Astway Pty Ltd v Council of the Shire of Albert [1996] QLC 128 (1996-1997) 16 QLCR 558
LAND COURT
BRISBANE
20 SEPTEMBER 1996
Re: A95-09
Determination of Compensation -
Resumption for Rubbish Depot Purposes -
Acquisition of Land Act 1967
Astway Pty Ltd
(Claimant)
v.
The Council of the Shire of Albert
(Respondent Constructing Authority)
J U D G M E N T
The Council of the Shire of Albert resumed by proclamation published in the
Government Gazette on 16 December 1994, land owned by the claimant, situated at Old
Coach Road and Nerang-Southport Road, Nerang. The land is described as Lot 241 on
Registered Plan No. 844822, Parish of Nerang, containing an area of 16.75 ha, being the
whole of the land in Certificate of Title, Volume 8500, Folio 248.
The land adjoins the eastern alignment of the Gold Coast railway reserve. It
comprises the balance area after an earlier but fairly recent resumption for railway purposes.
At the date of the hearing, the railway was under construction. Access is being provided
from Old Coach Road under the railway to the south-western corner of the site. A relatively
short frontage remains to the Nerang-Southport Road, also in the south-western extremity.
The land is bounded to the east by a water reservoir site. Although irregular in shape the
land has an average depth of about 585 metres north to south and a maximum width of about
300 metres east to west.
The land has been extensively quarried which activity has created an excavated land
form, benched at various levels with the quarried rock face adjacent to the north-eastern and
eastern boundaries. At the date of resumption the parties agree that an in situ volume of
approximately 120,000 m3 of hard rock material remained within the site. Also
accommodated on the site were various stockpiles of sand and soil material. A gully
watercourse (Quarry Creek) drains as an ephemeral stream from the north-western quarter
generally south to south-easterly, westerly of the centre of the site except in the southern
section where it traverses the south-eastern extremity.
[1996] QLC 128
-- 1 of 27 --
2
An easement for future electricity transmission purposes traverses the site from west
to east northerly of its centre with a branch easement surveyed back through the centre in a
south-westerly direction to an easterly extension of the railway reserve. A second easement
for access purposes is surveyed from near the eastern extremity of the Nerang-Southport Road
frontage in a direction north of west to that railway reserve extension.
The land at the date of resumption was zoned “Future Urban” in an area of the Shire
identified as “Industrial” in the then existing strategic plan as well as a draft strategic plan.
The differences between the claimant and the respondent lie in the assessment of the
highest and best use of the land at the date of resumption.
It is the opinion of the claimant that the potential of the site for development as a
“dry-inert” commercial landfill represented the highest and best use. With leave, and subject
to agreement being reached with the respondent relevant to continued occupation of the land,
(as eventually occurred) the claim for compensation was amended during the hearing. The
final claim before the Court is set out as follows:
1. Valuation of land resumed
(a) Market value of land $2,495,000
(b) Special value to the owner:
(i) $587,000
(ii) $651,000 $1,238,000
$3,733,000
2. Disturbance
(a) Relocation Costs $76,000
(b) Loss of Stockpile $122,000
$3,931,000
During the course of the hearing agreement was reached between the parties as to
professional fees expended in compilation of the claim for compensation and that will be
dealt with later.
The valuation put in evidence by the constructing authority was in the amount of
$1,450,000. That valuation represented market value of the in globo land with potential for
industrial subdivisional development.
Witnesses called by the claimant were:
Mr R.B. Bycroft, a Director of the claimant company. His evidence related to
the history of the use of the land, the business activities of the Bycroft Group
-- 2 of 27 --
3
of Companies with which Astway Pty Ltd was associated, and certain aspects
of the claim for compensation.
Mr G.A. Penridge, the Financial Manger of the related companies. His
evidence related to analysis of financial material relating to, in particular,
expenditure on waste disposal.
Messrs E.H. Briese and D.A. Houghton, who provided a joint geotechnical
feasibility assessment of the potential of the site for land fill development.
Mr R. V. Holland, whose evidence was related to town planning issues.
Mr A.R. Brown, who had conducted an environmental noise assessment
relative to the proposal for a landfill development.
Mr A.R. Midwood, who dealt with population statistics and anticipated
demand trends for landfill in the Gold Coast region.
Mr D.C. Clements, who provided financial projections for development of the
site as a landfill.
Mr J.A. Judd, who operates a business, once owned by the Bycroft Group,
involved in waste disposal.
Mr N.C. Calabro, an accountant who provided an assessment of the
hypothetical going concern value of the potential landfill development.
Mr. K.P. Walsh, the registered valuer on whose valuation the claim for
compensation was based.
Witnesses called by the respondent constructing authority were:
Mr D.W. Perkins, who dealt with the town planning issues.
Mr D.R. Davis, an engineer who had provided estimates of development costs.
Mr R.H. Amaral, an engineer involved in waste disposal planning.
Mr T.J. Lacey, a registered valuer who had been responsible for the
respondent’s valuation.
At the outset it may be said that there was no disagreement between the parties that the
subject land had potential for development as a private landfill. Modern waste disposal
planning has become orientated towards segregation of material. Receival fee structure at
public rubbish depots is designed to direct non-putrescible solid, dry/inert waste to specific
locations. Dry/inert waste is usually generated from the construction and demolition industry
but, to ensure a disposal site did not develop into an “uncontrolled” landfill, it was Mr
-- 3 of 27 --
4
Amaral’s evidence that it would be necessary, for reasons associated with potential
contamination, for a strict protocol to be developed whereby the following materials be
specifically excluded:
all conventional household waste (includes putrescibles)
all conventional Council “clean-up” collections (includes excess green waste,
fine timber, cans etc., etc.)
all green waste (biodegrades)
tyres (produces toxins and oil when burnt)
cars, motors etc. (includes greases, oils, etc.)
white goods (includes oils, CFC’s, etc.)
liquids (partly filled tins, containers)
asbestos (needs special treatment, cover)
batteries
dry chemicals/hazardous wastes.
Town Planning Issues
The town planning evidence was consistent to the degree that both Mr Holland and Mr
Perkins had concluded, that from their perspective, appropriate uses of the site included
development as a private landfill or as an industrial subdivision. There was some difference
in opinion as to the potential for the quarrying of the remaining rock reserves. The quarry
operation had commenced prior to gazettal of the first planning scheme for Albert Shire in
1973. The quarry had become registered as a lawful non-conforming use, after application in
1984. It seems that for the lawful use of a crushing and screening plant in association with
the quarry activity successful application for consent use of the site for a “temporary quarry”
was first made in 1989. The life of a temporary quarry was restricted to two years under the
planning scheme. A second successful application was made in 1991 but a third application
in 1993 was refused. The grounds of refusal were that the application was contrary to the
definition of “temporary quarry” in the planning scheme and that the appropriate form of
application should have been a rezoning application to include the land in the “Extractive
Industry” Zone. An appeal had been lodged in the Planning and Environment Court against
that refusal but had not been heard by the date of the resumption.
Mr Holland held the opinion that the refusal had resulted from a previous Planning
and Environment Court judgment relative to the definition of “temporary quarry” in the
Albert shire planning scheme. He was confident that a suitable rezoning to allow the
relatively small volume of remaining rock material could have been expected.
-- 4 of 27 --
5
Mr Perkins had no such confidence, for technical reasons. He did agree however that
the remaining rock was a valuable resource and being in small quantity, the short term
required to quarry the material would be a relevant consideration.
Both town planners agreed that the actual use of the site for stockpiling and sale of
various sand and soil material was unlawful within the “Future Urban” Zone. There was no
disagreement that such use, together with quarrying of rock on a temporary basis were
compatible with the potential use of the site as a landfill.
As early as 1991, the claimant company had, inter alia, requested the respondent to
advise if it had any objection to a proposal “in recognition of the dwindling rubbish disposal
site capacity in the city” to utilise the “existing quarry infrastructure and our crushing capacity
to recycle concrete from building demolition sites in Albert Shire and adjoining Gold Coast
City”. The respondent had replied to that written request by referring to an on-site meeting
and advising that it had no objection to the operation as demonstrated.
While it cannot be said with certainty I have formed the opinion on the overall town
planning evidence, that the subject site had the potential to be included within the “Special
Facilities” Zone, for a particular development which would have incorporated the further
preparation of the site for landfill by quarrying activities and the contemporaneous
development for that primary use as a commercial landfill in conjunction with the stockpiling
of soil, sand and associated materials for recycling and processing for sale.
The further quarrying of the rock material or the stockpiling of material would not be
seen to be compatible with the proposal for industrial subdivision.
Market Value for Development as an Industrial Subdivision
Mr Lacey’s was the only evidence presented as to the value of the land for industrial
development. Suffice to say that, based on his comprehensive research into sales evidence,
consideration of the gross realisation which would result from the sale of the land in
subdivision, and the various costs involved and appropriate allowance for profit and risk of
realisation, Mr Lacey valued the land in globo with subdivisional potential in the amount of
$1,450,000, exclusive of disturbance items. It is also relevant that the valuation included the
existing stockpiles of materials which, in the development cost exercise, were to be utilised in
connection with the siteworks requirements.
Market Value for Development as a Private Dry/Inert Landfill
-- 5 of 27 --
6
Because of the lack of local evidence of sales of sites for development as private
landfills, there had been a generally common valuation approach adopted. This involved
estimation of the following criteria:
the void space within the site available to be filled
the demand for such space
available market share
the appropriate charge for waste material receival
the costs of operation of a landfill
gross and net income
the appropriate “capitalisation/discount” rate to be adopted in assessment of the
value of the commercial operation as a going concern
the costs of establishing the commercial operation
holding costs during development of the landfill
The valuation exercises brought about widely varying opinions of site value for that purpose,
ranging from an initial $600,000 from Mr Lacey up to the various related amounts in the
claim. There was virtually no common ground initially in the evidence relative to the
valuation criteria, although eventually the charge for receival of the waste material at about
the resumption date, as suggested by the claimant, seemed to be accepted by the respondent.
Adjustments made by Mr Lacey to this and other criteria, resulted in calculations which, in his
opinion, had the highest and best use of the land remaining as a potential industrial
subdivisional development. It is necessary to consider carefully the evidence relative to the
various items of valuation criteria.
Void Space
The development proposed by Messrs Briese/Houghton for the claimant, recognised the
availability of further quarrying potential. It was Mr Houghton’s estimate that an in situ rock
resource of 755,000 m³ remained. Of that volume “about 120,000 m³ may be suitable as
hardrock aggregate, with the remaining 635,000 m³ being weathered material and argillite
which could be used as cover or sold for filling”. It was their proposal to provide a floor at
RL 13, as an extension of the development which existed and in their opinion above water
table level. The watercourse was to remain generally in its natural location, within a reserved
area 15 metres wide. The fill was to rise above that watercourse reserve in a benched batter
with a relatively flat upper surface on either side of the creek, the finished level not to be
above the natural adjacent ridge line. As I understood the proposal, an area in the south-west
corner was excluded from filling to accommodate the main entry and administrative area
including the weighbridge and to provide stockpiling facilities. The first estimate of void
space was in the order of 1,750,00 m³ with waste capacity of about 1,630,000 m³ after
-- 6 of 27 --
7
provision for the placement of cover material. During the hearing the void space was
recalculated to meet the restrictions on filling within the electricity easement. On the original
concept, this reduced the usable void space to about 1,300,000 m³. It was envisaged that the
final landform would be of suitable contour for some residual use.
Mr Amaral’s proposal was to create five mounded areas eventually occupying the whole of
the site, except for the watercourse area. He envisaged residual use limited to public open
space. The proposal was generally more conservative in that first, the watercourse reserve
varied in width from 30 metres to 40 metres (including adjacent access tracks). Second, 10
metre wide perimeter access and drainage berms were allowed where the claimant’s proposal
allowed a strip 5 metres wide for that use. Mr Amaral did not accept that the quarry floor
should be developed to RL 13 and his proposal did not envisage further quarrying although he
had recognised the availability of the rock resource. His proposal resulted in a void space for
receival of covered waste of 992,000 m³.
If Mr Amaral’s more conservative design relative to the watercourse and site perimeter was
applied to the Briese/Houghton concept (adjusted for the easement) then a usable void space
of about 1,100,000 m³ would have resulted, still excluding the south-west corner area.
There was no dispute that because of the nature of the existing topography and the various
site constraints, the final void space could be plus or minus 20% of the estimates. Although
significant volumes are involved in the differences, any deficiency in void space has minor
significance in terms of the deferred present value basis of assessment adopted by the valuers,
when the estimated ultimate life of the development and the earnings discount factor enter
into the calculations.
It is observed that Mr Walsh’s valuation effectively adopted a usable void of 1,200,000 m³.
While I accept that the gully location might have required a more cautious approach in
relation to future access requirements than was adopted in the claimant’s proposal, it seems to
me that Mr Amaral’s estimate is overly conservative particularly in that the further quarrying
potential was not incorporated within his proposal.
For the purpose of the exercise, I will adopt a usable void space after further quarrying and
exclusion of an unfilled area in the south-west corner, of 1,200,000 m³.
Waste Disposal Demand
At the date of resumption, there were in existence in the locality, two private solid waste
landfills. These were referred to in the evidence as “City Link” situated at Spall Street, off
the Gaven Way, at Carrara and “M & M” at Rudman Parade, off Reedy Creek Road, West
-- 7 of 27 --
8
Burleigh. Both were utilising void space provided by continuing quarrying operations. Both
are to the south of the subject land. There were then six Council operated tips with varying
remaining life spans. As a general comment the evidence indicates that the disposal of solid
waste of the type with which this matter is concerned, is actively discouraged at the Council
tips. While there also remains some demand for fill at low-lying sites, it was Mr Bycroft’s
evidence that this demand has reduced significantly over the years due to the more stringent
soil testing requirements for the development of filled sites.
It seems that both Mr Walsh and Mr Amaral had accepted that the waste disposal activities at
City Link and M & M represented the extent of the commercial market available in the Gold
Coast locality. There is some potential for further solid waste to be directed from the more
expensive Council tips but, as Mr Amaral pointed out, there are also times when suitable
cover material is sought by those tips free of receival charge.
Development of the subject site would have resulted in three commercial operations sharing
the existing demand. However, the separate investigations resulted in significantly different
interpretation of the private waste disposal requirements of the locality. Mr Walsh’s
inquiries at City Link had provided him with actual figures for the second half of 1995 when
an average of what he interpreted as 3,186 m³ of waste per month had been received. He had
been informed that the intake during the period reflected recessionary market conditions and
that “a couple of years ago” it would have been about double that volume. He recognised the
need to obtain more precise figures over a longer period but the best he could establish from
the accountancy section of that business was that the “range” over the last three years had
been between 2,500 and 6,000 m³ per month. He had adopted the average in that range - ie
4,250 m³ per month as representing the maintainable intake at that facility. Mr Walsh
accepted the criticism which was directed at him for adopting an average in a range but his
response was that he did the best that he could based on his interpretation of the information
provided to him. His inquiry at M & M revealed, in the absence of actual figures, an opinion
that the intake in the second half of 1995 “should be around 2,000 m³ to 2,500 m³” per month,
although it varied. Again he was informed that the particular period had been considered
recessionary and the intake would have been double “a couple of years ago”. He was unable
to take his inquiries to any higher level and decided to adopt a maintainable intake of 2,500
m³ per month at that facility.
On his estimates the total maintainable intake at both facilities amounted to 6,750 m³ per
month or 81,000 m³ per annum. His investigations revealed that within the industry some
-- 8 of 27 --
9
operators spoke of intake in terms of weight and some in terms of volume. After various
discussions he satisfied himself that as a rule of thumb 1 tonne of waste material such as was
accepted at the dry/inert landfills was generally regarded as equivalent to 1 m³.
Mr Amaral did not accept that ratio from his own considerable experience in the industry and
also from his own discussions with various operators. In his opinion, because the range of
material capable of being accepted at these facilities did not include such items as cardboard
cartons but was limited to solid waste and predominantly demolition material, the ratio was
more likely to be 1.8 tonnes per m³.
On this particular point, Mr Clements’ many years’ experience in the waste industry had
influenced him to adopt for the purposes of the exercise he had conducted the ratio of 1 tonne
to 1 m³. He was able to inform the Court however that the somewhat precise weight to
volume records of the Brisbane City Council which he had been able to check after
compilation of his report, indicated a ratio of between 1.1 and 1.2 tonnes per m³ for that
Council’s solid waste intake.
While it is observed that the private landfills had similar charges for either a tonne or a cubic
metre, for the purpose of estimating demand on a volume basis, I will adopt the Brisbane City
Council experience, of 1.15 tonne/m³, overall.
Mr Amaral’s first investigation at City Link indicated to him that the intake there averaged
3,500 tonnes per month, which on his weight to volume conversion resulted in a rounded
estimate of 2,000 m³. Evidence given by Mr Walsh caused him to go back to City Link
during the hearing. He was then informed that in the five months preceding the hearing the
intake on “actual truck measurements” had been 3,200 m³ per month. Mr Amaral enjoyed a
working relationship with M & M and confirmed there his earlier advice that while intake did
fluctuate, it had averaged 2,000 m³ per month over the last three years. Based on his first
inquiry at City Link he had adopted a total intake at both facilities of 4,000 m³ per month and
48,000 m³ per annum. Subsequent to his later inquiry he upgraded his monthly assessment
to 3,000 m² at City Link and 5,000 m³ per month at both facilities, totalling 60,000 m³ per
annum. In his opinion, had the subject land been developed as a landfill it would have shared
equally in the waste disposal demand for the locality. On that basis he had estimated that the
site had the potential to receive 20,000 m³ of waste per annum.
The Briese/Houghton report, in assessment of demand for “hardfill landfills” had included
reference to the “Draft Waste Management Strategy for Queensland - Discussion Paper”
(Queensland Department of Environment and Heritage, May 1994) according to which “the
-- 9 of 27 --
10
Industry Commission’s 1990 Report on Recycling estimated that the amount of demolition
waste generated in Brisbane in 1989 was 190 kg per person per year”. Mr Briese assumed
that such level of waste generation would also apply to the Gold Coast.
Mr Amaral had similar figures produced by several consultants. When the Environmental
Impact Study had been carried out for the Albert Shire on the Molendinar Landfill proposal,
190 kg per person per year had been adopted for the solid waste generation but not for the
whole of the Gold Coast statistical district. Instead the catchment for the Molendinar
proposal had been estimated as being a population of 189,000 persons. His verbal
evidence-in-chief included the following:
“So if I use, round that off even, and use a 200,000 figure and multiply it out, I come to about
38,000 tonnes using the Douglas & Partners” (Briese/Houghton) “figure and if I upgrade that,
because that was 1989 and this is now seven years later, and someone said that could be 45
or 50,000 tonnes I would say that wasn’t far off the mark. It’s a far lesser figure when you
revert it back to cubic metres of course than what I’m getting now looking at M & M and
City Link. But it would appear to be about appropriate, anywhere from 40 to 60,000 m³ a
year total.”
Mr Clements had been of the opinion that as the Brisbane figures were over the whole of its
population it was reasonable to assess the solid waste demand for the whole Gold Coast City
Council (now including Albert Shire) population which he had rounded to 300,000 persons.
However, Mr Clements had established that the hardfill waste generation in Brisbane had
been 565 kg per capita in the 1994/95 year based on a population of 1,000,000 persons. Had
the Gold Coast City Council population of 300,000 generated the equivalent capita hardfill
waste, that would have been the equivalent of 169,500 tonnes in 1994/95. At 90% of the
Brisbane figures then 80% and 70%, the calculations became 152,550 tonnes, 135,600 tonnes
and 118,650 tonnes respectively.
It is observed that at 70% of the Brisbane generation, and a conversion factor of 1.15
tonne/m3 overall, the Gold Coast figure would be about 103,000 m³.
Mr Walsh estimated the Gold Coast private hardfill demand as 81,000 m³ on a maintainable
basis. That figure is far in excess of the best estimate of the 1994/95 year when allowing say
3,250 m³ at City Link and 2,000 m³ at M & M there was private commercial disposal of only
63,000 m³. Even in a recessionary period those figures cannot be ignored. They indicate
that at least in 1994/95, the waste generation in the Gold Coast/Albert Shire statistical area
was far less than 70% of the generation in Brisbane, or alternatively large volumes were being
deposited at one-off filling sites or the Council facilities at the much higher receival rates.
Even accepting that the recessionary forces were at work in the Gold Coast area in the
-- 10 of 27 --
11
1994/95 period in terms of hardfill waste generation, I am unable to accept that there is
substantive evidence to support Mr Walsh’s estimate on a maintainable basis. Mr Bycroft’s
evidence was that the quantity of waste disposal work over the last five years had not changed
“a lot”. It was the cost of waste disposal which had risen significantly.
For the purpose of the exercise, and providing benefit of doubt, which must exist on the state
of the evidence, in favour of the claimant, I will adopt a maintainable commercial hardfill
demand estimate of 70,000 m³ per annum for the catchment area which had been served by
City Link and M & M at the resumption date.
Market Share
Mr Amaral’s opinion was that, of the private hardfill demand, the subject site could be
expected to attract an equal share, ie one-third. His first estimate had been 16,000 m³ per
annum and it was on this estimate which Mr Lacey had carried out his initial valuation. For
the reasons explained, Mr Amaral’s estimate had been upgraded to 20,000 m3 per annum.
Mr Walsh had been in possession of the hardfill disposal activities of both Bycroft
Earthmoving Pty Ltd (one of the Bycroft Group) and Mainflag Pty Ltd trading as Bycroft
Backhoe & Bobcat Hire (the company now operated by Mr Judd but no longer associated
with the Bycroft Group). In 1993/94 Bycroft Earthmoving had paid fees to Council Tips,
City Link and M & M involving solid waste disposal amounting to the equivalent of 15,025
tonnes/m³. This volume on the actual tonnage figures supplied would have reduced to about
14,107 m³ on the conversion rate which I have adopted. Then in 1994/95, the figures were
14,311 tonnes/m³ which I have converted to 14,264 m³ on the tonnages provided.
It is accepted by Mr Walsh that had the subject site been developed as a landfill and had it
remained in the ownership of the claimant company, all of this waste material would have
been directed to it. It is observed that in 1994/95, about 22% went to M & M and about 75%
to City Link, the balance to Council landfills.
The Mainflag business in the 1994/95 period had disposed of hardfill waste comprising
13,931 tonnes and 9,910 m³ to all sources. On the conversion adopted that would amount to
about 22,000 m3. Mr Judd gave evidence that because of the geographic area in which his
business was concentrated, he had estimated that 70% of his disposal requirements would
have been directed to the subject site had it been in operation.
On Mr Walsh’s figures (tonnes equating m³ ) Bycroft Earthmoving and the Mainflag business
accounted for a potential source to the subject site of 32,000 m³ per annum. The balance of
the Gold Coast generation was, on his figures, 49,000 m3 (81,000 m³ minus 32,000 m³). He
-- 11 of 27 --
12
felt that the subject site’s share of the balance would be one-third, rounded to 16,000 m³. He
adopted the potential intake at the subject site then as being the 48,000 m³ or 4,000 m³ per
month.
Mr Clements’ report contained reference to a review of the market carried out by Mr Walsh
“and others” which indicated that the local market would generate hardfill waste of
3,000-5,000 m³ per month that would be attracted to this site. After consideration of the
32,000 m³ per annum potential from Bycroft and Mainflag, Mr Clements had adopted Mr
Walsh’s 4,000 m³ estimate as the “starting” volume, for the financial model which he had
developed. He had taken comfort from the waste generation figures in Brisbane when
accepting that starting volume. For the purpose of this valuation exercise, it seems to me that
the potential Bycroft and Mainflag demand should not be ignored. Mr Amaral had not been
aware of these suggested disposal figures until reports had been exchanged. Even so, he felt
that little weight could be placed on, in particular, the Mainflag figures when the realism of
the commercial market was considered. I disagree because, as I understood the evidence of
Mr Judd, his estimate had been based on geographical considerations and related haulage
costs rather than any business bias towards the claimant. Also because of geographical
considerations, I am not convinced that Mr Walsh was entitled to be so confident that the
balance of the market would be equally shared. It seems to me that M & M would continue
to have an advantage in terms of haulage distances for the more southerly waste generation
but a disadvantage in terms of the more northern generation, including the older
Southport/Surfers Paradise area. Of the best information available, it seems that in 1994/95,
M & M’s share of the private market was about 38% and City Link’s 62%. If the more
generous maintainable estimate of 70,000 m³ was adopted, the relative shares would be say
26,500 m³ to M & M and 43,500 m³ to City Link (the best estimates of actual figures having
been increased by about 10% to arrive at 70,000 m³). On the conversions adopted it seems to
me that the combined Bycroft Earthmoving and Mainflag disposals would have been about
29,500 m³ in 1994/95 or similarly increased by 10% to find a maintainable basis, say 32,500
m³ out of the 70,000 m³ total. This would leave 37,500 m³ to be shared amongst the
hypothetical three operators. Accepting that M & M would suffer some loss of market share
and reducing its intake to say 20,000 m³ per annum, 17,500 m³ would remain to be shared
between City Link and the subject site. If that remainder was shared equally, City Link’s
share would fall to 8,750 m³ per annum or only 20% of its previous share of the total market.
The subject site would, with that remainder share improve to 41,250 m³ per annum. It would
-- 12 of 27 --
13
be seen as highly likely that City Link in particular would respond to such significant loss by
the use of aggressive trading practices to counter the competition created by development of
the subject site..
For the purpose of the exercise, after consideration of the actual trading figures of two
operators within the industry, and the northernmost location, I will adopt a market share on a
maintainable basis of 3,250 m³ per month or 39,000 m³ per annum.
Waste Receival Charge
Mr Amaral’s initial inquiry indicated that “in 1994 ” the gate charge at City Link and M & M
was $15 per tonne or m³. Mr Lacey’s calculations had been based on that advice. The fact
is that at about the time of the resumption both those operators had increased their charges to
$20 per tonne or m³. The Council landfill nearby to the subject site was and had been
charging $45 per tonne and directing, by signage, hardfill waste to City Link.
I will adopt a waste receival charge of $20 per m³, at the relevant date.
Costs of Operation
Relying primarily on the advice of Mr Amaral, Mr Lacey, in his initial valuation, adopted an
annual operating cost of $104,600, for the receival of 16,000 m³ of fill. On a gate fee of $15
per m³ the operating cost allowance was about 43.6% of gross revenue but on $20 per m³ gate
fee that allowance would have reduced to 32.6%. The cost structure would logically
decrease if fixed costs were then spread over a greater intake volume. Mr Amaral’s advice
had been that operating costs would be about $5 per m³ plus the costs of water control and
sampling.
Mr Clements’ financial analysis had been comprehensive and detailed. He had prepared a
financial model reflecting the requirements of a public company. Included in his costings
were allowances for depreciation (including depreciation on land) and interest costs.
Mr Calabro, in his business valuation approach, adopted Mr Clements’ basic estimates,
except that he deducted the allowance for depreciation on land and the interest costs. On an
estimated receival of 48,000 m³ per annum at commencement, Mr Calabro calculated net
earnings to be $547,000, operating costs being 43% of gross revenue. However on the
10-year projections adopted the operating costs fell to 28.3% of gross revenue.
Mr Walsh also adjusted Mr Clements’ figures as had Mr Calabro, but only in the
commencement year “setting aside projections of increases in income and costs”.
It seems to me reasonable that Mr Clements’ public company approach be adjusted for
market value assessment as adopted by Messrs Calabro and Walsh. I will adopt Mr Walsh’s
-- 13 of 27 --
14
commencement year approach, when costs of operation were estimated to be about 43% of
gross income. Although Mr Walsh’s revenue/cost ratio is based on the higher intake than I
have adopted in this exercise, it does make allowance, for example, for depreciation on items
other than land and might be seen to be quite pessimistic when the long-term projections are
considered.
Gross and Net Income
I have adopted a gross income on the basis of maintainable waste receival of 39,000 m³ per
annum at $20 per m³ or $780,000 per annum. Expenses at the rate of 43% of gross income
leave a net estimated income of $444,600 per annum.
Going Concern Discount Rate
The methodology adopted by the valuers was to discount to present value, the estimated net
income stream over the life of the development. The discount factor is obviously one of the
critical factors in the equation.
Relying on Mr Amaral’s estimates, Mr Lacey had adopted a discount factor of 15% in his
initial assessment. Although he had not conducted the demand investigation, the discount
factor he said was intended to reflect the “conservative” estimate of demand which would
have allowed a growth factor. I did not gain the impression that Mr Amaral intended his
initial estimate to be conservative. However, when Mr Amaral adjusted his demand estimate
(his initial estimate being wrong), Mr Lacey saw the need to increase the discount factor. His
reasoning for doing that was not convincing when he was relying on Mr Amaral’s estimates.
When it emerged that highest and best use as a landfill was not as remote as he had first
considered, through challenges to Mr Amaral’s evidence, it seemed to me that Mr Lacey
turned his mind more seriously to market considerations. He then suggested that some
comparison could be seen to exist between a commercial landfill operation and that of a
quarry operation. Although with the converse physical result, the analogy makes some sense.
From a valuation perspective the income estimates are based on demand as are life
expectancy considerations. It was necessary for Mr Lacey to rely on his professional
experience rather than providing specific market evidence, in providing his opinion that the
market discount factor for quarrying operations would be in the range of 25%. As I
interpreted his evidence, Mr Lacey had been prepared to adopt a discount factor of 15% on
what he seemed to accept as a conservative demand estimate or a minimum of 25% if the
demand estimate, on the best information available, was seen to be optimistic.
-- 14 of 27 --
15
Mr Calabro had adopted a discount factor of 30% in his going concern assessment, but it
needs to be recognised that his discount factor had taken into consideration not only the risk
associated with achievement of the initial income estimate but also the future projections of
the overall operation.
Having found that there was no reliable evidence of sales of potential landfill sites in
Queensland, Mr Walsh went as far as Melbourne to gain some valuation assistance from sales
evidence. He well recognised the difficulties in comparison between the two locations but at
the very least the available Melbourne sales evidence indicated to him a level of value which
was industry related. Two sales had taken place in that city. One was of no assistance
because of the limited void space available. The second sale took place in 1991. It was of a
site with 2,700,000 m³ of void space and sold for the analysed equivalent of $2.72 per m³ of
that void space. Mr Walsh’s investigation revealed that the estimated net income at the time
of sale showed “a present value over 13 years at 17.25% exclusive of establishment costs”.
No information was provided as to the estimated establishment costs or the discount factor
which would have been indicated on a going concern basis. Nevertheless, Mr Walsh in his
valuation adopted a discount factor of 17.25% for the hypothetical established going concern
basis of valuation for the subject site. He pointed out that on the resultant value of the site,
before establishment, on his estimate of net income, over a life of at least 25 years, the
discount factor equated 23.5%. This 23.5% was then the “like with like” comparison with
the discount factor of 17.25% shown by the sale. In Mr Walsh’s opinion increasing the
factor from 17.25% in Melbourne to 23.5% at the Gold Coast, reflected a reasonable
interpretation of the differing market and risk considerations. During the hearing, Mr Lacey
had made contact with a Melbourne based associate. He had been informed that another
valuer had analysed that same sale to show a discount factor of 20%. If strict reliance was to
be placed on the evidence provided by that sale, then in the circumstances, Mr Walsh’s
firsthand analysis would be preferred. Nevertheless the weight which might be placed on the
evidence is, in my opinion, most limited, when the Melbourne demand was clearly much
greater and the life of the landfill more finite.
In considering a hypothetical sale of the subject land the particular claimant, as the vendor,
had knowledge of the potential demand. Some of the risk factors associated with demand are
logically reduced significantly when one related business creates about 20% of the total
demand which has been estimated. The claimant, as a hypothetical vendor, also had specific
information as to the likely demand of others operating within the industry. It is unlikely
-- 15 of 27 --
16
then that in negotiations to sell the subject site the claimant, or any other prudent vendor,
would have been influenced by demand estimates which ignored that particular information.
If the claimant company was to be seen in the role of a hypothetical purchaser, while specific
knowledge of a particular source of demand would unlikely lead to a purchase price in excess
of market value, it would be expected to at least crystallise the price which it would be
prepared to pay rather than fail to obtain the site.
In discussing the concept of market value, Isaacs J said in Spencer v. The Commonwealth
[1907] 5 CLR 418 at p.441:
“To arrive at the value of land at that date, we have, as I conceive, to suppose it sold then, not
by means of a forced sale, but by voluntary bargaining between the plaintiff and a purchaser,
willing to trade, but neither of them so anxious to do so that he would overlook any ordinary
business consideration. We must further suppose both to be perfectly acquainted with the
land, and cognisant of all circumstances which might affect its value, either advantageously
or prejudicially, ...”
Under that test both the hypothetical vendor and purchaser are assumed to be in a similar
position when it comes to circumstances which might affect the value of the land.
The question of any special value to the owner will be addressed later.
The discount factor to be adopted in the preferred valuation methodology, will reflect the
market perception of the risk involved in maintaining the estimated income stream. The
evidence indicates that if the income stream was clearly conservative a discount factor as low
as 15% might be appropriate. Conversely where income stream estimate involves
projections incapable of proof but arguable on the available evidence, a discount factor as
high as 30% might also be appropriate.
In the subject matter, on the criteria which is adopted, no certainty exists. However, the
gross income is based on actual receival rate. The receival potential is based on a market
share which has, as its base and major component, the actual trading history of a related
company and prospective client and the geographical disposal history of another prospective
client. The cost of operation can be accepted with confidence, as the maximum likely.
On any view, in the range of discount factors available for consideration, neither the lowest
nor the highest would be appropriate. The income stream estimate adopted is seen to have
had some median elements of risk reasonably reduced, and I have decided to adopt a discount
factor of 20%, as a result.
Establishment Costs
Mr Clements had consulted with Mr Bycroft as to site specific matters. A detailed estimate
of establishment cost including the necessary plant and machinery was contained within his
-- 16 of 27 --
17
financial projection assessment. Generally, Mr Clements’ estimate was accepted by Mr
Walsh, although he had deducted an allowance of $43,000 for provision of a weighbridge and
site office, on the basis that these improvements already existed at the date of resumption (the
evidence is however that the weighbridge had been subsequently sold and it appears that the
claimant did not own the site office). Mr Clements’ estimate was in the amount of $602,200.
There was criticism of an allowance of only $23,000 within that amount for internal access
including the crossing of the watercourse. Mr Clements had sighted a quote for part of the
work and had accepted Mr Bycroft’s proposal that on-site concrete pipes could be used in the
construction of a watercourse crossing.
Mr Davis had provided the respondent with engineering estimates for the alternative
development proposals. He had understood that access to the landfill proposal would have
been gained off the Nerang-Southport Road and had allowed an intersection cost of $40,000,
sealed internal road access at a cost of $100,000 and the watercourse crossing at a cost of
$75,000. In his opinion, while access off Old Coach Road would eliminate the particular
intersection costs allowed, there would then be involved another intersection cost, an
additional 80 metres of road construction, rock cutting and drainage at a cost additional to the
alternative route of $69,400. The internal road construction was intended to have a service
life of 20 years requiring minimal maintenance. A properly designed permanent culvert for
the watercourse crossing was seen as essential. As I understood the evidence of Mr Davis,
(and no doubt this would have had some effect on the alternative subdivisional proposal
which gained access off Old Coach Road) he had not been aware that Queensland Rail, as a
consequence of an earlier resumption, was responsible for the provision of access under a
railway bridge to the south-west boundary of the site. Further, the claimant had already
constructed certain external roadworks in connection with an earlier rezoning proposal. Mr
Davis agreed that if that had been the case a concession could be expected relative to external
roadworks.
Although I have not been convinced that need existed for the standard of internal roadwork
envisaged by Mr Davis, for the landfill, it seems that approval for rezoning and development
of the site would reasonably have involved the provision of a more substantial culvert than
had been envisaged by Mr Bycroft.
It is not possible to make direct comparisons between the estimates of establishment costs
made by Mr Amaral and others and those of Mr Clements. More substantial drainage would
increase the cost estimate of Mr Clements, but it is observed that a siteworks contingency
-- 17 of 27 --
18
allowance was made. His allowance for the cost of obtaining approvals was significantly
higher than suggested by witnesses for the respondent. On the overall evidence of Mr
Clements, an establishment cost in the order of $600,000 would seem a reasonable estimate
and I will adopt that rounded amount.
Holding Costs
Mr Walsh’s approach to this aspect of the valuation considerations was to deduct an
“allowance of three months’ earnings to provide for a lead-up period prior to full operation”.
It seems to me that the holding costs would include the loss of interest on siteworks during
part of the actual development period, interest on the land value for the rezoning and
development period, together with rates and taxes. In the absence of any specific information
as to these individual holding costs I will adopt Mr Walsh’s broad methodology of allowing
three months’ loss of gross earnings. I am confident that actual holding costs would not be
greater than this allowance.
Market Value of Site as a Potential Landfill
Using the criteria which has now been discussed in detail I will adopt the following basis of
assessment of market value:
Void Space - 1,200,000 m³
Demand - 39,000 m³ per annum
Life of Land Fill - 30 years
Gross Maintainable Income - $780,000 per annum
Net Maintainable income - $444,600 (57% of gross)
Discount Factor to Present Value - 20%
Establishment Costs - $600,000
Holding Costs - $195,000 (3 months gross income)
Valuation as Going Concern:
Present value of $444,600 per annum for 30 years @ 20%
= $444,600 x 4.97894 $2,213,635
Less Establishment Costs including plant and machinery $600,000
$1,613,635
Less Holding Costs $195,000
Land Value as a potential landfill $1,418,635
In practical figures adopt $1,420,000
The foregoing exercise appears to indicate that as raw land there would be virtually no
difference in value for development either as a landfill or for an industrial subdivision.
However, that is not the case.
-- 18 of 27 --
19
As an industrial development, either the remaining rock reserve would be lost or that
development would need to be held over incurring associated holding costs until the quarry
operations were to cease. As a landfill, the quarry operations would continue as a
complementary use.
Another matter arises which is seen to be critical to the claim as it was calculated. I
have adopted a void space based on the further quarrying operations but excluding an area of
about 2 ha in the south-west corner. It was the loss of this area for which the claimant, on Mr
Walsh’s valuation advice, sought a special value component initially of $726,000. This
represented the present value of what Mr Walsh saw as the cost of renting an equivalent
parcel for a period of 25 years (Mr Walsh’s expectation of the life of the landfill).
I will deal with these matters as follows:
Rock Reserve
Mr Houghton identified an in situ hard rock reserve of 120,000 m³. Mr Walsh
calculated that after quarrying, that reserve would equate 240,000 tonnes. Mr Walsh
envisaged extraction of that rock by “a third party quarrier, paying a royalty back to the
property owner”. A royalty rate of $1 per tonne was adopted with sale of the reserve to be
effected over a two-year period. It is seen as relevant, in terms of the earlier discussion
regarding an appropriate discount factor for the landfill, that Mr Walsh adopted a “discount
factor” of 15% for this short-term operation with what was, it seems, far less risk relative to
demand than might have been expected with the landfill proposal.
Mr Walsh’s calculation was rounded to $195,000 which amount I will adopt.
Associated Stockpiling
On Mr Walsh’s adoption of a 2 ha area being utilised for this operation, the balance of
the site including the watercourse area would comprise 14.75 ha. As a raw land site with
potential for landfill development, the adopted valuation is $1,420,000 or about $96,000 per
ha.
Mr Lacey’s in globo valuation of the total site for industrial subdivision was
$1,450,000 or about $86,500 per ha. He had adopted values averaging about $85 per m² for
fully developed and serviced industrial sites, apportioning a value of $35 per m² to
“hardstand” land.
It seems to me that a realistic approach to the value of this 2 ha of land to any owner
would be to establish its worth as part of the land taken. It would not have been a developed
2 ha of industrial land as such. Its value as part of an overall particular development within
-- 19 of 27 --
20
the “Special Facilities” Zone might have been expected to be apportioned at a higher figure
than the overall pro-rata value of the potential landfill, but significantly less than for example
hardstand areas within a smaller fully developed industrial lot.
I will adopt a value of $12.50 per m² or $125,000 per ha for this 2 ha component of
the total site, being an amount of $250,000.
Total Market Value of Land
The market value of the land is determined as follows:
Potential landfill component $1,420,000
Potential site for stockpiling and sale of sand and soil $250,000
Rock Reserve $195,000
$1,865,000
Special Value to Owner
Special value was described by Kirby P in Yates Property Corporation Pty Ltd v.
Darling Harbour Authority (1991) 73 LGRA 47 at pp.52, 53 as follows:
“It is a term of art used to describe a characteristic of the expropriated interest
which is of economic value to the owner but which would not enhance the
market value of the interest and hence would not be included in the ‘market
value’ component as the compensation to which the statute entitles the owner
following resumption.”
In Arkaba Holdings Ltd v. Commissioner of Highways (1969) 19 LGRA 398, Bray CJ
said of special value at p.404:
“It is, of course, well established that it is the value to the owner which must
be paid, even if that value exceeds the market value (Pastoral Finance
Association Ltd v. The Minister [1914] A.C. 1083; Minister for Public Works
v. Thistlethwayte [1954] A.C. 475). The additional element is commonly
called ‘special value to the owner’, eg Thistlethwayte’s case (at p.491). But
this special value must, in my view, arise from some attribute of the land,
some use made or to be made of it or advantage derived or to be derived from
it, which is peculiar to the claimant and would not exist in the case of the
abstract hypothetical purchaser. Would a prudent man in the position of the
claimant have been willing to give more for this land than the market value
rather than fail to obtain it or regain it if he had been momentarily deprived of
it?”
The claimant has identified here two aspects of the use and potential use of the land
where it is submitted that the land possessed special value to the owner.
(1)Sand and Soil Business
-- 20 of 27 --
21
The first limb of the claim for special value to the owner related to the conduct of the
sand and soil business. Mr Walsh’s report contained the following passage in relation to this
aspect:
“It is considered that in the hands of Astway Pty Ltd, the subject property
value included a premium, reflective of the additional special value to Astway
Pty Ltd to conduct the sand and soil business, over and above the market value
of the property as a hardfill and quarry site.”
Mr Walsh equated that special value as being the present value of the cost of
leasing “a suitable land area (approx 2 ha) over the life of the landfill adopted at 25 years.”
He estimated, based on rental evidence, that the cost of rental of “the type of land and location
required” would be $4 per m² or $80,000 per annum.
Because the agreement had been reached with regard to continued occupation of the
site, Mr Walsh had agreed that it would be reasonable to reduce his calculation accordingly.
This resulted in the amended claim being $587,000, based on a rental period reduced by the
extended period of occupation.
I have accepted that the claimant was able to provide within the land taken an area of
about 2 ha from which, with overall rezoning approval, a “sand and soil business” might
lawfully have been conducted.
I am unable to accept that this component of the land taken possessed any attribute
peculiar to its use by the claimant which would enhance, above market value, its value to the
owner. If it had been necessary to consider rental value, such value would have been seen to
be related to the capital value of the land taken, or its equivalent.
Other than factors capable of further consideration under the “disturbance” heading of
claim, no award is made for special value to the owner under this segment of the claim.
(2)Land Fill Potential
Mr Clements’ financial model was based on acceptance of Mr Walsh’s estimated
demand of 48,000 m³ per annum in the commencement year of the proposed development,
projected then to increase through “best practice” management strategies and population
increases, by 15% in the second year. Over the total of the first 10 years’ operation of the
landfill a compound growth averaging 10% per annum was adopted. Total waste volume to
be accepted in that 10-year period was projected to be 756,000 tonnes (with a density of 1
tonne per m³). It was Mr Clements’ evidence that on the basis of “normal commercial
returns required by major public companies operating in the waste industry” the indicated
-- 21 of 27 --
22
purchase price of the site was $1,808,000. Such a purchase price would exclude any value
being attached to the residual void space after the initial 10 years of operation.
While I have found Mr Clements’ analysis of establishment and operating costs to be
most helpful in this matter, I have been unable to accept Mr Walsh’s estimate of demand. It
follows that I am unable to accept Mr Clements’ financial analysis based on demand of
48,000 m³ in the first year of operation. It is unnecessary to consider the veracity of the
growth projections on which his analysis further relied.
Mr Calabro’s main objective was to put aside what a public company might be
prepared to pay for the site. He set out to analyse, on Mr Clements’ financial model, adjusted
where Mr Calabro saw it as necessary, the value of the development in the hands of the
owner, on the following bases:
(1)with a waste volume capacity limited to 756,000 m³ in a 10-year period -
$2,471,944 based on a going concern value of $2,977,144;
(2)with a void capacity of 1,600,000 m³ (Mr Houghton’s original estimate) -
$2,950,727 based on a going concern value of $3,455,927.
As Mr Calabro acknowledged, his estimates of value to the owner stood or fell on
acceptance of Mr Clements’ commencement year demand estimate and subsequent
projections. Then Mr Calabro’s second calculation further relied on there being a void space
equivalent to 1,600,000 m³ when that volume estimate has been significantly reduced. It
follows that I am unable to place any reliance on Mr Calabro’s calculations.
Mr Walsh’s valuation of the land as a potential landfill was $2,300,000 calculated on
a maintainable demand of 48,000 m³ per annum, maintainable net income of $546,500 for 25
years, a discount factor of 17.25%, establishment costs of $559,200 and holding costs. It was
Mr Walsh’s opinion then that such amount represented market value exclusive of any special
value to the owner.
Mr Walsh was prepared to accept that Mr Calabro’s second calculation of $2,950,727
represented the value of the land to the claimant. He simply adopted the difference between
his and Mr Calabro’s assessment as representing that aspect of special value to the owner.
Even had Mr Calabro’s financial analysis basis been adopted, I fail to see how Mr Calabro’s
discounted earnings calculations could represent anything more than another opinion of
market value, albeit from an accountancy approach and then not supported by specific market
evidence.
-- 22 of 27 --
23
I have accepted that the claimant’s association with a company involved in and with
particular knowledge of the waste industry allows it to influence a more conservative estimate
of the risk involved in assessment of demand for the subject site. It is, as I see it, that aspect
which would cause the claimant to consider the value of the site in an optimistic light. If the
claimant wished to negotiate a sale of the land for landfill development, it would hardly be
likely that such information would not be disclosed to a prospective purchaser. The adopted
basis of valuation has been to make an assessment of demand and related income potential
and to discount the income stream over the life of the development. If the criteria adopted
are realistic having been influenced by evidence produced by the claimant, then it should
follow that market value has been established.
If it was to be argued that any advantage was possessed by the claimant, in its
ownership of the site for potential landfill development, it could in my opinion, relate only to
the demand which has been demonstrated to exist from a company associated with the
claimant. That demand has already been fed into the valuation exercise, both in terms of the
income stream and the discount factor..
It is my opinion that on the basis of valuation adopted there can exist no enhancement
in the resultant valuation, in the hands of the claimant.
Disturbance
(a) Relocation Costs
The claim for relocation costs related to the sand and soil business and, as amended,
was calculated on the basis of Mr Walsh’s assessment as follows:
Construction - Bund Wall and Fuel Tank Base $1,400
Provision of
- An Office Lunch Room and Toilet $9,000
- Concrete Paving, Walkways, Car Park etc $4,000
- 565 metres Security Fencing ($12,000) and
Lighting $14,500
- Ongoing Security Patrol $14,000
- Signage $1,000
Relocation of Equipment
- 2 Loaders, 3 Power Screens, Fuel Tank $1,375
- Dismantle, relocate and assemble Trommel $29,250
- Council Application Fees $1,000
Alteration to Yellow Pages advertising $200
Advise clients of alteration to premises’ location $100
-- 23 of 27 --
24
$75,825
Rounded to $76,000
As I understood the evidence, the items of “Construction” and under “Provision of”
were intended to effect reinstatement at a replacement site. On the evidence I am not
prepared to accept that the “office lunchroom and toilet” were owned by the claimant. Mr
Walsh’s evidence referred to the acquisition by an associated company of an alternative, albeit
unsuitable and consequently temporary site, for the continuation of the business. There
existed on the subject land a mobile home which does not form part of the claim, but which
provided accommodation for a work person who in return performed an after-hours security
role.
Mr Lacey was asked to comment on the claim from a valuation point of view.
Putting aside the question of ownership, he felt the claim for the structures and the concrete
paving etc, based on that which existed, was excessive and that the need for security patrol
was common to any site. He had no argument with the claim for security fencing.
It seems to me that the “concrete paving, walkways” etc, on the evidence would have
added minimal value to the land taken.
It is the respondent’s submission that as the use of the site for a sand and soil business
was unlawful, the constructing authority should not be expected to pay any compensation for
disturbance under the heading of relocation. As addressed under the town planning issues, I
have accepted that successful application for suitable rezoning of the land would have been a
reasonable expectation. The evidence indicates that even though technically unlawful, the
sand and soil business had operated for a relatively long period within the knowledge of the
respondent Council. If for any reason the use had been ordered to cease, I am satisfied that
closure would have been of a temporary nature for a period sufficient for the town planning
issues to be resolved.
In the absence of close examination of the basis of Mr Walsh’s assessment of
individual items under this heading, I will allow an amount of $14,500 for security fencing
and lighting, $3,500 as the value of siteworks and rounded relocation expenses, including
client advices and advertising, of $31,000. It would seem to be unrealistic to claim for
“Council application and fees” when, although necessary, such application had not been made
for use of the existing site. I agree with Mr Lacey’s opinion that some form of security patrol
-- 24 of 27 --
25
might be seen as a normal requirement of such a business, and that the claim under that
heading is too remote to be compensable.
The total award for the claim as formulated under the heading of “Relocation”
amounts to $49,000. Although relocation of most equipment has been deferred, the question
of interest payment will be considered later.
(b) Loss on Sales of Topsoil
The agreement reached between the parties relative to continued occupation of the site
resulted in identification of loss being restricted to the effect on the value of the stockpile of
“soil” for resale.
Again, the respondent argued that the unlawful activity was not deserving of an award
of compensation. Just as the respondent recognised the practicality of allowing an extension
of the use which was, in the ownership of the claimant, an unlawful activity, I reiterate that
any ordered cessation of that activity would have related to technicalities which, in my
opinion were capable of correction on reasonable grounds.
The history of soil sales had been established by Mr Walsh as amounting to 12,000
m³ per annum at a sale price of $13 per m³. That activity had continued subsequent to the
resumption until October 1995. At that date a stockpile of near 70,000 m³ remained, with a
sales period on past trading history of 5.8 years required to dispose of the stockpile. The
decision was then taken to reduce the sale price to $8 per m³ in an effort to dispose of the
stockpile more speedily. Sales increased significantly. Based on the actual trading results it
was estimated that the stockpile would reduce at the rate of 3,200 per month (38,400 m³ per
annum) lasting 1.8 years. This would enable the remaining material to be sold within the
period for which continued occupation of the site was arranged.
Adopting a discount factor of 15% Mr Walsh found that the present value of the
stockpile before the reduction in price, on sales of 12,000 m³ per annum @ $13 per m³ over
5.8 years was $577,634. After the price reduction, the then present value was found as
being 38,400 m³ per annum @ $8 per m³ for 1.8 years or $455,520. The loss in value was
$122,000.
Mr Lacey felt that if compensation was to be allowed, the after price reduction
calculation was appropriate, based on a discount factor of 15%. However he suggested that
there was greater risk associated with the longer selling period involved in disposing of the
stockpile before the price reduction situation, and suggested that a discount factor of 20% for
that calculation should be adopted.
-- 25 of 27 --
26
I have not been convinced that the risk as it previously existed, was greater than that at
the reduced sale price, with increased volume of sales necessary. I will adopt Mr Walsh’s
calculation of $122,000.
Professional Fees
Agreement had been reached as to the amount of $16,975 for professional fees outlaid
in the compilation of the claim for compensation. Of that amount, $1,000 had been paid by
the claimant in March 1995.
Summary of Determination
Compensation is determined as follows:
Market Value as zoned -
Land
- Potential landfill component $1,420,000
- Potential component for soil and sand business $250,000
$1,670,000
- Quarry Reserves 195,000
$1,865,000
Disturbance
Sand and Soil Business
- Relocation costs $49,000
- Loss on sales of soil $122,000 $171,000
Professional Fees - as agreed $16,975
Total Compensation $2,052,975
Interest
An advance payment of $1,000,000 was made on 19 May 1995. The submission of
the respondent was that as the claimant had been permitted to remain in possession of the land
it was inappropriate for interest to be paid on the compensation awarded for loss of land.
Apart from the reduced claim for loss on sales of soil, the claimant submitted that the
continued occupation of the land had eliminated claims for compensation for other stockpiles
of valuable material which will now be capable of disposal (without price reduction) before
the occupation agreement expires. Had there been no continued occupation of the site the
claimant submitted that the respondent would have been faced with additional significant
claims for compensation.
Section 28 of the Acquisition of Land Act (1967) provides the Court with the
discretion to order that interest be paid “upon the amount of compensation determined by it”
with the exception being in respect of any amount of compensation advanced.
-- 26 of 27 --
27
Ordinarily, continued occupation of the land free of rental would be accepted as a
consideration in lieu of the payment of interest.
The occupation arrangement in this matter had commercial implications for both
parties but in practical terms, related only to the sand and soil limb of the business conducted
on part of the land. Based on the finding, neither party is seen to have been disadvantaged
with respect to the use and continued occupation of that part of the land.
In the circumstances I see it as appropriate to order that interest be awarded but only
on that part of the determination which excludes any aspect of the sand and soil business, as
well as the advance.
It is ordered that interest at the rate of 8.75% per annum be paid on the amount of
$1,615,000 for the period commencing on and from 16 December 1994 ending on and
including 18 May 1995 then on the amount of $616,000 (including the professional fees of
$1,000 paid by the claimant near to that date) on and from 19 May 1995 ending on and
including the day immediately preceding the date on which the final compensation payment is
made.
RE WENCK
MEMBER OF THE LAND COURT
-- 27 of 27 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1996/128