Carnie, Re; Re Richmond & Ors [1994] QSC 287
IN THE SUPREME COURT
OF QUEENSLAND
O.S. NO. 249 OF 1994
IN THE MATTER of Section 83 of the District
Court Act 1967
- and -
IN THE MATTER of a certain action pending in
the District Court of Queensland, Southport
Registry between GREGORY JOHN CARNIE as
Plaintiff and JOHN FRANCIS RICHMOND and
DAPHNE CLAIRE RICHMOND as Defendants,
K & U FORMWORK PTY LTD as First Third
Party and SWAN & KAVANAUGH PTY LTD
as Second Third Party
- and-
IN THE MATTER of an Application by
GREGORY JOHN CARNIE to transfer this
action to the Supreme Court of Queensland
JUDGMENT - WHITE J
Judgment delivered: 3 November 1994
CATCHWORDS: District Courts Act 1967 - S.83 - Jurisdiction of Courts (Cross-vesting)
Act - S.5(2) - Proceedings in Queensland and New South Wales -
Queensland Limitation of Actions Act 1974.
Counsel: Mr. K. Wilson for applicant/plaintiff
Mr. K. Howe for respondent/defendants
Mr. D. Savage for respondent/first third party
No appearance for second third party
Solicitors: Baker Johnson as town agents for Price and Roobottom for
applicant/plaintiff
Thompson King and Partners as town agents for Keith J. Hunter for the
respondent/defendants
McKays for the respondent/first third party
Hearing date: 8 April 1994
-- 1 of 13 --
IN THE SUPREME COURT
OF QUEENSLAND
O.S. NO. 249 OF 1994
IN THE MATTER of Section 83 of the District
Court Act 1967
- and -
IN THE MATTER of a certain action pending in
the District Court of Queensland, Southport
Registry between GREGORY JOHN CARNIE as
Plaintiff and JOHN FRANCIS RICHMOND and
DAPHNE CLAIRE RICHMOND as Defendants,
K & U FORMWORK PTY LTD as First Third
Party and SWAN & KAVANAUGH PTY LTD
as Second Third Party
- and-
IN THE MATTER of an Application by
GREGORY JOHN CARNIE to transfer this
action to the Supreme Court of Queensland
JUDGMENT - WHITE J.
Judgment delivered: 3 November 1994.
The applicant seeks orders that the action pending in the District Court at Southport in
which he is plaintiff and the respondents are defendants and first third party respectively be
transferred to the Supreme Court pursuant to s.83 of the District Courts Act 1967. If that order
is made the applicant then seeks an order that the action be transferred to the Supreme Court of
New South Wales pursuant to s.5(2) of the Jurisdiction of Courts (Cross-vesting) Act 1987.
The respondents do not oppose an order transferring the action out of the District Court and into
the Supreme Court but they do oppose the transfer of that transferred action to the Supreme
Court of New South Wales. It is anticipated that if transferred to the Supreme Court of New
South Wales the action would be likely to be ordered to be consolidated with an action already
commenced in that court in 1993 by the plaintiff against all the respondents as defendants.
-- 2 of 13 --
2
The applicant's action is one for damages for personal injury sustained in a work related
accident which occurred on or about 4 April 1987 on land owned by the respondents/defendants
located near Southport. It will be convenient to refer to the parties by reference to their
description in the District Court proceeding. The defendants engaged the plaintiff to perform
roofing work on a building which was being constructed for them on their land. In the course of
carrying out this work the plaintiff was positioned on the steel roof framing fixing a purlin to a
structural steel bracket which the plaintiff understood to be securely fastened to the face of the
building. It came free and collapsed causing the plaintiff to fall some twenty feet to the ground
and sustain quite serious injury which included fractures to both elbows, fracture and injuries to
his spine and concussion. The plaintiff underwent a spinal fusion operation in early 1989 which
has left him with residual disability in his spine. As a further consequence of his injuries and
their sequelae the plaintiff has suffered depression and alcohol abuse. The plaintiff is now aged
38 years and has been largely self-employed as a roofing contractor throughout his working life.
He is seriously hampered in that work by his condition subsequent to the fall both physically
and psychologically. The plaintiff has obtained treatment in hospitals and from specialists in
Brisbane, the Gold Coast and at Tweed Heads. In about December 1990 he moved to Kingscliff
in northern New South Wales and has resided there since.
KPMG Peat Marwick have prepared a report based upon the plaintiff's pre-accident
earnings in which, inter alia, his past economic loss is estimated at approximately $76,000 and
his future economic loss at about $280,000. Without any other items of damage being
considered this document reveals that the plaintiff may well recover more than $200,000, the
jurisdictional limit of the District Court. The first third party has offered to consent to the
District Court having jurisdiction to give judgment above that limit, s.73 of the District Court
Act. The plaintiff has not accepted that offer and the defendants have not made such an offer.
-- 3 of 13 --
3
In my view the order should be made transferring the action to the Supreme Court.
Of much greater difficulty is the application to transfer the action to the Supreme Court
of New South Wales. In order to consider this part of the summons it is necessary to set out a
chronology of relevant events.
1. Supreme Court Writ No. 4514 of 1987 was issued on 9 December 1987 in which the
applicant is plaintiff and the first respondents are the named defendants.
2. On 15 June 1990 the plaintiff delivered a statement of claim.
3. By third party notices filed on 28 June 1990 the defendants joined the first and second
third parties to this action. They are respectively K & U Formwork Pty. Ltd. which had
erected the structural steel roof framing and was responsible for bolting the brackets to
the face of the building, and Swan & Kavanaugh Pty. Ltd. which had prepared plans and
specifications for the erection of the framing. The second third party has subsequently
been deregistered and prior thereto its insurer had withdrawn its cover. It was not
represented at this hearing. There was no intimation that any party proposed to seek to
revive it for the purposes of the litigation.
4. There then followed exchanges of pleadings between all the parties through the
remainder of 1990.
5. On 22 November 1990 a consent order was made in the Supreme Court of Brisbane
remitting the action to the District Court at Southport. This occurred without the
knowledge or consent of the plaintiff.
6. On 12 June 1992 the plaintiff applied unsuccessfully to join the first and second third
parties as defendants in the action it then being more than three years since the cause of
action arose.
7. On 17 August 1992 the plaintiff issued a writ against his former solicitors for damages
-- 4 of 13 --
4
for professional negligence in failing to join the first and second third parties as
defendants to the action within the period of limitation, namely, by the 3 April 1990.
8. A defence to that action was delivered on 12 February 1993 in which the former
solicitors pleaded, inter alia, by way of defence that the plaintiff had suffered no loss or
damage as up until 3 April 1993 he could bring an action in New South Wales against
the present defendant and the first and second third parties as defendants. Alternatively,
by reason of the failure to commence and maintain an action against the defendants and
first and second third parties as defendants in New South Wales he had unreasonably
failed to mitigate his damage.
9. Proceedings were commenced on 19 March 1993 against the defendants and the first
and second third parties as defendants in the Supreme Court of New South Wales issued
out of the Northern Rivers Registry. The statement of claim was served in November
1993. The second defendant (the first third party herein) delivered its defence on 25
February 1994. It alleges that the plaintiff's cause of action by operation of the
Queensland statute of limitations ceased or, alternatively, was statute barred at the time
when the New South Wales proceedings were instituted. It is further alleged that the
plaintiff's cause of action will merge with the judgment in the Queensland action and the
New South Wales proceedings will be estopped on principles to be found in Port of
Melbourne Authority v. Anschun (1981) 147 C.L.R. 589. In the further alternative it is
alleged that the New South Wales proceedings are an abuse of process whilst the
Queensland action is on foot.
The following matters are mentioned by either or both of the defendants and first third
party as pointing to the inappropriateness of transferring the action to the Supreme Court of
New South Wales:-
-- 5 of 13 --
5
. The current Queensland action is close to being ready for trial. The
plaintiff has delivered a signed Certificate of Readiness. A trial could be
obtained within six months in the District Court. (There is no estimate
for the Supreme Court, but my own knowledge of the state of the civil
list would suggest about 18 months absent an order for a speedy trial.)
. The Queensland action has proceeded very slowly to date. The
defendants have brought an application in the past to strike out for want
of prosecution and although unsuccessful the plaintiff was ordered to pay
the costs of the application.
. There is a possibility of a view of the accident site. (This seems most
unlikely.)
. Witnesses
. The accident was investigated by a senior inspector of
Construction Safety in Southport and he resides at the
Gold Coast.
. Witnesses as to the circumstances of the fall are resident in
Queensland.
. The plaintiff has received treatment at Queensland hospitals.
. Numerous Queensland medical specialists have either treated the
plaintiff or prepared reports in relation to his condition and some if not
all will be required at a trial. They include Dr. Robert Cooke,
orthopaedic surgeon, Dr. Graham Gartrell, psychiatrist, Dr. Ivan
Yaksich, neurosurgeon, Dr. Tony Blue, orthopaedic surgeon, Dr.
Andrew Eklund, orthopaedic specialist, Dr. B. Geissmann, general
-- 6 of 13 --
6
practitioner, Ms. Helen Craig, occupational therapist.
. In addition there are a number of medical practitioners from whom the
plaintiff has received treatment at Tweed Heads including Dr. G. Hunter,
Dr. Gregory Freeman, orthopaedic surgeon and Ms. Libby Gibson,
occupational therapist.
. The plaintiff has undergone a rehabilitation program through the
Commonwealth Rehabilitation Service at Tweed Heads and the Tweed Heads
District Hospital.
. There is a backlog of about 100 civil cases ready and awaiting trial in the
Northern Rivers Registry of the Supreme Court of New South Wales with
limited availability of sitting days. It presently is estimated to take about three to
four years from first appearance on the callover list of civil matters in that
registry to the date of trial.
. In the Sydney registry the period from first appearance on the callover list of
civil matters to trial can be as high as six years.
. The cost of airfares from Brisbane or Southport to Lismore together with the
available times of flights and the fees of the medical witnesses together with the
approximate time that they would be engaged should the matter be heard in
Lismore are set forth in the affidavit of Mr. McCormick, solicitor for the first
third party. He has estimated that on a conservative basis that these matters
would involve an extra $12,000 to $14,000 to the cost of the litigation if the
proceedings are head in Lismore. This would be about double for these items
than that which could be expected were the trial to be held in Southport or in
Brisbane.
-- 7 of 13 --
7
. The solicitors for all parties are Queensland solicitors and there would be further
expense involved in retaining New South Wales solicitors to act.
The Jurisdiction of Courts (Cross-vesting) Act 1987 provides in s.5(2) relevantly:-
"Where -
(a) a proceeding (the "relevant proceeding") is pending in the
Supreme Court (the "first court"); and
(b) it appears to the first court that -
(i) the relevant proceeding arises out of, or is related
to, another proceeding pending in the Supreme
Court of another State or of a Territory and it is
more appropriate that the relevant proceeding be
determined by that other Supreme Court; or
...
(iii) it is otherwise in the interests of justice that the
relevant proceeding be determined by the
Supreme Court of another State...
the first court shall transfer the relevant proceeding to that other Supreme
Court."
The New South Wales proceedings against all the defendants has been commenced in
time pursuant to that State's limitation statute. It is not submitted that that court does not have
jurisdiction, McKain v R.W. Miller & Co (S.A.) Pty. Ltd. (1991) 174 C.L.R. 1. The plaintiff
submits that it is not an abuse of process to have the two actions on foot because they are
different. This is said to be because the issues raised in the plaintiff's case in New South Wales
include allegations of negligence against the formwork and structural steel contractors and
structural and construction engineers as well as against the owners who contracted with him to
carry out the work. The plaintiff submits that because of the matters of defence pleaded by the
first third party in New South Wales to which I have referred and the refusal of that party to
consent to be joined as defendant in Queensland and waive the limitation defence justice
requires that the Queensland action be cross-vested to New South Wales and that consolidation
occur. In order for the plaintiff to succeed in his purposes of proceeding against the first third
party as defendant and rendering nugatory the first third party's defences based on estoppel and
-- 8 of 13 --
8
merger the Queensland action must be subsumed by the New South Wales proceedings.
Street CJ in Bankinvest A.G. v. Seabrook (1988) 14 NSWLR 711 observed of the
process of transfer pursuant to the cross-vesting legislation at p.714 as follows:-
"Viewed from this standpoint it can be seen to be highly desirable that the
judicial administration of the day to day working of the cross-vesting scheme is
not encumbered by an encrustation of judge-made pronouncements of principles
to be applied when considering making a transfer order. It calls for what I might
describe as a 'nuts and bolts' management decision as to which court, in the
pursuit of the interests of justice, is the more appropriate to hear and determine
the substantive dispute. Consideration of textured principle and deep learning -
in particular principles of international law such as forum non conveniens - have
no place in a cross-vesting adjudication. There is, in substance, no principle to
be enunciated other than the necessity of applying the specific considerations
stated in the cross-vesting legislation, primary amongst which is the pursuit of
the interests of justice. Internal administrative decisions within a court as to
where particular proceedings should best go forward in the interests of justice
are in many ways akin to the making or refusing of transfer orders under the
cross-vesting legislation. The two provisions I have mentioned, namely the
power of a court to make a transfer order on its own motion and the denial of
any appeal from an order in relation to a transfer, are clear pointers towards this
view."
Rogers A-JA in considering the approach to the exercise of the discretion to transfer had
regard to observations of the House of Lords in Spiliada Maritime Corporation v. Cansulex Ltd.
[1987] A.C. 460 as broadly corresponding to the criteria designated by the cross-vesting
legislation. At p.476 of that case Lord Goff stated:-
"...a stay will only be granted on the ground of forum non conveniens where the
court is satisfied that there is some other available forum, having competent
jurisdiction, which is the appropriate forum for the trial of the action, ie in which
the case may be tried more suitably for the interests of all the parties and the
ends of justice."
Mr. Savage for the first third party argued that if the Queensland proceedings were to be cross-
vested to New South Wales a distinct and substantial advantage would be accorded to the
plaintiff and a similar disadvantage accorded to the first third party because it would necessarily
defeat the defences pleaded in the New South Wales action. He also argued that the transfer
-- 9 of 13 --
9
would inappropriately shift the loss from the former solicitors of the plaintiff onto the first third
party if any liability is found to lie in the first third party. That seems to me to be an irrelevant
consideration to the question of transfer.
A number of cases have considered these matters. In Newton v. Queenstown Pty
Limited (unreported decision of Sully J in the Supreme Court of New South Wales of 7 May
1993) the plaintiff resided in Queensland and the accident occurred in Queensland. He brought
proceedings initially in Queensland but they were statute barred and he brought further
proceedings in New South Wales. Two of the four defendants had a corporate presence in New
South Wales. The defendants sought to cross-vest the action to Queensland. His Honour
declined to exercise jurisdiction under the cross-vesting legislation for the purpose of remitting
the matter to Queensland for hearing. He said:-
"At the end of the day I cannot see why it is unjust that the plaintiff, who has
been defeated by the limitation legislation in one State; who is lawfully entitled
to bring his cause of action afresh in another State free from those technical
limitations; and who has proceeded lawfully in accordance with those
entitlements, should be deprived of, as I see it, his plain right to proceed in the
forum of his choice.
I cannot think at the end of the day that the balance of justice is such as to
require that the Court should remit this matter to the Supreme Court of
Queensland. Indeed, in the events that have happened, I would regard it as
visiting upon the plaintiff a positive injustice to which he ought not be exposed."
Similarly in Maglan v. Mount Isa Mines Limited (unreported decision of Studdert J in the
Supreme Court of New South Wales of 31 August 1993) the plaintiff commenced proceedings
in the Supreme Court of New South Wales in respect of three work-related incidents which
occurred in Queensland. He had earlier issued a writ out of the Queensland Supreme Court
against the defendant but discontinued before the delivery of a defence when the defendant
declined to waive the limitation defence. The defendant sought to have the New South Wales
proceedings remitted to Queensland. Studdert J. following Newton noted that the plaintiff had
-- 10 of 13 --
10
indicated a willingness to consent to the remission to Queensland of the New South Wales
proceedings provided the defendant gave an undertaking that the limitation defence would not
be raised. He noted that the defendant was not so prepared and indeed had indicated that it
would rely upon the relevant limitation statute should the proceedings be remitted to
Queensland. His Honour said at p.6:-
"If I accede to the defendant's application the result will be that the plaintiff's
claim, at least on the first cause of action, would inevitably be defeated..."
His Honour declined to remit.
In an earlier decision of Jenkins v. Australian Shipping Co. (unreported decision of
Loveday J. in the Supreme Court of New South Wales of 13 September 1991) the defendant
sought to transfer to the Supreme Court of Queensland an action for damages in a work related
action. The plaintiff was injured in three incidents whilst he was employed as a seaman on
board a motor vessel. On each occasion the incidents occurred at or near Gladstone in the State
of Queensland. The plaintiff was resident in Queensland, the port of registry of the vessel was
Gladstone and the defendant carried on business in Queensland. The reason for instituting
proceedings in New South Wales was to take advantage of the longer limitation period provided
by the New South Wales legislation. There were some features of association with New South
Wales, for example, the defendant carried on business in New South Wales and the contract of
employment between the plaintiff and the defendant had been entered into in 1966 in
Newcastle. His Honour took the view that the connection between the action and New South
Wales was very slight. He observed that if the interests of justice for the plaintiff required that
the action be retained in New South Wales the same principles would require that it be
transferred to Queensland to protect the defendant's interests. His Honour said that if the
Queensland Supreme Court was the more appropriate court then the interests of justice required
-- 11 of 13 --
11
that a transfer order be made. With respect that seems to suppose that the conclusion as to
appropriateness in s.5(2)(b)(i) is the only determinant for the exercise of the discretion when it
is plain that the interests of justice are a separate basis for that exercise. His Honour further
considered that there was a possibility that the plaintiff may have been able to have the
limitation period extended on application pursuant to the Queensland legislation. Dowsett J.
had occasion to consider that same action on 21 January 1994 in Jenkins v. Australian Shipping
Commission trading as the Australian National Line (unreported decision) when the plaintiff
sought to have the action cross-vested back to New South Wales. It appears that on
consideration the plaintiff's legal advisers took the view that there was no prospect of an
extension of time being granted in Queensland. His Honour declined to make the order sought.
On a consideration of his reasons it seems that his Honour was reluctant to make an order
returning the proceedings to New South Wales because such an order would, in effect, operate
as an appeal from the decision of Loveday J. I am not inclined to follow the approach in the
first Jenkin's decision as it seems to give no separate weight to the effect of s.5(2)(b)(iii). In
Fielding v. Doran (1985) 59 ALJR 511 Dawson J hearing a remitter application in an action
commenced in the diversity jurisdiction of the High Court observed that had the Queensland
limitation statute been applicable to that action if it were remitted to Queensland he would have
regarded the limitation period in Queensland as a material circumstance, at p.514.
Mr. Savage for the first third party has submitted that the plaintiff could discontinue the
Queensland proceedings. That would be productive of a great deal of waste and impose an
onerous order for costs upon the plaintiff at this stage in the proceedings. He also submitted that
the New South Wales proceedings could be cross-vested to Queensland. That would indeed be
a most desirable course because of the factors of convenience and cost and delay reduction but
the first third party has declined to undertake not to rely upon the Queensland limitation period
-- 12 of 13 --
12
by way of defence if that should occur. Mr. Savage pointed to the possibility that the period for
bringing the action against the first and second third parties might on application be extended
pursuant to s.32 of the Queensland statute as was suggested by Loveday J. in Jenkins. It is quite
unlikely that any such extension would be granted. The first third party has not sought to have
the New South Wales action against it struck out as an abuse of process although it has pleaded
that as a defence but it is difficult to see how it could do so given that it is not a defendant in the
Queensland action. However I would say no more about that. The plaintiff has brought his
action in New South Wales which he is entitled to do. He has a connection with that
jurisdiction having resided there for some years prior to the commencement of the New South
Wales proceedings and has received treatment in that State. It is not appropriate that both
actions remain on foot. In the end it is not a compelling argument that by making an order to
transfer the first third party will be deprived of the defences which it has raised in the New
South Wales proceedings as defendant. Those defences are entirely dependent upon the
continuation of the Queensland proceedings and their earlier disposition. Of more concern are
the practical issues of convenience, expedition and cost reduction. I incline to the view that a
suitable costs order may address some concerns of the respondents. The delay is regrettable but
in all the circumstances I am of the opinion that in the interests of justice the proceedings now
pending in the Supreme Court of Queensland by virtue of the order that I have just made
transferring the District Court proceedings into the Supreme Court ought to be transferred to the
Supreme Court of New South Wales and I so order.
The action pending in the District Court at Southport be transferred to the Supreme
Court.
Further order that those proceedings be transferred to the Supreme Court of New South
Wales.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1994/287