Brownlow v Chief Executive, Department of Lands [1996] QLC 47
LAND COURT
BRISBANE
23 APRIL 1996
Re: Appeals against unimproved valuations -
Valuation of Land Act 1944
AV94-680 and AV95-592
N.G. & P.D. Brownlow
v.
Chief Executive, Department of Lands
D E C I S I O N
Mr and Mrs Brownlow are the owners of land situated at the Corner of Lamington
Avenue and Bradshaw Street, Lutwyche, in close proximity and to the west of Lutwyche Road.
The land is described as Lots 83 and 84, RP 19352, Parish of Enoggera, County of Stanley and
contains an area of 830 m2. It is zoned "Residential B-RX" (Res B-R4) and is used as a car
sales yard and residence.
As at 30 June 1993 and then 1 January 1995 the Department's unimproved valuations
(after alteration in terms of s.68 of the Valuation of Land Act (the Act)) became as follows:
30 June 1993 - $120,000
1 January 1995 - $127,000
Despite significant alterations to the valuations originally applied at those dates, Mr and
Mrs Brownlow hold the opinion that the valuations appealed against remain excessive. Their
estimates of value are $60,000 and $65,000 at the respective dates. The grounds of appeal are
generally similar in both appeals but the real problems are best summarised as in a statement
which Mr Brownlow tendered to the Court:
"1.Our land is the lowest point in this block and most of our problems
flow from this fact.
2.Largely an old dump site, resulting in subsidence, water problems and
bog after heavy rain.
3.Health problems occur due to the foregoing.
4.Construction costs required to combat inherent problems have no
relation to foundation costs.
5.Most difficult living conditions exist due to nature of area location."
The tendered statement covered nine points to which Mr Brownlow's evidence was
directed. Photographs and a statutory declaration, relative to the physical disabilities of the
land were also tendered. In its unimproved state, the land embraced "a gully or creek" draining
adjacent properties. The land had obviously, at some distant time in the past been used as a
[1996] QLC 47
-- 1 of 5 --
2
dump site. Considerable quantities of household-type rubbish and some soil fill had been
placed on the land by others. A retaining wall of substantial depth and construction protects
Bradshaw Street on the southern boundary, while the northern and eastern boundaries of the
land are retained by private walls, of varying standard of construction and condition both above
and below existing filled levels.
A brick dwelling with significant structural faulting and a used car yard are constructed
at various mostly retained levels.
The true unimproved state of the land is not precisely known. At some time subsequent
to the objection and appeal process being investigated, it was suggested to Mr Brownlow that he
should seek advice as to the cost which would be involved in correcting the site specific
problems. Quotations had been obtained and were tendered. The proposal in the quotes was
to excavate and place footings to allow construction of concrete block walls on the northern,
eastern and southern boundaries together with two internal north-south retaining walls and to
concrete, fill and reinforce the block work. All walls would be waterproofed and the site
drained to Lamington Avenue. The quotations were based on a direction to create three levels,
the lower level being 1 metre above the south-western corner peg with all fill to be compacted
and all rubbish removed. Excluding Council fees and the cost of removal of existing buildings,
the quotations dated 10 December 1995 and 19 December 1995 were in the amounts of $85,527
and $91,500 respectively.
Mr I.G. Savage was the registered valuer employed by the Department who had written
both the original valuations and reduced valuations appealed against. He generally agreed with
Mr Brownlow's statement as to the land having once formed a gully of some significance, which
had been filled to the levels it is today, at various mostly retained depths. He thought the gully
would have headed in the subject land, while Mr Brownlow held the opinion that the gully may
have partly affected the land adjoining to the east before its retention.
Mr Savage described the land as follows:
"The subject is the head of a partly filled gully. The gully appears to have started with a
steep fall from the south east corner and then gradually levelling out towards the
north west corner where it flowed into a swamp over Lamington Avenue. The
swamp has since been filled by the Brisbane City Council and made into
Bradshaw Park.
In its current state the subject falls from RL 20 metres AHD on the east boundary to RL
15 metres AHD on the north western corner, a distance of 40 metres.
On the southern boundary fronting Bradshaw Street the property has a natural drop of up
2 metres from the (filled) footpath to the natural ground level.
On the eastern boundary there appears to have been an easy fall onto the subject before
the land fell away steeply (guessed at 4 metres). Currently the subject is filled
on the eastern boundary to approximately 1 metre higher than the ground level of
the adjoining property (uphill).
-- 2 of 5 --
3
On the western boundary the land has been terraced for a unit development. This
property while having its main fall to Lamington Avenue (west) also has a cross
fall towards the subject which causes seepage onto the subject.
At the eastern end the subject has been filled to road level (Bradshaw Road). This
filled area plus an adjoining area of decking is used as a car yard."
Mr Savage agreed that the subject land was once used as a dump. Most of the fill was
household rubbish rather than clean fill. The site suffers from seepage problems.
However, despite:
(a)the poor quality of the fill and
(b) the quotes received by Mr Brownlow;
Mr Savage had concluded that as developed the existing site works, together with the structures
which had been erected added value to the site and therefore did not constitute a "worsement".
He conceded however that "if only the fill and retaining walls had been placed on the
site, they would not constitute an improvement, but would require remedial action and therefore
be a worsement." He took the view that "the works on the site must be looked at as a total
entity and the sum of the added value of the total works adds value to the land and therefore
comprises an improvement overall". He did not provide any valuation exercise to support that
opinion as to the improved value of the property.
As I understood the thrust of his evidence, the structures, although suffering the effects
of subsidence, water seepage and drainage problems generally, could not have existed in their
present form in the absence of the site works which have occurred, regardless of the poor quality
of the fill. As there has been no evidence offered to rebut Mr Savage's opinion that the
development on the site adds value to the unimproved value of the land, I lean to the view that
"worsement" does not exist. In other words, the site should be valued on the basis of its true
unimproved condition, in terms of s.3(1)(b) of the Act, where "unimproved value" means -
"in relation to improved land - the capital sum which the fee simple of the land might be
expected to realise if offered for sale on such reasonable terms and conditions as
a bona fide seller would require, assuming that, at the time as at which the value
is required to be ascertained for the purposes of this Act, the improvements did
not exist."
That was the exercise which Mr Savage set out to complete. He endeavoured to picture
the land in its unimproved pre-dump condition before any filling or internal retention had taken
place. This proved to be an almost impossible task. He saw the highest and best use of the
land being as zoned, for multi-unit residential development. He envisaged some style of
building development which would be designed to incorporate any site works development
within the foundations and drainage specifications. For example, as he understood it, the
quotations obtained by Mr Brownlow, included, unintentionally, work which could also be
regarded as part of the foundations of a building, and then not necessarily the best designed
building for the highest and best use of the site. Mr Savage had not understood the full extent
-- 3 of 5 --
4
of the unimproved disabilities of the site until it had become necessary to deal with the appeals.
He had specifically inspected the site and discussed the problems with Mr Brownlow. He was
frank in stating that without knowing the true unimproved physical state of the land, the
unimproved value could range anywhere between $20,000 and $60,000 below his original
valuation of $160,000, as at 30 June 1993. He indicated that the original valuation had taken
into consideration the environment in which the land was situated and its obvious features both
positive and negative. The amended valuation took that first valuation as a base then an
amount of $40,000 was deducted in a genuine attempt to find a value which should have been a
reasonable interpretation of the true unimproved market value. Previous valuations apparently
had not recognised or been based on any accurate knowledge of the actual unimproved state of
the land.
Mr Savage's amended 1993 valuation, of $120,000, is equivalent to a unit of area value
of $145/m2. Sales of four "Residential B" zoned sites showed values ranging from $152/m2 to
$200/m2. (On the evidence of those sales the original 1993 valuation of $160,000 had been
equivalent to a rate of about $190/m2).
In the 1995 valuation, from two sales showing analysed unimproved values of $208/m2
and $198/m2 Mr Savage had concluded that values for "Residential B" zoned land had increased
from the previous date. He had increased the valuation from $145/m2 to $152.50/m2.
I agree with Mr Savage that the subject land, although poor physically, should be
regarded as having highest and best use potential for multi-unit residential development, as
zoned.
However, it seems obvious that a vendor of unimproved land of such poor quality would
be confronted with a most limited and speculative type market. Buyers would be expected, in
the absence of precise development cost estimates, to negotiate on the worst case scenario.
Without intending to be critical of him, (and indeed to the contrary), Mr Savage has
taken it appears, a middle-of-the-range yet imprecise site works development cost estimate.
That estimate might, with precise investigation, prove to be reasonable or even generous.
However, it seems to me that this is a matter where this Court should further extend the benefit
of the real doubt which exists. The one thing which does seem clear is that if "worsement" is
not involved, then the quotes obtained are for works which reflect other than the condition of
the land and its potential as unimproved.
Mr Brownlow has proved the substantive grounds of appeal at least against the original
valuations. However, the amended valuations have now been carried out on the basis that the
unimproved condition of the land was significantly worse than was first thought. For the
reasons given, I am unable to gain specific assistance from the quotations obtained.
In extending the benefit of doubt I have decided to adopt a site value of $110,000 as at
30 June 1993. Then, on the evidence, it seems reasonable that some increase in value might
have occurred even for land of this quality, in the period between the two valuations. For
future reference, market trends relevant to land of relatively sound physical quality would not be
-- 4 of 5 --
5
seen to flow automatically to a site such as is the subject. I will adopt an .unimproved value
for the land of $115,000 as at 1 January 1995.
The appeals are allowed, the valuations of the chief executive set aside and the
unimproved values determined as follows:
As at 30 June 1993 - $110,000
As at 1 January 1995 - $115,000.
RE Wenck
MEMBER OF THE LAND COURT
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1996/047