Edgarange Pty Ltd v Redland Shire Council [1994] QCA 483 [1995] 2 Qd R 572; QPELR 146
IN THE COURT OF APPEAL [1994] QCA 483
SUPREME COURT OF QUEENSLAND Appeal No. 171 of 1994
Appeal No. 172 of 1994
Brisbane
[Edgarange Pty Ltd v. Redland Shire Council]
EDGARANGE PTY LTD
(Appellant) Appellant
- and -
REDLAND SHIRE COUNCIL
(Respondent) Respondent
Davies J.A.
Pincus J.A.
Derrington J.
Judgment delivered 15/11/94
Separate reasons for judgment of each member of the Court.
All concurring as to the orders to be made.
IN EACH CASE APPEALS ALLOWED. ORDERS MADE BELOW SET ASIDE.
RESPONDENT TO PAY APPELLANT'S COSTS OF THE APPEALS TO BE
TAXED. IN APPEAL NO. 171 OF 1994 DECLARE THAT THE PURPORTED
EXTENSION BY THE RESPONDENT COUNCIL OF THE PERIOD IN WHICH
THE RESPONDENT WAS TO DETERMINE THE APPLICATIONS THE SUBJECT
OF APPEAL NO. 252 OF 1994 IN THE PLANNING AND ENVIRONMENT
COURT IS INVALID BY REASON OF THE RESPONDENT'S FAILURE TO
COMPLY WITH THE PROVISIONS OF S. 4.4(4C) OF THE LOCAL
GOVERNMENT (PLANNING AND ENVIRONMENT) ACT 1990. IN APPEAL
NO. 172 OF 1994 DECLARE THAT THE PURPORTED EXTENSION BY THE
RESPONDENT COUNCIL OF THE PERIOD IN WHICH THE RESPONDENT WAS
TO DETERMINE THE APPLICATIONS THE SUBJECT OF APPEAL NO. 257
OF 1994 IN THE PLANNING AND ENVIRONMENT COURT IS INVALID BY
REASON OF THE RESPONDENT'S FAILURE TO COMPLY WITH THE
PROVISIONS OF S. 4.4(4C) OF THE LOCAL GOVERNMENT (PLANNING
AND ENVIRONMENT) ACT 1990.
CATCHWORDS: STATUTE - CONSTRUCTION - PLANNING AND
ENVIRONMENT - statute provided period in
which local authority was to determine
rezoning and subdivision application -
provision for extension of that period by
local authority's resolution - statute
further provided where local authority
extends period it must notify applicant
before the extension starts - failure of
local authority to notify applicant of
extension before expiration of original
period - whether obligatory to notify before
expiration of original period - whether
purported extension of period rendered
invalid
-- 1 of 19 --
2
Local Government (Planning and Environment)
Act 1990, ss. 4.4(4A), (4B), (4C)
Counsel: Mr C.L. Hughes for the appellant
Mr P. Lyons QC and Mr S. Ure for the
respondent
Solicitors: McCarthy, Durie, Ryan and Neil for the
appellant
King & Co for the respondent
Hearing dates: 14/10/94
-- 2 of 19 --
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 171 of 1994
Appeal No. 172 of 1994
Brisbane
[Edgarange Pty Ltd v. Redland Shire Council]
Before Davies J.A.
Pincus J.A.
Derrington J.
EDGARANGE PTY LTD
(Appellant) Appellant
- and -
REDLAND SHIRE COUNCIL
(Respondent) Respondent
REASONS FOR JUDGMENT - DAVIES J.A.
Judgment delivered 15/11/94
These are appeals from the dismissal of two applications for
declarations that, in each case, a purported extension by
the respondent Council of the period in which the Council
was required to determine an application for rezoning and
subdivision was invalid. The questions raised by the
appeals are identical and it is therefore unnecessary to
refer to them separately. The invalidity, it was submitted
by the appellant, arose for two reasons. The first was the
Council's failure to comply with the provisions of s.
4.4(4C) of the Local Government (Planning and Environment)
Act 1990. The second was because the length of time for
which the purported extension was granted exceeded 40 days.
The appellant had been an applicant to the Council for
-- 3 of 19 --
2
combined rezoning and subdivision of land pursuant to s.
4.11 of the Act. Subsection (3A) of that section provides
that the local authority must decide the combined
application, where both components require a decision before
the end of a period, before the end of the latest of the
periods applicable to those components. In the present case
s. 4.4(4) requires a local authority to decide a rezoning
application within 40 days of its receipt of the statutory
declaration required by s. 4.3(10); and s. 5.1(5) requires a
local authority to decide a subdivisional application within
40 days of its receipt of the application or its receipt of
any amended proposed plan whichever happens later. The
combined application was received by the Council on 3 June
1994. There was no evidence as to whether an amended
proposed plan was ever lodged. On 11 July 1994 the
appellant lodged a statutory declaration in compliance with
s. 4.3(10). It was common ground that the period of 40 days
ran from 11 July 1994. It also appears to have been common
ground that that period expired on Saturday, 20 August 1994
which, by s. 38(2) of the Acts Interpretation Act 1954,
became Monday, 22 August 1994. The Council had not decided
the application by that date.
By resolution of 10 August 1994 the Council purported to
extend the decision period to 31 October 1994. Although the
resolution referred only to the application for rezoning
nothing turns on that. That resolution was notified to the
appellant by letter dated 23 August 1994 received by the
appellant on 24 August 1994. On 23 August 1994 the
-- 4 of 19 --
3
appellant, apparently in ignorance of the resolution, lodged
a notice of appeal in the Planning and Environment Court
purporting to be an appeal against the deemed refusal by the
Council of the combined application. Section 7.1(2)(b)
entitled it to appeal where a local authority had, as the
Council here had, failed to decide the application within
the period specified. It provides:
"Where a Local Authority has failed to decide an
application within the period specified by this
Act, an appeal may be instituted at any time after
the expiration of the period specified for the
decision on the application by the Local
Authority."
Section 4.11(3) provides that, subject to the following
subsections, which include subs. (3A) to which I have
referred, where a component of a combined application would,
if it were made as a separate application, be subject to any
provisions of the Act, the combined application is also to
be subject to those provisions. Sections 4.4(4A) to 4.4(4C)
provide for extension and notification of the extension of
the decision period for rezoning applications; and s.
5.1(5A) to 5.1(5C) provide for extension of time and notice
of the extension in respect of subdivisional applications.
The former and latter sets of provisions are in identical
terms. It is sufficient therefore to set out the former.
"4.4(4A) [Extension of decision period] The
local authority may, by resolution, extend or
further extend the period mentioned in subsection
(4).
4.4(4B) [Minister's direction] The resolution
has effect subject to any written direction given
by the Minister to the local authority -
(a) shortening the extension or further
-- 5 of 19 --
4
extension; or
(b) directing that the extension or
further extension ceases to have effect
on the giving of the direction.
4.4(4C) [Notification of extension] If the local
authority extends or further extends the period
mentioned in subsection (4), it must notify the
applicant of the extension before the extension
starts."
The main question before the learned primary judge and
before this Court is whether the failure of the Council to
notify the appellant of the extension before 23 August 1994
had the consequence that no valid extension was made. The
second question, to which I will refer later, is whether the
purported extension for a period longer than 40 days was
invalid for that reason. The learned primary judge held
that an extension was validly made notwithstanding a failure
to notify within the period of 40 days; and that the Council
could validly extend for longer than 40 days.
Although subs. (4C) is in imperative terms, no consequence
is expressly provided for non-compliance with it. Moreover
its requirement that the Local Authority notify the
appellant "of the extension before the extension starts" on
one view appears to assume that, whether or not notification
is given, the extension starts when, in consequence of the
resolution contemplated by subs. (4A), it would otherwise
start. This view is consistent with the terms of subs. (4A)
which appear to create the extension by the making of the
resolution. These considerations support the conclusion
which the learned primary judge reached on the main
-- 6 of 19 --
5
question.
It is important, in order to determine the legislative
intention of a provision such as this, to look not only at
the language in which it and its related provisions are cast
but also at the consequences, upon the scheme of the Act, of
one construction rather than another. There can be little
doubt that the legislative intention, though not expressed,
is that an effective extension of the decision period
postpones an applicant's right to appeal pursuant to s.
7.1(2)(b). One difficulty with the construction which was
favoured by the learned primary judge is that, as this case
demonstrates, the commencing date for the institution of an
appeal pursuant to s. 7.1(2)(b) may be postponed
notwithstanding that the applicant has not been notified
and, in consequence, may institute its appeal in ignorance
of that postponement. Moreover, if that is the correct
construction, a local authority may feel no obligation to
comply with subs. (4C) if non-compliance with it has no
adverse consequences for the local authority. On the
construction favoured by the learned primary judge none were
suggested. Although the respondent submitted, and the
learned primary judge held, that subs. (4C) was directory,
it was not contended that this meant that it should be
construed so as to require, as a condition of validity of an
extension, substantial compliance with it.
It was submitted by the respondent that a local authority
should not be deprived of the opportunity to perform its
-- 7 of 19 --
6
statutory function of giving due consideration to the
matters relevant to an application which may require more
than 40 days. That much may be accepted. But on either
construction that period may be extended.
It is unlikely that the legislature intended a provision
such as this, in imperative terms and with the important
purpose of informing an applicant of postponement of its
right of appeal, to be without sanction for non-compliance
with the risk that, because of the absence of any sanction
it could be disregarded to the disadvantage of applicants.
Subsection (4C) may be construed to as to avoid that
consequence. It does no violence to the language of that
subsection to construe the phrase "before the extension
starts" to mean no more than "before the end of the period
mentioned in subs. (4)" and to give the word "must" its
literal meaning. The subsection may then more readily be
construed as giving effect to a legislative purpose of
ensuring that notification is given before the end of the
decision period. In my view that is the legislative purpose
of subs. (4C).
I would therefore allow the appeals, set aside the orders
made below and declare that the purported extension by the
respondent council of the period in which the respondent was
to determine the applications the subject of appeal numbers
252 and 257 of 1994 in the Planning and Environment Court is
invalid by reason of the respondent's failure to comply with
the provisions of s. 4.4(4C) of the Local Government
-- 8 of 19 --
7
(Planning and Environment) Act 1990. I would also order
that the respondent pay the appellant's costs of the appeals
to be taxed.
It is unnecessary, in view of the conclusion which I have
reached, to deal with the second ground of appeal. However
as the question may arise with some frequency and was fully
argued I propose to express my opinion on it. There is
nothing in s. 4.4(4A) which, expressly or by implication,
limits the extension which may be granted, to a period of 40
days. The period of 40 days, specified in the preceding
subsection, is specified in order to provide a certain
period after which an applicant may appeal against a deemed
refusal. But there is no justification for construing subs.
(4A) as limiting the power of the Local Authority to extend
only for a further 40 days. The power conferred by subs.
(4B) on the Minister to shorten or terminate an extension is
a specific and sufficient safeguard against the only
disadvantage of that view; that a Local Authority might
grant itself an extension for an unreasonably long time. In
my opinion therefore an extension under subs. (4A) may
lawfully be granted for a period longer than 40 days.
-- 9 of 19 --
8
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 171 of 1994.
Appeal No. 172 of 1994.
Brisbane
[Edgarange v. Redland Shire Council]
Before Davies J.A.
Pincus J.A.
Derrington J.
BETWEEN:
EDGARANGE PTY LTD (Appellant) Appellant
AND:
REDLAND SHIRE COUNCIL
(Respondent) Respondent
REASONS FOR JUDGMENT - PINCUS J.A.
Judgment delivered 15/11/1994
I have read the reasons of Davies JA and agree with
them. Section 4.4(4C) of the Local Government (Planning &
Environment) Act 1990, set out in those reasons, requires
the local authority to notify the applicant of an extension
of the period of 40 days within which an application of the
relevant sort must be decided "before the extension starts".
One way of expressing the question in the case is that it
involves, essentially, a construction of the words just
quoted.
Another and I think truer way is to say that it
involves deciding a point of implication: whether the words
-- 10 of 19 --
9
"before the extension starts" imply that the resolved-upon
extension does not start unless the Council's resolution has
been notified to the applicant before the starting date. The
alternative interpretation, or implication, is that the
resolved-upon extension starts whether or not it is notified
as the Act requires.
The subject of implications in language, so extensively
dealt with in the law of contract, has received little
attention in its application to statutes. Discussion of
this sort of question tends to use the language of
"inference" rather than "implication": see A.B.C. v.
Redmore Pty Ltd (1987) 11 N.S.W.L.R. 621 at 635, or perhaps
more commonly, to be framed as a search for legislative
intention: see the same case in the High Court, (1989) 166
C.L.R. 454 at 457.9. Here, there is nothing in the
statutory context or history to detract from the force of
the argument that the legislature could hardly have intended
the requirement in question to be one which may be ignored
without legal consequences or at least, without any sanction
which is likely to have practical effect. The sensible
implication to be made is that for which the appellant
contends.
The effect of non-compliance with the requirement of
notice is not that the resolution to extend time, valid at
inception, becomes invalid retrospectively; it is simply
that it fails to take effect. That is I think sufficiently
expressed by the first declaration sought in each
-- 11 of 19 --
10
application; in Appeal No. 171 of 1994 there should be a
declaration that the purported extension of the period in
which the respondent was to determine the application the
subject of Appeal No. 252 of 1994 in the Planning &
Environment Court, which purported extension is referred to
in the letter of the respondent to the appellant dated 23
August 1994, is invalid by reason of the respondent's
failure to comply with the provisions of s. 4.4(4C) of the
Local Government (Planning & Environment) Act 1990. In
Appeal No. 172 of 1994 there should be a declaration in
similar terms.
It will also be necessary to order that the respondent
pay the appellant's costs of these appeals, to be taxed.
-- 12 of 19 --
11
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND Appeal No. 171 of 1994
Appeal No. 172 of 1994
Brisbane
[Edgarange v. Redland Shire Council]
Before Davies J.A.
Pincus J.A.
Derrington J.
BETWEEN: EDGARANGE PTY LTD (Appellant) Appellant
AND: REDLAND SHIRE COUNCIL
(Respondent)Respondent
REASONS FOR JUDGMENT - DERRINGTON J.
Judgment delivered 15.11.1994
The imperative word "must" in s.4.4(4C)
undoubtedly requires the giving of the notice referred to,
but its imperative nature does not characterise it as
mandatory or directory, for it may take the same form in
either case. The real point of the enquiry however is
whether disobedience to it in some way invalidates the power
of extension of time which the local authority is entitled
to exercise under s.4.4(4A). In this respect the use of the
imperative word is not decisive: Hunter Resources Ltd v
Melville (1988) 77 ALR 8; Accident Compensation Commission v
Murphy (1988) V.R. 444 at 447.
This does not mean that that feature does not have some
weight; and there is some additional force to it because
there is no sanction, other than the general sanction in
-- 13 of 19 --
12
s.8.6(1), which is not apt, for disobedience. This latter
factor is not as strong as it might otherwise be because a
local authority is not entirely free to disregard this
provision without adverse consequences. Under subclause
(4B) the Minister may shorten or even terminate the
extension, and one suitable reason for such action would be
the council's disobedience of the statute by failing to give
notice. However this is clumsy and unsatisfactory in that
it would require the agitation of the Minister's action in
respect of a default that might not be known to either the
Minister or an applicant.
There are some other factors in the language and
framework of the Act that are relevant:-
1. By subs.(4A) the act of extension by resolution of the
local authority is said to be complete and operative,
though the time referred to in the extension would
start to run only at the end of the primary period
established by the statute. This is supported by the
terminology of subss.(4B) and (4C).
2. The notice required by subs.(4C) is therefore
contemplated as coming after the completed act of
extension, and it is expressed as such. This means
that if this provision has an effect on validity,
compliance is not a precondition to validity but rather
that non-compliance will invalidate an extension that
has been valid to that time, though it will not have
begun to run.
3. Subsection (4C) contains no express provision for
invalidation of the extension in the event of
-- 14 of 19 --
13
disobedience, nor does subs.(4A) carry any express
condition or qualification requiring compliance with
subs.(4C) for the validity of the exercise of the
power. It would have been easy to have imposed such a
restriction.
4. The requirement in subs.(4C) of notification of the
extension "before the extension starts" does not imply
any condition, and the quoted phrase is at best
equivocal. It would take that form if it were intended
to use the starting time of the period of the extension
as the definition of the time before which the notice
must be given. If it were intended that the phrase
should connote a conditional feature, then that could
easily have been expressed.
5. Although subss.(4A) and (4C) should be read together,
particularly as part of the same section, they are
separated by subs.(4B), which empowers the Minister to
shorten or cease the extension by direction; and that
subsection commences:
"The resolution has effect subject to any
written redirection given by the Minister
to the local authority...."
This confirms that the extension is operative
immediately upon resolution, and it is clear that it
may be terminated by the Minister even before the
notice required by subs.(4C) is required to be given.
The interposition of a provision relating to something
else tends to reduce the claim that the later provision
qualifies the validity of the earlier one; but if the
later is regarded as a subsequent validation for
-- 15 of 19 --
14
disobedience of the exercise of the power that has to
that time been valid, then there is nothing in this
point. Indeed, the interposition of a provision
relating to another modification of the original power,
a modification which could precede the invalidating
factor in time, is logical.
There is nothing else in the framework or language of
the statute that would help to resolve the difficulty,
but it is necessary to consider also the seriousness of
the implications of the provision as a guide to the
statutory intention. It is useful to consider the
respective adverse consequences following upon the
alternative conclusions.
If subs.(4C) affects the validity of the extension,
then a local authority which fails to comply, whether by
innocent mistake or otherwise, will irretrievably lose the
benefit of an extension which it has formally decided was
needed. However because in the absence of its approval
within the prescribed time the application is deemed to be
dismissed rather than approved, the effect on the local
authority of the loss of an extension is not particularly
serious. It still has the opportunity of supporting or
opposing any appeal which the applicant might bring, and
while this might not be as satisfactory as retaining the
original opportunity of investigating and deciding upon the
matter itself the difference would usually be marginal if
any. At least it would certainly have the same opportunity
for time to consider the matter as if an extension had been
invoked.
-- 16 of 19 --
15
If subs.(4C) does not affect the validity of the
extension, then the effect on the applicant who is left
without notice is mixed. If there were no enquiry or search
of the local authority's records, though prudence would
suggest that there should be, an applicant may commence an
appeal in the erroneous belief of a deemed refusal of the
application. Such an imprudent action might still be
compensated for by an order for costs in these circumstances
and it is not easy to find any serious prejudice in this
respect.
Nor is it correct to say that such an applicant would
have been vested with the right of appeal in the absence of
notice but then divested of it on receipt of late notice.
Any valid notice is required to be given before the start of
the extension. If disobedience of the provision does not
invalidate the extension, then an applicant would not be
vested with any right of appeal on the basis of a deemed
refusal. Equally if the default produces invalidity, it
will not be saved by a late notice and so there would be no
divestment. Because of the nomination of a specific time
limit, there is no room here for any digression into the
area of substantial compliance, the invalidation having
taken effect when the non-compliance existed at the
appointed time. Consequently the discussion should not be
diverted by any argument by the applicant of the
undesirability of its being divested of a vested right.
Indeed that is broadly the effect on the local authority
that would follow the success of the applicant's own case.
The most substantial issue of prejudice to an applicant
-- 17 of 19 --
16
concerns the possible commercial disadvantage in planning
and finance which might be suffered in the absence of
notice. The purpose of the Act's requirement of notice is
not merely the encouragement of courtesy but to provide
proper knowledge to and an opportunity to take action about
their affairs by applicants who may be adversely affected by
an extension. This possibility of serious consequences of
an extension which might be avoided by suitable notice is
both real and substantial, and the perception of this is no
doubt the reason behind the prescription of a time for
giving it. This accords with the tendency in cases
concerning the construction of such a provision to associate
such a procedural requirement as going to validity,
particularly where a limitation of time is expressed; and
even more so when the provision regulates the exercise of a
power or right: Hatton v. Beaumont (1978) 52 A.L.J.R. 589
at 591. For these reasons the nature of the provision and
the respective consequences of the alternative constructions
tend to indicate that the continued validity of the
extension brought into existence by a resolution should
depend on compliance with the requirement of notice.
This is the decisive factor in the equation. The
competing factors associated with the framework and language
of the Act tend to cancel each other out, while the
preponderance of the argument that the substantial nature of
the provision supports its effect on the validity of the
power is sufficient to justify a conclusion in that
direction.
This means that I agree with the orders proposed by
-- 18 of 19 --
17
Davies JA. With respect, I would also agree with his views
on the second ground of appeal which it has become
unnecessary to answer.
-- 19 of 19 --
Official source: https://www.sclqld.org.au/caselaw/QCA/1994/483