Congress Community Development and Education Unit Limited v Director-General, Department of Transport [1998] QLC 32
LAND COURT
BRISBANE
13 March 1998
Re: Determination of Compensation -
Resumption for future road requirement purposes -
Acquisition of Land Act 1967 and
Transport Infrastructure (Roads) Act 1991 -
Ref. A97-09.
Congress Community Development and Education Unit Limited
v.
Director-General, Department of Transport
(now Department of Main Roads)
J U D G M E N T
Falling for determination is compensation consequent upon the resumption by the
Director-General, Department of Transport, on 11 March 1994, for future road requirement
purposes of land described as part of Lot 3 on Plan 818236, County of Elphinstone, Parish of
Coonambelah, containing an area of 2.788 hectares. The resumed land is part of a 31.81
hectare parent parcel which is situated in Herveys Range Road in the City of Thuringowa and in
the suburb of Condon. At the date of resumption, the zoning of the parent parcel under the
provisions of the Thuringowa Town Planning Scheme was "Special Facility (Educational,
Cultural, Recreational and Associated Accommodation)". The parent parcel was, at the date of
resumption, subject to an access Easement A on RP 744340 in favour of Lot 1 on RP 744340
(which is an 8,496 square metre parcel located internally within the parent parcel and which is
also owned by the claimant company) with an area of approximately 1.01 hectares, and
Easement D on RP 840418 (which is a stormwater drainage easement traversing along and
adjacent to the whole of the eastern boundary of the parent parcel) with an area of
approximately 2.913 hectares. The resumed parcel is almost regularly shaped and adjoins the
whole of the southern boundary of the parent parcel. The land was resumed by the respondent
Director-General for the future construction of what has become known as the Townsville
Bypass Road which runs westerly from the southern Townsville suburb of Annandale across the
Ross River, through the suburb of Condon and then in a north-westerly direction linking up with
the Bruce Highway to the north-west of Townsville in the suburb of Deeragun.
At the date of resumption, the dispossessed owner company was in the process of
developing an education facility on the parent parcel known as "Shalom Christian College", the
stated philosophy and site environment of which is to address the special requirements of the
[1998] QLC 32
-- 1 of 40 --
2
education of Aboriginal and Islander children.
Under cover of a letter dated 9 January 1997, the Acting Crown Solicitor, acting on and
behalf of the respondent Director-General, Department of Transport, filed in the Land Court
Registry a claim for compensation dated 27 April 1996 which had been served upon him by
Congress Community Development and Education Unit Limited. The particulars of the claim
which was in the sum of $3,621,340 are:
Loss of Land $ 364,000
Severance
Loss Road Access
Extra Road Works $ 18,000
Internal Fencing $ 22,000
Screening $ 60,000 $ 100,000
Injurious Affection
Allowance Air Conditioning Dormitory $636,000
Sinking Fund Maintenance & Running
Costs $2,300,000
Additional Housing Construction Costs $200,000 $3,136,000
Disturbance
Architect Fees to redesign scheme and
building $3,500
Architect Fees in preparation of claim $3,000
Quantity Surveyors Fees in preparation of
claim $2,700
Engineers Fees in preparation of claim $1,740
Consulting Acoustic Engineers Fees in
preparation of claim $ 900
Legal Fees in preparation of claim $1,500
Valuation of property, research, co-ordination
and preparation of Report $8,000 $21,340
TOTAL CLAIM $3,621,340
At the outset of the hearing of the matter, Counsel for the claimant sought and obtained
leave to amend the claim for compensation to the sum of $1,646,295 made up as follows:
Heads of Claim
(i) Land 2.788 ha (approx $55,000 ha) $154,000.00
(ii) Construction of buffer wall
4m high on 1.5 mound 700,000.00
-- 2 of 40 --
3
(iii) Loss in value to remaining land by presence of buffer wall 89,000.00
(iv)Land for buffer wall 515m x 16m x 1/2 = .412 ha @ $55,000 ha 22,700.00
(v) Disturbance to ambience/concept 20,000.00
(vi) Architects costs for design changes 4,000.00
(vii) Cost to air-condition G/F 3 dormitory units 88,240.00
(viii) Loss of profitability 449,075.00
(ix) Interest on $285,700 @ 7.4% x 3.75 yrs 79,280.00
(x) Costs 40,000.00
$1,646,295.00
At a much later stage during the hearing, virtually at the end of the claimant's case, the
claim for compensation was further and finally amended to the sum of $1,387,340 based on the
following particularisation:
Heads of Claim
1. Value of land resumed at 11.3.94 (i) $154,000
2. Cost to construct buffer wall
• 4m high on mound 1.5m - as at 3.10.95
$595,000 488m = $1220 m
•cost at 11.3.94 - less 4% = $1170 m
•Length of wall 515m - 150m + 10m = 375m
•Cost of construction 375 m as at 11.3.94
375 x $1170 = $438,750
• 2.5m high as at 3.10.95 = $280m
•Cost of 11.3.94 less 4% = $270m
• Length of 2.5m high wall 75m + 150m = 225m
•Cost of construction 225 m as at 11.3.94
225 x $270 = $60,750
• Total cost of wall at 11.3.94
$438,750 + $60,750 = $499.500 say (i) $500,000
• (Discount for deferred expenditure 1994 to 2010
16 years @ 5% offset by allowance for escalation
@ 5 - 7.5%)
3. Loss in value to remaining land by presence of
buffer wall $89,000 deferred 16 yrs @ 5%
$89,000 x .458 = $40,762 say (i) $41,000
-- 3 of 40 --
4
4. Land for buffer wall
375 m x 16 m x 1/2 = .3 ha @ $55,000 ha = $16,500
deferred 16 years x .458 = $7,557 say (i) $ 8,000
5.Disturbance to ambience/concept (i) $ 20,000
6. Architects' costs for re-design $ 4,000
7. Cost to air condition G/F
3 Dormitory units - 1994 (i) $124,000
(Discount for deferred expenditure offset by
allowance for escalation)
8. Loss of profitability $498,037
deferred from 1994 to 2002 - 8 yrs
$498,037 x .677 = $337,171 say (i) $337,000
9. Interest on $1,188,000 @ 5% x 3.75 yrs = $178,200 say $178,000
10. Costs $21,340
$1,387,340
Note: (i) denotes that interest has been applied to this claim.
Before outlining the evidence upon which the litigants rely in the proceedings, I should
perhaps now indicate the extent of the dispute as to the quantum of compensation this is
sufficiently illustrated by revealing that the respondent Director-General, through practising
Registered Valuer Chris Caleo, assesses compensation for the resumption of the land, exclusive
of any of the claim for disturbance items (shown in the finally amended claim as costs), in the
sum of $128,000.
As has tended to be in cases involving the determination of compensation claims of
recent years in this Court, the hearing was lengthy, occupying seven sitting days. The transcript
runs to 435 pages. Evidence was called in person by the claimant from:
Rev. Shayne Francis Blackman, Minister of the Uniting Church and Chairman of the claimant
company;
Alan Ernest Randell, the First Principal of Shalom Christian College (from early 1991 to
December 1995);
Jeffrey Prehn Lowe, a Registered practising Valuer;
Anthony Russell Brown, a Registered Professional Engineer and Principal Consultant and
Associate of Ron Rumble Pty Ltd;
John Ernest Neilsen, a Quantity Surveyor;
Jon Alan Kuskopf, a practising Architect;
Kenneth Robert Crane, a Chartered Accountant;
-- 4 of 40 --
5
Neville Ross Marsh, Executive Officer in the employ of the claimant company;
and Stephen Doran, a Building Services Engineer in the employ of Connell Wagner Pty Ltd.
In addition, the claimant called telephone evidence from Sir Roland Darling Wilson,
former Judge of the High Court of Australia and who has had a long association with the
education and wellbeing of Aboriginal People, and from M/s Julia Glennie Koppe, who holds a
Bachelor of Education Degree and is currently working on a Ph.D., a Doctorate in Aboriginal
Education.
The respondent Director-General called evidence from six witnesses. They are:
Mr Caleo (introduced earlier in this judgment);
Frederik Hendrik Kamst, an Environmental Acoustic Consultant;
Raymond Charles Hall, a practising Architect;
Colin Bruce Horman, a Civil Engineer and Town Planner in the employ of the
respondent;
Philip Alexander George Dance, a practising Town Planner; and
Douglas Francis Hannah, a practising Accountant.
It is profitable for me to indicate here that, in general terms, it is the case for the claimant
that the resumption of the land along the southern boundary of the Shalom Christian College
land for the construction of what is proposed to be ultimately a 4-lane Townsville Bypass Road
has a severely deleterious effect on the operation of a college. It is said that not only does the
resumption cause loss of land, thereby restricting the ultimate development of the college, but
will result in the need for the college to take traffic noise amelioration measures to preserve the
ambience of the college in general and in particular for the occupation by college residents of
existing accommodation blocks and in accommodation buildings not yet constructed but
planned at a site location in close proximity to the bypass road. To obviate, or to lessen the
anticipate road noise problems, it is claimed that there is a need to construct at the claimant's
expense a noise amelioration block wall on an earth mound near the whole length of the
resumption boundary with return block walls to be constructed on part of both the eastern and
western boundaries. In addition to the construction of this wall, it is claimed that there will be a
need to install airconditioning in the ground floor of three dormitory units proposed for
construction in proximity to the bypass as part of the ongoing development of the college. On
the other hand, the respondent Director-General does not see the need for any noise amelioration
measures to be taken by the claimant, and does not consider there to be any assessable
compensation in respect of any claimed loss other than the value of the land resumed, along
-- 5 of 40 --
6
with certain agreed disturbance claim items.
Now as is always the case in extended trials of this nature, it is not meaningful, or
perhaps even possible if I am to restrict the text of this decision to reasonable proportions, to
cover all aspects of the evidence called by the parties. I propose to restrict reference to such
part of the evidence which I find helpful in assisting me in my task of the determination of
compensation.
EVIDENCE FOR THE CLAIMANT
Reverend Blackman told us that he has been involved with the concept of Shalom
Christian College from its inception and indeed was involved with the purchase of the land
which was acquired for the purpose of developing an educational complex directed towards the
education of persons of Aboriginal and Islander extraction. He informed us that when the
land was purchased in 1989, the College Board was informed that there was a proposal that
there might be a bypass road around the rear of the site, but there was nothing set in concrete at
that time which indicated that it was going to be constructed.
Reverend Blackman says that when the land was purchased it was virtually all chinee
apple bushes with plenty of wallabies, black and white cockatoos, snakes and all kinds of
animals on it and it was intended to develop the college in that type of environment by retaining
the open atmosphere of the property so that when students arrived at the college they would be
in a familiar environment. It was proposed to retain this environment while building a
community around it.
Reverend Blackman says that facilities provided at the school were not merely for
school children but also for families of students and elders as well. At present there is
accommodation for a preparatory class, through primary school and secondary school where
students are now educated to Year 11 level. College facilities are provided for both day
students and boarders. The elders accommodation was designed to cater for about 110 persons,
family home accommodation is to cater for 140 people and the pre-school, primary school and
secondary school requirements are for 650 students. Tertiary accommodation is to provide for
120 students in four dormitories, and staff accommodation is to be for 200 persons. Among
buildings remaining to be completed are one dormitory building (known during proceedings as
"Building B3" on the master plan) and the four tertiary accommodation buildings. Reverend
Blackman told us that although the college has had knowledge of the position of the bypass road
now for some time, it is still intended to build Building B3 and the four tertiary board buildings
in the planned position shown on the Master Plan, notwithstanding that these buildings will be
in relatively close proximity to the future bypass road. Reverend Blackman can see no practical
alternative to their construction as planned, since to start to move the buildings around would
-- 6 of 40 --
7
result in the college having to reshape its whole direction.
Also planned for construction is family housing which again is to be located as shown
on the master plan, and some of these buildings will also be in close proximity to the proposed
road. Reverend Blackman believes that the resumption of the land for the bypass road, which
equates approximately 10% of the parent land parcel, takes away an area where
students use the land to escape from the boarding and school activities and where they spend
time wandering around out in the open or around the trees. He naturally expressed the view
that the college preference would be that the road does not go there at all. Further, it is
suggested by Reverend Blackman that it well may be that the college cannot accommodate the
number of people originally planned for it due to the lost area of land, and this means that the
college will still have to provide the same resources for a lesser number of people - such as
dormitories, dining rooms and classrooms.
Reverend Blackman told us that the cost of capital works carried out on the college to
date is close to $13 million. He can see no practical alternative to overcoming the problems
which will result from the use of the bypass road by vehicular traffic other than construction of a
wall for the full distance of the college's southern boundary. The Board has not been able to
identify any alternative to the particular situation to this point of time. Reverend Blackman
does not favour building a wall at all which he says will be forced upon the college by the
resumption. Reverend Blackman also suggests there will be a need to aircondition the
proposed accommodation buildings to cope with the blocking of the breezes in the event of the
construction of the wall.
Sir Ronald Darling Wilson informed the Court by telephone that he was the Foundation
Patron of Shalom Christian College and that the college was first floated in 1989. Sir Ronald's
attraction to the college was that it was quite unique as a visionary concept of aboriginal
education in the holistic sense in that it involved understanding the aspirations of many
indigenous people, being a school which was very much an integral part of the wider
community. Sir Ronald regards Shalom College as a unique educational and community
facility and one to which its land is particularly important. Although the college land might be
seen to be very generously endowed in size, the prospects of community growth and
development with adventurous thinking and plans, makes what land is available fairly precious
and this would probably explain the particular concern that the college has about the
resumption.
Sir Ronald believes that the use of the future bypass road by vehicular traffic would
certainly disturb the college developments in that part of the complex, especially as he has been
told that the future road would be in the vicinity of boarding house facilities and that up that end
of the complex there would certainly be adverse consequences from a major highway on a
-- 7 of 40 --
8
major traffic facility nearby.
Sir Ronald believes that the erection of a noise amelioration wall such as proposed by
the college (a 4 metre high brick wall on a 1½ metre earth mound) along the entire length of the
resumption line would give the appearance of the college site being shut in. He had not heard
of this proposal until it was suggested to him on the telephone during this case, but his
immediate feeling was to people who have been identified with wide open spaces, the wall
would immediately create an inhibitory enclosed feeling simply by being there and shutting off
the site, this notwithstanding its objective to ameliorate the traffic noise.
Mr Randell was involved in the establishment of the college from the outset, having
been appointed its first Principal in 1991. He departed the college in December 1995 to make
way for its first Aboriginal Principal, but since retiring he has continued his involvement with
education issues concerning indigenous people.
Mr Randell told us that there are major differences in the educational requirements for
indigenous persons when compared with non-indigenous persons, particularly with indigenous
persons from remote or isolated regions. For these persons, Mr Randell says for education to
be fully effective it should be conducted in what he calls "a retreat atmosphere" since this is the
cultural approach to indigenous education. Mr Randell says that whilst noise, congestion, fast
traffic movement and exhaust pollution will be disruptive to all education, the effect upon
indigenous education will be compounded many times since children and young persons
coming from isolated locations do not cope with a pressurised environment.
Mr Randell told us that it was with this educational requirement in mind that the layout
of Shalom College was designed and the sense of space is vital. Further, he says that for
children coming from dysfunctional communities the effect of traffic noise, a congested living
environment, rapid traffic movement and vehicular pollution will have a greatly exaggerated
effect on the capacity of these children to learn, or even to remain at the college. Mr Randell
told us that all indigenous persons moving away from their familiar open environment will
experience an acute sense of homesickness and to assist in its control it was necessary to create
the "complete community" concept where communal support was available.
Mr Randell stresses that the presence of a highway (bypass road) along the southern
boundary of the college will be severely damaging to the whole concept of it, and the
construction of the proposed buffer wall would also be severely damaging to its concept and
will have a detrimental effect on the indigenous college occupants be they day students or
boarders.
M/s Koppe was asked by the claimant company to give telephonic evidence in the
matter. She is the author of a paper titled "Palm Island Community and the Demand for
Secondary School Boarding Facilities" which was produced by her late in 1992 and which was
introduced in evidence. In her paper, M/s Koppe says she was asked by the Board of Shalom
-- 8 of 40 --
9
Christian College to provide some documentation of the demand for secondary boarding places
by parents and students in the Aboriginal Community. She limited her focus to the Palm Island
community which she knew very well. Her research and involvement with education on Palm
Island extends over a period of 24 years. After discussing the situation with education on Palm
Island, M/s Koppe offered the view that the Aboriginal and Islander group which made the
original decision to found Shalom Christian College did so because of great concern over the
failure of schooling to equip children adequately for life and employment in their communities
and community organisations. It is also M/s Koppe's understanding that Shalom Christian
College was conceptualised initially by Aboriginal and Islander People with the needs of
Aboriginal and Islander students, communities and community organisation in mind. She told
us that she is very familiar with the Shalom College layout and its facilities.
In evidence is a report from Kennedy Consultants Pty Ltd under the hand of M/s
Jacqueline Downs, who is a psychologist, who was asked to provide the college with advice
about the effects of the resumption on it and its students. M/s Downs says in the report that it
appeared that the college had been thoughtfully developed, being particularly sensitive to the
environmental needs of Aboriginal boarding students. M/s Downs advises that the physical
environment is important for the development and maintenance of self identity, and the
adaptation of persons to a new setting such as a boarding school depends partly on personal
environment congruence. She says that incongruence may manifest as homesickness, with
severe or continuous homesickness having been associated with low self esteem, depressive
symptomatology and non-productive coping. M/s Downs recommends that to minimise
homesickness, professional landscaping be considered for the proposed perimeters of the
college land in order to preserve the illusion of space. M/s Downs recommends that due to the
resumption and the use of the proposed bypass road construction, although inconsistent with the
concept of natural ventilation, it will be necessary to install airconditioning in existing and
proposed dormitories in order to provide a stable environment for study and quiet time. She
also suggests that double-glazing of windows would also add to the concept of spaciousness by
allowing visual access to the natural environment without the distraction of noise and fumes.
M/s Downs is of the opinion that, on the basis of research evidence, a view can be taken that the
land resumption necessitates suitable compensation, an opinion which I feel perhaps does not
come within her field of expertise. But she is qualified to make the point that without adequate
provision for a quiet, acceptable environment, students' psychological wellbeing may be at risk.
It is to be noted that M/s Downs was not called in evidence by the claimant. The opinions
expressed by correspondence are accordingly of no probative weight.
Mr Lowe described the parent Shalom parcel as being reasonably flat land with a
gradual fall to the north, and situated within three kilometres of the Thuringowa City Council
Chambers. A major shopping centre, private and State schools, playing fields and parklands
-- 9 of 40 --
10
are located within two kilometres and the James Cook University within 10 kilometres.
Immediately to the north of the parent parcel across Herveys Range Road is the Brothers' Rugby
Club and associated playing fields and further to the north is a residential estate known as "The
Willows" which has been under development since the late-1970s. To the south there are two
residential estates known as "Orchard Ridge" and "The Palms" which are also being developed.
Mr Lowe told us that at the time of resumption, the college was in its third year of
operation and the development consisted of:
Yalga-Binbi Institute - existing house converted for this use (this building is not on the parent
parcel but on a separately surveyed site serviced by the internal access easement.
Five primary school buildings.
Six secondary school buildings.
Two storey buildings for 32 boarders.
Dining Room.
Headmaster's residence.
Four buildings under construction for hostel/retirement village.
Ground improvements including two ovals, an open drain, irrigation system and
access roads.
Mr Lowe says that since the date of resumption, further works have been carried out
towards completing the college development.
Mr Lowe originally assessed compensation for the resumed land in the sum of $173,000
by what he says is the process of a "before and after" valuation. But it seems to me that he
originally valued the resumed land itself at the rate of $62,025 per hectare without a "before and
after" valuation approach. Mr Lowe claimed originally that the resumed land had a special
value to the owner and suggested that the value of $173,000 should be doubled to reflect the
value to owner, but his assessment of special value was later abandoned. Indeed, his valuation
of $173,000 for the resumed land was also abandoned during the case in favour of a valuation of
$154,000 (at the rate of $55,000 per hectare) based on a "before and after" valuation as follows:
Value before resumption 31.81ha @ $62,024 per ha - $1,973,000
Less value after resumption - 29.02ha @ $62,680 per ha - $1,819,000
Value of land resumed $ 154,000
It seems the reason Mr Lowe has applied the higher valuer per hectare in the "after"
resumption situation is because in the post resumption situation there is no longer a need to
make a capital allowance in the valuation for the construction of Smith Road.
-- 10 of 40 --
11
Mr Lowe cited six sales of land as a basis for his valuation, but obviously the most
comparable of those are those of two parcels of en globo land in close proximity to the subject
land. They are:
"Willows Estate" - Lot 4 on RP 808592 and Lot 410 on RP 869267 - 105.6ha - Kern
Grazing Pty Ltd (in receivership) to Defence Housing Authority on 20.05.94 for $5,570,000 - or
$52,746 per hectare.
Mr Lowe has analysed this sale to show a value of $73,256 per hectare after deducting
an area of 0.56 area for a powerline easement and an area of 10.4 hectares for a future drainage
reserve, and adding to the sale price an allowance of $800,000 for a major outfall drain and
$560,000 for an access bridge which has been constructed over the drain.
Mr Lowe told us that pursuant to the subdivisional scheme for residential development
of "The Willows" estate by the vendor, there were some 778 lots remaining to be subdivided.
He says the purchaser was aware of the Council requirements for it to provide drainage reserves
and to complete the construction of the main outfall drain with sufficient capacity to service the
total catchment area which extends over three kilometres south from "The Willows" land, and
to provide access over the drain in order to subdivide the area west of the drain. Mr Lowe
accordingly calculates that the purchaser paid in effect $6,930,000 to obtain the en globo parcel
suitable for development - or $73,256 per hectare. He sees "The Willows" land to be very
comparable with the subject parent parcel. It is situated close by and in his view, has similar
potential for residential development.
"Carlysle Gardens" - Lot 1 on RP 722670 - 29.45 ha - RG Clare to Carlysle Gardens
Townsville Pty Ltd on 21 August 1996, for $1,100,000 - or $37,351 per hectare.
Mr Lowe has analysed this sale to show him a land value of $56,348 per hectare after
deducting an area of 3.96 hectares for a future drainage reserve and adding to the sale price
$43,000 for the cost of an outfall drain and $293,300 for required external roadworks. Mr
Lowe told us that this land was zoned "Residential B" at sale date and that Council approval for
the development of a 266 lot subdivision had been obtained on 15 December 1993. But the
subdivision did not proceed and the approval lapsed. Further, the purchaser was required to
construct an open outfall drain of sufficient capacity to service the total catchment area to the
south of the property and to construct Beck Road fronting the land and external to the
development scheme. The land is now being developed as a retirement village of in excess of
400 homes plus serviced apartments and sporting facilities. Mr Lowe considers the subject
land to be superior to the "Carlysle Gardens" site mainly because of what he describes its better
position and exposure from Herveys Range Road.
Mr Lowe has also been involved with the Shalom Christian College since its inception,
having provided advice to what was to become the Board when the property was being
purchased. He attended to the application for Consent Use for the College and confirmed that
-- 11 of 40 --
12
this was approved on 30 May 1989, and told us that at that time the development plans did not
show any reference to the Main Roads requirement for land adjacent to the southern boundary
for the bypass road.
Mr Lowe says that the subject land has in the past had some flooding problems. The
existing Harveys Range Road is currently built up and this tends to pond water especially as the
culverts under that road were of insufficient size.
Mr Lowe's attention was specifically drawn to the construction of the closest College
building to the resumption line. It is a dormitory building (shown as B2 on Plan S93). It faces
north/south, with large banks of louvres for ventilation. Mr Lowe feels that any noise emitting
from the future bypass road would affect occupants in the building, especially as they will be
indigenous people.
Mr Lowe told us that when the solicitors for the college were attending to the settlement
when the land was purchased in 1989, they made the normal requests and searches at the Main
Roads Department and were advised that investigation was proceeding for the future road
network in the area which indicated that there was a possible requirement from the subject land
for road purposes, but as he understood the position, it was then just a possibility, not even
probable that land for the bypass road would be required from the college property.
Mr Lowe is of the firm view that the bypass road will impact negatively upon the
college land. He sees there being a loss in value of land adjacent to the proposed buffer wall on
the resumption line, along with a loss in value of the land which will lie between the buffer wall
and the resumption boundary. It is Mr Lowe who assesses the loss in value of this land which
is included in the compensation claim (Exhibit 6A).
His assessment of compensation reads:
"It is evident from sales of vacant allotments that a Noise Barrier Wall when erected on or
adjacent the rear boundary of a vacant allotment separating that allotment from a main
road that there remains a lessening in the value of the allotment.
An analysis of sales has been carried out on three Stages of the Annandale Estate Subdivisional
Development located adjacent University Road which forms part of the Townsville By
Pass. The Developer has constructed a noise barrier wall some 2 metres high on the
rear boundary of the allotments bounding this road and a diminution in value is evident
when compared to other sales occurring in the Estate at that time and the selling period
for these allotments is noticeable longer.
From the results of the analysis, a claim for compensation is set out herewith based on the effect
such diminution in value would have on the net realisation of a hypothetical subdivision
analysis should a Noise Barrier Wall be constructed along the Southern Boundary of the
balance land. "
-- 12 of 40 --
13
1.Loss in Value due to reduction in prices in subdivisional lots adjacent wall.
(Consider 10% Depreciation in Value per lot for average value of allotments of $42,000 i.e.
$4,200 less selling costs = $4,100 loss in net realisation value)
22 LOTS @ $4,100 Loss in Realisation $90,200
Less Profit & Risk (Arguable Range 25%-33%-
allow 30%) results in a Loss of Value of $69,500
2.Loss in Value due to extended selling period for these lots - (4 months)
Holding Costs - Deferred Income
22 Lots @ $37,800 each $831,600
Less Selling Costs
Agents Commission ($1395)
Advertising ($300), Legals ($250)
22 Lots @ $1945/lot $42,800
DEFERRED INCOME $788,800
Loss of Interest Over 4 months @ 7.4%
(Bond Rate 3/94) $19,500
TOTAL CLAIM $89,000
CLAIM FOR LOSS OF LAND FOR NOISE BARRIER WALL
The Barrier Wall necessary to ameliorate the Traffic Noise from the Proposed By Pass Road
will need to be set some eight metres from the new boundary after resumption inside the
balance land.
As the Rear Boundary is some 515 metres in length this will in effect reduce the balance land
available to the Claimant by 0.412 hectares.
At $55,000 per hectare this results in a Loss of Value of $22,660
Say $22,700 "
It was Mr Brown who was asked by Mr Lowe on behalf of the claimant to provide it
with a report as to the effectiveness of the proposed buffer wall as a noise barrier. He quoted
"The Stated Objective of the QDOT Interim Guidelines and Technical for Road Traffic
Amelioration" is to "specify the maximum noise level with which the Department of Transport
shall, subject to availability of funding, endeavour to comply with the best cost technology.
-- 13 of 40 --
14
The levels specified in these Guidelines represent a balance between that which may be
desirable for various land uses and that which may be achievable."
Mr Brown says that with the new access controlled roads, the guidelines require that the
external noise level generated by road traffic must not normally exceed 63dBA L10(18 hour) before
amelioration measures will be initiated by the Queensland Department of Transport. In
addition, Mr Brown says that noise level must have increased by at least 3dBA above the
ambient noise level that prevailed prior to the construction of the road, and further if the
increase in ambient noise level is more than 10dBA, the noise level limit is to be restrained to
60dBA.
Mr Brown told us that for road traffic, internal noise level limits specified by the
Commonwealth Department of Administrative Services in 1985 are, for road traffic, the
following:
•Classrooms - LA10,T2 50dBA
•Classrooms - LA90,T3 40dBA
• Bedrooms in Apartments - LA10,T 45dBA
• Bedrooms in Apartments - LA90,T 40dBA
• Living Rooms in Apartments -LA10,T 55dBA
• Living Rooms in Apartments -LA90,T 45dBA
Mr Brown advised Mr Lowe that he has assumed in his noise level calculations that the
wall will be 5.5 metres high and built parallel to the line of the proposed road and located some
8 metres from the boundary of the resumption. For the purpose of his calculation, future road
traffic volume was set at 16,000 vehicles per day. Mr Brown sees the existing ambient noise
level at the existing and proposed dormitory buildings to be generally in the range of 35-45dBA,
and because the existing ambient noise level is less than 50dBA, the corresponding
L10(18Hour)noise level limit would be 60dBA as a result.
Mr Brown has made calculations as to the noise effectiveness of the proposed barrier wall for the
existing dormitory building (B2) and for the closest proposed dormitory building (B3), and in each case,
the effectiveness of the wall has been assessed for both dormitory levels inside the building. The result of
his calculations are tabulated as:
Building Calculated External L 10(18hour)Noise Levels (dBA)
Level 1 Level 2
No Wall With 5.5m Wall No Wall With 5.5m Wall
-- 14 of 40 --
15
B2
B3
61.2
66.9
50.1
54.5
62.2
67.9
52.4
60.0
Table 1 - L10(18hour) Road Traffic Noise Levels at the Closest Facade of Buildings B2 and B3 -
With and Without Proposed Wall
Building
Calculated Internal Maximum Daytime LA10(1hour)Noise Levels (dBA)
Level 1 Level 2
No Wall With 5.5m Wall No Wall With 5.5m Wall
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
B2
B3
52
57
37
42
41
45
<30
<30
53
58
38
43
43
51
<30
36
Table 2 - Calculated DAYTIME L10(1hour)Road Traffic Noise Levels Inside the Rooms of
Buildings B2 and B3 - With and Without Proposed Wall
Building
Calculated Internal Maximum Nighttime LA10(1hour)Noise Levels (dBA)
Level 1 Level 2
No Wall With 5.5m Wall No Wall With 5.5m Wall
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
Windows
Open
Windows
Closed
B2
B3
44
49
<30
35
33
37
<30
<30
45
50
<30
35
35
43
<30
<30
Table 3 - Calculated NIGHT TIME l10(1hour)Road Traffic Noise Levels Inside the Rooms of
Buildings B2 and B3 - With and Without Proposed Wall
Mr Brown suggests that his calculations show that the 60dBA external noise level limit is exceeded
at the facade of both levels of building B2 and the proposed building B3. Further, if the 5.5 metre
high wall is constructed, the noise level limit will be met comfortably at building B2 and the lower
level of building B3 when the wind is calm, but could be expected to exceed 63dBA under adverse
conditions. Without the wall, the internal noise level limit is expected to be exceeded inside both
levels of the proposed building B3 when the windows are open. Inside building B2, Mr Brown says
the noise level will only just be met when the windows are open. If the windows are closed, the
compliance with internal noise level limits will be achieved in both buildings under all wind
-- 15 of 40 --
16
conditions.
Mr Brown stresses that his calculations are based on noise level limits for non-indigenous
occupants. He understands that the work carried out by Kennedy Constructions Pty Ltd (M/s J
Downs) indicates that Aboriginal and Islander students at the college may be more sensitive to
external noise intrusion than are non-aboriginal students.
Mr Brown is of the view that if compliance with the Queensland Department of Transport Noise
Level Limit only is to be achieved, it may be more cost effective to construct a wall on Queensland
Department of Transport land. This, he says, may be a more aesthetically appealing option. Such a
wall would have to be built in accordance with QDOT specifications. Typically it would require the
barrier to be constructed using timber panelling on steel posts. Mr Brown estimates the cost of such
a fence, if compliance is sought at building B2, to be $55,000, or if compliance is sought at building
B3, $100,000.
Mr Brown is of the opinion that there seems to be scope within the Master Plan to relocate future
dormitory buildings further from the road and consideration should be given to placing less
acoustically sensitive buildings and activities in their place.
Mr Brown told us that at the time of the preparation of his report for Mr Lowe, he was under the
impression that there was projected to be 5% heavy vehicles in the 16,000 strong traffic stream. He
has since learned from the Main Roads Department that its current projection is for 10% heavy
vehicles, and he believes this change in traffic mix will necessitate increasing marginally the height
of the barrier wall to 5.75 metres to achieve compliance with the criteria proposed in his report.
Further, Mr Brown considers that the barrier should be extended and return along the eastern
boundary at the same height for 10 metres and along the western boundary for 75 metres with a
reduced height of 2.5 metres to minimise noise for the proposed detached housing development.
Mr Brown considers there to be some potential to reduce the height of the proposed barrier wall on
the resumption line on its western side by stepping down its height to meet the suggested 2.5 metre
high return on the western boundary. Mr Brown believes that if the object of the exercise was to
obtain the quietest environment internally in the existing building B2 and the proposed building B3,
then the best way of achieving that would be to aircondition those buildings rather than building the
wall.
Mr Brown says that the best way of controlling the noise problem with proposed building B3
would be, if it was physically possible, to relocate the building to a position parallel to building B2
to the south of the oval and therefore put it beyond the 60dBA line.
It was Mr Neilsen who costed the proposed barrier wall for the claimant. Originally, Mr Neilsen
was requested by Mr Lowe to cost the construction of the wall along the southern boundary of the
college land and returning for 100 metres along the western boundary. He calculated the cost of the
erection of this wall at $700,000 on 3 October 1995. Mr Neilsen says that to bring this cost back to
the date of resumption in this case (March 1994) then using the appropriate factors, he would reduce
-- 16 of 40 --
17
the figure of $700,000 by a factor of 3.96% - to a sum of $672,200 on my calculations.
Mr Neilsen's cost calculation was made taking account of preliminary instructions received from
Mr Johnstone (an engineer, in relation to the construction of the wall). Consequent upon receiving
further instructions, Mr Neilsen has calculated the cost of erecting a 2.5 metre high wall to the
western boundary in the sum of $28,000 again as at October 1995. Using the 3.96% discount
factor, I calculate the cost in March 1994 values to be about $27,000.
During the course of his evidence, Mr Neilsen told us that he had examined costings of a wall on
the southern boundary only made for the respondent by Mr Hall. He suggests that Mr Hall's costing
of $530,610 for the wall envisaged by him should have been $595,000 in October 1995 cost price
terms. Once again Mr Neilsen suggests that this cost should be reduced by a factor of 3.96% to
represent cost as at the date of resumption. Again I have calculated this sum and arrived at a figure
of $571,500 - certainly not much in excess of Mr Hall's cost estimate.
Mr Neilsen has placed in evidence the detailed calculations of his costings but I do not feel the
need to have them particularised in this decision.
Late in the case, indeed after the claimant and the respondent had closed their cases, leave was
sought and granted after I heard legal argument, for the claimant to re-open its case. This was in
relation to what was described as the simple aspect of the escalation in the building costs (of the
wall) which will take place between the date of resumption and the date upon which it will be
necessary for the claimant to construct the wall. This was obviously in response to a proposition
that compensation, if any, awarded for the cost of building the wall would be significantly reduced
by an appropriate discount factor to allow, for example, that the wall would not be needed until say
the year 2014 or the year 2020.
Mr Neilsen was asked for his estimate for escalation factor in building costs from 1977 to a date
some 16 years in the future. Mr Neilsen acknowledged the difficulty in forecasting building cost
trends for such a long period, and he too expressed the view that it is normally not done for more
than a two year forecast period. Mr Neilsen told us about past variations in building costs as
reflected in a published Cost Price Index published by the Australian Institute of Quantity Surveyors
going back to as far as 1963. Compounded, the Index suggests that building costs have risen over
the last 16 years at a rate of 5.1% per annum, and the best Mr Neilsen can do is to use that
calculation to forecast rises of a similar proportion in the future.
Mr Kuskopf told us that he has been associated with the development of the Shalom College site as
its architect since 1991 and before any building construction had begun. It was his task to interpret
a "sand diagram" which had been conceived by the Board in a practical way as far as the layout of
the buildings and planning of the site was concerned. Mr Kuskopf says that based upon population
densities, and after receiving town planning advice, it was determined that the area of the college site
in its former "Residential B" and "Residential C" zoning would allow about 1,200 people overall.
The site was then planned so that the maximum number of persons on it during the day would not
-- 17 of 40 --
18
exceed 1200 but that during evenings and after school hours, the number would reduce to about 600.
The reason for the lower after school occupancy was the perceived need for open spaces and
tranquillity to accommodate the particular needs of the children coming from remote areas to board
at the site, while at the same time maximising the usage of the site.
Mr Kuskopf told us that in planning the location of the various college buildings, he had to take
into consideration that there already was the Yalga-Binbi Institute building on the land. This was a
substantial structure which the Board could not afford to remove so that the development had to be
planned around it. Mr Kuskopf told us that the possibility of a land resumption did not become an
issue until 30 January 1992, when he received a brochure showing a possible land resumption along
the southern boundary of the college land, after which the possibility of a land resumption by the
Department of Transport was taken into account in the design and to that extent no buildings were
constructed on that part of the site. It was planned that the proposed resumed area would form part
of the open space on the whole site. If there was no proposed resumption, Mr Kuskopf would have
placed buildings on the resumed land to give more space between the buildings on the site.
Mr Kuskopf has designed the college buildings using natural ventilation and taking account of the
prevailing breezes. The master plan he drew in early 1992 showed the possible resumption at the
southern end and a roadway between the primary and secondary schools accessing the community
centre. It was considered this might be dangerous and the roadway location was changed in 1993,
and this change meant the boarding accommodation had to be moved to the east and south. Mr
Kuskopf does not believe that it is possible to relocate the boarding accommodation without
impinging on the need for space between the buildings.
After considering other designs for the boarding buildings, which he thought would not sufficiently
reduce the impact from the bypass road, Mr Kuskopf then considered the construction of a barrier
wall. After considering the position of building B2 accommodation, he came to the conclusion that
a 5.5 metre wall was required. Mr Johnstone prepared sketch plans of two alternatives involving
mounds and brick walls in a combination of heights to achieve this wall level. Mr Kuskopf then
prepared a cross-section of the proposed wall and this was submitted to Mr Brown (the acoustic
engineer) for his report.
Mr Kuskopf considered airconditioning as an alternative solution to the anticipated traffic noise,
traffic movement, light and exhaust pollution from the bypass road but this will only have an effect
of reducing the internal noise level in the buildings.
Mr Kuskopf told us that the original master plan for the college development was prepared in
1991, and in fact he built a model of it in June 1991. The model is in evidence. No structural work
had been commenced at that time but Mr Kuskopf was in the stage of producing working drawings,
with some of the buildings required to be opened for the first year of school in 1992.
Mr Kuskopf says that the formal council approval for the development of the college was
obtained on 17 February 1993, and as a condition of approval, council advised that the development
-- 18 of 40 --
19
should be in accordance with the master plan so it was not intended that the development should
digress from the plan to any extent at all. Of course, in reality the development did eventually
depart from the plan in so far as the relocation of the internal road and the siting of the
accommodation building B2 further to the south is concerned.
With regard to the possibility of installation of an airconditioning system in accommodation
building B2, Mr Kuskopf is of the opinion that the best type of airconditioning is a "split" system
such as proposed by Mr Hall whose evidence I shall deal with later in this decision.
Mr Kuskopf was asked during his evidence if it would be his advice to locate the proposed
boarding accommodation building B3 as indicated on the master plan in the event of it being
constructed, and he responded by saying it would be his advice to so do.
He was also asked to comment upon a plan shown to him which indicated a different site
location from that proposed in the master plan so as to locate the buildings further from and away
from the influence of the Bypass Road. Mr Kuskopf acknowledges that the buildings could be
constructed in the indicated positions but the basket ball court would have to be demolished.
Further, he commented that his client had shown a wish to include the conference centre as indicated
on the plan with associated accommodation for the conference centre.
Mr Crane was called by the claimant to make an accountancy assessment of the loss in future
profitability of the college consequent upon the resumption. Mr Crane originally assessed
compensation for loss of income due to the resumption in the sum of $449,075. He was provided
with operational revenue and expenditure projections for the college for the years 1993 to 2000,
pre-audit financial statements and reports for the year ending 31 December 1996, and management
accounts for the period 1 January 1997 to 30 September 1997. Other advice provided by the
claimant to Mr Crane includes that the zoning of the complex provides for an occupancy rate of 35
persons per hectare and that there are currently approximately 300 occupants in the complex. Based
on the completed facilities, Mr Crane has assumed that this occupation reflects 230 students and 70
persons in the elders' village. Mr Crane has also been advised that by 1998 full occupancy of the
college will be achieved.
Mr Crane calculates that the full potential capacity of the college land based on 35 persons
per hectare is 1113 persons (31.8 hectares x 35). He then calculates the loss of occupancy due to
the resumption to be 112 persons (3.21 hectares - the resumed land and an area of land required for a
future buffer wall x 35). But this number includes staffing, estimated at 200 once the complex is
fully developed. As a result then, Mr Crane says the net loss of revenue contribution occupants
would be approximately 91.
Based on the material provided to him, Mr Crane calculates that the average net contribution
per person to college revenue is $478. Accordingly, he suggests the total annual contribution loss is
$43,498 (91 x $478). But Mr Crane has been advised that compensation in respect of the value of
the land resumed is expected to be $285,700. Assuming an interest rate of 5 percent per annum, he
then calculates that the investment of compensation monies would generate an income of $14,285
per annum, so the net annual loss would be $29,413. Mr Crane says that this annual loss will
continue into the future and has applied a 5 percent interest table to the annual loss indicated for a
-- 19 of 40 --
20
period of 30 years. This produces his calculated assessment of compensation for loss of income in
the sum of $449,075.
As a result of some further investigations since Mr Crane has read a report made by Mr
Hannah, the accountant to be called by the respondent, he has amended marginally his calculations
of loss of income over 30 years to be $498,037. This is as a result of him increasing the actual
contribution per head from $478 to $513. But this figure was further amended during the case by
deferring the claim for loss of profitability for 8 years (1994 - the date of resumption - to the year
2002 - the period during which it is not expected that roadworks on the bypass road will commence)
at an interest rate of 5 percent to $337,000.
Mr Marsh informed us that he has been associated with the claimant company since its
incorporation in his former role as Director of the Department of Mission and Parish Services with
the Queensland Synod prior to being appointed as Executive Officer of the company, which position
he has held since 11 May 1996. Mr Marsh too says that the college site was planned on completion
to have during daytime approximately 35 persons per hectare across the whole site, and that after
school hours the numbers will reduce to approximately half to cater for the need of the children and
adults living on the site for open space. Mr Marsh says that the school currently has about 230
students in classes from preparatory to Year 11. Full occupancy of the school is expected in the
Year 2001. There are currently 70 people in the elders' village but these numbers are expected to
increase. There is an adult education training facility in operation as a construction arm which is
responsible for undertaking building work on the site.
Mr Marsh was called mainly to give us his idea of the impact of the resumption on the
college. He says that to maintain similar proportions of people to the area of the site remaining after
resumption, as it was intended at the commencement of planning, it is necessary to reduce the
overall people numbers on the site by about 10 percent. Mr Marsh agrees with Mr Crane in that the
overall number of people on the site post resumption will have to be reduced by about 91 persons.
Because of this, he also suggests there will be a reduction in operating revenue while the
administration costs remain the same, and any reduction in capital expenditure will be minimal
given that the reduced number of persons will be shared across all facilities on the site.
Mr Marsh told us that to date the capital sum of $13.5 million has been expended on the
development of the college including the cost of land purchase, and that a sum of $4.7 million is
required to complete the college development as planned by, he hopes, no later than 1999, including
the planned accommodation building B3 and the planned four tertiary accommodation buildings.
Mr Doran was called by the claimant company to provide costings for the airconditioning of
existing dormitory accommodation building B2, and of the proposed dormitory accommodation B3,
and of the four proposed tertiary accommodation units. Mr Doran has based his cost calculations
for the installation of an AC system which involves distribution of air through a ducted system. He
calculates the cost of airconditioning using this system to be $36,619 for the ground floor of building
B2 and of $38,519 for the first floor which represents the total cost to aircondition the building (after
allowing 20% contingency) of $90,166 including an allowance of 15 percent for sales tax.
Mr Doran assumes that the proposed extra five dormitory buildings will be the same size and
-- 20 of 40 --
21
orientation as existing building B2. Using the same type of system, he accordingly calculates the
cost to aircondition the five proposed buildings, inclusive of an allowance of 10 percent for
contingency, to be $413,259. This makes his estimate for airconditioning all six buildings to be
$503,425.
Mr Doran also provided estimates of the running costs of the airconditioning plants but this
evidence is not relevant to my determination of compensation since the claimant has abandoned the
claim for airconditioning running costs in the amended claim for compensation.
It was pointed out to Mr Doran that in the event of Shalom Christian College being not
subject to sales tax, then his calculations should be amended downwards so that, for example, the
cost to aircondition the ground floor of building B2 with the ducted system, should be $34,037 - or
$86.35 per square metre - which cost can be applied to the total floor area of the six buildings
involved in his cost estimate. Mr Doran told us that to adjust his estimated costs of airconditioning
back to 1994 (the date of resumption), his costings should be divided by a factor of 1.2 to take
account of the Building Price Index fluctuation.
Mr Doran has also provided the Court with his estimated costs for the airconditioning of the
ground floor only of the proposed building B3 and that of two of the proposed tertiary boarding
accommodation units (adjusted for the need not to pay sales tax). His 1997 cost to aircondition
those proposed buildings is $89,300 as at 1997, and an adjusted cost as at the date of resumption (11
March 1994) of $88,242.
Mr Doran also furnished to the Court his assessment of running and maintaining an
airconditioning system known as the "Split" airconditioning system proposed for the buildings by Mr
Hall who was called by the respondent. His estimates of airconditioning running costs for the
existing building B2 is $22,801 per annum, but again and for the same reason earlier outlined, I do
not see this evidence as being relevant.
EVIDENCE FOR THE RESPONDENT
Mr Caleo has assessed compensation for the resumption using the traditional "before" and
"after" method of valuation as follows:
Land value before resumption - 31.81 ha @ $46,000/ha $ 1,463,260
Less Land value after resumption - 29.03 ha @ $46,000/ha $ 1,335,380
$ 127,880
Compensation - say, $128,000
Mr Caleo sets out in his valuation document his description of the physical site details and
this is largely in accord with the same information provided by Mr Lowe as already outlined in this
decision. He told us that at the date of resumption, the college land was being progressively
developed with the purpose-built low density boarding college and education facility primarily in
accordance with the council approved Master Plan S93. Mr Caleo has calculated that as at the date
of proclamation, the building with closest proximity to the resumption boundary is the existing
boarding accommodation building B2 which, he suggests, is located 90 metres from the bypass road
resumption line. Mr Caleo says that the staging of the bypass scheme work as at 1994 indicated a
-- 21 of 40 --
22
projected completion date for the initial construction of two lanes from Upper Ross River to Herveys
Range Road (passing the college) to be in the Year 2014. He expects the speed limit for this section
to be 80 kms per hour, but it seems that it may range up to 100 kms per hour. Mr Caleo sees the
operation of this first part of the road scheme as having little impact on the existing building B2 or
other college buildings or facilities.
Mr Caleo told us that in making his compensation assessment, the following factors are
relevant:
(1)Engineering studies for the Townsville By-pass Scheme were first commissioned in 1982.
A General Location Plan appeared in the Townsville Bulletin in April 1985 and the
Townsville City Council and Thuringowa City Council were given draft reports for
comment and referral to affected developers. As was demonstrated by the proposed
subdivision approval in 1985 on the subject land.
(2)The subject property was acquired in March 1989. At that time, solicitors for the
purchaser, Kinsey Bennet & Gill, Solicitors of Brisbane, carried out a search with the
Department of Main Roads requesting details of any future requirements for road
purposes. This search reveals that there is a possible requirement from the land for
road purposes.
(3)In May 1989 the purchasers of the college land, Congress Community Development and
Education Unit, sought consent use approval from the Thuringowa City Council for
an educational establishment primary and secondary school. This application was
referred to Main Roads which in reply stated that `Main Roads has no objections in
principle to the application providing adequate provision is made along Herveys
Range Road for the traffic generated, and land is set aside to accommodate the future
Townsville by-pass corridor'. Further Main Roads advised that `no direct access to
the Townsville by-pass shall be allowed'.
(4)Development of the college proceeded under the Consent Use Approval with building
commenced in 1991.
(5)In February 1993 an application for rezoning of the land from Residential B and
Residential C to Special Facilities (Educational, Cultural, Recreational and
Associated Accommodation as shown on Plan of Development No S93), was
approved by Council. The plan clearly shows the future road requirement along the
southern boundary of the subject land although the widening towards the eastern
boundary has since been removed.
(6)Investigations with the Building Department of Thuringowa City Council show that
works commenced on Building B2 in August 1993.
(7)The impact of a main road on englobo land in Townsville is considered to be neutral.
Several of Townsville's main residential subdivisions including Annandale and
Riverside Gardens front the by-pass corridor.
Mr Caleo has, as a result of these considerations, come to the conclusion that the claimant
was well informed of the Bypass Scheme and its requirements, both prior to land purchase and
-- 22 of 40 --
23
during planning and development of the college. He further says that acting prudently, the claimant
should have taken reasonable action through the planning stages to minimise any loss. As a result,
he does not believe there is any entitlement to compensation for injurious affection or severance, and
this is why he applies the same value per hectare in both his "before" and "after" valuation exercises.
Like Mr Lowe, Mr Caleo believes that the best basis for the valuation of the college land is
the sales of englobo land with potential for residential subdivision. He has referred to five sales in
his tendered valuation report, but clearly the two most comparable sales are those of "The Willows"
Estate and "Carlysle Gardens" (two of the sales relied upon also by Mr Lowe as outlined earlier in
this decision).
Mr Caleo says that "The Willows" Estate land is the balance of Kern's "Willows Estate"
which has enjoyed outstanding success under the control of a Receiver Body up to the date of sale,
averaging sales of approximately 170 lots per annum. He told us that "The Willows" englobo
parcel was severed by a drain known as the "Kern drain", which is a constructed drain requiring
batter adjustments to accommodate the full residential lot yield of the balance area. Mr Caleo says
this drain is to encompass an area of 5.2 hectares, which I note is half the area suggested by Mr
Lowe. Mr Caleo points out that the englobo land has a frontage to "The Willows" golf course on its
western boundary where about 40 potential residential lots abut the 18 hole course.
Mr Caleo stresses that the Defence Housing Authority was already a driving force in "The
Willows" market at time of sale, accounting for between 25% and 30% of sales activity, and that the
land is currently being developed in a joint venture arrangement with the Delfin Group with the
Authority continuing to be the major purchaser of lots.
Mr Caleo told us that at the date of sale, two undeveloped stages had been approved for
subdivision with a yield of 79 lots and completing the development to the eastern side of the drain,
and that park land credits existed in respect of those approved stages. In addition, there was some
300,000 cubic metres of fill stockpiled on the site with further fill being available from drain batter
variations and road construction.
Mr Caleo described what he calls the main impediment to "The Willows" Estate as being the
construction of the Sandstone Drive Bridge, which he says had a vendor (Receiver/Manager) cost
estimate of $350,000 at date of sale, but which was subsequently built at a cost of $600,000 for what
he describes as an "over-specified" structure reflective of the estate superior developmental standard.
In addition, external drainage works were predicted at sale date to cost $500,000, with filling
costs of land abutting "The Willows" golf course being estimated to cost $300,000. Mr Caleo has
made a further allowance of $50,000 for the Martello Drive/Evergreen Drive crossing in his analysis
of the sale, As a result then, he says "The Willows" Estate sale shows a value of $52,746 per
hectare overall for the 105.6 hectare prime englobo parcel with a proven sales record, or $63,362 per
hectare after allowing for the bridge cost (at $350,000), for the filling, for the drainage works and for
the parkland advantages.
Mr Caleo sees "The Willows" Estate parcel to be far superior to the subject land in location
and topography, but recognises that it is much larger. He points out that in addition, "The Willows"
Estate was at sale date an active subdivision with a successful marketing history.
-- 23 of 40 --
24
Mr Caleo describes the "Carlysle Gardens" site as being "Residential B" englobo land with a
potential residential lot yield of 270 lots providing no parkland and allowing for Beck Road
requirements. The sale reflects an englobo value "as is" of $37,351 per hectare. The contract of
sale was conditional upon the purchaser obtaining a rezoning to "Special Facilities - Retirement
Village". Council imposed conditions including road upgrades, drain construction, levee bank
construction and contributions to the western collector road system with a combined estimated cost
of $450,000. Mr Caleo says that the external infrastructure and Beck Road access costs estimate for
a 1995 residential subdivision were $250,000, and that the internal designated drainage areas totalled
4.0 hectares. In his sale analysis, after making the above adjustments, Mr Caleo says the reflected
englobo value with upgraded access, infrastructure and drainage is $45,840 per hectare.
Mr Caleo points out that the "Carlysle Gardens" land is directly opposite the southern
boundary of the resumed land and that it will have a similar frontage to the future bypass road and
will also front the upgraded western collector road. Mr Caleo sees the sale land to have superior
topography (slightly more elevated than is the subject land) and superior access, but it is in a slightly
inferior location. He sees the sale of "Carlysle Gardens" to be the best evidence of value of the
resumed land.
Mr Hall has examined the engineering design plan of the proposed buffer wall designed by
LC Johnstone and Associates and has, as an architect, prepared costings of it. They are:
1. (a) Earth mound $220,500
(b) Fill drain $ 37,500 $ 258,000
2. (a) Block work $ 42,061
(b) Laying $ 42,442
(c) Concrete fill $ 25,663
(d) Re-enforcing steelwork $ 21,676 $ 131,842
3. (a) Strip footing $ 17,050
(b) Pier footing $ 40,841
Preliminaries $ 9,300
TOTAL COST $ 457,033
Add Builder's Profit 7.5% $ 34,277
$ 491,310
Add Professional Fees 8% $ 39,300
TOTAL COST $ 530,610
Mr Hall told us that his cost estimate was prepared on 17 November 1997. It is for the
construction of a wall only along the resumption line with no return walls. He notes that the area
upon which the proposed wall is to be constructed is not restricted by buildings or other elements,
and he sees no difficulties in carrying out the works.
Mr Hall offered criticism of the development costs of the wall provided by Mr Neilsen. He
-- 24 of 40 --
25
says there is no need to provide landscaping (Neilsen $50,618) as the Thuringowa City conditions
for rezoning the site required it to be landscaped. Further, Mr Hall suggests that as the construction
of the wall is simple, then it would not require the expertise of a builder, nor is there any statutory
authority requirement to engage a builder. Mr Hall says the claimant's cost of construction would
be reduced by $30,000 if the builder was removed from the process. He also says that an astute
developer would not pay $39,300 in professional fees for the wall. But I note that Mr Hall has also
made an allowance for builder's profit and professional fees in his calculations.
Mr Hall's costings are as at 1997 rates but because of the depressed state of the building
industry over the last three to four years, he says that rates have not changed substantially, and
concrete rates have, if anything, actually reduced. Accordingly, Mr Hall suggests his costings are
relevant to the date of resumption - in March 1994.
Mr Hall has also prepared cost estimates for airconditioning the ground floor of the future
boarding accommodation building B3 and the ground floors of two of the proposed four tertiary
boarding buildings. But before setting out his costings, Mr Hall had some criticism of the costings
by the claimant (Mr Doran) based on his opinion that a better type of airconditioning plant was for a
wall or ceiling "split" system rather than a "ducted" system. The "split" system is also the type
preferred by Mr Kuskopf.
Mr Hall's airconditioning costings are:
Proposed Building B3 - $ 40,620
Proposed Building TB1 - $ 32,960
Proposed Building TB2 - $ 32,960
Total costs to aircondition all buildings - $ 106,540
Mr Hall points out that these are also 1997 costs - and feels that costs as at the date of
resumption would only be marginally lower.
During the course of his evidence, Mr Hall was asked for his opinion as to the likely trends
in building costs in say 15 years time when the barrier wall may need to be erected. He does not
believe that one could really look so far ahead because costs are governed by inflation rates,
governments may change and policies may change, exchange rates may change, so that to predict so
far ahead is very difficult. In fact, Mr Hall personally would not predict past two years. Mr Hall
asked the Quantity Surveyor firm, Rider Hunt, the same question, and he says they said it is too risky
to predict cost movements.
Mr Horman was called by the respondent to inform us mainly as to matters of historical
interest leading up to the resumption. Mr Horman has been in the employ of the resuming authority
as an engineer and town planner for a little over five years. One of the reasons for his employment
was to complete the planning for the Bypass Road. Mr Horman told us that in August 1982,
McIntyre and Associates, Consulting Engineers, were commissioned to carry out a feasibility study
-- 25 of 40 --
26
to determine the location for a future Townsville bypass road. Mr Horman confirmed Mr Caleo's
evidence that in January 1987, the McIntyre Report was forwarded to both the City of Townsville
and the City of Thuringowa for official comment with a request that any developers affected by the
proposed route be referred to the then Department of Main Roads. The City of Thuringowa Council
passed a motion supporting the Bypass Route in February 1988. Since August 1983, Mr Horman
says any effect on land was declared by Main Roads on any requisitions for information received
from solicitors during conveyancing activities, and a plan of the general location of the bypass road
appeared in the local newspaper as early as 1985. The brochure was prepared in July 1990 for
circulation to property owners.
Mr Horman confirmed that on 5 May 1989, solicitors for the claimant were informed that
"investigation proceeding into the future developments of the road network in the area indicates a
possible requirement from the subject land for road purposes. There is no intention to resume any
part of the land at this time. The owners and/or prospective owners may see current planning at this
office. Contact should be made with Mr Cook to arrange a time."
Mr Horman told us that following referral by the City of Thuringowa Council in May 1989
of a consent application by the claimant company, the District Office replied that "Main Roads has
no objections in principle to the application providing adequate provision is made along Herveys
Range Road for traffic generated, and land is to be set aside to accommodate the future Townsville
Bypass Corridor".
Mr Horman informed the Court that the subsequent development of the Shalom Christian
College had taken place based around access to Herveys Range Road. He submitted an internal
Queensland Transport Route Selection Report for the Condon to Derragun section of the Bypass
Road on 7 September 1994. The following table shows the projected staging and completion dates
for the stages as set out in his report. Some modification has been made since the preparation of the
report. These modified times are shown in brackets. The table reads:
Section Completion Date Speed Limits
1. Douglas - Condon
Two Lane
2002
(2002)
80 or 100
2. Hervey - Shaw
Two Lane
2004
(2004)
80
3. Upper Ross - Hervey
Two Lane
2014
(2008)
80 or 100
4. Douglas - Condon
Four Lane
2015
(2011)
100
5. Hervey - Shaw
Four Lane
2017
(2011)
100
-- 26 of 40 --
27
6. Shaw - Bruce
Two Lane
2020
(2015)
80 or 100
7. Four Laning the
Balance
2020 100
Mr Horman also provided us with 1994 traffic flow counts and his estimated traffic flows on
the Bypass Route and Herveys Range Road for the future years 2011 and 2021. The table is:
Road Segment Parameter 1994 2011 2021
Herveys Range Road AADT
%hv
7,200
7
11,00
0
5
12,60
0
5
Ring Road
(West of Upper Ross River
Road
AADT
%hv
n/a 10,00
0
10
16,20
0
10
AADT - Average Annual Daily Traffic
%hv - Percentage of heavy vehicles
It is upon this statistical information and forecasts that the acoustic engineers prepared their
evidence for this case.
Mr Horman recalls attending a meeting with representatives of the claimant including Mr
Johnstone, Mr Lowe and a Mr Hicks on 13 October 1993. In response to assertion that he made the
comment at the meeting to the effect that mounding and sound barrier fencing would almost
certainly be required along the perimeter of the land adjoining the resumption for noise amelioration
purposes, Mr Horman told us that he could not find any diary notes of the meeting. But he did say
that he would not have committed the Main Roads Department to erect any fencing or barrier since
he does not have the authority to so do. But Mr Horman, in the event of the barrier wall being
constructed by the claimant, can see no need for it to be built wholly within the claimant's retention
area. He says the type and specifications of the wall envisaged by the claimants could be
constructed on the resumption boundary with part of the earth mound on the road reserve, and he
would have the authority to authorise that.
Mr Dance was called by the respondent to provide town planning evidence. He confirmed
that on 30 May 1989 the Thuringowa Shire Council granted town planning consent over Lot 2 on RP
744340 for the purpose of an educational establishment - primary and secondary school and that
shortly after the issue of the consent permit, a rezoning application was lodged over the whole of the
land to take the zoning from "Residential B" and "Residential C" to the ultimately approved "Special
Facilities (Educational, Cultural, Recreational and Associated Accommodation)" zone. This
application was approved on 17 February 1993, and gazetted on 20 August 1993. Mr Dance told us
-- 27 of 40 --
28
that the master plans submitted with the rezoning application indicate that the land at the southern
end of the allotment was to be preserved for Future Road Reserve purposes. He accordingly
concludes that there could be no doubt that the claimant company was aware of the proposal to take
land for road purposes as and from that time.
Mr Dance produced a copy of the plan prepared by Mr Kuskopf showing the location of all
existing buildings on the site. This plan has been colour-coded to show whether the buildings were
constructed prior to or after the date of resumption, and he suggests that the majority of the
development on the college land was completed prior to the date of resumption. Mr Dance says that
the site master plan was drawn with anticipation of the resumption of land for the Bypass Road, yet
it has made provision for all the buildings in a reasonable and uncluttered manner. He is of the
opinion that the resumption has not fettered or constrained progressive development towards the
master plan, and there is no apparent restriction in the layout of it, although more recent plans
submitted to council in connection with building work show that there has been considerable
departure from the master plan. Mr Dance says these departures show there is still flexibility in site
planning notwithstanding the resumption, and that the master plan was never a "fixed in concrete"
plan. Mr Dance summarises his opinion to be that the resumption has had little, if any, effect on the
overall plan of the college development.
Mr Dance told us that with the former zoning of the land in the "Residential B" and
"Residential C" zone, when the college land was acquired, population densities related to multiple
dwelling use mainly to the "Residential C" zone, and that those density arrangements do not apply in
any other zones. This seems particularly relevant in view of the evidence of Mr Crane. He does
not agree with the proposition that as the college has lost 10% of its land due to the resumption, it
would have to gear back its operations by 10%. Mr Dance says it does not necessarily follow, as the
development proposal could be reduced in scope or it could be designed slightly differently so as to
accommodate development more efficiently. It would, in his opinion, be necessary to cut back the
development only if the original proposal occupied all of the land including the resumed area.
Mr Hannah was called by the respondent as an accountant to provide his comments on Mr
Crane's compensation assessment for loss of profitability. He outlined the difficulties in the
adoption of Mr Crane's report, including the fact that it is based on many variables, but offers the
opinion that, depending upon the interest rate used for capitalisation, the assessment of
compensation for loss of profitability could vary from $120,862 to $246,236. But I do not feel the
necessity to critically analyse Mr Hannah's evidence as will become apparent later in this decision.
Mr Kamst provided us with acoustic engineering evidence on behalf of the respondent. The
stated aim of his report is to quantify the noise impact on the retention area due to road traffic at the
time of resumption as well as for a number of future scenarios. Mr Kamst is not seriously at odds
with Mr Brown's findings, although he uses a slightly different noise level standard for consideration
of amelioration measures. It is 63dBA (Mr Brown used 60dBA). In summary, Mr Kamst contends
-- 28 of 40 --
29
that for the four lane section of the Bypass timed for construction in the year 2021, would result in
an L10(18 hour) noise levels of 59 dBA to 61 dBA at the ground floor of the existing accommodation
unit. At the first storey, the L10(18 hour) noise level is predicted to be between 61dBA and 63dBA.
Accordingly Mr Kamst suggests the 63dBA noise level would be met at Building B2. Further, the
Bypass would result in L10(18 hour) noise levels of 66dBA to 68dBA at the ground floor of the
proposed accommodation units (Building B3 and Buildings TB1 and TB2). At the first floor, the
L10(18 hour) noise levels are predicted to be between 63dBA and 69dBA. Accordingly, Mr Kamst
suggests that the 63dBA noise limit would not be met at these proposed accommodation units
without noise amelioration measures.
Consideration of Evidence and Reasons for Decision
I shall now set out my consideration of the evidence. But before so doing, I might express
the view, as I indicated during the hearing of the matter, that the claim for compensation as amended
- (Exhibit 6A) might have been better formulated. It goes without saying that, in compensation
cases, dispossessed owners are entitled to be compensated for their loss, but I cannot see that, in this
case, such losses include the cost of the construction of the proposed buffer wall (Item 2 in the
claim) or the cost to aircondition the ground floor of the three proposed dormitory units (Item 7 in
the claim).
It may well be, notwithstanding the determination of the board of the college to build the wall and
aircondition the proposed buildings for noise amelioration purposes, that these structures may never
be built. Now in those circumstances, and in that respect, it cannot be said that the dispossessed
owner could demonstrate a loss in a monetary sense, and this decision in the fullness of time will
obviously be seen to be flawed if an award for the cost of the wall and airconditioning per se is
made.
In my opinion, the better way to have formulated the claim would have been to consider by
what amount the value of the college land would have been diminished after resumption for the
perceived need, at resumption date, to construct a barrier wall on the resumption boundary and for
the need to install airconditioning in the proposed accommodation buildings when they are
constructed in the site locations as indicated in the Master Plan (Plan S93).
Having said that, I do not propose to eliminate from my considerations the evidence and
submissions made in respect of this aspect of the case, notwithstanding the deficiency, as I see it, in
the claim for compensation.
Now this case is somewhat unusual in that, of the total claim for compensation (excluding
interest, architect's costs for redesign and costs) of $1,184,000, only $154,000 is claimed for the
value of the resumed land, although it could be said that a sum of $41,000 (loss in value of land by
presence of the presumed buffer wall, and value of land occupied by the proposed buffer wall) is
land value related. In this respect, the dispute as to land value is relatively insignificant - as Mr
-- 29 of 40 --
30
Caleo values the resumed land at $128,000. I now examine the valuation evidence.
Now there is no doubt, and it is well established that, for partial resumptions, the best basis
of valuation is the use of the "before" and "after" method of valuation, and I propose to base my
compensation determination for the value of the land resumed using this method.
My task in finding an appropriate "before" land valuation is made easier by the adoption by
the valuers of some of the same comparable sales - "The Willows" and "Carlysle Gardens". But
they have approached their sales analyses on a different basis. Both valuers have analysed the sales
by adding to the raw land value as disclosed by the sales the cost of remedying development
constraints - such as upgrading road infrastructure, access roads and bridges, drainage requirements,
etc. But Mr Lowe has excluded from the area of the sale lands the land required for future drainage
requirements and in some cases for easements, and as a result obtains generally higher analysed land
values with the infrastructure in place than did Mr Caleo. But I offer no serious criticism of Mr
Lowe for him so doing, since he often stressed during the course of his evidence that he was only
trying to compare "apples with apples", by reducing his value levels to a common denominator.
The valuation evidence leaves me in no doubt that the most appropriate sale upon which to
rely in my compensation determination for the value of land "before" resumption is that of "Carlysle
Gardens". It is very comparable in respect of its location (directly opposite the southern boundary
of the subject land prior to resumption), is almost identical in area, is appropriately conditionally
zoned within the sale contract, and is of similar topography to the subject land, although marginally
more elevated. But the obvious advantage enjoyed by the subject parent parcel in comparison with
"Carlysle Gardens" is its comparatively long frontage to the well-trafficked Herveys Range Road.
In analysing the sale of "The Willows", I think it is more appropriate to allow for the cost of
bridging the Kern Drain as made by Mr Caleo ($350,000) than the cost used by Mr Lowe ($560,000)
although I can well understand that the purchaser of the land (Defence Housing Authority) in
erecting a more costly bridge, did so prudently in upgrading the standard of the development and to
give the estate a high profile entrance statement. But this, of course, adds value to the land and
perhaps in that respect, and as a result, Mr Lowe's analysed unimproved value is reflecting an
upstaged land value. I also find that in analysing the sale of "The Willows", allowance should be
made, as did Mr Caleo, for the value of the fill on site at sale date ($300,000) and for the value of the
parkland credit.
I am satisfied that the land value reflected by the sale of "The Willows" should be higher
than is the value of the parent parcel at date of resumption, notwithstanding that it is a
receiver/manager vendor sale. A factor of some influence on the value of that land is the joint
venture arrangement with the Delfin Development Group, and the proven subdivisional track record
with Kern Grazing Pty Ltd (the vendor).
Based primarily upon the valuers' analyses of the "Carlysle Gardens" sale, I find that an
appropriate "before" land valuation of the parent parcel at date of resumption is $55,000 per hectare -
-- 30 of 40 --
31
or $1,749,550.
I round off this finding to $1,750,000.
I now consider the value of the land after resumption.
Despite the persuasive submission made by Senior Counsel for the Respondent in support of
its contention that no compensation should be awarded for the perceived need to construct the buffer
wall and to aircondition the ground floor of the proposed Dormitory Building B3 and two of the
proposed Tertiary Boarding Buildings TB1 and TB2, I have decided to make an award of
compensation for these items of claim. It is, of course, acknowledged that dispossessed owners are
to act reasonably although they are not expected to mitigate their losses (vide Pejama Pty Ltd v.
Commissioner of Main Roads (1988-89) 12 QLCR 278 p. 289), but they are also entitled to full and
fair compensation for their losses. In this case, the claimant company has proceeded with the
college development largely as originally planned and substantially in accordance with the Council
approved Master Plan for the development of the site. I say substantially because there have been
some departures from it e.g. the repositioning of the internal road system and the siting of the
dormitory buildings further to the north. But it must be recognised that at date of resumption the
college development was well progressed as illustrated by a colour plan in evidence showing the
years during which the college buildings were constructed. This being the case, I cannot see it as
being unreasonable that the claimant company would expect to be fairly compensated for any loss in
the value of the college complex at resumption date due to the resumption.
Now although no concession was made by the respondent about there being no need for the
claimant company to take any noise amelioration measures for the full development of the college, I
found it of assistance, if the Court was not of a similar view, that the respondent did make
submissions in respect of the discounted cost of taking those measures until the Bypass construction
became four lanes in the Year 2021.
I am satisfied on the evidence as a whole that the value of the college land is deleteriously
affected by the resumption and the proposed use of it by the respondent (a two-lane bypass road by
the Year 2014 - although the projected date may be 2008), and a four-lane bypass road by the Year
2020. It seems to me inconceivable that the future use of the bypass road by a high volume of
vehicular traffic, including 10 percent heavy vehicles, would not have some effect on the ambience
and peaceful use of the college by its occupants. This finding flows automatically from the largely
convergent evidence of the acoustic engineers. But to determine compensation for this diminished
land value post resumption is not by any means a simple matter.
I am satisfied that noise amelioration measures should be undertaken by the claimant in the
fullness of time, notwithstanding that it was aware of the possible requirement of land for road
purposes as early as its date of purchase of the parent parcel for the college, and again
notwithstanding that provision was made in the approved Design Plan S93 for the road reserve.
I am also satisfied on the evidence provided by many witnesses called by the claimant
-- 31 of 40 --
32
company that the weight of probability is that the college will proceed with the completion of its
development and with the construction of the boarding accommodation building B3 and the four
tertiary accommodation buildings within the time frame indicated. I am satisfied that, again on the
weight of probability, these buildings will be constructed on the site locations indicated on Plan S93.
I do not intend to try and reconcile the differing cost assessments for the proposed buffer
wall. Mr Neilsen estimates this cost for a 5.5 metre wall for the entire length of the resumption line
with some return fencing on both the side boundaries and the retention area as at resumption date to
be $672,200 ($700,000 adjusted by me to $672,200 to represent cost as at the date of resumption).
Mr Neilsen's costs of the wall based on Mr Hall's workings (along the resumption line only) is
$595,000 in October 1995 cost price terms - or $571,500 adjusted to the date of resumption. Mr
Hall's cost estimate is $530,610 as at both 1997 and the date of resumption.
But it was conceded by the claimant during the case that it may not be necessary to construct
a wall to the height of 5.5 metres along the whole of the resumption line. On the premise that there
will be a need to construct the wall 5.5 metres high for 375 metres of this frontage, and that the wall
for the balance of the frontage and returns will be only 2.5 metres high, then it says the cost of its
construction will be $500,000. Mr Hall's cost of the same wall is $466,875. I adopt a cost of
$500,000 as a basis for my compensation determination.
Next I propose to deal with the component part of the claim for the cost of the proposed
airconditioning (Item 7). I am satisfied if and when building B3 and buildings TB1 and TB2 are
constructed, the airconditioning of them as proposed by Mr Hall will be warranted. I have come to
this conclusion after careful consideration of the evidence of the acoustic engineers. I adopt Mr
Hall's design for the airconditioning units (the "split" system) in preference to the "ducting" system.
Mr Doran has calculated the cost of airconditioning the ground floor of the proposed building B3
and two of the proposed tertiary boarding accommodation units, using Mr Hall's "split" system, in
the sum of $88,242 as at the date of resumption. Mr Hall's 1997 cost estimate for airconditioning
for the same buildings is $106,540, and only marginally lower at the date of resumption. I adopt Mr
Hall's estimate.
But there is some dispute as to when the necessary capital may be needed for outlay on the
wall and airconditioning. The claimant suggests the wall should be built and the airconditioning
installed in the Year 2010. The respondent suggests that, if noise amelioration measures are to be
taken, they will not be necessary till the Year 2021 (the date of the completion of the four lane
section). After having examined Mr Kamst's noise level projections for the two-lane bypass (Figure
3 in Exhibit 17), I have come to the conclusion that there is sufficient likelihood of noise penetration
onto the subject site to acoustically affect proposed buildings B3 and TB1 and TB2 (they are located
between the 63dBA line and the 68dBA line) by the Year 2010. Further, Mr Kamst says that along
the bypass road without any noise attenuation measures, noise levels are predicted at the proposed
accommodation buildings to be 66dBA, and this is in excess of his adopted 63dBA standard for the
-- 32 of 40 --
33
implementation of noise amelioration measures. I find again on the balance of probabilities that
noise amelioration measures should be in place by the Year 2010. This being the case, it is
necessary for me, in order to determine the loss in the value of the retention area land, to calculate
the present value (at resumption date) of the cost of the wall ($500,000) and of the cost of the
airconditioning ($106,540) due in the Year 2010 - a period of 16 years - using an appropriate interest
rate.
Now the claimant has used in its claim for compensation calculations an interest rate of 5
percent. The respondent uses an interest rate of 8 percent which, it says, is consistent with the
long-term Bond Rate at the time of resumption. But long-term these deferred capital sum discounts
certainly are - 16 years - and recent trends in interest rates certainly provide an illustration as to just
how volatile the interest rate market can become over time. Again extending any doubts I have in
favour of the claimant, and for the purpose of this exercise, I propose to adopt the discount interest
rate of 5 percent proposed by the claimant.
But before proceeding to my relevant date cost calculations, I should comment that the
evidence of the recalled Mr Neilsen does not assist the claimant with its submission that a likely
escalation in building costs and airconditioning costs during the 16 year period should offset, as it
were, the discount cost factor. Mr Neilsen, and Mr Hall, could not forecast movements in building
costs with any conviction over a longer period than two years - and price movements over the last 16
years certainly cannot be taken as a basis for forecasting future price movements.
Additionally, while I cannot find an authority which deals directly with the issue of
allowances for inflation (or escalation in prices), in the Judgment of the High Court in Re: The
Commonwealth v. Milledge (1953-4) 90 CLR 157 it was held that an additional sum allowed by the
trial judge by reason of the fall in the purchasing power of money between the date fixed for
assessment and the date of his judgment ought not to have been included.
I now proceed to calculate, using the publication "Inwards Tables", the present cost (although
to remove any confusion this really is the cost as at the date of resumption (11 March 1994)), of the
projected capital expenditure costs of the proposed wall and airconditioning. It is:
Buffer Wall
Present value of $500,000 due in 16 years @ 5% interest per annum -
$500,000 x 0.45811 = $229,055
Airconditioning
Present value of $106,540 due in 16 years @ 5% interest per annum -
$106,540 x 0.45811 = $ 48,807
I now consider other items included within the claim for compensation. With respect to the
claim of $41,000 for the loss in value to the retention area by the presence of the future buffer wall
(Item 3), I find the basis for Mr Lowe's assessment is untenable. Firstly, he values the land claimed
to be affected (at $89,000 before discounted in the claim to $41,000 for delayed expenditure) having
-- 33 of 40 --
34
regard to the effect of the proposed wall on the value of 22 potential residential allotments adjacent
to it. Now this method of compensation assessment lacks cogency since what will be affected by
the presence of the wall if and when it is erected is not potentially subdivisable lots, but land with no
potential for residential subdivision within the zoning as at the date of resumption - which was
"Special Facility (Educational, Cultural, Recreational and Associated Accommodation)". Now the
effect of the proposed wall on the value of the college retention area land has to be assessed on the
basis of the value of the land to the owner - i.e. to the claimant company, and in its hands any land
which is affected in value by adjacency or proximity to the proposed wall, has to be valued as part of
the land used as an educational institution.
Nevertheless, I am satisfied on the evidence that the proposed wall have a deleterious effect
on the value of the college land due to such factors as the interruption of breezes, the confining
nature of the proposed structure and the effect on the general amenity and ambience of the college.
But the problem is to quantify the loss in value. Doing the best I can, I find that the proposed wall
has a deleterious effect on such part of the retention area as extends from the resumption line to the
approximate position of the 60dBA line as shown in Mr Kamst's report - Figure 4 in Exhibit 17. I
estimate this area to extend approximately 100 metres from the resumption line - containing an area
of approximately 5 hectares. I adopt the valuation diminution factor of 10 percent used by Mr Lowe
in his valuation exercise, and calculate the loss in value of the retention area due to adjacency or
proximity to the proposed wall-to-be, as at the date of resumption:
5 hectares @ $55,000 per hectare x 10% - or $27,500.
But again this loss in value will not occur until the wall is constructed, the need for which I
have already found to be the Year 2010. So that this compensation assessment has also to be made
based on the present value of $27,500, due in 16 years at an interest rate of 5 percent or -
$27,500 x 0.45811 - or $12,598.
I now consider the claim for the loss in value of land for the proposed buffer wall in the sum
of $8,000 (Item 4).
I find there is no need for the buffer wall to be set 8 metres from the resumption line, post
resumption. I adopt the evidence of Mr Horman that the wall could be built on the resumption line
with one earth mound extending 4 metres into the retention area. This earth mound will be
required, in accordance with the claim for compensation, for a distance of 375 metres along the
resumption boundary. Accordingly, the area to be rendered unavailable for use by the college,
although it must be said it would be available for landscaping, is adjusted from the area used by Mr
Lowe (0.412 hectares) to 0.15 hectares. The loss in land value as at the date of resumption is
therefore calculated as:
0.15 hectares x $55,000 - or $8,250.
This loss, too, has to be deferred as follows:
$8,250 x 0.45811 - or $3,779.
-- 34 of 40 --
35
Summarily, I now consider the effect of the perceived need for the construction of the barrier
wall, the perceived need to install airconditioning in the proposed accommodation buildings, the
diminution in value of the retention area due to proximity to the proposed wall and the loss in land
value of the land to be occupied by the wall mound has on the value of the retention area land. In so
doing, and adopting the foregoing calculations of present value (or cost at date of resumption) I find
the value of the claimant's land after resumption should be reduced as follows:
Present cost of buffer wall $229,055
Present cost of airconditioning $ 48,807
Present value diminution in land
adjacent or in proximity to proposed
wall $ 12,598
Present value of loss in land
value to be occupied by
wall mound $ 3,779
Total Value Diminution $294,239
This value diminution equates $10,135 per hectare over the area of the retention area land
(29.03 hectares). I round this calculation off to $10,000 per hectare. It follows then, to compensate
the claimant for its loss for the value of the land resumed (Item 1 in the Claim for Compensation),
the perceived need to erect the proposed buffer wall (Item 2 in the Claim for Compensation), the loss
in the value of land by presence of the proposed buffer wall (Item 3 in the Claim for Compensation),
the loss of land for the buffer wall (Item 4 in the Claim for Compensation) and the cost to
aircondition the ground floor of three of the proposed dormitory buildings (Item 7 in the Claim for
Compensation), the following calculation is made:
Value of Land before resumption -
31.8 ha @ $55,000 per ha - $ 1,750,000
Less
Value of land after resumption -
29.03 ha @ $45,000 per ha - say $ 1,300,000
Compensation for Loss in Land Value $ 450,000
-- 35 of 40 --
36
I now consider other items in the claim for compensation.
Item 5 - Disturbance to Ambience/Concept
This claim is in the sum of $20,000. I agree with Senior Counsel for the Respondent that
there is no justification that such a claim exists. While I have some sympathy for the reason the
college makes such a claim, an award of compensation cannot be made based on sentiment. There
is simply no objective evidence to support the claim. No compensation is awarded under this head
of claim.
Item 6 - Architect's Costs for Redesign
I propose to deal with this item under the heading "Item 10 - Costs".
Item 8 - Loss of Profitability
A claim is made in the sum of $337,000 for this item. I am again indebted to Senior
Counsel for the Respondent for his remark, with which I agree, that "this claim must be the most
opportunistic the Court has seen for a long time". It is opportunistic because the very foundation for
Mr Crane's calculations is unsoundly based. Mr Crane told us that he was given information that
the zoning of the college complex provides for an occupancy rate of 35 persons per hectare, and it is
upon this occupancy rate he calculates loss of revenue contribution occupants due to the resumption
would be 91. Now this assumption is fundamentally flawed for two reasons. The evidence of Mr
Dance, which I accept, is that the declared population densities within the relevant Town Planning
Scheme relate to multiple dwelling use mainly in the "Residential C" zone, and that population
density arrangements are not applicable in any other zone. Clearly it is not open then to use
population densities as a basis for calculating future loss in the number of contribution occupants
since the zoning of the college land as at the date of resumption was "Special Facility - (Educational,
Cultural, Recreational and Associated Accommodation)".
The second reason is that Mr Crane's assumptions include that the population density is
spread evenly over the whole of the parent parcel, and this is simply not the case since the evidence
is that there was never any intention to construct buildings on the resumed land. Further, the
Council imposed no such restrictions in respect of the approved development. Again, there has
been no reduction in the number or scale of any building works proposed for the land, this
notwithstanding that the claimant had knowledge of the respondent's requirements for road purposes
for the Bypass Road since the beginning of 1992.
The claim for loss of profitability fails, and no compensation is awarded under this head of
claim.
Item 9 - Interest
-- 36 of 40 --
37
This claim will be dealt with at the end of this decision.
Item 10 - Costs
Amount of claim $21,340
(this item is more commonly called
"Disturbance")
I propose to deal with each item of the costs claim individually, but before so doing, I should
say that there is authority for the proposition that, in compensation matters, dispossessed owners are
entitled to recover from resuming authorities compensation for costs reasonably incurred in the
preparation and lodgment with this Court of a claim for compensation.
It is submitted by the respondent in this case that, for the purpose of determining
compensation under the heading of Costs (Disturbance), it is the costs involved in the preparation of
the original claim for compensation which are to be considered for compensation assessment
purposes. The original claim for compensation is set out on page 2 of this judgment. As discussed
earlier, this original claim was amended twice during the hearing of the matter. The final claim
details (Exhibit 6A) are set out on pages 3 and 4 of this judgment.
The Costs (Disturbance) claim items which are pursued by the claimant are set out in the
original claim for compensation - vide page 2 of this judgment. I propose to deal with each item in
turn, but in a slightly different order than that used in the original claim. But before considering
each item on merit, I might say that it is necessary to decide just which of the claims is "the claim for
compensation". It is urged by the respondent that the Court should not award compensation in
respect of the Quantity Surveyor's fees in the preparation of the claim, the Engineer's fees and the
Acoustic Engineer's fees in the preparation of the claim as there was no mention in the claim about
an award of compensation for the cost of the erection of a buffer wall until the opening day of the
case when the first amended claim was lodged with the Court.
I have decided that, for the purpose of a compensation award under the heading of
"Disturbance" for fees involved in the preparation of a claim for compensation, the "claim for
compensation" is the claim finally lodged with the Court.
I now consider each individual item of claim.
Re: Legal Fees -
Claim $1,500. By consent, this claim is allowed and in the agreed sum of $1,500.
Re: Valuation Fees -
Claim $8,000. By consent, this claim is allowed and in the agreed sum of $8,000.
Re: Architect's Fees to Redesign Scheme and Buildings -
-- 37 of 40 --
38
Claim $3,500 and
Re: Architect's fees in the Preparation of the Claim -
Claim $3,000.
It is submitted by the respondent that this claim is not compensable as there was insufficient
evidence led to its proof, and that the changes in the Master Plan were the result of other factors
unrelated to the resumption.
Now the only available evidence on this matter was that provided by Mr Kuskopf, who told
us that the claimed fees were rendered to the claimant on the basis that they were purely and simply
incurred because of the assessment of compensation and for no other matter. Mr Kuskopf also told
us as a result of the resumption, more additional work is anticipated in the future which will involve
extra fees of in the order of $3,500 to $4,000 - but understandably no provision is made in the claim
for possible future fees. Mr Kuskopf told us that his fees were based on time which was spent
preparing particular documents to enable the claimant company to look at the matter. He prepared
sketch plans, and had meetings with other consultants. The work involved himself and other staff
members. There were meetings on the site, meetings with officers of the Department of Transport,
telephone calls and the like. All activities are entered in an office diary. One of the plans prepared
by Mr Kuskopf is in evidence (Exhibit 10) and it clearly relates to the buffer wall design.
I am satisfied the architect's fees were reasonably incurred for the purpose of the preparation
of the claim for compensation and on the re-design scheme, and the amounts claimed are verified by
a copy of an invoice rendered to the claimant on 28 March 1996 (Exhibit 44). I award $6,500 for
these items of claim.
Re: Quantity Surveyor's Fees in Preparation of the Claim -
Claim $2,700.
It is submitted by the respondent that these fees are not compensable as a disturbance item as
the work carried out by Mr Neilsen was directed to the issue of the construction of the proposed
buffer wall, and that no such claim was pursued by the claimant until the commencement of the
hearing. But I have already held that for disturbance claims, the claim for compensation is the
finally amended claim, and there is an obvious reference to the cost of the wall construction therein.
I find this item of claim allowable. In evidence is a copy of Mr Neilsen's (Townsville Cost
Consultants) invoice/statement dated 29 March 1996 (Exhibit 41) which verifies the quantum.
Compensation for Quantity Surveyor's fees in the preparation of the claim for compensation is
awarded in the sum of $2,700.
Re: Engineer's Fees in Preparation of the Claim -
Claim $1,740.
It is again submitted by the respondent that these fees are not compensable for the same
-- 38 of 40 --
39
reasons as in Re: Quantity Surveyor's Fees. As with the Quantity Surveyor's fees, and also for the
same reason I find that compensation for this item is payable. Also in evidence is a copy of a
memorandum of fees served upon the claimant (Exhibit 70) dated 28 March 1997 verifying the sum
claimed. Compensation for Engineer's Fees in preparation of the claim for compensation is
awarded in the sum of $1,740.
Re: Consulting Acoustic Engineer's Fees in Preparation of the Claim -
Claim $900.
Again for the same reason, it is submitted by the respondent that these fees are not
compensable. But as with the earlier claims, and also for the same reason, I find this claim is
compensable. In evidence is a copy of an account served on the claimant by Ron Rumble Pty Ltd
dated 29 February 1996 (Exhibit 69) in the sum of $877.50. I award $877.50 compensation for this
item of the claim.
In summary, then, my award of compensation under the heading of "Costs (Disturbance)" is:
Legal fees in preparation of the claim $ 1,500.00
Valuation fees in preparation of the claim $ 8,000.00
Architect's fees to redesign scheme and buildings $ 3,500.00
Architect's fees in preparation of the claim $ 3,000.00
Quantity Surveyor's fees in preparation of the claim $ 2,700.00
Engineer's fees in preparation of the claim $ 1,740.00
Consulting Acoustic Engineer's fees in preparation of the claim $ 877.50
Total award of Costs (Disturbance) $ 21,317.50
In making compensation orders, it is usual to round off the quantum of compensation awards
but to do so for this award of costs would have implication for a pending interest rate award, so I
decline to so do.
My determination of compensation in the matter is -
COMPENSATION FOR LOSS IN LAND VALUE -
(See page 42) $ 450,000.00
COMPENSATION FOR DISTURBANCE $ 21,317.50
TOTAL AWARD OF COMPENSATION $ 471,317.50
Section 28 of the Acquisition of Land Act 1967 provides that the Court may order that
interest be paid upon the amount of compensation determined by it, that such interest shall be at such
-- 39 of 40 --
40
rate percentum per annum as the Court deems reasonable, and that interest shall not be payable in
respect of any compensation advanced under Section 23 of the Act.
The Court has been informed that no compensation has been advanced in respect of this
resumption.
Accordingly, I ORDER that, in addition to compensation payable, interest be paid by the
respondent Department of Transport to the claimant Congress Community Development and
Education Unit Limited at the rate of 8.5 percent per annum on the following sums and for the
following periods:
(a)On the sum of $450,000 for the period commencing on the date of resumption (11 March
1994) and ending on the day immediately preceding the date upon which payment of
compensation is made;
and
(b)On the compensation award for disturbance items commencing upon the dates the
respective award items fees were paid by Congress Community Development and
Education Unit Limited (if they were paid) and ending upon the day immediately
preceding the date upon which payment of compensation for disturbance is made.
Member of the Land Court
-- 40 of 40 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1998/032