Chief Executive, Department of Transport v Nadco Pty Ltd [1998] QLAC 23 (1997-1998) 18 QLCR 408
IN THE LAND APPEAL COURT No. A96-05
HELD AT BRISBANE
In the matter of an appeal to the Land Appeal Court by the Chief Executive,
Department of Transport, from the decision of the Land Court in the matter
of the determination of compensation payable consequent upon the
resumption by the Director-General, Department of Transport, for future
road purposes under the provisions of the Acquisition of Land Act 1967 and
the Transport Infrastructure Act 1994 of an area of approximately 7843
square metres being Lot 1 on RP 32951, County of Stanley, Parish of
Tingalpa.
and
In the matter of an appeal to the Land Appeal Court by the Chief Executive,
Department of Transport from the decision of the Land Court in the matter
of an application for costs of, and incidental to, the hearing of the claim for
compensation.
BETWEEN
CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT
AND
NADCO PTY LTD
Appellant
Respondent
JUDGMENT
Judgment delivered at Brisbane this Twenty-third day of February 1998
There are two appeals before this Court from decisions of the Land Court in this matter. The
first, dated 28 April 1997, was a determination of a claim for compensation under Part 4 of the
Acquisition of Land Act 1967 arising from the resumption of land owned by the claimant at 20
Brand Street, Hemmant for “future road purposes”. The second decision, dated 18 July 1997,
concerned the costs of the compensation hearing. The constructing authority is the appellant in
both instances.
The land, which is freehold having an area of 7,841 square metres, is described as Lot 1
on Registered Plan 32951, Certificate of Title Volume 4377, Folio 49, in the County of Stanley,
[1998] QLAC 23
-- 1 of 10 --
2
Parish of Tingalpa. It is near a number of factories. The Brisbane-Cleveland railway line runs
beside the southern boundary. It was zoned “Residential A”. At the time of the resumption the
Brisbane City Council had given its consent to its use as “R1 Density Villa Units”. The claimant
purchased the land in May 1991 and had begun construction of twenty residential villa units on
it. Sewerage and stormwater drainage works had been carried out, the land had been filled,
piling had been completed, six concrete slabs had been poured, and an acoustic barrier fence had
been partly built. The claimant had intended to complete the construction of the units and later
to sell or let them. It was agreed that, had the work not been brought to a halt, construction
would have been completed by the date of resumption.
The claimant ceased construction in early October 1993 in response to a request from the
constructing authority dated 30 September 1993. Before receiving that request a letter dated 28
September 1993 had been written on behalf of the claimant to the constructing authority offering
to sell the land for $1,300,000.00. That offer was not accepted, and on 29 March 1994 the
constructing authority wrote to the claimant giving a statement of reasons for the proposed
resumption. On 14 April 1994 the claimant agreed to the taking of the land, and the resumption
was proclaimed in the Queensland Government Gazette of 13 May 1994. The claimant served a
claim for compensation dated 17 May 1994 on the constructing authority in which it sought
$1,113,262.50. On 24 June 1994 the constructing authority paid $598,000.00 to the claimant by
way of advance against compensation pursuant to s.23 of the Acquisition of Land Act.
On 25 January 1996 the claimant referred the determination of the amount of
compensation payable in respect of resumption to the Land Court. The total sum then claimed
was $1,193,593.63. At the hearing before the learned member, which began on 1 August 1996
and continued on 2 and 5 August 1996 and 26 and 27 September 1996, the constructing authority
contended for $483,500.00. On the final day of the hearing the claimant, with the leave of the
Court and without opposition from the constructing authority, amended its claim to $892,000.00.
Before the member two disturbance items, valuation and legal fees, were agreed between the
-- 2 of 10 --
3
parties at $8,575.00.
The member determined that compensation of $718,611.00 should be paid: $710,036.00
as the value of the land, together with the $8,575.00. The constructing authority was ordered to
pay interest at the rate of 8.75 per cent. per annum on the $710,036.00 from 13 May 1994 up to
and including 24 June 1994, and on the sum of $112,036.00 from 24 June 1994 up to and
including the day immediately preceding the day on which payment of compensation was made.
There was a further order for interest on the $8,575.00.
The member ordered the constructing authority to pay the claimant’s costs of and
incidental to the compensation hearing.
The member arrived at the figure of $710,036.00 by adopting the same method as that
used by the valuers who gave evidence before her. They were unable to find sales of comparable
properties and so they assessed the value of the land by estimating the gross returns on the sales
of the units and then making appropriate adjustments to that figure. She assessed the gross
realization of the twenty proposed units at $2,060,000.00 from which she deducted selling costs
of $77,250.00, a figure for “Profit/Risk of Realization 15%” of $258,620.00, development costs
remaining of $936,700.00, interest of $27,476.00 for half the development and a selling period of
eight months at 8.8 per cent., holding costs of $23,292.00, and acquisition costs of $26,626.00.
The first issue raised by the constructing authority on these appeals concerned the
member’s determination of the development cost at $936,700.00, which was made up of
$927,260.00 as the cost of completing construction and $9,440.00 for title and registration fees.
Mr Gibson Q.C., on behalf of the constructing authority, submitted that the member had erred in
her conclusion as to the cost of completion of the development. The member had arrived at the
$927,260.00 after she had assessed the total construction cost at $1,285,942.00 to which she
added $181,318.00 (14.1 per cent. for preliminaries, professional fees, and the builder’s margin),
and from which she subtracted $540,000.00 as the cost of the work completed.
Mr Gibson argued that the member had erred in two respects in those assessments: first,
-- 3 of 10 --
4
by concluding that the claimant intended a standard finish for the units, as assumed by Mr
Stephen Baird, a building estimator called by the claimant, rather than a medium finish as
assumed in an estimate prepared by Mr Robert Popplewell, a quantity surveyor called by the
constructing authority; and secondly, by failing to include an allowance for contingencies in the
estimate of the costs of construction of the development.
Mr Baird’s estimate of the cost of construction of the units as adjusted to rectify errors,
was $886,238.00 and Mr Popplewell’s corresponding figure $979,265.00. The member adopted
Mr Baird’s estimate, as adjusted, because she was satisfied that the difference between the two
estimates, $93,027.00, resulted from the different assumptions made as to the finish which was to
be used for the units. The member concluded that the finish intended was standard and for that
reason preferred Mr Baird’s estimate. To the $886,238.00 she added $399,704.00, derived from
Mr Popplewell’s evidence, for the cost of external works and services, thus reaching her figure
for total construction cost of $1,285,942.00.
Mr Gibson argued that there was no evidence before the member upon which she could
have concluded that the units were to have a standard finish rather than a medium finish. He
pointed to the evidence of Mr Peter Griep, a director and shareholder of the claimant, that the
finish for the units was to be the same as that of another unit development of the claimant called
Hemmant Village, which was south of the resumed land across the railway line, and to the
evidence of Mr Popplewell that he assessed the finish of Hemmant Village as “medium”.
If that had been the only evidence on this subject the claimant’s argument before us
would have been a sound one. There was, however, other evidence - in particular that of Mr
Douglas Merritt, the managing director of Peter Kurts Properties Limited, who was called by the
constructing authority, to the effect that the finish of Hemmant Village was only standard. He
was asked in cross-examination for his assessment of the building standard and replied that it
was “in the bottom end”. Furthermore, Mr Stephen Austin, registered builder and director of
Austin Constructions Pty Ltd, gave evidence that Austin Constructions Pty Ltd entered into a
-- 4 of 10 --
5
cost-plus building contract dated 2 June 1993 with the claimant to construct the twenty units
which left to the claimant the right to specify the fittings as the work progressed. That a standard
finish was intended for the buildings on the land seems probable when one considers Mr
Merritt’s overall assessment of the site. In a letter dated 15 July 1996 to the constructing
authority (Exhibit 16) he recorded that, at the request of the constructing authority and in his
capacity as an “on-going developer”, he visited the site with a view to forming a “market
opinion”, which he gave as follows:
“The site is an inferior low grade property adjoining a railway line and existing
older homes in the lower end of Hemmant. It has obviously been filled for re-
development purposes.
The general area is of a lower standard and if the property was offered to our
Company we would not be interested in purchasing it raw, or marketing the
proposed units on behalf of another developer.
There is no value in the site, and in my opinion the proposed development will
produce an inferior product. The only market available would be to investors and
it would require professional marketers to sell it, at a very high fee. It would
probably present difficulties even in this market as the proposed plans do not
actually suit a stylish rental market as there is only one bathroom configuration,
and the two and three bedroom units are almost of equivalent size.
As far as I can ascertain, there will be no amenities available on site, such as
swimming pool, barbecue cabana or common area, which further devalues a site
that has little appeal and no marketing attraction.”
In the light of that assessment, which appears on the evidence to be a reasonable one, it would
seem unlikely that the claimant would have intended to spend more in developing the site than
was absolutely necessary and so would have been likely to use a standard finish on the buildings.
Before the member it was submitted on behalf of the constructing authority that a further
sum for contingencies should be added to the estimates of Messrs Baird and Popplewell. Mr
Popplewell said he would allow five per cent. on the value on the structural work. Mr Baird said,
however, that he saw no reason to allow for contingencies for “what is a straightforward
construction”. The member concluded that since she was adopting Mr Baird’s detailed estimate
-- 5 of 10 --
6
of costs, and since the development had reached the stage it had, she would not allow any sum
for contingencies.
While it may be thought that as a matter of ordinary experience in matters of this kind it
is prudent to allow something for contingencies, it must be observed that not all contingencies
are adverse. It may also be accepted that there is not an inflexible rule that contingencies must
always be provided for. No doubt in many cases of this sort there will be an allowance for
adverse contingencies, but the conclusion that no such allowance should be made cannot be
rejected out of hand. Making no allowance will be justified if the likelihood of increases in costs
is so remote as to justify their being ignored, or if, after the possibilities of adverse and
favourable contingencies are weighed up, they are found to cancel each other out. The member’s
conclusion was based on the former assessment since she regarded Mr Baird’s detailed estimate
as sufficiently certain. She noted that Mr Baird’s evidence was independently verified. We are
not persuaded that it has been demonstrated that the member erred in rejecting Mr Popplewell’s
evidence and in accepting Mr Baird’s concerning contingencies. The constructing authority
therefore fails on that issue.
In the second appeal the constructing authority contended that the member had erred in
making the order for costs in favour of the claimant. It was asserted that the member should
have made no order as to costs, or alternatively should have ordered that the parties bear their
own costs.
The constructing authority relied chiefly upon the claimant’s eleventh-hour amendment
of its claim, the effect of which was, by operation of s.27(2) of the Acquisition of Land Act, to
turn the tables on the constructing authority on the matter of costs. Had the claim remained at
$1,193,593.63 until the member’s determination of compensation the constructing authority
could have applied for an order for costs in his favour and the claimant could not have applied
for an order for costs in its favour because the amount of compensation as determined would
have been neither the amount finally claimed by the claimant in the proceedings nor would it
-- 6 of 10 --
7
have been nearer to that amount than to the amount of the valuation finally put in evidence by the
constructing authority.
The member, in giving her reasons for her decision on costs, referred to two matters that
she said may be relevant to the exercise of the Land Court’s discretion in appropriate cases: first,
that a successful claimant is entitled to recover the costs of obtaining compensation in the
absence of any special circumstances, and secondly that the Court “can inquire whether the
conduct of the parties has been such as to force unreasonable and unnecessary litigation”.
Mr Gibson did not challenge the second proposition, authority for which may be found in
Moyses v. The Townsville City Council (1979) 6 Q.L.C.R. 271 at p.274. He did, however,
challenge the first proposition. But authority for it may be found in the often-cited decision in
Minister for the Environment v. Florence (1980-81) 45 L.G.R.A. 127 to which the learned
member referred. That case was a disputed claim referred to the Supreme Court of South
Australia for the assessment of compensation under the Land Acquisition Act 1969 (S.A.). Wells
J. made these general observations concerning costs:
“Compulsory acquisition cases differ of course from ordinary claims dealt with in
the general jurisdiction in one significant respect: the claimant, unlike the
ordinary plaintiff, had no choice whether to make a claim or not; the mere
acquisition by compulsory process gave him, by virtue of s.18 of the Act, a claim
to compensation which he could hardly be expected to renounce.
Upon an ordinary claim in the general jurisdiction it is, generally speaking,
obvious who has won and who has lost, and correspondingly clear why costs
usually follow the event. Upon a claim for compensation for land compulsorily
acquired, it is not, generally speaking, appropriate to speak of one party as having
won; compensation is awarded to one who had already been given, by statute, the
right to receive it. It is therefore as just to say of the latter sort of case that the
claimant ought, in the absence of special circumstances, to receive his reasonable
costs of obtaining the compensation that is, ex hypothesi, his due, as it is to say of
the former sort of case that prima facie costs follow the event in favour of the
party who has won. But costs are, as always, discretionary, and no hard and fast
rule will ever be allowed to occupy part of an area controlled by a discretion,
however predictable the result of its exercise may be in certain sort of cases.”
(pp.149-150)
We see no reason to question the authority of that passage which is well accepted in cases of this
kind as a general statement of principle. We should add, however, that in the recently decided
-- 7 of 10 --
8
case of Yalgan Investments Pty Ltd v. Council of the Shire of Albert (unreported, 11 December
1997, A94-94) this Court discussed in some detail the legislative provisions and general
principles relevant to a decision on costs. We shall not repeat that discussion here.
The late amendment of the claim resulted from the claimant’s abandoning during the
hearing what the learned member referred to as “significant parts of its claim”: an item for
injurious affection and another arising from the builder’s claim to compensation. The member
observed that the parties were a considerable distance apart in their estimates of compensation
and that the $1,193,593.63 was “significantly higher” than the sum claimed on the final day of
the hearing. She was not satisfied, however, that the course of events would have been different
had the claim been reduced sooner. She noted the payment of the $598,000.00 and the low
valuation finally put in evidence by the constructing authority. She concluded: “While the
claimant was not ‘wholly successful’, the facts available to me indicate that the claimant would
not have obtained full compensation had it not proceeded with the litigation. I am not, therefore,
prepared to find that the claimant acted unreasonably in pursuing its claim and I have decided
that, in all the circumstances, the claimant should be awarded costs.”
As appears from what we have said already, the member treated the relevant sums relied
on by the parties as those finally advanced at the hearing. In doing so she was correct in our
view. She applied the construction of s.27(2) adopted by McPherson J.A. in Commissioner for
Railways v. Buckler [1996] 1 Qd.R. 18:
“Stated in general terms, what the court is now required to do in fixing the
incidence of costs under this rule is look to the final positions taken up by the
parties. In the case of the claimant, it is the quantum of compensation last
claimed. Theoretically at least, its amount might not be known until the final
address of counsel for the claimant. In practice, however, s.24(2A) furnishes a
disincentive against conduct like that. It does so by restricting the right to amend
a claim once it has been filed in accordance with s.24(2A) of the Act. Thereafter
an amendment may be allowed; but on terms including payment of costs: see
s.24(3).
On the other hand, there seems to be no comparable restriction preventing the
constructing authority from deferring disclosure of its final position until a late
stage of the proceedings. It will be discoverable only from ‘the amount of the
-- 8 of 10 --
9
valuation finally put in evidence by the constructing authority’, which means that
it cannot with confidence be known what the amount of it is until the constructing
authority closes its case.” (p.23-24)
That construction accords with the natural meaning of the words of the subsection whereas that
adopted in Arcpoint Pty Ltd v. Director-General, Department of Transport (1992) 14 QLCR 115
does not. In that case the learned member construed the word “finally”, where it appears in
s.27(2), as referring to “the point where the ‘battle lines’ have been drawn”, that is, after an
exchange of valuations and all supporting data either before or on the first day of the hearing. In
his opinion, following that whatever is done by a party during the hearing is done at his peril as
to costs (p.119).
In this case, the member clearly did not ignore the lateness of the amendment to the
claim. The complaint that is made is rather that she failed to give it sufficient weight in deciding
how her discretion should be exercised.
A number of considerations support the proposition that no error was made on costs. The
amendment was not opposed, and no order for costs was sought or made under s.24(2A). There
is no reason to doubt the member’s conclusion that the claimant would not have obtained full
compensation had it not proceeded with the claim. The terms of the Act, particularly the word
“finally”, indicate after all that late amendments will be permitted - by leave in the case of a
claimant - in the course of proceedings. It would be strange if the Land Court’s discretion to
award costs were to be regarded as automatically circumscribed once a turn of events obviously
contemplated by the subsection has occurred.
Giving all of those matters their full weight we nonetheless conclude that the member’s
discretion on costs miscarried. A clear intention evident in s.27(2) is to discourage exhorbitant
claims in compensation cases. It would not be unreasonable to describe the claim to
$1,193,593.63 as exhorbitant since it exceeded the sum arrived at by the member by such a large
amount. It remained the claim until nearly all of the costs of the hearing had been incurred.
With hindsight it can be seen that the claimant was permitted the substantial advantage of
-- 9 of 10 --
10
avoiding any possibility of an order for costs against it by its late amendment; to add to that an
order for costs in its favour went far too far we think. In the result we conclude that the
member’s discretion on the matter of costs miscarried and that she should have made no order as
to costs.
The constructing authority’s appeal against the decision of the Land Court of 28 April
1997 will therefore be dismissed, and his appeal against the costs decision of 18 July 1997 will
be allowed. The order for costs made by the member will be rescinded and no order will be
made as to the costs of the compensation hearing in the Land Court.
We shall invite further submissions on the costs of the appeals.
HELMAN J
JUSTICE OF THE SUPREME COURT
GJ NEATE
MEMBER OF THE LAND COURT
CH CARTER
MEMBER OF THE LAND COURT
-- 10 of 10 --
Official source: https://www.sclqld.org.au/caselaw/QLAC/1998/023