alternative water supply schemes that would have been further
investigated if there had been no Burdekin scheme, I do not think that they could be regarded
as likely to be implemented in the forseeable future. In my view, a hypothetical prudent
purchaser would regard any such likelihood as too remote to pay any premium for dry arable
land which is suitable for sugar cane.
-- 63 of 78 --
64
However, for the possibility of being granted further allocations up to a maximum of 1
megalitre per hectare, I think that a prudent purchaser would have paid something over and
above the dry arable value. As in the Davco case, I do not think such a purchaser would pay a
great deal more. Therefore, I propose to adopt the same value as found in the Davco case of
$1700 per hectare for land in that category. While the reasons are different, I think the
prospect of getting irrigation water in the future could be regarded as similar.
Dry Arable/Grazing Sales
Appended to Mr Eales’ reports were schedules of ten sales, which he referred to as
“grazing sales”. However, they include lands which have the potential for cultivation as dry
arable lands. The evidence shows that only three of those sales are in any way comparable to
the subject lands. For various reasons, the other sales can be rejected:
Sale 1 - An earlier sale of part of the land in Sale 4; Mr Eales conceded that it
can be ignored;
Sales 2 and 3 - Apart from other reasons, those sales which occurred in December
1984 and June 1986 are simply too old;
Sales 5 and 6 - Those sales occurred in July and September 1993, they are in the
Black River area north of Townsville, in a different market environment to the subject
lands;
Sale 7 - The sale of 108.6 hectares near the town of Brandon in July 1993; I accept
that it is more indicative of the value of a grazing rural hobby farm than of the value
of commercial grazing land;
Sale 9 - The sale of 2,291 hectares of low-lying coastal forest tidal flats, with an
extensive ocean frontage for $6,679,500; I accept the evidence that the property had
potential for development quite different to that of the subject land and for that reason it
is not comparable.
That leaves Mr Eales’ Sales 4, 8 and 10. Sales 4 and 10 were also relied on by Mr
Moloney and will be discussed later.
Sale 8 is a property of 633.8 hectares, situated on the Bruce Highway near Giru, which
sold for $540,000, or $852 per hectare, in May 1991. Mr Eales described the land as
timbered gently undulating coastal forest grazing land. Since the sale, it has been selectively
cleared and grassed with improved pastures, and other structural and fencing improvements
effected. He regarded it as having limited potential for “dry arable rainfed cultivation”. It
seems that he regarded the $852 per hectare as a fenced and watered value, but with no timber
treatment. The purchaser used the property principally for grazing and fattening beef cattle.
-- 64 of 78 --
65
Mr Moloney did not rely on that sale, as he did not consider the property to be
comparable to the subject land. He thought it was superior in a number of respects: it was
very well situated, it had a greater potential for subdivision in the future, it had a better
carrying capacity with the potential even greater, it was in a higher rainfall area, it had a
higher component of dry arable land, and it could grow cane. However, despite Mr
Moloney’s concerns, the fact remains that the sale is situated in the same general vicinity as
Lots 42, 43 and 5, and cannot be ignored.
Apart from the two sales that he had in common with Mr Eales, Mr Moloney relied on
the sale of a property from CSIRO to TS and JS Griggs, comprising 15 lots with a total area
of 1,178.533 hectares, in April 1995, for $480,000. It is situated about 44 kilometres south of
Townsville, with three kilometres of unformed access from the Flinders Highway. Physical
access is through a neighbouring property from the Giru-Woodstock Road.
Mr Moloney analysed that sale to show $466,062 treated, fenced and watered, which
he classified as follows:
dry arable land:
32 hectares cleared to cultivation @ $900/ha
146 hectares cleared to grass @ $650/ha
110 hectares pulled and burnt or poisoned @ $550/ha, and
132 hectares without timber treatment or regrown @ $500/ha.
grazing land:
778.5 hectares of coastal forest grazing @ $277/ha.
Overall he concluded that the dry arable and grazing lands on Lots 42, 43 and 5 were
“marginally superior” to those on the sale property, due to their marginally better situation
and country. He felt that it was a fairly good comparison with those lands, but he conceded
that there was a problem with its access.
Mr Eales rejected that sale as a basis of valuation. He was of the opinion that the
property was inferior to the dry arable and grazing lands on Lots 42, 43 and 5; quite apart
from its access problem, it is situated in a different area, related more to the grazing areas of
Thuringowa Shire than the coastal grazing locality of the subject lands.
The two sales common to both valuers were the sale of a property known as “Dingo
Park” and the sale of a property near Gumlu, about 40 kilometres south of Ayr (the Gumlu
sale). “Dingo Park” has an area of 5.199.895 hectares, including 1241.124 hectares of
Special Lease Purchase Freehold. It is situated about 60 kilometres south of Townsville, with
-- 65 of 78 --
66
access by 10 kilometres of formed gravel road from the bitumen sealed Woodstock-Giru
Road. It sold in March 1992 for
$1 million, which Mr Moloney adjusted by adding a further $147,342 for the “payout figure”
of the leasehold land (SLPF).
There is little between the two valuers in their analyses of the sale on a treated, fenced
and watered basis. Mr Eales analysed it to $200 per hectare and Mr Moloney to $202.40 per
hectare. However, Mr Moloney classified the land and attributed a value to each
classification:
arable land:
60 hectares cleared by raking and burning @ $450/ha
45 hectares partially raked and burnt @ $375/ha
600 hectares pulled/parts tordoned @ $300/ha
428 hectares pulled only @ $280/ha
grazing land
355 hectares partially raked but not burnt @ $263/ha
400 hectares pulled/parts formerly tordoned @ $188/ha
2700 hectares pulled only @ $168/ha, and
612 hectares not cleared at $138/ha.
Overall Mr Moloney regarded the dry arable and grazing lands on Lots 42, 43 and 5 as
superior per hectare to those on the sale property, due mainly to their situation.
Mr Eales did not classify the land, but described it as “semi and open forest country
with creek frontages to Majors Creek”. He did not agree with Mr Moloney’s classifications
or the values ascribed to them. “Dingo Park” is situated in the same area as Mr Moloney’s
Sale No 2, and Mr Eales was of the opinion that it also was inferior to the grazing lands on
Lots 42, 43 and 5, because it was in a different area and could not be regarded as coastal
grazing.
On the other hand, Mr Moloney did not think that there was any evidence that a
premium was paid for coastal grazing lands over and above those situated further inland. He
regarded the sale as a good comparison for dry arable and grazing lands. It was a well-
developed, well-watered property, with basically the same carrying capacity as the subject
lands and with potential for pasture improvement.
The other sale relied on by both valuers was a property of 955.2 hectares situated just
north of Gumlu. It was sold in 1993, in either March (Mr Moloney) or July (Mr Eales), for
$460,000 and was analysed by Mr Eales to show $300 per hectare, partly treated, fenced and
watered, and by Mr Moloney to show $288.72 per hectare, treated, fenced and watered. Mr
-- 66 of 78 --
67
Eales described it as open coastal forest country, with a small area of cultivation, while Mr
Moloney classified it as follows:
dry arable:
28 hectares formerly cultivated forest @ $600/ha
56 hectares tordoned and then pushed @ $450/ha
70 hectares tordoned/rung @ $375/ha
346 hectares uncleared arable forest @ $350/ha
grazing
10 hectares tordoned, rung @ $240/ha
442 hectares uncleared forest @ $190/ha
Overall, Mr Moloney regarded the dry arable and grazing lands on Lots 42, 43 and 5 as
superior to those on the sale, because they were better situated; while the sale property was
good grazing land, he admitted that its value was at the lower end of the scale. Mr Eales
regarded it as substantially inferior to the subject lands.
The Value of Dry Arable Land
Mr Eales did not value any of the subject lands as dry arable land, because he felt that
all the arable land had some potential for irrigation from some source. However, he did
express the opinion that if the Court should reject the argument that the arable land should be
valued without potential for irrigation, he would have valued the dry arable land on Lots 42
and 43 at $1550 per hectare cleared to cultivation and at $850 per hectare uncleared, the cost
of clearing to cultivation being $700 per hectare. When asked his opinion of value of similar
land cleared to cultivation on Lot 44, he said $1400 per hectare.
However, when asked a similar question in respect of dry arable land, cleared to
cultivation, without irrigation potential on Lot 5, he replied, “I haven’t really looked at that
particularly, but $850 to $900 a hectare on that property is what I believe the sales, the
grazing sales show me”. If that response was in respect of the question asked, then the values
are totally inconsistent with the values he gave for similar land on Lots 42 and 43. There is
no evidence that the dry arable lands on Lot 5 are in any way inferior to those on Lots 42 and
43. Such values are also inconsistent with the $700 per hectare which he applied to the
uncleared grazing land on Lot 5.
I have come to the conclusion that Mr Eales’ answer was in respect of the uncleared
dry arable value, not the value cleared to cultivation. If the cost of clearing to cultivation of
$700 per hectare is added to the values advanced by Mr Eales, the result is consistent with his
opinion of the value of dry arable land, cleared to cultivation, on Lots 42 and 43.
-- 67 of 78 --
68
Mr Moloney adopted $600 per hectare for uncleared dry arable land on Lot 44 and
$550 per hectare for such land on Lots 42, 43 and 5, probably because they are differently
situated. If the cost of clearing of $700 per hectare is added, Mr Moloney’s values for dry
arable land, cleared to cultivation, would be in the range of $1250 to $1300 per hectare.
The sales do not assist in resolving the differences between the valuers in respect of
the value of dry arable land without potential for irrigation. The Land Appeal Court in the
Davco decision determined the value of dry arable land with Davco irrigation potential at
$1700 per hectare. In so finding, the Land Appeal Court reasoned that in analysing the
decision of the Land Court in Fabrellas, Mr Moloney apportioned $550 per hectare to
uncleared dry arable land and $1241 per hectare to former cultivation (very similar to the
figures above). After considering the other evidence concerning the sales of dry arable land,
the Land Appeal Court concluded that the value of dry arable land without potential for
irrigation from the Davco project would have been greater than the value of the Fabrellas land
($550 per hectare uncleared and $1241 per hectare cleared to cultivation), but something less
than the value of the 1980 Cox sales ($2,150 per hectare to $2,500 per hectare uncleared).
However, the Court made no finding as to the value of dry arable land without potential for
irrigation.
In the circumstances, I propose to adopt Mr Eales’ values of $1400 per hectare for
cleared dry arable land without potential for irrigation on Lot 44 and $1550 per hectare for
such land on Lots 42, 43 and 5.
The evidence is to the effect that there is no such land on Lot 15, as all the potentially
dry arable land is included in the land with irrigation potential.
The Areas of Dry Arable Land
I had some difficulty determining the area of dry arable land without irrigation
potential on Lots 44, 42, 43 and 5. Mr McClurg set out the various areas of each lot which
were suitable for different uses. In respect of “Rainfed Cropping” and “Furrow Irrigation of
Sugarcane” his land suitability tables showed:
Rainfed Cropping Sugarcane (Furrow)
Lot 44 1235.7 hectares 1469.7 hectares
Lot 42 524.6 hectares 961 hectares
Lot 43 671.5 hectares 998 hectares
-- 68 of 78 --
69
Lot 5 767.4 hectares 1170.4 hectares
Mr MacGregor did not determine a separate category for dry arable land. He
concentrated on the land suitable for the furrow irrigation of sugar cane and the trickle
irrigation of horticultural crops. He concluded that the same land could be used for either
purpose.
Mr Eales did not determine a separate area for dry arable land without potential for
irrigation. In his opinion, all the land suitable for sugar cane had some such potential.
However, it seems clear that when he gave his opinion of the value of dry arable land, he was
referring to those areas which he valued as land suitable for growing sugar cane, with
potential for irrigation. He admitted that he was not a soils expert and for the suitability of
various soils, he had relied on the two experts, principally the report of Mr MacGregor, but he
also had regard to Mr McClurg’s report.
Mr Eales valued Lots 42 and 43 together, so the area of potential irrigable arable land
on both lots amounts to 1781 hectares; and for Lot 44 for that classification valued 1247.43
hectares, while for Lot 5, he valued 1204 hectares. Those areas exceed the areas of “rainfed
cropping” calculated by Mr McClurg. Mr Moloney adopted Mr McClurg’s areas for rainfed
cropping.
Reference to the soil suitability maps shows that to a large degree the areas suited to
furrow irrigation of sugar cane and those suited to rainfed cropping are the same land.
It would seem that suitability for dry land farming depends at least to some extent on
soil moisture retention ability, but avoiding excessively wet areas. Barratta clays seem to be
amongst the most suitable. However, the areas suited to rainfed cropping (dry arable) are, on
each of the four lots, smaller than the areas suited to furrow irrigated sugar cane. From Mr
McClurg’s evidence, the inference can be drawn that there are areas of land which are suited
to growing irrigated sugar cane, which are not suited to rainfed cropping. Mr MacGregor did
not address this issue.
In the circumstances, I am not convinced that the total areas on those three lots which
Mr Eales considers should be valued as dry arable land with potential for irrigation, should
also be considered as suitable for dry farming. In the absence of any evidence to the contrary,
I will adopt the areas calculated by Mr McClurg as suitable for rainfed cropping (dry arable):
Lot 44 1235.7 hectares
Lot 42 524.6 hectares
Lot 43 671.5 hectares
Lot 5 767.4 hectares
-- 69 of 78 --
70
Determination of Compensation
Applying the findings I have made in respect of each of the subject lands,
compensation is determined by arriving at the value of each lot as fully economically
developed at the date of resumption, and then deducting the cost of achieving that state of
development. In making these calculations, I will adopt the development costs used by Mr
Eales.
Lot 44 - 1,817.577 ha
Value fully economically developed (treated, fenced and watered):
57 hectares irrigable arable land (from the WRC water
allocation policy of 0.25 megalitres/ha) @ $6,000/ha $ 342,000
57 hectares irrigable arable land (because of the finding of an
increase in water allocation by a further 0.25 megalitres per
hectare by date of resumption) @ $6,000/ha $ 342,000
50 hectares dry arable land with potential for irrigation from the
dam/drain @ $3,000/ha $ 150,000
114 hectares dry arable land with potential for increase in the
future of water allocation policy by a further 0.5 megalitres per
hectare @ $1700/ha $ 193,800
1072 hectares dry arable land without potential for irrigation
@ $1400/ha $1,500,800
(Balance of the total of 1236 hectares dry arable land,
less the land with irrigation potential, of 164 hectares)
Grazing lands:
468 hectares grazing land similar to the lands the subject of
the Davco decision @ $400 per hectare $ 187,200
Value fully economically developed (TFW) $2,715,800
Development required to bring Lot 44 to fully economically
developed (TFW)
At the date of resumption approximately 45 hectares
had been cleared to cultivation, approximately 575 hectares
had been cleared and burnt, but with light regrowth, while
a further 20 hectares had been pushed, but with regrowth.
An equipped irrigation bore was situated near the southern
boundary with power connected and, presumably, a haul-out
road constructed.
Therefore, a further 69 hectares would need to be
-- 70 of 78 --
71
developed to the standard of laser levelled cultivation at
$800 per hectare $ 55,200
That leaves 506 hectares, of the 575 hectares
which had been cleared and burnt, to be developed
to dry arable standard at a cost of $500/ha. $253,000
That would leave a further 730 hectares to be
developed to dry arable standard at a cost of $700 per
hectare. $511,000
The grazing area would require no timber treatment.
No further allowance need be made as there was
already an irrigation bore, power and a haul-out road.
Total development required to bring Lot 44 to
fully economically developed (treated, fenced and watered) $ 819,200
Therefore compensation payable for Lot 44 is assessed at $1,896,600
Lot 15 - 344.5 hectares
Value fully economically developed (treated, fenced
and watered):
11 hectares irrigable/arable land (in accordance with
WRC water allocation policy) @ $6,000/ha $ 66,000
11 hectares irrigable arable land (because of the finding of an
increase in water allocation by a further 0.25 megalitres
per hectare by date of resumption) @ $6,000/ha $ 66,000
289 hectares of land with potential for increase in the
future of water allocation policy of a further 0.5
megalitres per hectare (22 ha) and the balance (267ha)
from the Davco scheme, @ $1700/ha $ 491,300
34 hectares grazing land (similar to Davco lands)
@ $400/ha $ 13,600
Value fully economically developed (TFW) $ 636,900
Development required for full economic development (TFW):
At the date of resumption approximately 256 hectares
had been cleared, stick raked and burnt, with light regrowth.
To bring 22 hectares to laser levelled cultivation would cost
$800 per hectare.
22 hectares @ $800/ha = $ 17,600
-- 71 of 78 --
72
That leaves 234 hectares of the 256 hectares of cleared land
to be developed to cultivation, which would cost $500/ha.
234 hectares @ $500/ha $ 117,000
The remaining 55 hectares (of the 311 hectares with
irrigation potential) would cost $700 per hectare to
bring to dry arable standard. 55hectares @ $700/ha = $ 38,500
The total development required to bring Lot 15
to full economical development (TFW) $ 173,100
Therefore, compensation payable for Lot 15 is assessed at $ 463,800
Lot 42 - 1,328.178 hectares.
Value fully economically developed (treated, fenced
and watered):
42 hectares irrigable arable lands (in accordance with WRC
water allocation policy) @ $6,000/ha $ 252,000
42 hectares irrigable arable land (because of the finding of
an increase in water allocation of a further 0.25 megalitres
per hectare by date of resumption) @ $6,000/ha $ 252,000
83 hectares dry arable land (with potential for increase in
the future of a further 0.5 megalitres per ha) @ $1700/ha $ 141,100
442 hectares dry arable land, without potential for irrigation
(balance of the 525 hectares of dry arable land less land with
irrigation potential 83 hectares) @ $1,550/ha $ 685,000
719 hectares grazing land (superior to Davco lands
and Lot 44) @ $500 /ha $ 359,500
Value fully economically developed (TFW) $1,563,600
Development required for full economical development (TFW):
At the date of resumption about 41 hectares had been
pulled, with moderate to heavy regrowth and a further 15
hectares had been cleared to grass. To bring the pulled area
to laser levelled cultivation would cost $800 per hectare.
42 hectares (say) at $800 per hectare $33,600
To bring the remaining 15 hectares of cleared
land to laser levelled cultivation would cost $500/ha.
15 hectares @ $500 per hectare $ 7,500
To bring another 27 hectares of uncleared
land to laser levelled cultivation would cost
-- 72 of 78 --
73
$1000 per hectare. 27 hectares @ $1000/ha $ 27,000
To bring 525 hectares of uncleared
dry arable land to cultivation would cost $700 per
hectare. 525 hectares @ $700/ha $367,500
In addition, a bore must be sunk, power provided and
a haul-out road constructed at a cost of at least $50,000. $ 50,000
Therefore, the total development cost required to
bring Lot 42 to full economical development (TFW) $485,600
Therefore, compensation payable for Lot 42 is assessed at $1,078,000
Lot 43 - 1,328.178 hectares.
Value fully economically developed (treated, fenced and
watered):
42 hectares irrigable arable land (in accordance with WRC
water allocation policy) @ $6,000 per hectare $ 252,000
42 hectares irrigable arable land (because of the finding of
an increase in water allocation of a further 0.25 megalitres
per hectare by date of resumption) @ $6,000 per hectare $ 252,000
83 hectares dry arable land (with potential for increase in
the future of a further 0.5 megalitres per hectare)
@ $1,700 per hectare $ 141,100
589 hectares dry arable land, without potential for irrigation
(balance of the total area of dry arable land of 672 hectares
less 83 hectares with irrigation potential) @ $1550 per
hectare $ 912,950
572 hectares grazing (superior to Davco lands and Lot 44,
but similar to Lot 42) @ $500 per hectare $ 286,000
Value fully economically developed (TFW) $1,718,050
Development required to bring Lot 43 to full
economical development (TFW):
At the date of resumption approximately 159
hectares had been pulled, with moderate to heavy regrowth,
and 6 hectares cleared to grass. To bring 84 hectares of the
pulled area to laser levelled cultivation would cost $800
per hectare.
84 hectares @ $800 per hectare $ 67,200
To bring the balance 81 hectares of cleared
country to dry arable cultivation would cost $500 per hectare.
-- 73 of 78 --
74
81 hectares @ $500 per hectare $ 40,500
To bring 591 hectares of uncleared land to
dry arable land cultivation would cost $700 per hectare.
591 hectares @ $700 per hectare $ 413,700
In addition a bore must be sunk, power
provided and a haul-out road constructed at a cost
of at least $ 50,000
Cost of total development required in Lot 43 to
full economical development (TFW) $ 571,400
Therefore, compensation payable for Lot 43 is assessed at $1,146,650
Lot 5 - 1781.831 hectares.
Value fully economically developed (treated, fenced and
watered):
56 hectares irrigable arable land (in accordance
with WRC water allocation policy) @ $6,000 per hectare $ 336,000
56 hectares irrigable arable land (because of the finding of an
increase in water allocation of a further 0.25 megalitres
per hectare by date of resumption) @ $6,000 per hectare $ 336,000
111 hectares dry arable land (with potential for
increase in the future of a further 0.5 megalitres per hectare)
@ $1700 per hectare $ 188,700
656 hectares dry arable land without potential for irrigation
(balance of the total dry arable land of 767 hectares less
111 hectares with irrigation potential) @ $1550 per hectare $1,016,800
903 hectares grazing (superior to Lots 42 and 43) @ $600 per ha $ 541,800
Value fully economically developed (TFW) $2,419,300
Less development required to bring Lot 5 to full economical
development (TFW):
At the date of resumption about 78 hectares
had been pulled, part stick-raked and burnt, but with
some regrowth. It would cost $800 per hectare to bring
that land to laser levelled cultivation.
78 hectares @ $800 per hectare $ 62,400
To bring the remaining 34ha of irrigable arable
uncleared land to laser levelled cultivation would cost
$1000 per hectare. 34 hectares @ $1000 per hectare $ 34,000
To bring the 767 hectares of dry arable
land to cultivation would cost $700 per hectare $ 536,900
In addition a bore must be sunk, power
provided and a haul-out road constructed at a cost of
-- 74 of 78 --
75
at least $50,000. $ 50,000
The total development required to bring Lot 5
to full economical development (TFW) $ 683,300
Therefore, compensation payable for Lot 5
is assessed at $1,736,000
Disturbance
Valuation and Legal Fees
During the hearing the parties agreed to the claims for legal fees as set out in the
respective amended claims. These may be summarised as follows:
Lot 44 - $1500, paid 19 January 1998.
Lot 15 - $1000, not paid.
Lots 42 & 43 - $1500, paid 19 January 1998.
Lot 5 - $1000, paid 19 January 1998.
However, the claims for valuation fees were not resolved. These claims were as
follows:
Lot 44 - $4514, paid as to $2257 on 19 August 1993.
Lot 15 - $2500, not paid.
Lots 42 & 43 - $9028, paid as to $2257 on 19 August 1993.
Lot 5 - Nil, no valuation made.
There was some confusion about the basis for those fees. When cross-examined about
them, Mr Eales said the valuation fee for Lot 15 was in accordance with the standard fee
recommended by the AIVLE, while the fees for the valuations of Lots 42, 43 and 44 were
“twice the standard fee”. When re-examined, he explained that he made a single valuation
report for Lots 42, 43 and 44, with fees split one-third to each. He then went on to say, “They
are generally in line with the recommended scale of fees”.
From that I infer that Mr Eales based his fee of $13,542 on the total of the valuations
of those three lots then, for the purposes of these claims, apportioned one-third to each
regardless of quantum. Since he valued Lot 42 and Lot 43 together, the apportionment for
them was two-thirds.
While the AIVLE recommended Scale of Fees makes provision for charging twice the
standard fees for valuations for compulsory acquisition, a perusal of the Scale of Fees as at 1
January 1992 indicates that the fees charged by Mr Eales do not exceed the recommended
standard fees.
-- 75 of 78 --
76
The respondent has not agreed to the claims for valuation fees, but has not argued the
matter. It may be because the claims for compensation were substantially amended on the
first day of hearing. However, it has been the practice of this Court to award reasonable
valuation fees necessarily incurred in the lodgment of compensation claims. Mr Eales gave
evidence that the valuations were made for the purpose of assisting the claimants in lodging
their claims for compensation, except of course for Lot 5, in respect of which, for some
reason not explained, no valuation was made. Mr Eales’ evidence was not challenged, nor
any alternative fees suggested. The fact that the valuations were substantially amended and
that the fees have not been paid in full, are matters for the claimants and Mr Eales, and not for
this Court.
The claimants are entitled to the award of reasonable valuation fees as claimed.
Lot 44 $ 4,514
Lot 15 $ 2,500
Lot 42 $ 4,514
Lot 43 $ 4,514
Interest
Under the provisions of section 28 of the Acquisition of Land Act 1967, the Court has
a discretion to award interest on compensation determined. In these cases there was no
argument or submissions concerning interest. Therefore, I propose to follow the usual
practice of this Court and award interest on compensation determined in each case.
Orders
Lot 44
In this case I determine compensation payable by the respondent to the claimant under
all heads of claim at One million, nine hundred and two thousand, six hundred and
fourteen dollars ($1,902,614) (made up of loss of land, $1,896,600, legal fees $1500 and
valuation fees $4514).
The respondent is also ordered to pay to the claimants interest at the rate of 8.75
percent per annum on $1,896,600 from the date of resumption, 22 December 1990, up to and
including the day immediately preceding the date upon which payment of compensation is
made.
-- 76 of 78 --
77
The respondent is further ordered to pay to the claimants interest at the rate of 7.75
percent per annum on $2,257 from 19 August 1993 up to and including the day immediately
preceding the date upon which payment of compensation is made.
Lot 15
In this case I determine compensation payable by the respondent to the claimant under
all heads of claim at Four hundred and sixty-seven thousand, three hundred dollars
($467,300)(made up of loss of land $463,800, plus legal fees $1000 plus valuation fees
$2500).
The respondent is also ordered to pay interest at the rate of 8.25 percent per annum on
$463,800 from the date of resumption (7 September 1991) up to and including the day
immediately preceding the date upon which payment of compensation is made.
Lot 42
In this case I determine compensation payable by the respondent to the claimant under
all heads of claim at One million, eighty-three thousand, two hundred and sixty-four
dollars ($1,083,264) (made up of loss of land $1,078,000, legal fees $750 and valuation fees
$4,514).
The respondent is also ordered to pay the claimants interest at the rate of 8 percent per
annum on $1,078,000 from the date of resumption (18 December 1992) up to and including
the day immediately preceding the date upon which payment of compensation is made.
The respondent is further ordered to pay to the claimants interest at the rate of 7.75
percent per annum on the amount of $1,128.50 from 19 August 1993, up to and including the
day immediately preceding the date upon which payment of compensation is made.
Lot 43
In this case I determine compensation payable by the respondent to the claimant under
all heads of claim at One million, one hundred and fifty-one thousand, nine hundred and
fourteen dollars ($1,151,914) (made up of loss of land $1,146,650, legal fees $750 and
valuation fees $4,514).
The respondent is also ordered to pay to the claimants interest at the rate of 8 percent
per annum on $1,146,650, from the date of resumption (18 December 1992) up to and
including the day immediately preceding the date upon which payment of compensation is
made.
The respondent is further ordered to pay to the claimants interest at the rate of 7.75
percent per annum on the amount of $1,128.50 from 19 August 1993, up to and including the
day immediately preceding the date upon which payment of compensation is made.
Lot 5
-- 77 of 78 --
78
In this case I determine compensation payable by the respondent to the claimants
under all heads of claim at One million, seven hundred and thirty-seven thousand dollars
($1,737,000)(made up of loss of land $1,736,000, and legal fees $1,000).
The respondent is also ordered to pay to the claimant interest at the rate of 7.75
percent per annum on $1,736,000, from the date of resumption (5 November 1993) up to and
including the day immediately preceding the date upon which payment of compensation is
made.
I give the parties liberty to apply on five days’ notice to the other in respect of any of
the compensation and interest calculations.
(JJ Trickett)
President of the Land Court
-- 78 of 78 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1998/141