BM Culley & Associates Pty Ltd v Metal Roofing & Cladding Pty Ltd [1996] QCA 365
IN THE COURT OF APPEAL [1996] QCA 365
SUPREME COURT OF QUEENSLAND
Appeal No 246 of 1995
Brisbane
[BM Culley & Associates Pty Ltd
v. Metal Roofing & Cladding Pty Ltd]
BETWEEN:
BM CULLEY & ASSOCIATES PTY LTD
(Defendant) Appellant
AND:
METAL ROOFING & CLADDING PTY LTD
(Plaintiff) Respondent
Macrossan CJ
de Jersey J
Dowsett J
Judgment delivered 01/10/1996
Judgment of the Court
APPEAL DISMISSED WITH COSTS TO BE TAXED.
CATCHWORDS: JUDGMENT for price of materials ordered by
appellant as disclosed agent - whether judge
entitled to find that appellant remained
liable notwithstanding agency - approach of
appeal court to conclusions drawn from
unchallenged factual findings.
Counsel: Mr D Gore QC, with him Mr P Hackett for the
appellant Mr PA Keane QC, with him Mr R Oliver for the
respondent
Solicitors: Hallets for the appellant
Hemming & Hart for the respondent
Hearing Date: 3 September 1996
-- 1 of 11 --
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No 246 of 1995
Brisbane
Before Macrossan CJ
de Jersey J
Dowsett J
[BM Culley & Associates Pty Ltd
v. Metal Roofing & Cladding Pty Ltd]
BETWEEN:
BM CULLEY & ASSOCIATES PTY LTD
(Defendant) Appellant
AND:
METAL ROOFING & CLADDING PTY LTD
(Plaintiff) Respondent
JUDGMENT OF THE COURT
Judgment delivered the 1st day of October 1996
This appeal is brought against a judgment given in the
District Court in favour of the respondent, for the price of
steel products manufactured and delivered by the respondent
for incorporation into a building being constructed by the
appellant at Yatala. The total cost of the steel was
$165,378.88, of which the appellant had paid $64,991.51.
Judgment was given against the appellant for the balance of
$100,387.37. The appeal relates, however, to only
$79,478.88 of that latter sum.
A company named Inverse Construction Systems Pty Ltd
("ICS") was a sub-contractor of the appellant, engaged to
design supply and install the steelwork. On 9 June 1994 the
-- 2 of 11 --
2
appellant placed a written order with the respondent for the
supply of roof purlins, for the price of $85,900. The order
said that the supply was "on behalf of Inverse Construction
Systems Ltd", raising the question whether the appellant, as
agent, would itself be liable for the cost. Significantly,
the respondent had, through its manager Lucas, previously
made clear to the appellant (through Bartlett), that because
the respondent was not happy dealing with ICS (because ICS
lacked "an established financial track record"), the
respondent required the appellant "to open an account on
this particular job". The appellant therefore completed an
application for credit which it provided to the respondent.
In these circumstances, the learned judge determined that,
notwithstanding the notation on the order of 9 June 1994,
the appellant retained a liability to the respondent for
that price of $85,900, "whether or not it was the disclosed
agent of ICS". The appellant does not challenge that
finding. The amount which is the subject of the appeal,
$79,478.88, is the difference between the total cost of all
steel supplied, $165,378.88, and $85,900.
The respondent supplied the additional steel, that is
steel beyond the value of $85,900, in response to
specifications provided orally, mainly by ICS. The
appellant had all along appreciated that much more steel
than $85,900 worth would be required. It fell within the
expertise of ICS, not the appellant, to provide the details,
so the appellant effectively left the ordering to ICS. As
time went on and delays occurred with the construction, the
-- 3 of 11 --
3
appellant became anxious to keep up the supply of the steel,
lest a liquidated damages clause in its contract with the
owner be activated. As the learned judge found, the
appellant was "pressuring the (respondent) to manufacture
and deliver (the) goods". As the respondent supplied the
additional steel, the respondent progressively invoiced the
appellant for the price. The appellant did not respond by
saying to the respondent that payment of the accounts was
not its responsibility.
The learned judge rested her judgment in favour of the
respondent, in respect of that part of the amount
outstanding in excess of the amount specified on the order
($85,900), on a contract arising from the conduct of the
parties, obliging the appellant to bear that cost. That is
the only finding which the appellant challenged on this
appeal.
Both parties accepted that the relevant test is
"whether a reasonable bystander would regard the conduct of
the (appellant) ... as signalling to the (respondent)" that
the appellant was undertaking an obligation to pay for the
additional steel delivered: see Empirnall Holdings Pty Ltd
v. Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523, 534-5.
The learned judge expressed the following circumstances
as warranting her conclusion:
"The defendant (appellant) was aware the plaintiff
(respondent) was manufacturing and delivering
goods of a value well beyond the $85,900 order it
gave the plaintiff; it accepted invoices from the
plaintiff without comment or protest and it
pressured the plaintiff to supply these goods as
quickly as possible, knowing the plaintiff was
only prepared to offer credit to it and not I.C.S.
-- 4 of 11 --
4
When looked at in this context, together with the
accepted practice within the building industry in
these circumstances, the defendant has by its
conduct agreed to pay a fair and reasonable price
for the plaintiff's goods sold and delivered to
it, even if on behalf of I.C.S. Those goods have
been supplied and delivered but not paid for.
There is no suggestion that the price charged is
not a fair and reasonable one."
With one reservation, Mr Gore QC, who appeared for the
appellant, accepted that those factual observations were
supported by the evidence. He queried only her Honour's
reliance on "accepted practice within the building
industry". We take it that the judge had in mind these
matters, to which she had only just referred:
"At first blush, it seems at least sloppy
housekeeping and even uncommercial conduct on
behalf of the plaintiff to continue supplying
expensive goods without a firm order from the
defendant. When looked at in context and taking
into account industry practice, I am satisfied
this is not necessarily so.
The plaintiff's Lucas explained that once the
building work started, further signed orders are
not required:
"Well, with project work it tends to grow
like Topsy, should I say, and orders keep
coming through from - maybe from a
detailer, we have mentioned previously.
It may be from the builder himself. It
could be from anywhere for us to proceed
and produce that material quickly".
(Transcript 62-3)
He added that it was not unusual in the trade to
receive details as to fabrication from I.C.S.
rather than the defendant.
Most of the work on the wall girts was done in
August 1994. I.C.S.'s Shepherd told the
plaintiff's Gibb: "forget about the price, just
get the purlins underway or the girts underway
because they were in a hurry for them."
(Transcript 123).
Gibb, when asked about the lack of any further
order from the defendant and why goods were
-- 5 of 11 --
5
supplied without an order, said:
"We do a lot of jobs for various people
and it's quite common for the order
number to be left as it is. There is a
lot of variations, so usually companies
just leave the one order number there."
(Transcript 122).
As the job reached the wall girts stage in about
August, there were difficulties because of
problems with material and because the defendant
was unaware of the manufacturing procedure and
during this period there was contact with the
defendant's Bartlett every second or third day as
he pressured Gibb for the goods."
We read her Honour's reference to "accepted practice
within the building industry in these circumstances" (our
underlining), to relate to the respondent's preparedness in
this particular case to continue to supply although not
armed with a further formal order, a preparedness explicable
by the pressures and practice to which the judge referred in
the passage just extracted. It was permissible for her to
take those matters into account.
We set out these further findings by the learned judge,
to provide a little more detail of the factual foundation
for her ultimate conclusion:
"The plaintiff continued to supply purlins and
girts for walls beyond the $85,900 of roof purlins
ordered by the defendant, in response to details
or specifications provided orally, mainly by
I.C.S.
The defendant was certainly aware that a further
order would be required for facia purlins and
girts and sections required for wall panels to
complete the job, (See Exhibit 19) but the
defendant did not place such an order. These
specifications had to be supplied by I.C.S. whose
expertise this was. The defendant's Bartlett
agreed that at the stage the walls were to go in,
there was a delay in the progress of the job which
was running behind schedule and the defendant was
concerned about a liquidated damages clause in its
-- 6 of 11 --
6
contract with McDonalds. It was imperative to the
defendant and to completion of the project that
the plaintiff continue to supply its products as
soon as possible. (Transcript 151). Bartlett, as
the defendant's project manager, was aware that
the plaintiff continued to supply goods beyond the
$85,900 order and to invoice the defendant for
these goods. By 3rd August 1994 something like
$90,000 worth of goods had been delivered by the
plaintiff without payment. The defendant did not
inform the plaintiff at any time that payment was
the responsibility of I.C.S. as the defendant
needed the goods on site to finish their contract
with McDonalds. Indeed, the defendant was
pressuring the plaintiff to manufacture and
deliver those goods."
Mr Gore submitted that her Honour's conclusion as to
the existence of a contract obliging the appellant to pay
for the steel was unsustainable, in light of the following
eight additional circumstances:
"1. under the earlier relationship between the
parties (which was temporally very close),
the appellant was an agent, not a principal;
2. under that earlier relationship, the
appellant's liability was limited to a
specific amount;
3. the orders for goods were placed by ICS, for
incorporation in work being done by ICS;
4. a "contract" with ICS was consummated before
any conduct on the part of the appellant, in
that the goods were ordered by ICS,
manufactured and/or delivered by the
respondent, and invoices were sent by the
respondent;
5. to the extent that the appellant's conduct
consisted of silence, silence is not normally
assent;
6. the respondent deliberately took a commercial
risk about payment;
7. as soon as a concern about payment arose, the
respondent demanded payment of ICS;
8. a lack of entitlement to recover against the
appellant does not defeat the respondent's
right to recover against ICS (it being
-- 7 of 11 --
7
immaterial, for this purpose, that ICS is now
in liquidation)."
Mr Gore relied on Warren v. Coombes (1979) 142 CLR 531,
submitting that because the primary facts are not in issue,
this appeal court is in as favourable a position as was the
trial judge, to reach a conclusion on the question whether
or not such a contract arose, and there being apparently no
credibility issue in the case, we should be prepared to
substitute any different view we hold on that issue. In
particular, he would rely on this passage (p. 551):
"... The established principles are ... that in
general an appellate court is in as a good a
position as the trial judge to decide on the
proper inference to be drawn from facts which are
undisputed or which, having been disputed, are
established by the findings of the trial judge.
In deciding what is the proper inference to be
drawn, the appellate court will give respect and
weight to the conclusion of the trial judge, but,
once having reached its own conclusion, will not
shrink from giving effect to it."
Mr Keane QC, who appeared for the respondent, submitted
that her Honour's conclusion was both open, and the correct
conclusion in the circumstances.
We consider that the circumstances she summarised as
justifying that conclusion do provide a substantial
foundation for it. The respondent had previously supplied
the appellant with $85,900 worth of steel with the express
reservation, accepted by the appellant, that because of the
respondent's concern about ICS's financial position, the
appellant would have to bear the liability to pay. The
appellant knew that the respondent would be providing much
more steel than the quantity subject to the order worth
$85,900. The appellant accepted that further steel, and
-- 8 of 11 --
8
incorporated it into its own construction. In fact, as time
went on, the appellant pressured the respondent to expedite
the supply. There is no suggestion that the respondent's
lack of assurance about ICS's financial position ever
subsided. The appellant accepted the steel; it also
received the respondent's invoices, and without challenge or
complaint. There is compelling basis, therefore, for the
conclusion that, as with the supply which occurred under the
written order, where the appellant was liable, so likewise
the appellant was to be taken as accepting liability in
respect of this subsequent supply.
We offer the following brief observations on the
additional circumstances offered by Mr Gore. As to 1, the
appellant was not simply an agent, but an agent obliged to
pay, notwithstanding that agency, as her Honour found. That
finding was not challenged. The significance of the
circumstance which led to that finding - the respondent's
insistence because of the financial doubts about ICS -
subsisted throughout the period of the further supply. As
to 2, the important additional circumstance is that the
appellant knew that much more steel than the $85,900 worth
would be required. As to 3, the significant point is that
the steel was incorporated into a building being constructed
by the appellant: the work was being done by ICS, it is
true, but it was being done by ICS for the appellant. As to
5, the appellant's "conduct" is not limited to silence -
highly significant other aspects were its utilisation of the
steel, and its applying pressure to the respondent to
-- 9 of 11 --
9
expedite delivery. Against that background, the "silence"
involved in such features as the appellant's failure to
challenge the invoices, takes on significance. As to 6, Mr
Lucas gave an explanation which apparently satisfied her
Honour (p. 64 transcript). As to 7, her Honour saw this as
"an attempt by the (the respondent) to keep its options open
at a worrying time", a reasonable view of the matter which
diminished any significance the point would otherwise bear.
Matter 8 is, in our opinion, simply irrelevant.
The additional circumstances relied by Mr Gore would
not therefore persuade us to differ from her Honour's
conclusion, which we consider to have been the correct
conclusion. We would dismiss the appeal, with costs to be
taxed.
In the course of the hearing, we reserved the costs of
an application by the respondent that the appeal be struck
out as an abuse of process. The basis of the application
was a contention that a compromise entered into after the
judgment was given precluded any appeal. Both counsel had
been prepared to argue that application concurrently with
the appeal. Although the facts which led to it were not in
dispute, any inference to be drawn from those facts, as to
the particular scope of the compromise agreement, would have
had to be the subject of argument. The members of the court
queried the appropriateness of ventilating that issue for
the first time in this forum. Mr Keane ultimately abandoned
the application, essentially, as we saw matters, to
facilitate the progress of the appeal. Mr Gore then asked
-- 10 of 11 --
10
for costs. Because the parties had been prepared to argue
the application concurrently with the appeal, because it was
the court which raised the question of the appropriateness
of that course, and because there was no adjudication on the
merits of the application, which, as we say, Mr Keane
ultimately abandoned so that the appeal could proceed, we
consider it appropriate that no order be made in relation to
those costs.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCA/1996/365