Bulk Materials (Coal Handling) Pty Ltd, Re [1997] QSC 18
-~-.
(/) ..,'
.~.. -"""
t=. ',-- ,... •..,.~
.,....._._ ..:0- .. 1
·State .Reporting Bureau
TRANSCRIPT OF PROCEEDINGS
(Copyright in this transcript is vested in the Crown. Copies thereof must not be made or sold
without the written authority of the Director, State Reporting Bureau.)
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
DEMACK J
No 3 of 1997
IN THE MATTER OF THE SUB-CONTRACTORS
CHARGES ACT 1974
and
IN THE MATTER OF ORDER 64 RULE 1B OF THE
RULES OF THE SUPREME COURT
and
REVISED COPIES ISSUED
State Reporting Bureau
Date :r I 'd.. I '1 f . _,.....,.
IN THE MATTER OF AN APPLICATION BY BULK
MATERIALS (COAL HANDLING) PTY LIMITED
(ADMINISTRATORS APPOINTED) (ACN 001559 655)
and
IN THE MATTER OF "THE CORPORATIONS LAW II
and
IN THE MATTER OF THE ADMINISTRATION OF
BULK MATERIALS (COAL HANDLING) PTY LTD
(ACN 001 559 655)
and
Iu THE MATTER OF AN APPLICATION BY QUEENSLAND
STEEL PRODUCTS PTY LTD (ACN 010 632 694)
FOR LEAVE TO INSTITUTE PROCEEDINGS AGAINST
BULK MATERIALS (COAL HANDLING) PTY LTD
(IN ADMINISTRATION)
-- 1 of 6 --
ROCKHAMPTON
.. DATE 07/02/97
JUDGMENT
10
20
30
50
60
2
-- 2 of 6 --
070297 KHW (Demack J)
HIS HONOUR: There are two applications before me but the
principal one is an application to determine whether
Queensland Steel Products Pty Limited ("Queensland Steel") is
entitled to a charge on money payable by Queensland Magnesia
(Operations) Pty Ltd ("QMag") to Bulk Materials (Coal
Handling) Pty Limited ('~Bulk Materials") in respect of a
contract between QMag and Bulk Materials for the construction
of an ore sorting magnesium plant at QMag's Kunawarara mine.
In a notice given to Bulk Materials on 25 November 1996 under
the Subcontractors Charges Act 1974 (liThe Act"), the charge
was claimed upon the money that will be payable by QMag to
Bulk Materials in respect of work done by Queensland Steel
"Under the contract with (Bulk ~1aterials) to supply,
fabricate, blast clean, paint and deliver structural steel
work for the QMag's Ore Sorting." The amount of the charge
was $256,769.75.
While the agreement between Queensland Steel and Bulk
Materials was expressed more fully in the affidavits filed in
Court, it seems to me that the words in the notice accurately
express Queensland Steel's obligations - lito supply,
fabricate, blast clean, paint and deliver" - structural steel
to QMag's Kunawarara mine. In performing those obligations,
Queensland Steel's managing director, David Parker, made
suggestions and recommendations about matters of design and of
protective coating. He also visited the construction site.
It was also Queensland Steel's responsibility to touch up
paint work on the steel and this would be done at the
construction site.
JUDGMENT
3
10
20
30
40
50
60
-- 3 of 6 --
070297 KHW (Demack J)
Bulk Handling appointe~ an administrator under Part 5.3A of
the Corporations Law on 19 November 1996.
On 12 January 1997, QMag paid Queensland Steel the amount of
$256,769.75 on the condition that Queensland Steel would
indemnify it for any loss it might sustain should the charge
not be valid.
Mr H Fraser QC, 'for Bulk Materials, submitted that the charge
was not valid because the defini tion of "work" in section 3 (1 )
of the Act refers to work upon the land where the contract or
subcontract is being performed. Here the work done by
10
20
Queensland Steel was not performed on the mine site at
Kunawarara. He relied on William Andrew Pty Ltd v. Santalucia ~
(1983) Qd.R. 349, ex parte Peter Fardolulys Pty Ltd (1987)
Qd.R. 345, re Leighton Contractors Pty Ltd (1985) 2 Qd.R. 377,
and Dowstress Pty Ltd v. The Mission Congregation Servants of
the Holy Spirit (1987) 1 Qd.R 150 C'DoVlstress").
Mr Jones QC, for Queensland Steel, submitted that, while the
contract between QMag and Bulk Materials was required to be
upon land, there was no requirement under the Act that the
work done by a subcontractor had to be on the land at
Kunawarara. He relied on the judgment of Derrington J in 50
Dowstress, re R A Story Pty Ltd (1993) 2 Qd.R. 355 ("Story")
and Kaldow Propriety Limited v. H J GLow & Associates Limited
(1971) N.Z.L.R. 311.
In my opinion, the Full Court decision in Dowstress is
JUDGMENT
4
60 .
-- 4 of 6 --
070297 KHW (Demack J)
indistinguishable from the present set of facts and requires
me to find that Queensland Steel has no valid charge.
In Dowstressi the subcontractor agreed to supply prestressed
hollow floor beams to the contractor which was constructing
extensions to the owner'~ hospital. The Full Court held that
no valid charge existed. Moynihan J (with whom Kelly ACJ.
agreed) based his decision on the words in s.3 of the Act
which defined "work in terms of 't;1hat is done or commenced upon
the land where the contract is being performed. II (p .157) .
Derrington J did not regard these words as signi£icant,
pointing out that under s.5 the charge may attach whether the
contract is in respect of land, buildings or chattels. He
based his decision on the fact that a charge applies only in
respect of "work done under the subcontract. II (p.152), so
that, "a contract to supply goods on which work of manufacture
is performed by a subcontractor is not a contract for work
within the meaning of the Act." (p.152).
Relying on the reasoning of Derrington J, Ryan J in Story held
that where a subcontractor who was to fabricate and erect
structural steel engaged another subcontractor to perform work
on the steel away from the land where the steel was to be
10
20
30
40
erected, the second subcontractor had a valid charge. With 50
respect, that is correct, but a very different situation from
the present case.
As I have said, this case is not distinguishable from
Dowstress. Queensland Steel has attempted to show that its 60
JUDGMENT
5
-- 5 of 6 --
070297 KHW (Demack J)
"work" can be separated from the cost of materials. That does
not alter the situation because the entitlemenf to the charge
arises from a contract to perform work alone, unless the
subcontractor is performing work on the land the subject of
contract. In these circumstances, the materials used on that
land are embraced withiI) the inclusive definition of "work" in
section 3. That is not the case here.
An attempt was made by Queensland Steel to demonstrate that
its contribution to the whole project of constructing an ore
sorting magnesium plant was very substantial. That is not a
factor that has any significance under the Act.
I am satisfied that Queensland Steel does not have a valid
charge and I order accordingly. Queensland Steel's
application for leave to proceed against Bulk Materials is
dismissed.
I order that Queensland Steel pay Bulk Materials' costs of
both applications.
JUDGMENT
6
10
20
30
50
60
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1997/018