Angsea Investments Pty Ltd v Gauci, Fox, Rincono Pty Ltd & Wade [1995] QSC 300
IN THE SUPREME COURT
OF QUEENSLAND
No. 2954 of 1989
BETWEEN: ANGSEA INVESTMENTS PTY LTD
(Plaintiff)
AND: GEORGE GAUCI
(First Defendant)
AND: JENNIFER LYN FOX
(Second Defendant)
AND: RINCONO PTY LTD
(Third Defendant)
AND: STANLEY THOMAS WADE
(Fourth Defendant)
REASONS FOR JUDGMENT - G N WILLIAMS J.
Delivered: 14/12/1995
CATCHWORDS: Contract - supply of fill - plaintiff's agents
fraudulently retained part of price - supplier
party to fraud - held plaintiff entitled to
recover from agents and supplier - payments to
supplier calculated on mistake as to quantity
delivered - held plaintiff entitled to recover
over-payment.
Counsel: D.J.S. Jackson Q.C. for plaintiff.
G. Gauci, first defendant, on his own behalf and
on behalf of second and third defendants.
Mr McHugh for fourth defendant.
Solicitors: Barker Gosling for plaintiff.
Primrose Couper Cronin and Rudkin for fourth
defendant.
Hearing Dates: 17, 20, 21, 24, 25, 26, 27, 28, 31 July 1995
1, 2, 3, 4, 9, 10 August 1995.
-- 1 of 55 --
IN THE SUPREME COURT
OF QUEENSLAND
No. 2954 of 1989
BETWEEN:
ANGSEA INVESTMENTS PTY LTD
(Plaintiff)
AND:
GEORGE GAUCI
(First Defendant)
AND:
JENNIFER LYN FOX
(Second Defendant)
AND:
RINCONO PTY LTD
(Third Defendant)
AND:
STANLEY THOMAS WADE
(Fourth Defendant)
REASONS FOR JUDGMENT - G N WILLIAMS J
Judgment delivered 14/12/1995
The pleadings in this action raise a number of causes of
action for determination. In broad terms the plaintiff, Angsea
Investments Pty Ltd, through its agent and managing director
John Kenny, orally agreed in about February 1988 with George
Gauci, the first defendant, acting as the agent for the third
defendant, Rincono Pty Ltd, that Angsea and Rincono would enter
into a joint venture for the development of a complex of duplex
residential units at Labrador on the Gold Coast. Rincono was
to inject $150,000 by way of capital and would for that amount
acquire one half of the share capital in Angsea. Thereafter
the parties to the joint venture would contribute equal amounts
-- 2 of 55 --
2
of capital. Pursuant to that joint venture arrangement Angsea
appointed Gauci to be the licensed builder and the manager of
the project; included in that managerial work was the
management of earthworks to be carried out on the project site.
Angsea acquired the land at Labrador (Parkview site) where
the development was to occur and obtained finance in the sum of
$2.894 million through Elders Lensworth Finance Limited. But
Rincono did not inject the capital funds pursuant to its
obligation under the joint venture agreement prior to the
arrangement being terminated in June 1989. However the project
proceeded between February 1988 and June 1989 as originally
planned, and that failure by Rincono is not relevant for
present purposes.
A substantial quantity of fill had to be placed on the
subject land as the first step in the development. In giving
this broad overview it is sufficient to say that Gauci on
behalf of Angsea contracted with ST Wade, the fourth defendant,
for the latter to deliver the necessary fill to the site. The
first delivery was made on 18 November 1988 and the last on 16
June 1989.
By the date of trial the second defendant, Jennifer Lyn
Fox, was married to Gauci. They had a close relationship
during 1988-89. Fox was a director and nominally the
controlling mind of Rincono throughout that period. But that
was undoubtedly because Gauci was then an undischarged bankrupt
and disqualified from being the director of a company.
Throughout the relevant period prior to June 1989 Fox did
-- 3 of 55 --
3
clerical work in connection with the project, working in the
main from the office of Angsea. From July 1988 she was an
authorised signatory with the ANZ Bank with respect to the
drawing of cheques by Angsea.
As part of the joint venture agreement Rincono was paid
$6,000 per month on account of the services provided to Angsea
by Gauci and Fox; the first payment was in August 1988.
Angsea alleges that Gauci and Fox acted fraudulently or in
breach of the fiduciary duty they owed to Angsea in retaining
for themselves $1 out of the amount invoiced by Wade for each
cubic metre of fill delivered to the site. To that end it is
alleged that fraudulently and in breach of their fiduciary duty
they agreed to pay more than a reasonable price for the fill to
Wade. It is alleged that they agreed to pay Wade 50 cents in
cash for each cubic metre of fill delivered to the site. In
consequence there is a claim against each of Gauci and Fox for
an account of monies received, damages for fraud or deceit, and
damages for breach of contract. Similar claims are made
against Rincono, together with a further claim for an order
that it repay the total of $60,000 it had received on account
of the services provided to Angsea by Gauci and Fox.
As against Wade, Angsea alleges that he was a party to the
fraudulent conduct of Gauci and Fox referred to above, such
participation being evidenced by his invoicing Angsea for an
amount for each cubic metre of fill delivered to the site which
he knew included an amount to be retained illegally by Fox and
Gauci, and in falsifying contractual and other documents to
-- 4 of 55 --
4
give apparent validity to all relevant transactions. In
consequence Angsea seeks from Wade an account of the additional
amounts he received, equitable damages or compensation, damages
for fraud or deceit, and damages for breach of contract.
There is an additional claim made by Angsea against Wade.
According to the delivery dockets (exhibit 3) a total of
241,350 cubic metres of fill was delivered between November
1988 and June 1989. According to calculations made by experts
on behalf of Angsea only 127,500 cubic metres or thereabouts of
fill has actually been delivered to the site and compacted.
Angsea claims to recover the value of the difference between
those two quantities as money had and received.
When Angsea first became aware of the alleged fraud in
June 1989 it stopped payment on a cheque for $60,000 drawn in
favour of Wade on 9 June (cheque 367079), and it also
terminated the contract for the supply of fill. By way of
counterclaim Wade claims $60,000 in respect of the dishonoured
cheque, and $194,200 damages for breach of contract being lost
profits upon his being wrongfully prevented from completing
delivery of the fill. In addition Wade alleges that Angsea has
not paid for 12,990 cubic metres of fill delivered between 7
and 16 June 1989 and claims $84,435 with respect thereto.
Finally Wade also claims an additional $2,496.62 for materials
supplied.
The conduct of Gauci which is at the heart of the claims
made by Angsea in this action resulted in him facing criminal
charges; some more detail about that will appear later. After
-- 5 of 55 --
5
being convicted of misappropriating money belonging to Angsea,
Gauci successfully appealed to the Court of Appeal; the
relevant reasons are reported at (1995) 1 Qd. R. 296. In the
course of their reasons their Honours said: "We are
nevertheless left with the faint impression that perhaps the
full story has yet to be told." After a trial lasting 15 days
resulting in 1,140 pages of evidence and 126 exhibits
comprising many hundreds of pages, I have a much clearer
picture of what occurred, but nevertheless I still feel quite
certain that there are aspects of the dealings between the
parties I have not been told about, or at least the full story
has not even now been revealed to the court.
Gauci and Wade each tried to deflect allegations of fraud
directed towards themselves by making accusations against
Kenny. With respect to some transactions not central to these
proceedings there probably is on the evidence some doubt as to
the role played by Kenny, but those issues were collateral to
the causes of action raised by the pleadings and I was not
prepared to permit the trial to be totally deflected in order
to reach definite conclusions thereon. In so far as Kenny's
credibility was in dispute the issues were fully canvassed.
Kenny was subjected to lengthy cross-examination and many
allegations of improper conduct were put to him. At the end of
the day, on the evidence which emerged at the trial, I am
prepared to accept him as a witness of truth. On the evidence
I am not persuaded that he was a party to any dishonesty. On
the other hand, for reasons which I will develop at some
-- 6 of 55 --
6
length, I formed a very unfavourable impression of both Gauci
and Wade. Indeed I have felt compelled to find that each of
them lied in the course of giving evidence at the trial; it is
not a finding which I am ordinarily prepared to make, and in
this case it is not one I have lightly made. In all the
circumstances I cannot accept any evidence given by either
Gauci or Wade except where it is confirmed by other reliable
testimony.
The first issue which needs to be addressed relates to the
terms of the agreement pursuant to which fill was supplied. An
advertisement was placed in a local newspaper calling for
tenders to supply and place approximately 160,000 cubic metres
of fill; the advertisement gave a specification for the fill of
CR 25. In response Wade submitted a quote specifying a CBR
rating of 15; in fact the CBR rating can be disregarded for all
purposes. Wade's tender was for $1.30 per cubic metre ex
quarry and cartage on a loose measure basis of $3.70 per cubic
metre, making a total per cubic metre loose measure delivered
of $5. The tender required payment consequent upon the issuing
of a monthly certificate by the engineer, payment being within
14 days of the issue of the certificate. It also asked that
the whole of the money payable be guaranteed; it stated that
the form of the guarantee should be worked out by the parties
prior to the commencement of the work. It also contained the
following sentence: "The above tender is a firm one and
includes the cost of survey before and after completion of the
work and attention during its progress."
-- 7 of 55 --
7
There is a dispute on the pleadings as to the contract
which thereafter came into existence, and that dispute became
even more significant as the trial progressed. In paragraph 8
of the Statement of Claim the terms of the contract were
alleged to be:
"(a) the Plaintiff would pay to the Fourth Defendant
the sum of $3.00 per cubic metre of loose fill
delivered to the project;
(b) the Fourth Defendant would invoice the Plaintiff
for an additional $1.50 per cubic metre of loose fill
delivered to the project (hereinafter called "the
additional sum invoiced");
(c) the Fourth Defendant would receive 50 cents per
cubic metre in cash in respect of the additional sum
invoiced;
(d) the First Defendant would receive the balance of
the additional sum invoiced."
Those allegations appear to be based essentially on the
acceptance of Wade's quotation (as amended after negotiation
between Gauci and Wade) established by the following notation
and signatures which were placed at the foot of a copy of the
tender:
" 19 September 1988
Agreed by Mr George Gauci and Mr Stan Wade that the
revised price to supply loose measure would be
$4.50/m3 and payments every second Friday from
commencement of deliveries.
Stan Wade George
Gauci"
I am satisfied that as at 19 September 1988 and for
considerable time thereafter Wade was not aware of the
involvement of Angsea. On the balance of probabilities I would
-- 8 of 55 --
8
accept that he believed until about 16 December 1988 that he
was dealing with Gauci as principal. It is not necessary in my
view to say more about that; from the time the first payment
was made it was known by all that Angsea was the principal and
at all material times all parties treated Angsea as such.
I am also satisfied that Wade originally tendered on the
basis that the source of the material would be his quarry at
Reedy Creek. As at September 1988 he had tendered for the
removal of fill from the Colgate site but that tender was not
awarded to him until late November 1988. The deliveries made
between 18 November 1988 and 3 December 1988 were from the
Reedy Creek quarry. Wade's agreement to reduce the price from
$5 to $4.50 per cubic metre was probably partly due to his
expectation that cheaper material would become available from
the Colgate site. There was no further price reduction once it
was known that the fill would come from the Colgate site and
there would be a shorter hauling distance from there to the
subject site.
Angsea did not prove a specific agreement containing the
terms (a) (b) (c) and (d) as pleaded. The evidence clearly
establishes that until about 15 May 1989 Wade's invoices were
for $4.50 per cubic metre, that he received $3.00 in payment by
way of a cheque, that he received a further 50 cents cash, and
that the balance of $1.00 was retained in cash by Gauci and/or
Fox. The court was asked to draw the inference from what in
fact occurred that there must have been an agreement to the
effect pleaded.
-- 9 of 55 --
9
In Wade's Defence and Counterclaim the original agreement
is pleaded as follows in paragraph 4:
"(b) the Plaintiff and the Fourth Defendant entered
into a contract in writing dated 5 December, 1988 for
supply of fill by the Fourth Defendant at a price of
$4.50 per cubic metre;
(i) it was a term of the said written agreement of
5 December 1988 that the Fourth Defendant would be
permitted to supply to the Plaintiff all the fill
required for the Plaintiff's project and that the
Plaintiff would accept the supply of all the said
fill by the Fourth Defendant:
PARTICULARS
The said agreement provided inter alia:
"The contract ... shall be irrevocable by either
party for the duration of filling operation of the
area. In case of a sale, the rights and
responsibilities shall recast to and be acquired by
the new owner".
(c) In or about January 1989 the said contract was
varied by oral agreement between the First Defendant
on behalf of the Plaintiff and the Fourth Defendant;
(d) The following were terms of the agreement as
varied:
The Fourth Defendant would accept $3.50 per cubic
metre in satisfaction of the price of $4.50 per cubic
metre if the payment of invoices was made strictly
weekly and if the roads on the site were watered and
maintained by the Plaintiff."
That pleading would appear to be based upon the document
which is found at exhibits 76 and 77 (during the plaintiff's
case those documents were exhibits C and D for Identification).
I will not set the document out in full but the following
points should be noted in addition to the extract quoted in the
pleading. The principal is said to be Angsea Investments and
it is signed for the principal by Gauci. It specifies that the
fill shall be supplied from the Colgate site and gives Angsea
-- 10 of 55 --
10
the sole right to that material so long as it shall be
available. The document also provided that invoices should be
given on the Tuesday of each week and payment made on the
following Friday. The last two sentences were as follows:
"Principal shall pay for all materials supplied for
haul roads and for any machine work performed
thereon.
At the termination of supply from Colgate Palmolive
Site a new contract shall be negotiated for further
supplies".
In his evidence at the trial Wade said that those
documents were created "a little before" 5 December, and signed
on that date. However, as I have already mentioned, Wade was
not aware of Angsea as at that date. There is ample evidence
to justify such a conclusion. The first invoice prepared by
Wade was for fill supplied up to and including 16 December
(exhibit 21); it is addressed to Gauci only. Subsequently, but
prior to delivery, it was amended (for example, see document 8
in exhibit 5) to have "Angsea Investments Pty Ltd" typed in
above the reference to Gauci. That suggests that when the
invoice was first prepared it was not known that Angsea was the
principal. Indeed Wade expressly conceded that in his
interview with the police (exhibit 29 page 41). Under cross-
examination during the trial he indicated that he became aware
of Angsea through statements made by his truck drivers who were
delivering the fill. There are other passages in that cross-
examination which confirm that initially he believed he was
dealing with Gauci. I am satisfied on the whole of the
evidence that the first correctly dated delivery docket bearing
-- 11 of 55 --
11
the name of Angsea was that of 12 December 1988.
Wade was confronted under cross-examination with the
question how could the agreement purportedly signed on 5
December have referred to Angsea if he was not aware of
Angsea's involvement until about 12 December at the earliest.
He responded by saying: "Well, of course, Mr Gauci told me
Angsea Investments at the time, yes. I therefore must have
known before that." Having considered all of the evidence -
much of which will be referred to in some detail later - I have
come to the conclusion that that was a deliberate lie concocted
whilst in the witness box in an endeavour to explain away the
impossibility which otherwise confronted him.
There are also other indicators which throw doubt on the
veracity of the testimony that the document relied on by Wade
(exhibit 76) was in fact executed on 5 December. As at that
date there was no local authority requirement that there be a
haul road and the reference in that document to the haul road
does not mesh with known requirements as at the date of the
document. Sometime after 5 December the local authority
directed that deliveries of fill to the site cease until a haul
road had been established across an adjoining public water
reserve. There is also no satisfactory explanation for the
inclusion in that document of the reference to change of
ownership of the subject land. There was no such reference in
the document signed 19 September 1988, and there is nothing in
the evidence which would explain the inclusion in such a term
in a document executed on 5 December. Finally, as at 5
-- 12 of 55 --
12
December it would appear that Wade believed that there was
sufficient material in the Colgate site to provide the 160,000
cubic metres required to satisfy the tender. In his statement
exhibit 7 Wade said that in about September 1988 he had made a
rough calculation that the Colgate site would yield fill in the
order of 300,000 cubic metres loose (or about 187,500 cubic
metres of solid fill).
At this stage it should also be noted that there is
nothing apart from the say so of Wade and Gauci to support the
allegations made by Wade in his Defence and Counterclaim that
there was a variation of the December 5 agreement in or about
January 1989. The alleged variations do not fit well with the
objectively known circumstances. There was never any basis for
an argument that Wade was responsible for maintaining the
access roads to the site. That obligation always rested with
Angsea and it is ludicrous to suggest that Wade was prepared to
pay $1.00 per cubic metre to secure Angsea's performance of
that obligation. Even if there was some basis for Angsea and
Wade agreeing as to the cost of maintaining the access roads,
that cost would have been nowhere near represented by $1.00 per
cubic metre of fill delivered (a total of $232,588 was
involved). So far as payment weekly is concerned that was
already part of the contract between the parties if the
document dated 5 December was that which evidenced the
agreement. The variation added nothing of substance. Further,
from almost the first week in January payments in fact were not
made strictly on a weekly basis; on a number of occasions post-
-- 13 of 55 --
13
dated cheques were given. But Wade always gave the discount.
In all the circumstances I am not satisfied that there were
agreed variations in January as alleged by Wade; to some extent
in arriving at that conclusion I have relied upon my findings
as to matters subsequently referred to which reflect adversely
on the credibility of Wade and Gauci.
It is convenient at this stage to consider the competing
contentions with respect to subsequent variations of the
agreement between the parties whatever it was. Angsea did not
plead any subsequent variation and the witnesses called on its
behalf were unable to do more than refer to invoices received
and amounts paid. The statement of claim merely acknowledges
that deliveries after 9 May 1989 were invoiced at $6.50 per
cubic metre and paid at that rate.
In the Defence and Counterclaim as it stood at the
commencement of the trial (the pleading delivered 16 January
1995) the following allegations were made in paragraph 4:
"(e) By an agreement partly in writing dated 15 May
1989 and partly orally made at the same time the said
agreement was further varied to increase the price of
fill to $6.50 per cubic metre;
(i) The oral part of the said agreement was made
between the First Defendant as agent of the Plaintiff
as aforesaid and the Fourth Defendant and was that
the written part of the said agreement of 15 May 1989
would pertain only for so long as the prior site for
the obtaining of the fill (the Colgate Site) was
inaccessible to or unavailable to the Fourth
Defendant and that when the Colgate Site was
accessible or available to the Fourth Defendant, then
the agreement of $4.50 per cubic metre supplied from
the Colgate Site would revive;
(f) In or about May 1989 the said agreement in
writing was further varied by oral agreement between
the First Defendant on behalf of the Plaintiff and
-- 14 of 55 --
14
the Fourth Defendant;
(g) The following were the terms of the agreement as
varied:
The Fourth Defendant would accept $5.50 per cubic
metre in satisfaction of the price of $6.50 per cubic
metre if payment of invoices was continued to be made
strictly weekly and if the Plaintiff continued to
water and maintain the roads on site."
The contention in that pleading that there was a written
agreement dated 15 May 1989 is clearly a reference to the
document exhibits 78 and 79 (which throughout the plaintiff's
case were exhibits E and F for Identification). That document
purports to contain an addition to the agreement said to have
been executed on 5 December. There is a date "15 May 1989" and
under it the body of the variation is in these terms:
"New negotiated price
Whereas supplies from the abovementioned site have
become exhausted, a new price of $6.50 per cubic
metre shall now apply.
All rights and responsibilities outlined above shall
apply to deliveries which shall now be made from
Hymix Quarries."
The document was signed by Gauci on behalf of the "principal"
and Wade.
This was a managed case and the reviewing Judge gave
directions that the parties exchange witness statements. The
first witness statement lodged by Wade was that which became
exhibit 100. In it he clearly asserted that when the agreement
of 5 December 1988 was executed there was no date "15 May 1989"
on it nor any of the words which appear after that date on
exhibit 78. He went on in that statement to say that by "May
1989 there was extensive wet weather on the Gold Coast and I
-- 15 of 55 --
15
could not remove the fill from the Colgate Palmolive Site
because of that wet weather". He there claimed that in
consequence he "told Gauci that I could not get any more fill
from Colgate Palmolive but I could get some from Hymix but the
price for such fill would be greater. I told him the price
would be $6.50 per cubic metre and Gauci agreed to pay the
price. We signed an amendment to document number 3 on 15 May,
1989." Clearly Wade was there saying that the bottom
signatures on exhibit 78 were placed there on 15 May 1989.
A little later on in that statement Wade says that he was
pressured by Gauci to reduce the price to $5.50 per cubic metre
because Gauci asserted he could obtain fill from another
supplier at that price. Wade says that he was able to
negotiate that, but his statement goes on:
"Gauci said again to me that he would rather me
continue to invoice him at $6.50 because he had
arranged for further finance on those terms and he
would be able to use the $1.00 extra on the site. He
also told me that he would still like to pay me 50
cents in cash."
It is convenient to record here that Wade at a late stage in
the trial sought to distance himself from those statements on
the ground that he had not read the document before he signed
it. Again I am satisfied that that was a lie. Some of my
reasons for so concluding will emerge later. Suffice it to say
at this stage that in exhibit 100 Wade was attempting to
explain away remarks made in a statement to police which he had
signed and dated 14 June 1989 (exhibit 96). I will not refer
to that police statement in any detail; suffice it to say that
it does not support much of the critical evidence given by Wade
-- 16 of 55 --
16
in the course of the trial. What is important for present
purposes is that in exhibit 100 Wade said with respect to
exhibit 96:
"With regard to my statement to the police I say the
agreement to supply fill from the Colgate Palmolive
Site for $4.50 did not include consolidation but was
for loose measure as agreed with Gauci in 19
September, 1988. Sergeant le Gros must have got this
mixed up with the first quote or it might have been
my fault. I did not re-read the statement at the
Police Station. I did not have my reading glasses
and was very agitated, having been taken to the
Police Station without any warning at all that there
might be trouble in the wind.
The statement I gave to the police is not entirely
accurate because at that time I really did not know
where I stood and I did not know whether I was in
trouble or not want to get myself or Gauci into
trouble. I also had not the opportunity to look back
over the history of the matter. I had not had the
opportunity of obtaining legal advice and I did not
have any idea where I stood. Sergeant le Gros took
me to the areas which he wanted me to comment on and
after he summarised things I'd explained to him in
detail. Having had the opportunity to think back
over the matter, and review the documentation I am
able to say that this statement is entirely correct."
(my emphasis)
In the light of the last sentence in particular Wade's
evidence at trial that he did not read over exhibit 100 before
signing it rings hollow. It should also be noted that in the
passage I have just quoted Wade seems to suggest that the basic
agreement for the supply of fill was that reached on 19
September 1988 - the document relied on by Angsea.
Wade's next relevant statement was that prepared by police
for the criminal proceedings against Gauci. The statement is
dated 25 September 1990 (exhibit 101) and was the basis of the
evidence given by Wade on 20 December 1990 in committal
proceedings against Gauci. In that statement the following
-- 17 of 55 --
17
relevant passage appears relating to the agreement dated 15 May
1989 forming part of exhibit 78:
"This is an original and photostatted copy of an
amended contract, dated 15 May 1989. It bears the
signature of George Gauci and myself. After signing
this addendum, I would have retained an original copy
and George Gauci would also kept one. This is
reflected in the fact that our signatures appear in
different positions on each of the copies before me,
indicating that two of the same addendum have been
signed on the reported date.
The wording on this amendment was derived well before
its reported signing on 15 May 1989. I had
formulated this amendment, in the anticipation of the
Colgate Palmolive fill genuinely running out. ...
I cannot recall the exact date when Gauci verbally
agreed to the conditions of this new amendment,
however I believe that the addendum to the contract
was signed on 15 May 1989. ... Gauci offered no
argument to the signing of the new addendum, and I
recall thinking it strange, at the time, that he did
not negotiate as hard as he did with the previous
contract."
Exhibit 7 was another statement of Wade filed pursuant to
a practice direction; it was another pre-trial statement dated
10 January 1995. In it he said, relevantly for present
purposes:
"Although I cannot specifically recall my
conversations with Gauci leading to the supply from
the Hymix Site, I believe that I must have had his
verbal approval to supply from the Hymix Site before
15 May 1989. In any event, Gauci and I signed an
agreement as an addendum to the contract of 5
December 1988 headed 15 May 1989 whereby it was
agreed that I would supply fill from the Hymix Site
at the rate of $6.50 per cubic metre. A copy of the
contract of 5 December 1988 has an addendum of 15 May
1989 at the foot thereof. Gauci raised no objection
to the signing of the document for the supply at
$6.50 per cubic metre from the Hymix Site at the time
he signed the agreement for that supply. A couple of
days later he approached me however and said he could
get fill material from a firm called Marshall and
Rankin for $5.50 per cubic metre."
-- 18 of 55 --
18
On the basis of all that material I have no hesitation in
concluding that all of Wade's pre-trial statements were to the
effect that the addendum agreement of 15 May 1989 was signed on
or about that date by he and Gauci, and after some brief
negotiations between them in which there was reference to
circumstances prevailing at that time.
In the course of opening the case for Angsea Mr DJS
Jackson QC said that a handwriting expert would be called to
give evidence that all four documents (exhibits 76, 77, 78 and
79) were signed on the one occasion using the same pen.
Mr McHugh, counsel for Wade, asked for permission to have
Wade's document expert examine those four documents in the
light of the opening. That was granted. Subsequently it was
conceded by counsel on behalf of Wade that there was no dispute
as to the fact that the four documents were signed on the one
day using the one pen. In consequence the evidence opened by
Angsea was not led orally, but the expert's report was admitted
as exhibit 59.
On the afternoon of the eighth day of trial counsel for
Wade made an application to further amend the Defence and
Counterclaim particularly with respect to allegations regarding
the addendum of 15 May 1989. Leave was granted to make the
amendments and in consequence the relevant portion of Wade's
pleading read as follows:
"(d)(i) It was further agreed on 5 December 1988
between the Fourth Defendant and the First Defendant
for an on behalf of the Plaintiff that:
(a) During the course of supplying fill to the
Plaintiff's site the Fourth Defendant might be
-- 19 of 55 --
19
obliged to supply fill from the Hymix Site;
(b) If the event referred to in (d)(i)(a) eventuated
the price of the Hymix fill would be $6.50 per cubic
metre;
(c) The said agreement be reduced to writing in an
undated addendum to the written agreement of
5 December 1988.
(d)(ii)(a) On 15 May 1989 deliveries from the Hymix
Site commenced;
(b) The addendum to the agreement of 5 December 1988
referred to in paragraph (d)(i)(c) aforesaid was
dated 15 May 1989;
(e) After 5 December 1988 and prior to the supply of
fill from the Hymix Site on 15 May 1989 an oral
agreement was made in respect to the undated addendum
being the written agreement for the supply of fill
from Hymix made on 5 December 1988:
(i) The oral part of the said agreement was made
between the First Defendant as agent of the Plaintiff
as aforesaid and the Fourth Defendant and was that
the written part of the said agreement dated 15 May
1989 would pertain only for so long as the prior site
for the obtaining of fill (for Colgate Site) was
inaccessible or unavailable to the Fourth Defendant
and that when the Colgate Site was accessible to or
available to the Fourth Defendant then the agreement
of $4.50 per cubic metre supplied from the Colgate
Site would revive."
There was then a further consequential amendment to the
pleading which asserted that after 15 May 1989 the addendum was
further varied by oral agreement to the effect that the Fourth
Defendant would accept $5.50 per cubic metre in satisfaction of
the price of $6.50 per cubic metre if payment of invoices was
continued to be made strictly weekly and if the plaintiff
continued to water and maintain the roads on site.
What perhaps those amendments do not make entirely clear,
but what was made abundantly clear by statements made by
counsel for Wade at the time, is that from and after the
-- 20 of 55 --
20
afternoon of the eighth day of trial it was Wade's case that
the four documents, exhibits 76, 77, 78 and 79, were all signed
in all places on 5 December; the only matter added subsequently
was the date 15 May 1989 on exhibits 78 and 79.
To meet the obvious inconsistency between that position
and the statements previously made by Wade referred to above, a
supplementary statement was then tendered (exhibit 85). In it
the following passages appear:
"On 5 December 1988, Gauci came to my house to sign a
contract for the supply of fill. I prepared two
copies of a contract which was the contract of
5 December 1988 (without the addendum). Gauci and I
signed that contract. I gave him a copy and kept a
copy for myself. Then I produced a document which
was the contract dated 5 December 1988 with an
addendum. There was no date above the addendum. I
deliberately left the date out.
I then said to Gauci something like, "The Colgate
Site might not give us enough fill to complete the
Angsea job and we might have to get fill from
somewhere else". I said I could get fill from Hymix
and supply it at $6.50 per cubic metre. Gauci
agreed. It was important to me to have Gauci tied
down to a price from another source because I didn't
want an argument when or if the occasion arose when
the fill couldn't be supplied from Colgate. I wanted
Gauci tied into a price for any further fill from a
different site before I started the job so the fill
from a source other than Colgate which was going to
be dearer for me to purchase could be specified from
the outset as costing more than $4.50 per cubic
metre. ...
I kept the contracts with the addendum on them (but
undated) in my safe in my home office. When I did
have to supply material from Hymix on 15 May 1989, I
inserted the date "15 May 1989" above the addendum on
both copies with my IBM Composer. I gave Gauci a
copy with the dated addendum on or after 15 May
1989."
Throughout his period in the witness box Wade made a
valiant attempt to adhere to the revised version of events set
-- 21 of 55 --
21
out in exhibit 85, but he failed miserably. His whole evidence
on the point was entirely unconvincing and was clearly the
product of an attempt at the last minute to concoct a story
which would fit the expert evidence which Angsea could lead.
Once it was accepted that all four documents were signed on the
one date, Wade's position had to be that all were signed on 5
December 1988. If none was signed on that date then his whole
case fell to the ground. He lied in an attempt to establish
that the all documents were signed on 5 December but his
evidence in that regard was entirely incredible. He gave no
satisfactory explanation for his many statements (referred to
above) to the effect that the addendum was signed on 15 May.
Gauci was no help to Wade on this issue. In his statement
(exhibit 82) he spoke of renegotiating for the supply of fill
from Hymix in April-May 1989, but readily acceded to
suggestions from Wade's counsel that all documents being
exhibits 76, 77, 78 and 79 could have been signed on 5
December. But basically he had no real recollection, or at
least none that he clearly articulated, with respect to the
signing of those documents. Initially he said that exhibits 78
and 79 were signed on 15 or 16 May, but then he readily
accepted they could have been signed on 5 December.
I do not propose to record in detail evidence as to the
location of exhibits 76, 77 78 and 79 at material times. I
accept that none was in the records of Angsea as at June 1989.
The evidence compels the conclusion that the four
documents referred to were not signed on 5 December 1988. It
-- 22 of 55 --
22
is not strictly necessary to determine when in fact they were
signed, but there are certainly indications that they were
prepared and signed after matters came to a head in June 1989,
and with a view to providing Wade with some material to support
his position. On the balance of probabilities I would find
that they were prepared after Kenny became aware of Gauci's
fraud in June 1989.
I mention in passing the oddity of the proposition that
the documents were in fact prepared and executed on 15 May 1989
yet they did not reflect the variation as to payment being
required strictly weekly and the obligation on Angsea to
maintain the haul road. According to Wade there was a further
oral variation dealing with those matters. His evidence to
that effect contradicts what he said in exhibit 100 about Gauci
forcing him to agree to $5.50 but requesting that invoices
continue to be made out for $6.50.
I have outlined the evidence in relation to the
contractual position between the parties in some detail because
in my view it is of the utmost importance. It proved to my
mind that both Gauci and Wade lied during the trial. They were
prepared to alter their evidence significantly in an endeavour
to make it fit with facts which could be objectively
established by Angsea. I have had regard to Wade's age and
hearing disability but I have no doubt that he was a shrewd,
cunning business man and was fully aware of what was happening
in the course of the trial and of the changes in his evidence.
I therefore reject the contentions of Gauci and Wade that
-- 23 of 55 --
23
the relationship between Angsea and Wade was governed by a
contract made on 5 December 1988, varied in about January 1989,
and with an addendum of 15 May 1989 with subsequent agreed
variations. I am satisfied that the only document evidencing
an agreement between the parties is that dated 19 September
1988 to which I have referred earlier. I would make one
qualification to that, a matter virtually conceded by counsel
for Angsea. From about 15 May 1989 it was necessary for Wade
to obtain fill from the Hymix Quarry because of prevailing
weather conditions and that necessitated a somewhat higher
charge. The reasonable higher fee must be taken to have been
agreed to by Angsea through the person responsible for managing
the project at the time, namely Gauci. Further, on the
evidence I am not satisfied that I should infer an agreement in
the specific terms alleged in paragraph 8 of the Statement of
Claim.
As already mentioned deliveries of fill began on 18
November 1988 and continued through until 16 June 1989.
Generally throughout the period Wade delivered an invoice to
Gauci on the Tuesday of each week. Gauci (or some other
employee in the office) would submit that invoice for
certification to Messrs Herron Todd White; one Steve Herbert
was the person mainly responsible for making such inspections
as were deemed necessary before certification. Angsea would
then write (usually under the hand of Gauci) to Elders
Lensworth Finance Limited particularising the accounts and
referring to certification by Herron Todd White. On receipt of
-- 24 of 55 --
24
that material the financier would make a further advance
pursuant to the facility arrangement. That would then enable
Wade to be paid, usually on the Friday after the Tuesday upon
which he had submitted his invoice.
I have prepared a Schedule which is annexed to these
reasons giving particulars of Wade's invoices, particulars of
the cheques drawn in payment of those invoices, and particulars
of the amounts actually received by Gauci.
With respect to all payments up until the end of April
1989 the cheques were signed by Fox. Two requisition forms and
two cheques were drawn with respect to each payment. There
would be a crossed cheque, payable to ST Wade Earthmoving in
most instances, representing the invoiced quantity of fill at
$3 per cubic metre, and a second open cheque made payable to ST
Wade for the balance $1.50 per cubic metre. As appears from
the Schedule annexed to this judgment the two cheques were
often not dated the same date. It would appear that the open
cheque was always dated within the week that the invoice was
submitted. As the cheques were usually consecutively numbered
the logical inference is that when the dates do not coincide
the crossed cheque was post-dated. Fox would then take the
open cheque (either on the day it was drawn or the following
day) to the bank and cash it. After cheques bearing an
imprinted "not negotiable" crossing began to be used the cheque
bore a handwritten endorsement "please pay cash" signed by Fox.
Gauci's evidence is to the effect that Wade received all
of the cash; that is, Wade received in cash the amount
-- 25 of 55 --
25
specified in the second cheque. Wade, of course, denies that.
His case is that Gauci retained $1 per cubic metre in
accordance with the terms of the agreement he asserted existed;
he admits to receiving the total sum of $116,000 in cash. The
only amount Gauci admits to receiving is the $12,000 being part
of the last cheque, the one cashed by Fox on 14 June. Of
course he had to do that seeing the police found $10,000 in
Fox's handbag. Gauci claimed that the $12,000 was a loan from
Wade but the latter denied that proposition. Gauci was
convicted of misappropriating the total amount represented by
the $1 per cubic metre but on appeal his conviction was
quashed. The charge alleged that the money was the property of
Angsea, but the Court of Appeal held that on the evidence there
was an issue whether the money was the property of Angsea or
Wade. It was because of that technicality that the conviction
was quashed. It would appear that Wade's evidence on that
trial as summarised in the report (1995) 1 Qd. R. 296 was
vastly different to that which he gave before me.
On the whole of the evidence I am satisfied that Wade only
received one-third of the amount of the second cheque in cash.
I find that the remaining two-thirds, representing $1 per
cubic metre, was retained by Gauci and Fox. There is no
objective evidence pointing to that amount of money in the
possession of either Angsea on the one hand or Gauci and Fox on
the other, but I accept Kenny as a truthful witness and treat
the absence of any evidence that Angsea received the money as
indicating that in fact it did not do so.
-- 26 of 55 --
26
If all the money was to go to Wade there was no need for
two cheques, or at least no need for Gauci and Fox to cash the
cheques and then deliver cash to Wade. The fact that Fox
opened the second of the cheques signed by Kenny on 11 May and
1 June strongly suggests that some impropriety was involved and
that Gauci and Fox were implicated in it. For the reasons I
have given I conclude that Gauci received the amounts shown in
the Schedule annexed to these reasons, and that Fox was
knowingly concerned in bringing about that result.
There were some changes in May-June 1989 in the procedure
for paying Wade. It seems that by early May the relationship
between Kenny and Gauci had broken down. In his statement
Kenny refers to Gauci's failure to contribute his capital share
to the joint venture and also to Gauci's "drinking problem" as
contributing factors to the breakdown. Around that time,
possibly on or about 11 May, Kenny informed Gauci that the
association could not continue. I am satisfied that at or
about that time Kenny put it to Gauci that one or other would
have to buy the other out. Gauci professed to be in a position
to arrange for a buy out of Kenny's interest in the project,
but nothing appears to have eventuated.
It was Kenny who signed each of the two cheques drawn to
pay the invoice submitted on 9 May 1989; he merely signed the
cheques prepared by the office staff. Though Kenny signed
cheque 360032 it was then endorsed "please pay cash" and that
endorsement was made and signed by Fox. Kenny does not appear
to have been concerned on that occasion about the drawing of
-- 27 of 55 --
27
two cheques rather than one. Further, it would appear that the
crossed cheque for $60,000 was post dated; see endorsements on
the back. A similar pattern was followed with respect to the
cheques drawn in payment of the invoice submitted 30 May 1989
for $91,000; the two cheques drawn were for $70,000 and
$21,000. Again the cheque for $21,000 bore the endorsement
"please pay cash" made and signed by Fox. The $21,000 was
divided in the usual proportion. This was the first payment
for fill from Hymix at the higher price.
Late in May Kenny became concerned as to the payments made
by Angsea to Wade. He became aware of the fact that one of the
two cheques was being cashed; at that time he received no
satisfactory explanation as to why that was being done. He had
some further concerns about Gauci's control of the project; in
the circumstances it is not necessary to review those matters
in any detail. Suffice it to say that on or about 1 June 1989
Kenny instructed Angsea's office staff that no further accounts
were to be paid without his approval. Kenny made enquiries of
Angsea's bank with respect to the cheques for $70,000 and
$21,000 he had signed on 1 June, and on becoming aware that the
one for the smaller amount had been "opened" he decided to
remove Gauci from his managerial position. On Tuesday 6 June
Kenny sacked Gauci and told him "to get his gear and get off
the site right away". Shortly after that Gauci informed office
staff that he would be delivering Wade's invoice the following
morning for processing "as usual". On the morning of 7 June
Gauci handed Herbert on the project site Wade's invoice.
-- 28 of 55 --
28
At that point of time Kenny decided to engage private
investigators to follow up the processing of cheques drawn in
the usual way. The invoice delivered by Wade for that week was
for 12,000 cubic metres of fill at $6.50, a total of $78,000.
Two crossed cheques were drawn and signed by Kenny. One was
for $60,000 (cheque 360079) and one was for $18,000 (cheque
360078). On this occasion it was Kenny who opened the cheque
for $18,000 to cash. Kenny also gave instructions to the bank
to stop payment with respect to the cheque for $60,000.
One Ashford had been employed by Angsea as contracts
manager from early February 1989; he worked mainly in the
office. On 8 June Gauci spoke to Ashford at the office of
Angsea by telephone and asked him to deliver the cheques to
Wade on Friday morning. Later Ashford telephone Wade and
confirmed those arrangements. About midday on Friday 9 June
Ashford delivered the two cheques to Wade's home; he handed
Wade an envelope containing the two cheques. Ashford asked
Wade if that arrangement was correct and Wade replied that it
"seems alright".
The weekend was the Queen's Birthday long weekend and the
next banking day was Tuesday 13 June. Gauci claimed, and it
may well be true, that he spent that weekend at Noosa. Clearly
there was contact between Gauci and Wade on the Wednesday,
Thursday and Friday 7, 8 and 9 June. I am satisfied that after
receiving the two cheques on the Friday Wade became suspicious
that something was wrong. In his evidence he asserts that as
and from the time he received the two cheques he began to
-- 29 of 55 --
29
believe that Gauci may have been acting fraudulently, but he
does not make it clear what he meant by that. Indeed there was
no objective reason for Wade to believe that Gauci had been
acting fraudulently if all dealings between he and Gauci had
been above board as alleged in his pleadings. This was another
occasion upon which Wade was prepared to manufacture evidence
in an endeavour to exculpate himself.
At some stage during the period 6 to 9 June Gauci informed
Wade that he was selling out his interest in the project to
Japanese interests. I am satisfied that Wade on learning that
decided to take further steps to extricate himself from the
situation.
About 4.00pm on Tuesday 13 June Gauci (by obvious
arrangement) collected the cheque for $18,000 from Wade. There
is ample evidence to support the conclusion that early the
following morning Fox cashed the cheque for $18,000 at the bank
and gave the money to Gauci. Gauci then delivered $6,000 in
cash to Wade which the latter accepted. Later that day police,
acting on the complaint of Angsea or Kenny, searched the
residences of both Gauci and Wade. $6,000 in cash was seized
at Wade's residence. Gauci and Fox were also taken to the
police station on that day, and $10,000 cash was located in
Fox's handbag.
It can be seen from the Schedule annexed to this judgment
that Gauci received in all $232,588, representing $1 for each
cubic metre of fill allegedly delivered to the site by Wade.
That far exceeds any possible reasonable cost of watering and
-- 30 of 55 --
30
maintaining the access road on the Parkview site. On the whole
of the evidence I find that no satisfactory explanation has
been given either by Gauci or Wade for the retention of that
amount by Gauci. The only conclusion on the evidence, and I
bear in mind the onus of proof in a matter such as this, is
that both Gauci and Wade were parties to a scheme to defraud
Angsea of that amount.
I am satisfied that one of the benefits Wade was to get
from the scheme was the right to payment of $116,000 in cash.
At no stage in the course of his evidence was Wade able to give
a satisfactory explanation for his receiving the bulk of the
payment by way of crossed cheque and an amount, representing 50
cents for each cubic metre of fill delivered, in cash.
Further, Wade's method of dealing with the cash confirms his
knowledge that the money was tainted. All the cash was stashed
away in a ship container located at Wade's truck yard two miles
from his house. He said: "I wouldn't take it to my house. It
was too dangerous. I wouldn't let my wife bank it because it
was too dangerous, but I did claim it. I entered it in my cash
book." Later he said that he "wasn't going to let my family
handle it. I wouldn't take it near the house. It was quite
alright where it is apart from that, if I had spent it it
wouldn't make any difference." He agreed that he did not bank
any of it until after the initial police investigations; it was
banked in two lots in July and August 1989.
I am by no means satisfied that Wade duly recorded the
cash receipts in his cash book as he claimed he did. A
-- 31 of 55 --
31
document purporting to be Wade's cash book was one of the
exhibits. It does not accurately record when money (cash or
cheque) was received. It gives a total for cheque and cash,
though different dates should strictly have been recorded on
some occasions. There is also an error in the doubling up of
the entry for $84,000. It has all the earmarks of a document
subsequently prepared, rather than a document prepared on
either a weekly or monthly basis. All the indications are that
if the cash receipts of $116,000 had not come to light in June
1989 because of the police investigations Wade would never have
disclosed receipt of those monies, for example, to taxation
authorities. Clearly as at 9 June his intention was that the
cash should remain in the shipping container.
It is necessary to say something about four bogus invoices
which were used by Gauci in order to obtain funds from Elders.
Gauci's involvement in the fraud in that regard is proven by
the certificate of conviction, exhibit 80. He was convicted of
the offence that by means of a fraudulent device he induced
Elders to pay an amount to Angsea. The total amount involved
was well over $300,000. For purposes of these proceedings it
is not necessary to make findings as to which persons or
companies benefited from that fraud. It is sufficient to say
that Gauci was a prime mover with respect thereto.
What is more significant for present purposes is that Wade
admits that he prepared and signed one of the bogus invoices,
that purporting to be for the supply of fill up to 23 May 1989
totalling $162,500. The other three bogus invoices appear to
-- 32 of 55 --
32
be on Wade's stationery, but Wade asserted that they were
forgeries. It is not necessary to make any findings in
relation to that contention for present purposes. What is
sufficient for present purposes is that Wade admitted that one
of the bogus invoices was prepared by him and bore his
signature. In his statement, exhibit 7, Wade asserted that he
prepared the invoice for $162,500 (25,000 cubic metres of fill
at $6.50 per cubic metre) knowing that it was false. He says
he did so because he was asked by Gauci to create it for
Angsea. According to Wade, Gauci told him that the invoice
would create a tax advantage for Angsea which the company
needed. Wade also asserts that Gauci informed him that he
would clear it with his financier before using the document.
Wade says that after giving the matter some thought he agreed
to act as requested. He claims that in so deciding he was
partly motivated by the fact that he believed Gauci was the
principal of Angsea. Wade then claims that about a week later
Gauci told him that he had decided not to use the document;
whether or not that latter statement was made it was untrue -
the dummy invoice was used to obtain $162,500 from Elders.
Under cross-examination Wade conceded that he realised
that the dummy invoice had to go through office staff and be
reconciled; he expressly conceded he knew there were valuers
who had to certify as to the quantities involved. He further
conceded that he expected to get a phone call from the
financiers or the valuer about the invoice. However he did
not, whilst in the witness box, give any indication as to what
-- 33 of 55 --
33
he would have said if such a phone call had been received.
In the circumstances the evidence satisfies me on the
balance of probability that Wade knowingly participated in the
fraud on Elders by preparing that dummy invoice. As I have
already said, it is not necessary to make findings as to Wade's
participation in the transactions based on the other three
bogus invoices, but it is worth noting some aspects of the
evidence which tended to suggest that he was more involved than
he conceded. For at least the periods covered by three of the
dummy invoices fill had actually been delivered but for some
unexplained reason no invoice relating to that fill was
delivered in the week in question; the fill actually delivered
in that week was included in a subsequent legitimate invoice.
In the week ended 23 May 1989 Wade in fact delivered over 9,000
cubic metres of fill from Hymix for which no invoice was then
delivered.
The transactions involving the dummy invoices directly
impact upon the credibility of both Gauci and Wade, and
strongly suggest that both were guilty of fraud in the wider
context alleged by Angsea.
Counsel for Wade spent much time (particularly in his
address) in seeking to establish that Angsea and Kenny were
parties to the fraud on Elders involving the dummy invoices. I
am not concerned with that issue; it is collateral so far as
this trial is concerned. The only significance for present
purposes is that it affects the credit of a number of key
witnesses. For the reasons given I have concluded that the
-- 34 of 55 --
34
evidence on this issue reflects badly on the credibility of
Gauci and Wade and that it is not shown that Kenny's
credibility is similarly affected. It is not necessary to make
any further findings with respect to that fraud on Elders.
Wade tried to explain everything away by claiming that at
all material times he believed that Gauci and Angsea were in
effect the one person. He does not give any convincing reason
for that belief. He knew Gauci was an undischarged bankrupt,
and made no specific enquiries to find who the directors and
shareholders of Angsea were. Further, it is clear from his
evidence that he knew that Angsea was being financed with
respect to the project, though it may well be that for much of
the relevant period he was not aware of the precise name of the
financier. A belief that Gauci was the controller of Angsea
does not explain and justify Wade's conduct in submitting a
dummy invoice knowing it would be used to obtain money from the
financier on a false premise. That was also the position with
respect to the charges being made for the fill. Throughout the
period Wade continued to submit his invoice based on a charge
of $4.50 per cubic metre (rising to $6.50 when the material
came from Hymix) notwithstanding that he was only receiving a
total of $3.50 (rising to $5.50). Under cross-examination Wade
conceded that Herbert, the valuer, telephoned him on at least
two occasions and asked whether he was being paid "in terms of
the contract". On each occasion he responded by saying that he
was. In the circumstances that was a false representation, and
on the balance of probability I find that it was made to
-- 35 of 55 --
35
facilitate the fraud.
There is another matter which in my view seriously damages
Wade's credibility and strongly points to his being a knowing
participant in the defrauding of Angsea. It will be remembered
that on Friday 9 June Ashford delivered two cheques to Wade's
home. Those two cheques were for a total of $78,000, the full
amount of the invoice delivered 6 June. Though he apparently
indicated to Ashford that everything was alright, Wade must
have then known that something was wrong. He was getting
$12,000 more than ordinarily he would have expected. As
already noted he claims that he thought that something was
strange and Gauci must have been defrauding Angsea. What in
truth the evidence establishes is that he then believed that
someone had become aware of the fraudulent conduct to which he
was a party. Undoubtedly motivated by those considerations
Wade on the following day, 10 June, prepared an invoice for
fill delivered up to and including that day. The document in
question forms part of exhibit 15. The quantity in question
was 5,000 cubic metres and the charge $27,500. But what is
significant, if not startling, is that the fill was invoiced at
$5.50 per cubic metre. This was the first occasion on which an
invoice was prepared showing the actual amount which, pursuant
to the arrangement existing between Wade and Gauci, the former
would receive. That invoice was never sent. Deliveries
apparently continued up until 16 June when the invoice to that
date was prepared by Wade; it is the handwritten document in
exhibit 15. The first paragraph recites the previous invoice
-- 36 of 55 --
36
to 10 June, making a claim for $27,500. But it then goes on to
invoice a further 5,955 cubic metres again at $5.50. With an
addition for some road base the total for that invoice was
$60,707. Though he was invited under cross-examination to do
so, Wade gave no satisfactory explanation for invoicing fill
delivered from Hymix after 6 June at the rate of $5.50 per
cubic metre. The only rational inference open is that he
realised that his previous invoices were submitted on a
fraudulent basis. What highlights his inability or refusal to
give an explanation for charging out at $5.50 per cubic metre
in those documents is his statement in exhibit 7 with respect
thereto; there he said:
"On 16 June 1989 a further invoice was posted by me
to Angsea for 12,990 cubic metres fill at $6.50 per
cubic metre, total $84,435. Accordingly, I was to be
paid $64,950 by cheque and $6,495 in cash. This
invoice was for fill delivered between 7 June 1989
and 16 June 1989. I was never paid on that invoice.
I am unable to locate a copy of that invoice."
Undoubtedly the documents he was there referring to were
those produced by Angsea which became exhibit 15. There is
nothing in the evidence to indicate where the figures referred
to in that quoted passage came from. Certainly there is
nothing to suggest that an invoice for the period was sent
charging at $6.50 per cubic metre, nor is there anything to
confirm a total quantity of 12,990 cubic metres. The total
quantity referred to in exhibit 15 is approximately 11,000
cubic metres. Again this demonstrates in my view Wade's
propensity to manufacture evidence in order to support the
position he wanted to adopt. It should be noted that in the
-- 37 of 55 --
37
counterclaim Wade seeks to recover $84,435; the only evidence
of that is to be found in the passage quoted above from his
statement. As already indicated there is no evidence at all to
support such a claim. In his final address counsel for Wade
foreshadowed an amended claim for $60,707 in accordance with
exhibit 15.
Whilst dealing with Wade's counterclaim and exhibit 7 it
is convenient to refer to the claim for $2,496.62 for unpaid
deliveries of material. The only evidence relating to that is
to be found in paragraph 62 of the statement exhibit 7. There
Wade says:
"Also in my counterclaim I have a claim for $2,496.62
in the paragraph numbered 9 of my pleading. Between
January 1989 and mid-May 1989 Gauci asked that ST
Wade Earthmoving place road base on a "soft spot" on
the haul road to prevent further deterioration of the
road. Annexed hereto and marked "STW 26" is a true
copy of my invoice dated 23 May 1989 in that amount."
When one turns to that invoice it does not at all support what
is said by Wade. It purports to bear the date 23 May 1989, but
gives particulars of deliveries on 25 May, 1 June, 10 June and
13 June. Not surprisingly no attempt was ever made by Wade
whilst in the witness box to explain the obvious
inconsistencies in those dates. There is nothing in the
evidence to suggest that such a document was ever received by
Angsea. If, as one should assume, the last item was correct
then the invoice must have been prepared on 13 June at the
earliest. That was, of course, well after Wade knew that the
game was up. On the whole of the evidence I can only conclude
that the invoice in question is a fraud, and there is
-- 38 of 55 --
38
absolutely no evidence to support the claim in the counterclaim
for $2,496.62.
There are some other points which, in my view, impact on
Wade's credibility, and upon the issue whether he was knowingly
implicated in the fraud. He gives no explanation for why he
received part payment in cash. His acceptance of the unusual
method of paying him strongly suggests that he had knowledge of
the impropriety. That factor is of even greater significance
when it is appreciated that the contract was an extraordinarily
profitable one for him. As is demonstrated by his counterclaim
for loss of profits, even at $3.50 per cubic metre he was
making a profit of more than $2 per cubic metre on all fill
delivered from the Colgate site. Another matter I mention
briefly is that, at the first committal hearing dealing with
criminal charges against Gauci, Wade claimed privilege from
giving evidence on the ground of self incrimination. That was
a surprising stance to adopt if his evidence on this trial was
the truth.
So far as each of Gauci and Fox are concerned their
evidence is also devoid of credibility except where confirmed
by other evidence. As indicated above I am satisfied that
Gauci defrauded Elders through using the dummy invoices, and I
am also satisfied that he defrauded Angsea of the total sum of
$232,588 referred to in the Schedule. At least Fox was
knowingly concerned in that activity. Her personal
relationship with Gauci during the relevant period, and her
conduct in signing and cashing the cheques, is enough on which
-- 39 of 55 --
39
to base a finding that she was, at least, knowingly concerned
in what happened.
Further, for the reasons which I have already given I am
satisfied that Wade was knowingly concerned in all that
transpired. He was making, as I have found, a very good profit
from supplying fill even at $3.50 per cubic metre and that was
undoubtedly a factor in his becoming a party to Gauci's overall
fraudulent conduct. The benefit he obtained was 50 cents per
cubic metre cash. At the very least it is abundantly clear
that Wade closed his eyes to the very obvious fact that fraud
was being committed against Angsea; but for the reasons I have
given, bearing in mind the burden of proof, I am satisfied that
Wade was an active participant in the fraud to the extent, at
least, that he was knowingly concerned in its implementation.
On the findings I have made Gauci was an employee of
Angsea. Even if he were not strictly so classified, the
evidence clearly establishes that he was in a situation where
he owed fiduciary obligations to Angsea. The facts as I have
found them give Angsea a variety of causes of action each of
which would result in recovery of $232,588. Money stolen by an
employee can be recovered as a debt (Chowne v. Bayliss (1862)
32 L.J. 757). In my view the money could also be recovered in
an action for money had and received. Probably a similar
result could be achieved by suing for conversion of the
cheques. I also am of the view that in the circumstances Gauci
was in breach of the duty of fidelity he owed to Angsea as its
manager. The facts could give rise either to a claim for
-- 40 of 55 --
40
damages for breach of that contract at common law or for breach
of fiduciary duty in equity. In either event the result would
be the same. (cf. Reading v. Attorney-General (1951) A.C.
507.) On any one of those causes of action, all of which are
relied on in the statement of claim, Angsea is entitled to
judgment against Gauci for $232,588.
But Angsea also claims to recover from Gauci an additional
$116,000 being the total of the amounts received by Wade
representing 50 cents cash for each cubic metre of fill
delivered. The position here is a little more complex. It is
rather difficult on the evidence to decide when the fraudulent
arrangement was first agreed to. It probably was not in the
minds of Gauci and Wade on 19 September 1988 when the agreement
bearing that date was signed. It may well be that as at that
date, when it was contemplated the fill would come from Reedy
Creek, there was a genuine agreement to pay $4.50 per cubic
metre. The probability is that the fraudulent arrangement
originated in December 1988 after Gauci became aware that, with
the fill coming from the Colgate site, Wade would make a
considerable profit if only $3.50 per cubic metre was charged.
On that basis a manager of Angsea complying with all his
obligations as such would have taken steps to ensure that no
more than $3.50 per cubic metre was paid. Gauci and Wade took
advantage of the price of $4.50 per cubic metre mentioned in
the written agreement of 19 September 1988 in order to divide
up the spoils. Wade got advantages through receiving part of
his payment in cash. My concern is whether or not one can
-- 41 of 55 --
41
really say that the amount represented by 50 cents per cubic
metre of all fill delivered is recoverable. The fact that Wade
was knowingly concerned in the fraudulent arrangement resulting
in Gauci receiving $1 for each cubic metre of fill delivered
does not necessarily mean that he had no legal entitlement to
$3.50 per cubic metre for the fill delivered. In the
circumstances I am not persuaded that the additional $116,000
is recoverable.
It follows that there will be judgment against Gauci for
$232,588.
I have also come to the conclusion that the position of
Fox is not distinguishable from that of Gauci. She was, in
accordance with my findings, knowingly concerned in the fraud,
and she was also an employee of Angsea. In those circumstances
on a number of bases Angsea is entitled to judgment against her
for $232,588.
Gauci and Fox clearly breached their common law and
fiduciary obligations owed to Angsea. The arrangement with
Angsea was that Rincono would be paid for the services provided
by Gauci and Fox. A total of $60,000 was paid between August
1988 and May 1989. Fox was the nominal controller of Rincono
and on the evidence Gauci and Fox were its only agents. On my
findings both Gauci and Fox disqualified themselves from the
right to any remuneration from Angsea because of their
fraudulent conduct. Rincono must be taken to have had
knowledge of the fraud of Gauci and Fox from December 1988.
The question then arises whether or not the $60,000 paid to
-- 42 of 55 --
42
Rincono is in the circumstances recoverable by Angsea. Senior
counsel for Angsea relied on decisions such as Morison v.
Thompson (1874) L.R. 9 QB. 480 and Andrews v. Ramsay (1903) 2
K.B. 635 in support of a submission that the money was
recoverable. The argument in effect was based on the
proposition that in the circumstances each of Gauci and Fox and
Rincono became a constructive trustee of all monies received by
way of remuneration from Angsea. I accept the argument and
hold that Angsea can recover payments made after Rincono had
knowledge of the fraud. That means that Angsea can recover the
six payments each of $6,000 for the period December 1988 to May
1989, a total of $36,000.
It is convenient at this stage to deal with the claims by
Angsea against Wade (other than with respect to alleged under-
delivery of fill) and Wade's counterclaim against Angsea. I
have already found that Wade was knowingly concerned in, and an
active participant in, the fraud committed by Gauci (and Fox)
against Angsea whereby Gauci obtained $1 per cubic metre of
fill delivered by Wade to the Angsea site. With respect to
that fraud Angsea is clearly entitled to recover against Wade
damages in the sum of $232,588.
Angsea also sought to recover by way of damages against
Wade the amount represented by the 50 cents cash received by
Wade for each cubic metre of fill supplied to Angsea. For the
reasons given above with respect to that claim against Gauci I
am not persuaded that the additional sum of $116,000 is
recoverable.
-- 43 of 55 --
43
Because of the stopped cheque for $60,000, and because
there has been no payment for deliveries made between 6 and 16
June 1989, Angsea has not made full payment for all fill
delivered. There are also accounting adjustments which have to
be made with respect to the payment for fill.
As indicated by the Schedule to this judgment all fill up
to that invoiced on 9 May 1989 came from either the Wade pit or
the Colgate site. The invoices for that fill particularised in
the Schedule give a total of 206,392 cubic metres delivered.
That does not accord with the total of the dockets for fill
supplied from the Wade pit and Colgate site (exhibit 3); the
total of those dockets comes to 202,138 cubic metres, a
difference of 4,254 cubic metres. The invoices are supposedly
based on the signed dockets, and the signed dockets constitute
the basic source of Wade's calculation. In the circumstances
the calculation should be made on the dockets, and that means
that Wade has prima facie established an entitlement to payment
for 202,138 cubic metres. For the reasons I have given he is
only entitled to payment at the rate of $3.50 per cubic metre.
That means that with respect to fill delivered from the Wade
pit and Colgate site, Wade is entitled to a total of $707,483.
But as can readily be deduced from the figures in the Schedule
he in fact received with respect to those deliveries $722,176.
In other words Wade has been overpaid to the extent of $14,693
with respect to fill from the Wade pit and Colgate site.
Wade is also entitled to be paid for fill as docketed from
the Hymix site. Those dockets are also included in exhibit 3
-- 44 of 55 --
44
and the relevant ones give a total of 39,212 cubic metres of
fill delivered from that site. In accordance with my findings
Wade is entitled to payment for that quantity at the rate of
$5.50 per cubic metre, a total of $215,666. With respect to
that he has already been paid $70,000 (cheque 360069), $7,000
(part of cheque 360068) and $6,000 (part of cheque 360078).
When those payments totalling $83,000 are deducted Wade is
entitled to $132,666; that takes into account the stopped
cheque. From that has to be deducted the $14,693 overpayment
leaving a balance owing of $117,973.
For the reasons already given the evidence does not
establish any entitlement to the sum of $2,496.62 referred to
in the counterclaim.
Wade also claimed for loss of profits pursuant to the
contract bearing date 5 December 1988 (exhibit 76). I have
already found that that document was a sham; it was brought
into existence as part of the fraudulent scheme to defraud
Angsea. It follows that there was no contract having a term
that all the fill required for Angsea's project should be
supplied by Wade, nor was there any express term that a
contract between the parties should be irrevocable. That is
sufficient to dispose of Wade's claim for loss of profits.
But in any event, once Angsea became aware of Wade's
participation in the fraud it had a clear right to determine
any contract then existing between it and Wade (cf. Panama and
South Pacific Telegraph Company v. India Rubber, Gutta Percha,
and Telegraph Works Company (1875) L.R. 10 Ch. App. 215) and it
-- 45 of 55 --
45
clearly did so on or about 13 June 1989 or on 19 June 1989. In
the circumstances Wade would have no valid claim for damages
for lost profits.
I should also record that I am by no means satisfied that
Wade's evidence establishes that he suffered any loss as a
result of his inability to deliver material from the Colgate
site to the Angsea site after 16 June 1989.
It follows that, if one leaves aside Angsea's claim for
under-delivery of fill, it would be entitled to damages
totalling $232,588 against Wade, but would have to offset
against that Wade's entitlement to $117,793 for fill delivered
but not paid for. That would mean that Angsea was entitled to
recover from Wade a net $114,795.
It remains to consider Angsea's claim for under-delivery
of fill. As already mentioned, according to the delivery
dockets (exhibit 3) a total of 241,350 cubic metres of fill was
delivered between November 1988 and June 1989. Angsea led a
body of expert evidence suggesting that only somewhere between
127,500 and 143,000 cubic metres of fill was actually delivered
to the Parkview site from Colgate.
The parties at the outset of the trial agreed that the
total quantity delivered from Wade's pit was 6,255 cubic
metres. As the evidence emerged that erroneously included the
408 cubic metres referred to in delivery docket 49, but Angsea
adhered to the agreement.
As all deliveries from Hymix were verified by a
weighbridge docket there was also no dispute as to the quantity
-- 46 of 55 --
46
of fill delivered to the Parkview site from the Hymix quarry.
In all, as exhibit 3 establishes, 39,212 cubic metres of fill
were so delivered.
The difference between the quantities delivered from the
Wade pit and the Hymix quarry and the alleged 241,350 cubic
metres in total delivered to the Parkview site must have come
from the Colgate site. On the figures given above that means
that, according to Wade, 195,883 cubic metres were delivered to
Parkview from the Colgate site.
Each driver made a number of trips in the course of a day,
and each load was, prima facie, recorded on the day's docket
for that truck. Further, the delivery of each load was
confirmed on the face of the docket by a signature (in the form
of initials) placed against each delivery by an Angsea
employee. Two observations should be made on that procedure
with respect to deliveries from the Colgate site. Firstly,
generally each load was for the same quantity, usually a round
figure of 10 or 11 cubic metres. That is to be contrasted with
the position when the weighbridge at Hymix was used. The
evidence discloses that there was no difference in the manner
of loading the trucks as between the Colgate and Hymix sites,
yet the weighbridge readings revealed quite a significant
variation in the quantity of each truckload. No one on behalf
of Angsea made an assessment of the quantity in each truck-load
from the Colgate site. Secondly, a perusal of the delivery
dockets, and this is supported by the oral evidence, suggests
that at least on some occasions a number of loads (perhaps even
-- 47 of 55 --
47
all the loads for a day) were signed for on the one occasion.
In all the circumstances the dockets are not conclusive of
quantity delivered, and indeed are not even a reliable
indication of true quantity.
Certainly the system adopted at the Parkview site was not
designed to represent a real check on the deliveries in fact
made. Gauci was responsible for the system and it was
extremely lax. What in fact happened has to be assessed
against the background of the finding that Gauci was guilty of
fraud, and stood to make a personal gain of $1 for each cubic
metre of fill delivered to the site. The observation must
therefore be made that he stood to gain from the adoption of a
system which allowed for an exaggerated assessment of the
quantity of fill delivered.
Angsea's case that there was a significant overstatement
of the quantity of fill delivered to Parkview from Colgate must
also be considered in the light of the fact that an independent
engineer had to certify with respect to the quantities
delivered before Elders made finance available for payment of
the accounts. The engineer who performed that task was not
called as a witness and that is a factor which must be taken
into account; counsel for Wade made much of that in his final
address. But the difficulties facing that engineer in making
his certification were obvious. He would not sight the
relevant invoice and dockets until the Wednesday or Thursday of
the week following the deliveries in question. By then, on an
average week, some thousands of cubic metres of fill would have
-- 48 of 55 --
48
been delivered to the site subsequent to the deliveries the
subject of his certification. It would have been virtually
impossible to verify the deliveries in question with any degree
of accuracy from a mere site inspection. To a large extent he
had to rely on the honesty of the people making and signing for
the deliveries.
But as Wade recognised in his initial tender at the end of
the job a calculation could be made by engineers as to the
total quantity of fill delivered. It will be remembered that
Wade's initial tender contained the following:
"The above tender is a firm one and includes the cost
of survey before and after completion of the work and
attention during its progress."
The survey there mentioned could only relate to a survey to
determine the quantity of fill delivered in accordance with the
contract.
When Angsea terminated Wade's contract steps were
immediately taken to retain the services of surveyors and
engineers to assess the volume of fill in fact delivered to the
Parkview site. Surveys were carried out of the Parkview and
Colgate sites, and a test pad was used for the purpose of
assessing compaction of fill at the Parkview site. The
engineers and surveyors who carried out such work on the
Parkview and Colgate sites in June/July 1989 had a considerable
advantage over those who were only called upon many years later
to express an opinion upon the calculations involved. In
particular the experts in this area called as part of Wade's
case were at the singular disadvantage of not having seen
-- 49 of 55 --
49
either site in 1989 when the work in question was being carried
out.
The exercise of calculating the volume of fill delivered
included the preparing of before and after contour surveys of
each site, and bringing into account bulking and compaction
factors for the material in question. The presence of features
such as vegetation and dams meant that there were variable
factors present, and it was not possible to make a strict
arithmetical calculation. Further, the factor for bulking and
compaction of the same material provided another possibly
significant variable; the evidence of Morrison, the expert soil
engineer called by Wade, highlighted the significance of that.
Most of the evidence given by the engineers and surveyors
on this topic can only be fully appreciated when read with
detailed plans and diagrams which each prepared. In
consequence it is difficult, if not impossible, in reasons for
judgment such as this to analyse their evidence and to give
precise reasons for arriving at a particular conclusion. But
after considering all of the expert evidence I have formed the
clear view that I should accept and act upon, at least in broad
terms, the evidence given by the expert witnesses called as
part of Angsea's case. In general terms I found the evidence
of the engineers (Hawkes, Guesdon and Litwinowicz) and the
surveyors (Swane, Henderson, Finn and Arnold) convincing and
preferable to the body of evidence to the contrary. To a
significant extent that preference was fortified by the fact
that most of them had the advantage of seeing the site and the
-- 50 of 55 --
50
work in about the June/July 1989 period. Hawkes in particular
was in a very advantageous position because he visited the
Parkview regularly throughout the period of Wade's deliveries;
he was on site almost every second day.
Hawkes calculated that 124,738 cubic metres had been
delivered to the Parkview site from Colgate. His calculation
of the quantity of fill removed by Wade from the Colgate site
during the relevant period gave the figure 129,055 cubic
metres. In the light of evidence given by McAnany and Morrison
on Wade's behalf, Guesdon, a very experience engineer, made
adjustments to the calculations of Hawkes to allow ample
provision for considerations such as survey accuracy, overlap
in survey, the volume for the dams, and the variation in
compaction factor for the fill in question. With all of those
adjustments he arrived at figures, best for Wade, of 143,000
cubic metres delivered to Parkview from Colgate, and 140,000
cubic metres removed from Colgate.
Perhaps the most critical consideration is that the
evidence does not support Wade's contention that 195,883 cubic
metres was either removed from the Colgate site during the
relevant period, or delivered to the Parkview site.
The real difficulty that I have is in determining with
precision the figure which should be adopted for purposes of my
judgment. As I have already mentioned there are a number of
variables and due allowance should be made for them. Some
weight must also be given to the fact that dockets were signed
for, and deliveries certified for, but in the circumstances
-- 51 of 55 --
51
outlined above. In my view I should err on the side of caution
in determining a figure to be adopted in calculating the actual
quantity of fill from the Colgate site for which Wade is
entitled to payment. In all the circumstances I have come to
the conclusion that I should find that the quantity of fill
delivered from the Colgate site to the Parkview site was at
least 25,000 cubic metres less than that referred to in Wade's
dockets. Though in my view the true figure would probably be
more than 25,000 cubic metres justice will be done if allowance
is made for that quantity.
Angsea claims that it can recover the amount overpaid as
money paid under a mistake of fact. The basic principle is
that derived from Kelly v. Solari (1841) 9 M. & W. 54; 152
E.R. 24. That principle has recently been the subject of major
consideration by the High Court in Australia and New Zealand
Banking Group Ltd v. Westpac Banking Corporation (1988) 164
C.L.R. 662 and David Securities Pty Ltd v. Commonwealth Bank of
Australia (1992) 175 C.L.R. 353. None of the cases expressly
deals with a mistake of the type in question here, that is
where the operative mistake is one where the payer has promised
to pay the payee for material supplied at a particular rate and
payment has been made under a mistake as to the quantity
delivered. But the learned authors of Goff and Jones The Law
of Restitution (3rd ed.) at 91 say:
"For similar reasons, restitution should be allowed
where the contract calls for payment according to a
certain formula and where the payer has overpaid
because he has mistakenly applied that formula."
Whilst that again is not precisely in point, the principle
-- 52 of 55 --
52
would clearly extend to the present situation. I am satisfied
that progress payments were made by Angsea on the mistaken
belief that particular quantities had been delivered, and the
mistake did not come to light until June/July 1989 when experts
were called in to make the necessary calculations.
In the circumstances Angsea is entitled to recover the
money paid for the 25,000 cubic metres I have assessed to be
the under supply of fill. That was actually charged at the
rate of $4.50 per cubic metre, but I have already held that one
dollar thereof is recoverable from Gauci, Fox and Wade because
of the fraud. If Angsea was allowed to recover for the under
supply at the rate of $4.50 per cubic metre it would be
recovering the one dollar component twice. It follows that on
this part of its claim Angsea is entitled to recover for 25,000
cubic metres at $3.50 per cubic metre, a total of $87,500.
It follows that Angsea is entitled to recover from Wade
$87,500 in addition to the $114,795 referred to above. There
should therefore be judgment for Angsea against Wade in the
total amount of $202,295.
For all the above reasons the formal judgment will be as
follows:
(i) Judgment for the plaintiff against the first defendant,
George Gauci, in the sum of $232,588 with costs of and
incidental to the action to be taxed.
(ii) Judgment for the plaintiff against the second defendant,
-- 53 of 55 --
53
Jennifer Lyn Fox, in the sum of $232,588 with costs of an
incidental to the action to be taxed.
(iii) Judgment for the plaintiff against the third defendant,
Rincono Pty Ltd, for $36,000 with costs of and incidental
to the action to be taxed.
(iv) Judgment for the plaintiff against the fourth defendant,
Stanley Thomas Wade, for $202,295. Counterclaim of the
fourth defendant dismissed. Further order that the
fourth defendant pay the plaintiff's costs of and
incidental to the action, including the counterclaim, to
be taxed.
-- 54 of 55 --
Date of
Invoice
Quantity
m3
Rate m3
$
Amount of
Invoice
$
Date of Crossed
Cheque and
Number
Amount of Crossed
Cheque
$
Date of Open
Cheque and
Number
Amount of
Open Cheque
$
Wade
$
Gauci
$
16.12.88 12,392 4.50 55,764 6.1.89 (358842) 37,176 6.1.89 (358843) 18,588 6,000 12,588
10.1.89 15,000 4.50 67,500 12.1.89 (358848) 45,000 12.1.89 (358849) 22,500 7,500 15,000
17.1.89 12,000 4.50 54,000 26.1.89 (358800) 36,000 20.1.89 (358859) 18,000 6,000 12,000
24.1.89 7,000 4.50 31,500 26.1.89 (358867) 21,000 26.1.89 (358866) 10,500 3,500 7,000
31.1.89 9,000 4.50 40,500 10.2.89 (358880) 27,000 3.2.89 (358879) 13,500 4,500 9,000
7.2.89 9,000 4.50 40,500 17.2.89 (358895) 27,000 14.2.89 (358893) 13,500 4,500 9,000
14.2.89 8,000 4.50 36,000 17.2.89 (358904) 24,000 17.2.89 (358903) 12,000 4,000 8,000
21.2.89 16,000 4.50 72,000 3.3.89 (358915) 48,000 24.2.89 (358913) 24,000 8,000 16,000
- 8,000 4.50 36,000 10.3.89 (358927) 24,000 3.3.89 (358926) 12,000 4,000 8,000
14.3.89 26,000 4.50 117,000 23.3.89 (358957) 78,000 17.3.89 (358958) 39,000 13,000 26,000
21.3.89 12,000 4.50 54,000 23.3.89 (358964) 36,000 23.3.89 (358965) 18,000 6,000 12,000
28.3.89 10,000 4.50 45,000 7.4.89 (358974) 30,000 30.3.89 (358975) 15,000 5,000 10,000
11.4.89 24,000 4.50 108,000 18.4.89 (358990) 72,000 14.4.89 (358991) 36,000 12,000 24,000
18.4.89 12,000 4.50 54,000 21.4.89 (360010) 36,000 21.4.89 (360009) 18,000 6,000 12,000
22.4.89 6,000 4.50 27,000 28.4.89 (360016) 18,000 28.4.89 (360017) 9,000 3,000 6,000
9.5.89 20,000 4.50 90,000 19.5.89 (360033) 60,000 11.5.89 (360032) 30,000 10,000 20,000
30.5.89 14,000 6.50 91,000 1.6.89 (360069) 70,000 1.6.89 (360068) 21,000 7,000 14,000
6.6.89 12,000 6.50 78,000 [STOPPED CHEQUE] 14.6.89 (360078) 18,000 6,000 12,000
TOTALS 232,392 1,097,764 689,176 348,588 116,000 232,588
Total to Wade
$805,176
-- 55 of 55 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1995/300