Eagle Star Trustees Ltd & Permanent Trustees Ltd v White Industries Qld Pty Ltd & Ors [1994] QSC 78
./A• State Reporting Bureau
TRANSCRIPT OF PROCEEDINGS
(Copyright in this transcript is vested in the Crown. Copies thereof must not be made or sold
without the written authority of the Director, State Reporting Bu:-eau.)
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
AMBROSE J
No 2600 of 1989
EAGLE STAR TRUSTEES LTD
and
PERMANENT TRUSTEES LTD
and
WHITE INDUSTRIES QLD PTY LTD
and
HENNESSEY GLASS & ALUMINIUM
SYSTEMS PTY LTD
and
FORD MOTOR COMPANY
and
FORD GLASS AND METAL INC
and
PITTSBURG PLATE GLASS COMPANY
and
WILLIAM JAMES JOB
First Plaintiff
Second Plaintiff
First Defendant
Second Defendant
Third Defendant
Fourth Defendant .
Fifth Defendant
Sixth Defendant
4th Floor, The Law Courts, George Street, Brisbane, Q. 4000 Telephone: (07) 227 4360. Facsimile: (07) 227 5532
-- 1 of 56 --
and
HARVEY DAVID RUSSELL
and
GRAHAM J DANIELS
and
WILLIAM JOB & ASSOCIATES PTY LTD
(in liquidation)
and
GRAHAM BELL
BRISBANE
.. DATE 2 5 I 0 3 I 9 4
JUDGMENT
2
Seventh Defendant
Eighth Defendant
10
Ninth Defendant
Tenth Defendant
20
30
40
50
60
-- 2 of 56 --
250394 ham (Ambrose J)
HIS HONOUR: In this action I give judgment for the plaintiff
against the second defendant in the sum of $897,531 with costs
to be taxed. I give judgment for the first defendant against
the second defendant for the sum of $938,561 plus the amount
of the plaintiff's costs against the first defendant to be
taxed on a party and party basis. I tentatively order that
the second defendant pay to the first defendant its costs of
the action, including its costs of its third party proceedings
against the second defendant to be taxed.
I publish my reasons for all those judgments and orders.
HIS HONOUR: I will vary the order from the form of judgment I
announced and the order I made and I make the variation on the
basis of an offer to settle made by the plaintiff to all
defendants pursuant to Order 26 on 27 October 1993. I make
that having taken into account, or keeping in mind, that Eagle
Star Trustees Limited exercised a power of appointment to
appoint Permanent Trustees Limited to be the trustee in its
stead of the trust relating to the property at Albert Street
subject to the action in December 1991.
The orders which I make now presently in substitution for the
orders that I made prior to hearing submissions on costs are
these: I give judgment for the plaintiff against the second
defendant for the sum of $897,531, together with costs to be
taxed on a solicitor and client basis. I give judgment for
the first defendant against the second defendant in the sum of
- JUDGMENT
3
10
20
30
40
50
60
-- 3 of 56 --
250394 ham (Ambrose J)
$938,561, together with the judgment given in favour of the
plaintiff by consent of the first defendant for costs to be
taxed on a solicitor and client basis. I order that the
second defendant pay to the first defendant its costs of and
incidental to the action, including the third party
proceedings upon which it has succeeded, such costs to be
taxed on a solicitor and client basis.
_ JUDGMENT
4
10
20
30
40
50
-- 4 of 56 --
JN THE SUPREME COURT
OF QUEENSLAND
No. 2600 of 1989
Brisbane
Before Mr. Justice Ambrose
/
[ Re :/ Eagle Star Trustees Ltd]
BETWEEN:
EAGLE STAR TRUSTEES LTD
First Plaintiff
AND:
PERMANENT TRUSTEES LTD
Second Plaintiff
WHITE INDUSTRIES OLD. PTY LTD.
First Defendant
HENNESSEY GLASS & ALUMINIUM SYSTEMS PTY LTD.
Second Defendant
FORD MOTOR COMPANY
Third Defendant
FORD GLASS AND METAL INC.
Fourth Defendant
PITTSBURG PLATE GLASS COMPANY
Fifth Defendant
WILLIAM JAMES JOB
Sixth Defendant
HARVEY DAVID RUSSELL
Seventh Defendant
GRAHAM J. DANIELS
Eighth Defendant
WILLIAM JOB & ASSOCIATES PTY LTD
(In liquidation)
Ninth Defendant
GRAHAM BELL
Tenth Defendant
-- 5 of 56 --
2
REASONS FOR JUDGMENT - AMBROSE J.
Judgment delivered: 25/3/1994
CATCHWORDS: Building Contract - Property Law Act s.52 -
whether owner can enforce contract between
head contractor and subcontractor - inherent
defect in goods supplied - future breakage.
Counsel:
Solicitors:
Hearing Date(s):
Whether offeror in contract liable in tort -
whether duty of care owed by subcontractor
to owner - pure economic loss - inherent
defect in imported goods - whether offeror
in breach of duty by not making reasonable
investigation.
Mr S. Doyle for first and second plaintiffs
Mr H. Fraser Q.C. with him Mr P. Hastie for
first defendant
Mr S. Couper for second defendant
Mr D. Ryan for seventh and tenth defendants
Mr P. Lilley for ninth defendant
Clayton Utz for first and second plaintiffs
Minter Ellison Morris Fletcher for first
defendant
John McGaw Solicitors for second defendant
Thynne & Macartney for seventh and tenth
defendants
Sly Weigall Cannon & Peterson for ninth
defendant
15/11/93- 3/12/93
-- 6 of 56 --
IN THE SUPREME COURT
OF QUEENSLAND
No. 2600 of 1989
Brisbane
Before Mr. Justice Ambrose
[Re: Eagle Star Trustees Ltd]
BETWEEN:
EAGLE STAR TRUSTEES LTD
First Plaintiff
AND:
PERMANENT TRUSTEES LTD
Second Plaintiff
WHITE INDUSTRIES OLD. PTY LTD.
AND:
AND:
AND:
AND:
First Defendant
HENNESSEY GLASS AND ALUMINIUM SYSTEMS PTY LTD.
Second Defendant
FORD MOTOR COMPANY
Third Defendant
FORD GLASS AND METAL INC.
Fourth Defendant
PITTSBURG PLATE GLASS COMPANY
Fifth Defendant
WILLIAM JAMES JOB
Sixth Defendant
HARVEY DAVID RUSSELL
Seventh Defendant
GRAHAM J. DANIELS
Eighth Defendant
WILLIAM JOB & ASSOCIATES PTY LTD
(In liquidation)
Ninth Defendant
GRAHAM BELL
Tenth Defendant
-- 7 of 56 --
2
REASONS FOR JUDGMENT -AMBROSE J.
Judgment delivered: 25/3/1994
In about 1983 the ninth defendant, William Job & Associates
Pty Ltd (In liquidation) ("William Job & Associates") prepared
an illustrated conceptual plan of a building that might be
erected on a site at 80 Albert Street, should it be redeveloped
in accordance with the terms of a planning consent obtained for
redevelopment of that site from Brisbane City Council. It was
the seventh defendant, Harvey David Russell ("Russell"), who
actually drew or was responsible for the drawing of that plan.
The planning consent was obtained by the then owner of the
building site.
Armed with that planning consent and the plan drawn by
Russell the owner made efforts to sell the land together with the
planning consent which, pursuant to s.20D of the City of Brisbane
Town Planning Act would be irrevocable for only two years. Time
was running out by the time that Brick Securities ("the
developer") showed interest in acquiring that land for the
purpose of its development with a high rise glass clad commercial
building in accord with the current town planning consent.
In fact the town plan for the city of Brisbane was changed
after planning consent for the proposed development had been
given and under the new town plan it was not likely that consent
for a development in terms of that obtained earlier would be
obtainable. It seems likely that the current planning consent
was a matter canvassed in negotiations leading to the purchase
of 80 Albert Street by the developer in about 1983.
-- 8 of 56 --
3
Immediately after the property was purchased the developer
established a property trust to which members of the public
subscribed. The object of the trust was to redevelop the land
at 80 Albert Street in accordance with the planning consent then
current with a building having the appearance of that shown on
the illustrated plan drawn by Russell in 1983.
The appearance of the proposed building was significantly
different from other high rise buildings in Brisbane at that
time. Indeed, it was different in material respects from other
glass clad high rise commercial buildings in Australia.
Mr Donovan the person acting for the developer at the time
in connection with redevelopment of the site, was conscious of
two things -
(1) that there had been a public subscription of funds which
were to be invested in a building having the size, shape,
and appearance of that drawn by Russell to facilitate the
sale of 80 Albert Street as a redevelopment site. Mr
Donovan was anxious to avoid the possibility of any
problems with the Australian Securities Commission which
might result from a development upon that site of a
building different in appearance from that represented to
investors to persuade them to subscribe funds for the
proposed trust.
(2) If there were not substantial progress made in the
construction of the proposed building within two years of
the giving of planning consent, that consent would be at
risk of revocation under s.20D of the City of Brisbane Town
Planning Act. Once progress with the building construction
-- 9 of 56 --
4
was under way it was likely that any necessary extension of
time would be granted.
(3) The matter was further complicated by the fact that
planning consent was conditional upon building approval
being obtained for the construction of the proposed
building and at the date of the land purchase by the
developer no plans had even been drawn for submission to
the Council for building approval. The only thing that had
been prepared was the illustrated plan by Russell as
employee of William Job & Associates. A plan had been
drawn, it seems, principally, if not solely for the purpose
of facilitating the obtaining of planning consent for
construction of the building sketched and for the
subsequent sale of the undeveloped land to a purchaser
interested in carrying forward that development.
The illustrated plan drawn to facilitate the sale of the
land at 80 Albert Street showed an 18 storey building comprising
a 14 storey tower block upon a 4 storey podium. The external
walls of this building were almost entirely sheeted in glass
panels of different colours. The appearance of the building
showed no framework to hold the glass panels. No builders in
Brisbane (or perhaps Australia) had any experience in
constructing such a glass curtain wall exterior to a building of
that height, although such walls had been constructed overseas,
particularly in North America.
The method eventually adopted to fix the glass curtain walls
to the building was to glue the glass panels involved onto
aluminium framework in a factory and then transport each panel
-- 10 of 56 --
5
to the building site where it was lifted by various means to its
ultimate location where the aluminium frame to which it was stuck
was bolted on to the concrete building structure. Each panel was
separated from adjacent panels by about 30 rnrn.
Obviously the building technique for application of glass
panels to the external surface of a building which rose 18
storeys above street level when adherence of the panels to the
framework depended upon the strength and durability of glue used
for that purpose and the way in which the frames were fixed to
the building structure was of great importance.
Not merely did William Job & Associates involved in the
project have no previous experience in the installation of glass
curtain walls in this manner, but nobody associated with that
organisation seems to have had much, if any, experience in the
installation of glass curtain walls of the sort envisaged in the
sketch drawn by Russell in any other manner.
The sixth defendant, William James Job, ( "Mr Job"), had
reservations about William Job & Associates being involved with
the "innovative" building techniques necessary to erect the glass
curtain wall proposed to produce a building having the appearance
of that shown in the illustrated diagram prepared by Mr Russell.
It eventually fell to Mr Russell who had drawn the plan of the
proposed building to investigate the system, which on all
accounts corning to the knowledge of the architects involved, had
been used successfully in other parts of the world. One of the
men employed by William Job & Associates who was involved in this
investigation and research work was Mr Windress. Mr Windress had
-- 11 of 56 --
6
no prior experience in the installation of glass curtain walls
of the sort proposed for the redevelopment of 80 Albert Street.
It was Mr Windress who investigated the matter and
eventually took over the preparation of the specifications etc.
for the erection of the glass curtain wall. He did this under
the supervision of Russell.
I accept the evidence of Mr Parker and Mr Hartog, both
practising as architects in the 1980s, that by 1983-84 there was
information available to them which led them to suspect that
"toughened" or "tempered" glass sometimes failed because of
nickel sulphide inclusions. However, expert opinion differed at
this stage as to the part played by nickel sulphide inclusions
in the failure of panels of fully toughened glass. Mr Calderonie
of Pilkington Glass recommended against its use in locations
where it would be subject to heat stress; his view was that
toughened glass should be heat soaked to avoid spontaneous
failure when heat stressed. Comalco said that it had had "bad
experiences" with toughened glass. H.H. Robertson, carrying on
the same business as Hennessey, recommended against the use of
toughened glass for curtain wall construction and referred to
heat soaking the glass to reduce the failure rate due to nickel
sulphide.
By October, 1985, contractual documents had been prepared
by solicitors for the developer for the development work to
proceed at 80 Albert Street. The long specifications for the
work to be performed by the builder pursuant to the contract were
prepared by William Job & Associates. Tenders were called and it
was decided to accept one submitted by Hutchinson & Co. However
-- 12 of 56 --
7
that contract was abandoned when the builder asserted that
computer error had resulted in a mistake in the tender submitted.
The builder was released from contractual obligation.
The developer at this stage became anxious to have
development work commence, inter alia, to avoid the risk of
revocation of planning consent and because significant funds had
been subscribed by investors for the purpose of effecting the
proposed redevelopment of the site.
Hutchinson & Co had apparently arranged for another glass
erecter, J. James & Co, to be its subcontractor to erect the
glass curtain wall although the terms of that arrangement did not
emerge upon trial.
The specifications for the construction of the building are
very detailed and only those dealing with the supply and erection
of glass curtain walls, the subject of the action, were
considered upon trial.
Eventually the first defendant, White Industries Qld Pty
Ltd, ("White") negotiated with the developer and William Job &
Associates to become the contractor to build the proposed
commercial building.
It was White which introduced the second defendant,
Hennessey Glass & Aluminium Systems Ltd ("Hennessey"f, as the
proposed subcontractor for the supply and erection of the glass
curtain wall. It is clear on the evidence that all parties
involved in the tender at this stage regarded Hennessey and
experts it retained from the United States (Cal Asia), as the
source of knowledge and expertise necessary to design and erect
the glass curtain wall proposed for the building.
-- 13 of 56 --
8
The specifications drawn by William Job & Associates were
performance specifications. That is they specified the result
to be achieved and relied upon the expertise of Hennessey to
supply and fix glass panels to produce a curtain wall having the
appearance and characteristics required. It was Hennessey who
was to select the appropriate glass and design the manner of its
fixing. This involved Hennessey designing the aluminium frames
to be glued to the glass panels, selecting the type and thickness
of glass, supplying materials, sticking the glass panels to the
frames in its factory off site and then erecting the curtain
walls. I will refer later in more detail to the specific terms
of the contractual specifications.
It is clear that White had commenced to construct the
building sometime before Hennessey was accepted by Job &
Associates as the subcontractor to supply and erect the glass
curtain wall.
I will deal in more detail later with what passed between
White, Hennessey, and the architects preceding acceptance of
Hennessey as the glass supplying and erecting subcontractor for
the construction of the building at 80 Albert Street and
preceding also the completion of that subcontract work.
Under the contract practical completion was required by 28
August 1987. A certificate to that effect was given by the
architect in compliance with cl.25 of the contract on 5 October
1987.
On 29 June 1987, White forwarded an instruction of William
Job & Associates to and notified Hennessey that 24 glass panels
were scratched to such an extent at date of practical completion
-- 14 of 56 --
9
as to be unacceptable under the terms of the subcontract.
Subsequently demands were made on a number of occasions upon
Hennessey that the damaged panels be replaced. Hennessey,
however, denied any legal obligation to replace them and refused
to do so.
Shortly after the building construction had been completed
glass panels commenced to shatter spontaneously for no apparent
reason. Exhibit 42 records chronologically the shattering of
various glass panels between February 1987 and January 1993.
After the building had been completed an architectural
company called Resource Co-ordination Partnership Pty Ltd was
retained by the developer to do the internal fitting out for
tenants obtained for the building. It was in the course of that
work being performed by this company that the glass panels
commenced to explode spontaneously and it was asked to
investigate the matter and take steps to correct whatever problem
there was. Mr. Bylett of that company dealt with this problem
and in the course of his investigations obtained advice from a
Mr Ballantyne, who while employed as a scientist with CSIRO in
the 1960s had examined a similar spontaneous shattering of glass
panels in a high rise building in Melbourne. That building is
known as the I.C.I. Building.
Mr. Ballantyne, having investigated the matter thoroughly,
had concluded that the cause of the spontaneous shattering in the
I.C.I. Building was the presence of impurities comprising
particles of nickel sulphide in glass panels which had been
toughened by a heat process to which they were subjected. This
heat process caused a reduction in volume of the nickel sulphide
-- 15 of 56 --
10
particles which over time expanded to their original volume.
Depending upon the size of the particles the pressure exerted
upon the toughened glass in which they were imbedded caused the
glass to shatter without warning. The glass shattered in a way
leaving a pattern which was recognisable as one caused by the
sort of pressures exerted by the expanding impurity.
Mr Ballantyne published his conclusion in a number of articles
including one published in Melbourne in 1961. (vide ex.?)
In about 1974 another building in Adelaide clad with
toughened glass also had glass panels shatter spontaneously and
an investigation of that failure led to publication of a
conclusion as to the cause of the shattering similar to that
reached and published by Mr Ballantyne 13 years earlier, that the
shattering resulted from the expansion in toughened glass of
nickel sulphide impurities which had suffered a volumetric change
in the heat toughening process.
In this case, unsuccessful efforts were made by the first
plaintiff, Eagle Star Trustees Ltd ("Eagle Star") to be
compensated by one or more of the current defendants in this
action and by various other persons including the manufacturers
and suppliers of the glass used, which were American companies.
I infer that Eagle Star was the nominee of Eagle Star Nominees
Ltd, the corporation used by Brick Securities to develop the
project at 80 Albert Street.
Not having succeeded in these attempts to negotiate a
settlement, Eagle Star commenced this action in 1989. By date
of trial Eagle Star had been acquired by the second plaintiff,
Permanent Trustees Ltd, ("Permanent Trustees") which conducted
-- 16 of 56 --
11
the case on the basis that it was entitled to all the rights to
which Eagle Star had been entitled to enforce the rights of the
developer. Upon the evidence I find that Permanent Trustees did
have that entitlement.
When this trial commenced the only defendants in the action
were the builder White, the glass subcontractor Hennessey, the
architectural group William Job & Associates (in liquidation) and
two of the architects involved with William Job & Associates Pty
Ltd at the material time, Russell and Bell.
At the trial Permanent Trustees based its case against White
and Hennessey in contract, negligence, and a breach of obligation
under the Trade Practices Act; against the archi teet William Job
& Associates Pty Ltd in contract and tort and against the two
architects Russell and Bell in tort.
On the twelfth day of the trial on 30 November 1993, the
issue in dispute between White and Permanent Trustees was
settled. In effect, White conceded liability in contract and
consented to have judgment entered against it by Permanent
Trustees in the sum of $938,561 plus costs.
This settlement between Permanent Trustees and White
occurred during the course of the case being led for Bell. At
the close of the evidence for Bell (the evidence for Russell
already having closed), Permanent Trustees then discontinued its
action against Russell, Bell and William Job & Associates.
Russell, Bell and William Job & Associates then discontinued
third party proceedings against White and Hennessey.
The case then continued so that the only live issues to be
determined upon the whole of the evidence led to that time was
-- 17 of 56 --
12
the issue between Permanent Trustees and Hennessey and the third
party proceedings between Hennessey and White.
At the close of evidence Permanent Trustees did not pursue
its claim against Hennessey under the Trade Practices Act. While
it did not abandon its claim against Hennessey in negligence it
certainly relied principally upon its claim in contract.
White claimed a contractual indemnity against Hennessey.
One of the bases of the claim was that White in fact was
contractually liable to Permanent Trustees by reason of
Hennessey's breach of its obligations under the subcontract and
the settlement it had made of the plaintiff's claim against it
was a reasonable one and therefore recoverable against Hennessey
under the principles applied in Biggin v. Permanite (1951) 2KB
314.
I will deal only with the issues debated between Permanent
Trustees, Hennessey and White at the conclusion of the evidence.
The claims by Permanent Trustees against White in contract
include claims in respect of -
(1) The replacement of the scratched glass panels.
(2) Loss flowing from the spontaneous shattering of the
toughened glass panels, being -
(a) the likely cost of future replacement plus various
items of loss associated with failure of the glass;
the liability for the cost of replacement to date is
in issue but the quantum of that cost is not;
(b) the cost of erecting works to protect pedestrians in
the street in the vicinity of the building on
80 Albert Street from falling glass.
-- 18 of 56 --
13
Consideration of these matters will involve determination
of what, if any, contractual obligation there was between Eagle
Star Nominees Ltd and Hennessey. It is Hennessey's case that in
fact there was no contractual arrangement between Eagle Star
Nominees Ltd as principal and Hennessey as subcontractor, but
only one between Hennessey as subcontractor and White as
contractor, and that it was only that arrangement which included
the long specifications. It is contended that William Job &
Associates did not on behalf of Eagle Star hand to White those
long specifications for the supply and installation of glass wall
panelling.
With respect to the indemnity claim between White as
contractor and Hennessey as subcontractor, White claims of course
that the long specifications were part of the subcontract it had
with Hennessey and consequently Hennessey's liability under the
subcontract is to be determined by reference to what it was
obliged to do under the long specifications. Hennessey concedes
that the long specifications did form part of the subcontract it
had with White, but contends that the subcontractor's breach of
the subcontract is irrelevant to White's contractual obligations
to Eagle Star because the long specifications, which were
admittedly part of the subcontract, were not part of the head
contract and so White is not liable to Eagle Star for breach of
the long specifications.
It is a contention of Hennessey that upon the evidence the
characteristic of the toughened glass supplied and fitted to the
building to shatter was simply one of its inherent
-- 19 of 56 --
14
characteristics and it breached no contractual obligation either
express or implied in supplying and fitting it.
With respect to the condition, quality and characteristics
of the glass in issue at relevant times, I find that 24 of the
glass curtain wall panels erected by the subcontractor at date
of practical completion in October 1987 were scratched to such
an extent as to make them unacceptable.
The subcontractor was asked to replace those scratched
panels on 29 June 1987 and on subsequent occasions.
The subcontractor denied any obligation to replace them and
has failed to do so.
Upon the evidence I infer that the panels were probably
scratched by employees of the subcontractor when they were
working in the course of fixing those panels to the building.
In any event there was a contractual obligation upon Hennessey
to have in place panels of glass free of such scratches by date
of practical completion.
Between 28 February 1987 and 6 January 1993, 26 of the glass
panels failed. 24 of those failures were spontaneous and not
related to or caused by impact or the application of mechanical
force to them.
Most of the panels which have so far failed have been
replaced by Hennessey which has reserved its right to claim
payment pending the determination of its liability in this
action. Only one panel has been replaced at the plaintiff's cost
and that is reflected in item "D" in ex.102 and is assessed in
accordance with that schedule.
-- 20 of 56 --
1 5
On the balance of probabilities I find that each of the 24
failures was caused by the expansion of "stones" of nickel
sulphide contained in the panels. Only a relatively small
percentage of the panels seems to have contained nickel sulphide
particles of a size and in a position to cause spontaneous
fracture of the panels to date. The fractures probably resulted
as a consequence of the nickel sulphide inclusions gradually
increasing in volume as time passed to achieve their original
volume or mass which had been reduced in the heat process applied
to them in the course of toughening.
The toughened glass supplied and fixed to the plaintiff's
building by the subcontractor was manufactured in the United
States of America. The manufacture involved, inter alia,
subjecting sheets of annealed glass cut to the size ultimately
required to a very high temperature and then rapidly cooling
them. This process resulted in the glass cooling more quickly
on its surfaces than between the surfaces. This resulted in the
surfaces being subject to tension forces while between the
surfaces the glass was subjected to forces of compression. Some
of the sheets of annealed glass so treated, contained particles
of nickel sulphide in various sizes. When subjected to extreme
heat the mass or volume of the nickel sulphide particles was
reduced. When not subject to such heat, the particles gradually
(over some period of time) expanded to attain their former size.
This expansion generated forces within the glass sheet resulting
in its spontaneous fracture. The time taken for the expanding
particles of metal sulphide to exert sufficient force to the
toughened glass to cause spontaneous fracture depended upon the
-- 21 of 56 --
16
size of the deposits and/or the forces exerted on or generated
within the panel of toughened glass from time to time as the
result of wind pressure and/or the application of heat from the
sun.
The effect of heat toughening annealed glass upon deposits
of nickel sulphide in it has been known at least by a limited
number of people for many years. Efforts to extract the nickel
sulphide from the material used in making annealed glass have not
been successful. Some batches of annealed glass appear to
contain less deposits of nickel sulphide of a size and in a
location likely to cause problems than other batches.
Upon the evidence, of the 1354 sheets of toughened glass
applied to the building in 1987, 24 have failed in the absence
of impact. It appears therefore that the result to date is that
nearly 1.7 percent of the panels supplied have been so defective
that while fixed to the building they needed replacement within
seven years. Upon the evidence, I find that over the next three
or four years it is likely that further panels of glass will fail
as a result of nickel sulphide impurities in them. On the one
hand, both the history of failures to date and some of the
scientific evidence suggests that the rate of failure lessens
with the passage of time. On the other hand, there is little
evidence as to possible effects in the future of wind and heat
on panels of glass containing nickel sulphide deposits of a size
which to date have not led to failure. The manufacturers of the
glass panels were apparently only prepared to warrant their
product to the subcontractor to the extent that the
sub-contractor was prepared to "guarantee" the performance of the
-- 22 of 56 --
17
glass for 10 years and not for 15 years as initially sought by
the plaintiff's architect.
I find that the reasonable cost of replacing the 24
scratched panels which need replacing will be $77,346.00. In fact
one scratched panel has been replaced at a cost of $3,642 (vide
"D" at p.107 of ex.102). That sum for convenience is included
in item "D" rather than "D1" in that exhibit.
Upon the evidence I find that it is reasonable for the
plaintiff/owner to employ experts to examine carefully all the
glass panels which have not yet failed (with the exception of the
24 scratched panels that must be replaced) to determine the
location and size of nickel sulphide particles in them.
It is unfortunate that testing was not performed prior to
trial. Had that been done, the cost of the test plus the cost
of replacing all panels in which particles of nickel sulphide of
a size and position which would make it likely that they would
cause failure at some time in the future, would prima facie be
one of the measures of damage.
I propose to assess damages to compensate for the cost of
an investigation to detect panels which will fail in the future
and as well, the present value of the cost of replacement of
panels which will probably fail in the future.
The outcome of the test to be performed in the future as
advised by Drs McKinnon and Barry may only be predicted at this
stage. It is possible no doubt that no future failures may occur.
On the other hand many more failures may occur. Mr Bylett has
expressed the opinion that 27 further failures are likely by
approximately 1998.
-- 23 of 56 --
18
On the state of the evidence I have regard to the whole of
the cost of investigation services available from Drs McKinnon
and Barry. This sum will however, only partly compensate the
plaintiff for undertaking a necessary expense which might
reasonably have been undertaken prior to trial to make more
certain by scientific means the probable number of future
failures of panels which will need replacing. Doing the best I
can I find on the probabilities that about 21 panels will have
to be replaced at some time in the future by reason of their
failure as a consequence of the nickel sulphide deposits in them.
In coming to this conclusion I have had regard to the evidence
of Dr Mckinnon who said that a minimum of 15 panels would fail
during the next four or five years and the evidence of Mr Bylett
that another 27 panels would fail by 1998 or thereabouts. Mr
Bylett has had a lot to do with the failure of the glass panels
in issue up to date and his evidence is consistent with the
advice he gave to the building manager in February 1993. I find
that at least 15 of those 21 panels will probably have failed
within three years if not replaced and a further 6 panels will
probably have failed within four or five years by reason of
nickel sulphide inclusions presently detectable by Drs McKinnon
and Barry. All failures have resulted and will result in the
future by reason of inherent defect which interferes to an
unacceptable extent with their appearance, service and function
as glass curtain wall panels.
I take into account both the cost of performing the test
over all panels in the building to identify those at risk which
amounts to $144,500 and the adjusted cost of replacing 21 panels
-- 24 of 56 --
19
postponed for one year using the 7 per cent tables which amounts
to $93,458. Both sums are relevant in the assessment of damages
to compensate the plaintiff for the supply and fixing of
replacements for defective glass panels which have not yet but
which will probably fail in the future. I assess this sum at
$237,958. I make no assessment of the cost of replacing the 24
panels that have failed to date.
I find that monies reasonably spent by the plaintiff in the
erection of screens, baffles etc. around the building to protect
public areas from falling glass should the glass panels fracture
spontaneously, are recoverable. It was reasonably necessary for
the owner of the building to take those steps to prevent injury
to people and property in public areas in the vicinity of where
glass might fall, and indeed, where it did fall upon spontaneous
fracturing of the panels. The necessity to spend this money
resulted directly from the supply and fitting of the defective
glass panels to the plaintiff's building. It was really a matter
of good fortune that people were not injured by falling glass
which commenced in 1987.
The money so spent amounts to $276,159.96.
The legal consequences of the findings I have made require
consideration of -
(1) relevant contractual
Nominees Ltd (as
contractor);
obligations between
owner/developer) and
Eagle
White
Star
(as
( 2) relevant contractual obligations between White (as
contractor) and Hennessey (as subcontractor); and
-- 25 of 56 --
(3)
1 .
relevant
Nominees
20
contractual obligations
Ltd (as owner/developer)
subcontractor).
Contractual obligation between
Contractor
between Eagle
and Hennessey
Owner/Developer
Star
(as
and
The lump sum contract is dated 13 March 1986. It is not
entirely clear at what precise date the contract was made. In
specifications of work and materials tendered as part of ex.113
there is an endorsement suggesting that perhaps the contract was
entered into on 9 April 1986. However that may be, in s.150 of
the specifications of that date headed "windows and doors" brief
mention is made of "windows & curtain wall". The provisional
sums included in the contract are set out on p. 12 (a) of the
general specifications. The provisional sum specified for
windows and curtain walls in s.020-01 on p.12(a) is $1,540,000.
In annexures (b) and (c) to the contract reference is made
to discounting the p.c. sum for curtain walling and glazing by
$150,000. Each annexure goes on to provide "and we would then
use our buying power to achieve the same general specifications
as that specified".
It is quite clear that the general specifications, ex. 113,
contain no specifications whatever as to quality or type of glass
for walls and windows.
In the preamble to the agreement dated 13 March 1986 it is
recited that the proprietor "has caused drawings and/or
specifications and/or documents showing and/or describing the
work to be done ... ".
Under cl.1 (a) of the agreement, it is provided, inter alia:
-- 26 of 56 --
21
"The architect may in his absolute discretion and from
time to time issue further drawings details and/ or
written instructions ... respecting
(iii) any errors omissions or discrepancy in or
divergence between the contract drawings
and/or specifications".
It is clear upon the evidence that a document referred to
as "the long specification" setting forth in very considerable
detail the requirements for the glass curtain wall were in fact
produced in March - May 1985 at a time when Hutchinson & Co and
J James & Co were negotiating for the construction of glass
curtain wall work on the proposed development. In this respect
I refer to the evidence of Mr Russell.
It is clear that reference was made to these long
specifications prior to the execution of the contract dated 13
March 1986. Indeed, the builder had discussed them with G James
which according to Mr Russell played a significant part in their
preparation when the original building contract with Hutchinson
and Co was on foot or in contemplation.
It is abundantly clear from the way the owner and its
architect and the contractor and subcontractor discussed matters
relating to the glass curtain walling that the long
specifications were available to and acted upon by all parties
involved in the construction of the glass curtain wall. Indeed
they were included in and became part of the subcontract (ex.131)
-vide cl.44(d).
It is clear that the contractor provided the long
specification to the subcontractor prior to 13 February 1986 (see
ex.114), and it formed part of Subcontract Agreement No. 16.060
-- 27 of 56 --
22
forwarded to the subcontractor for signature on 30 May 1986 (see
ex. 1 31 ) .
On 26 February 1986 the architect acting for the owner at
site meeting number two advised the contractor that guarantees
to be provided by the subcontractor with respect to the windows
and curtain walls must be those specified in the long
specification. At this stage a number of glaziers had offered
to do the work although Hennessey had not yet submitted a tender.
In its letter of 18 March 1986 the contractor forwarded to
the architects a copy of the subcontractor's tender dated
17 March 1986, for the very works described in the long
specification. It was subsequent to that correspondence that the
architect, on behalf of the owner by letter of 26 March 1986,
advised the contractor that it accepted Hennessey as
subcontractor for the performance of the work described in the
specification. By letter of 27 March 1986 the contractor advised
the subcontractor that its tender had been accepted and that the
long specifications would form part of the agreement.
On 3 April 1986 the contractor, at a special projects
meeting, requested that the architect ask the owner to shorten
the 15 year period of guarantee specified in the long
specification to one of 10 years. On 30 April 1986 the owner
agreed to a reduction in the period of guarantee from 15 years
to 10 years. On 30 May 1986 the contractor submitted to the
subcontractor the form of subcontract including the long
specification which was subsequently executed.
It is abundantly clear in my judgment that the glass curtain
wall erection as part of the building to be constructed was a
-- 28 of 56 --
23
complicated and quite expensive part of the overall construction
work. The specification was a performance specification and in
my view, it would be most unlikely that White in those
circumstances would not be under a contractual obligation to
Eagle Star for the performance of the work to be performed by the
subcontractor in accordance with the long specification. Indeed,
without reference to the long specifications there is no
contractual provision whatever concerning the design or weather
sealing of the structural glazing. Neither is there any
specification of colour, thermal properties or wind loading of
the glass to be fixed.
Not surprisingly, it was conceded on behalf of the
contractor that the long specifications were part of the contract
between contractor and owner. It was only the subcontractor who
contended that the long specifications were never part of the
contract between contractor and owner, while conceding that they
were indeed part of the subcontract between contractor and the
subcontractor.
I find upon the material that the long specifications which
are ex.142 did form part of the contract between the owner and
the contractor. The same specifications are included in the
subcontract under cl.44(d) thereof (ex.131).
In any event, in my view, even had the long specifications
not been part of the contract, there would certainly have been
a contractual obligation imposed upon the contractor to supply
a curtain walling system which was reasonably fit for its purpose
and which was of merchantable quality. I accept the contention
of the plaintiff in this respect without need to rely upon the
-- 29 of 56 --
24
concession of the contractor. I refer only to Young and Martin
Ltd v. McManus Childs Ltd (1969} 1 AC 454 and Gloucester Shire
County Council v. Richardson (1969} 1 AC 480. Clearly the glass
panels which failed and which will fail did not meet the standard
required to comply with this obligation.
2. Contractual obligations between Contractor and Subcontractor
For the reasons I have already expressed, the evidence
establishes clearly that the long specifications (ex.142} did
form part of the contract between the contractor and
sub-contractor. Those specifications together with other
material are expressly incorporated in the subcontract pursuant
to cl.34(d} thereof (ex.131}.
It is clear upon the evidence that the subcontractor
specifically requested that the period of guarantee under
subs. 002 of the long specifications be reduced from the period
of 15 years specified in specifications 02, 03, and 04, to one
of 10 years. This request was made at a special projects meeting
on 3 April 1986. It was on 30 April 1986 that the owner agreed
to the reduction of the periods of guarantee referred to subs.
002 -01, 02, 03, and 04. There is no reference whatever to any
period of guarantee in the general specification being part of
the contract between the owner and the contractor.
In the course of argument reference was made to condition
3 of the general conditions of subcontract between the contractor
and subcontractor. Under 3A( 1}, it is specifically provided that
except to the extent that they are:
"strictly inconsistent with the express provisions of
this subcontract all provisions of the head contract
as may be applied and/or related to the works and to
the rights and obligations to be observed, performed
-- 30 of 56 --
25
and complied with by the company and the principal
under the head contract in relation to the head
contract works and in particular the works shall be
deemed to be included in and to form part of the
subcontract which shall be read as though such
prov1s1ons of the head contract were (mutatis
mutandis) expressly set forth herein ... ".
Had the long specifications not been specifically included
as part of the subcontract no doubt general condition 3A (i) and
perhaps (ii) may have been called in aid to demonstrate that the
subcontractor was contractually bound to the contractor, inter
alia, in terms of the specifications to be found with other
documents in ex.132.
In my view, however, it is unnecessary to have resort to the
general condition 3 of the subcontract. On the express terms of
the subcontract it is clear beyond argument that the long
specifications did form part of it.
In my view, on the material to which I have referred the
contractual obligations to be found in the long specifications
for the construction of the glass curtain wall are imposed upon
both the contractor (White) and the subcontractor (Hennessey).
It follows that one has regard to the obligations imposed
by the long specification in determining both the liability of
the contractor (White) to the plaintiff and also the liability
of the subcontractor (Hennessey) to the contractor (White).
The liability of the contractor (White) to the plaintiff
under the head contract, is now relevant only in determining the
remaining issue between the contractor (White) and subcontractor
(Hennessey). White has settled its obligation to the plaintiff
by consenting to judgment against it for the sum of $798,561 plus
interest of $140, 000 plus costs in full settlement of the
-- 31 of 56 --
26
plaintiff's claim. White.now seeks a contractual indemnity from
Hennessey under general condition 3B of the subcontract. Even
without this express provision, the subcontractor would be
obliged to indemnify the head contractor against loss suffered
by the head contractor as a direct consequence of the
subcontractor's breach of its contractual duty to the contractor.
If the settlement of the action between the plaintiff and White
be reasonable in the circumstances then the amount paid under the
settlement is to be taken as the measure of damages. In this
respect I refer to Biggin & Co Ltd v. Permanite (1951) 2 KB 314.
With respect to the contractual liability of the contractor
to the owner and of the subcontractor to the contractor on the
findings which I have made, it is necessary to go only to
subs.003 - 09 of the long specifications which reads:
"09 Glass Generally - Glazing
Glass shall comply generally with BS 952 be the kinds
and grades specified or shown on the drawings and
shall be free from cracks, scratches, bubbles,
blisters and other defects which will interfere with
the appearance or service."
Under sub-section 002 - 01 "Guarantees" it is provided that the
subcontractor shall:
"Provide in the name of the proprietor Guarantees
effective from the date of Practical Completion of the
Building Contract for the supply, manufacture and
installation of the total works of the subcontract as
set out below ...
04 GLAZING INCLUDING STRUCTURAL SILICONE.
A further guarantee shall be given to the Proprietor
which assures making good any glazing defects which
result in air or water infiltration and replacement of
glass which fractures due to workmanship or materials
and including all associated glazing materials as may
be required to make good for a period not less than
( 15) years. Allow for all costs associated with
making good any defects or breakages ... "
-- 32 of 56 --
27
I would construe the term "guarantee" used in these
specifications to mean or at least to include "warranty".
I find that Hennessey breached the obligations imposed on it by
the specifications, to which I have referred, in failing to
replace the scratched glass panels and in supplying and fixing
to the plaintiff's building glass which was defective by reason
of nickel sulphide impurities in it which have interfered and
will interfere with its appearance and service.
On 30 November 1993 White consented to judgment being
entered against it in favour of Permanent Trustees Limited:-
"On the basis of contractual liability for a breach of
the term alleged in paragraph 7 of the amended
statement of claim delivered 22 November 1993 without
any finding of negligence or breach of the Trade
Practices Act or otherwise in the sum of $798,561
(together with an amount of $140,000) as interest
together with costs awarded on a solicitor and client
basis."
Paragraph 7 of the amended statement of claim delivered
22 November 1993 alleged:-
"7. Subsection 01 0. 003. 09 of the specification
provided that the glass to be provided pursuant to the
contract should comply generally with BS952 be the
kinds and grades specified or shown on the drawings
and should be free from cracks, scratches, bubbles,
blisters and other defects which would interfere with
the appearance or service."
In the revised quantum schedule which is ex.102B the loss
and damage suffered and to be suffered by the plaintiff as the
result of the installation of glass curtain wall panels with
scratches and defects attributable to nickel sulphide inclusions
is stated to be $798,561.06.
The summary of damage is expressed as follows:-
(A)
(B)
Erection and removal of scaffolding
Construction of external permanent canopy
$477,90.27
$269,659.96
-- 33 of 56 --
28
(C) Installation of safety features
(D) Replacement of glass
(D1) Replacement of scratched panels
(E) Costs of administration
(F) Expert reviews and reports
(G) Legal Costs (exclusive of the costs of
these proceedings)
(H) Loss of rental income
(I) Other loss and damage
Sub Total
(J) Estimate of investigation to localise Ni s
$6,500.00
$16,135.00
$77,346.00
$53,176.36
$25,430.75
$24,614.15
$21,513.32
$1,897.25
$544,061.06
inclusions and replace affected panels (Estim) $254,500
Total $798,561.06
The basis upon which the first defendant consented to
judgment against it for interest in the sum of $140,000 is not
apparent. However the losses incurred up to the date of trial
(excluding items (D1) and (J)) were specified at $466,715. The
initial expenses were incurred about the end of 1989. If
interest of $140,000 were awarded on that sum for a period of
2! years it would be awarded at the rate of 12 per cent; if
awarded in respect of a period of 3 years it would be interest
at the rate of 10 per cent.
Without attempting to go into minute detail of calculations
it would seem to me that in arriving at the figure of $140,000
for interest under the Common Law Practice Act a rate of from
10 per cent to 12 per cent was applied to $466,715 for a period
of between 2~ and 3 years.
Upon the whole of the material I am satisfied that the
first defendant acted reasonably in settling the plaintiff's
-- 34 of 56 --
29
action on the terms in which it did settle it. There was not a
great deal of time spent in evidence investigating the voluminous
material tended to support the revised quantum schedule, which
is ex. 102B. Upon the evidence however I find the items contained
in this schedule to be established.
In my view upon the evidence adduced against it upon trial,
the first defendant had no real prospects at all of succeeding
against the plaintiff on the issue of contractual liability. I
am satisfied upon the evidence that each of the items A to I were
items of damage and expense resulting to the plaintiff as a
consequence of the breach by the first defendant of the
contractual obligations referred to in para. 7 of the amended
statement of claim of 22 November 1993.
I am further satisfied that the estimated cost of
investigating and locating the nickel sulphide inclusions and the
replacement of the affected panels was reasonable.
The only item requiring consideration is Item (J) which is
based upon the estimated cost of replacing 25 panels at a cost
of $4,000 each. In my view the expenditure of the sum of
$144,500 to have Drs McKinnon and Barry inspect those glass
panels which have not yet fractured and by scientific means
determine which of them are likely to disintegrate in the future
is reasonable.
A matter for consideration in respect of this aspect of the
plaintiff's claim is the estimate contained in the quantum
schedule that 25 panels are likely to need replacement. Upon the
evidence I have already found that probably 21 glass panels will
have to be replaced as a result of nickel sulphide inclusions.
-- 35 of 56 --
30
It does not follow from that however that White in settling Eagle
Star's claim on the basis that 25 glass panels will fail was
acting unreasonably. In arriving at the conclusion that 21 would
fail, I have simply taken the mean between two estimates given -
15 and 27 failures. It cannot be contended that settlement on
the basis of 25 failures was unreasonable in the circumstances
which involved also the consideration of minimising the incurring
of further costs. The estimated cost of replacement of each
panel is $4,000. Between February, 1988 and January, 1993, 24
panels failed by reason of the inclusion in them of nickel
sulphide. Nine failed in the first two years. Twelve failed in
the following two years and four failed in the year following the
second two year period. All told then, 24 panels failed in a
little over five years.
By date of trial a period of nearly six years had elapsed
from the time the glass panels commenced to fail in February
1988. While it is true that most of the failures had occurred
within a period of about four years of the first failure, the
scientific evidence seems to have been sketchy with respect to
experimental work conducted to enable confident prediction to be
made as to the likely time within which some remaining glass
panels may crack, keeping in mind the length of time that has
elapsed since their manufacture. The effect of wind pressures
and temperatures generated by exposure to the sun and the size
of the nickel sulphide inclusions, as well as their location in
the panels, are all factors which make it difficult to predict
what failures may occur over the next few years or when they may
occur. The evidence indicates that there have been no strong
-- 36 of 56 --
31
wind pressures exerted on the glass panelling from the time the
building was constructed. The effect, which cyclonic winds may
have upon glass less able to withstand wind pressures by reason
of nickel sulphide inclusions in it, is a matter which, while not
specifically addressed in the evidence, is, to my mind, a factor
which ought be taken into account.
What is clear upon the scientific evidence is that the
glass panels on the plaintiff's building have failed at a much
greater rate than the rate at which similar types of glass panel
have been recorded as failing on other buildings in other
locations.
There were 1,354 glass panels applied to the building. So
far 11 silver coloured panels have failed and 10 grey coloured
panels have failed. Only two blue coloured panels and one green
coloured panel have failed. It seems clear that the silver
panels and grey panels commenced to fail well before any failures
in the blue panels and green panels were experienced although
there has been a failure of a silver panel and a grey panel since
failures have occurred in the blue and green panels.
Upon the whole of the evidence I am persuaded that even if
the sum paid in settlement of the plaintiff's claims against the
first defendant was towards the upper limit of what was
reasonable having regard to the history of glass panel failures
to date of trial it was nevertheless a reasonable sum. It does
not cease to be reasonable merely because upon my assessment of
the evidence I have preferred to select 21 future failures rather
than 25 in exercising judgment in the difficult task of
prediction of uncertain future events. Accepting as I do that
-- 37 of 56 --
32
the scratched panels were probably scratched by the second
defendant's workmen in the course of erecting them and were not
scratched as the result of other building operations and in any
event had occurred before date of practical completion and that
the 24 failures of glass also were caused by the spontaneous
fractures of the panels caused by the expansion of nickel
sulphide inclusions in the glass it was reasonable for the first
defendant to accept full responsibility in respect of the
replacement of the panels of glass.
Prior to the time of settlement it had been strenuously
contended on behalf of the second defendant that many, if not
all, of the glass panels which failed had been scratched or
broken upon impact with a building maintenance unit which was
suspended from the top of the building and moved up and down some
distance away from the glass panelling to enable it to be
cleaned. This was a matter strenuously contested on behalf of
the second defendant and it was reasonable in my view for the
first defendant to wait until all evidence along those lines had
been called before deciding whether or not to admit to
contractual liability in respect of the broken and/or scratched
glass.
The evidence led and suggestions made in cross-examination
on behalf of the second defendant failed to make out this matter
so strenuously argued on its behalf. Indeed it became clear that
some of the affected panels could not possibly have come into
contact with the building maintenance unit having regard to the
configuration of the structure where the damaged panels were
located. A witness called for the second defendant said that on
-- 38 of 56 --
33
the only occasion he had seen the building maintenance unit come
into contact with the glass panelling no damage had been caused
to it. The evidence showed that the unit had been constructed
with a view to avoiding any of its parts which might scratch the
glass coming into contact with it. The scratches on the glass
in respect of which the plaintiff claims damages in any event
were scratches to the inside of the glass which could not have
been caused by contact with the building maintenance unit.
Detailed examination on behalf of the second defendant of the
glass panelling indicated that there was some chipping at the
very edges of some of the panels. I am quite unpersuaded as to
how the chipping occurred. In any event it seemed to have
nothing to do with any of the fractures of the glass which were
attributed by the plaintiff to the nickel sulphide inclusions in
it.
I infer in the present case that the settlement of the
plaintiff's claim by the first defendant was made on legal
advice. That legal advice was given upon the basis of an
evaluation of all the evidence adduced in the case prior to the
settlement being effected. Upon settlement, the plaintiff
discontinued its action against the architects and the
architectural firm involved in the design of the building. Had
there been no such discontinuance no doubt further days would
have been spent litigating the question of their alleged
negligence and/or breach of contract. Although the evidence led
upon the trial indicated that some scientific investigation had
been carried out in Australia years before the construction of
the building in question in this action and publications had been
-- 39 of 56 --
34
made of views that nickel sulphide particles in heat toughened
glass led to spontaneous fractures of that glass, the matter here
was complicated by the fact that the architects on behalf of the
plaintiff called for tenders for a performance specification
placing upon the glazier who accepted the tender the obligation
of providing glass, framework, glue etc. and fittings to fix it
to the building to achieve the specified result. The long
specifications were also drawn to require the glazier to provide
"guarantees" that the glazing would be free of defects, etc. for
a period of 15 years. Subsequently of course at the request of
the glazier this period was shortened to 10 years. It further
emerged at the close of the case that in fact as one might
perhaps expect Hennessey also provided the usual sort of
financial guarantee of its work - presumably to avoid any part
of the subcontract price for the work performed being retained
during the period "guaranteed" or warranted.
Upon the whole of the evidence I find that the figure for
which White settled the plaintiff's action was a reasonable one.
I further find that it was reasonable in the circumstances for
White to consent to pay the plaintiff's costs of and incidental
to the action against it to be taxed.
On that finding the first defendant, White must have
judgment against the second defendant, Hennessey upon the
indemnity proceedings taken by it against Hennessey for the sum
of $938,561 together with the amount of the plaintiff's taxed
costs in its action against the first defendant on a party and
party basis.
-- 40 of 56 --
35
I am unpersuaded upon the whole of the evidence as to items
which may be included in a solicitor and client taxation which
would not be recoverable if the costs were taxed on a party and
party basis. In the circumstances then I am unable to come to
any conclusion as to the reasonableness of those costs
recoverable on a solicitor and client basis which might not be
recoverable on a party and party basis.
The second defendant should pay to the first defendant its
costs of and incidental to the third party proceedings between
it and the second defendant, such costs to be taxed.
3. Contractual obligations between Owner /Developer and
Subcontractor
For the plaintiff it is contended that by entering into the
subcontract with the contractor, Hennessey made promises with
respect to the glass to be installed under the subcontract for
the benefit of the owner, Eagle Star.
Under cl. 2 (a) of the subcontract, Hennessey agreed to carry
out and complete the works "to the satisfaction of the principal
and the company" (i.e. Eagle Star and White Industries). It is
contended that upon this very wording it is clear that the
promises of the subcontractor were made for the benefit of the
owner.
Under subs.002 of the long specifications it is required
that the "guarantees" (i.e. warranties) be provided "in the name
of the proprietor". It is contended that this wording of the
specifications makes it clear that the subcontract made by
Hennessey which includes these terms is one made for the benefit
of the owner, Eagle Star. Reference is made to sub-cl.04 under
-- 41 of 56 --
36
the heading "Glazing including structural silicone" to which
reference has already been made. That sub-clause provides, inter
alia:
"A further guarantee shall be given to the
proprietor which assures making good any glazing
defects which result ... "
It is contended that the owner, Eagle Star, clearly
accepted the benefit of the warranties given by Hennessey under
the subcontract and that the acceptance was demonstrated by the
owner agreeing to accept a reduction to a period of 10 years in
the guarantee or warranty specified in the long specifications
to be for a period of 15 years. Reference is made to exs.124 and
127. It is contended that the necessity for Hennessey to obtain
the assent of the owner to reduction of the "warranty period" and
the owners giving such assent to that reduction demonstrates
clearly that the owner, Eagle Star accepted, not merely Hennessey
as a subcontractor but accepted indeed the benefit of the various
warranties made by Hennessey in the subcontract.
Section 55 of the Property Law Act provides:
"(1) A promisor who for valuable consideration
moving from the promisee promises to do or
to refrain from doing an act or acts for a
benefit of a beneficiary shall upon
acceptance by the beneficiary be subject to
a duty enforceable by the beneficiary to
perform that promise ... "
Under s. 55 ( 6), the term "acceptance" is defined to mean "an
assent by words or conduct communicated by or on behalf of the
beneficiary to the promisor or to some person authorised on the
promisor's behalf in the manner (if any) and within the time
specified in the promise, or if no time is specified within a
reasonable time of the promise coming to the notice of the
-- 42 of 56 --
37
beneficiary". It is contended for the plaintiff that on the
facts to which I have referred, Eagle Star clearly accepted the
benefit of the obligations imposed upon Hennessey under its
subcontract with White and under s.55(3) Eagle Star is entitled,
as beneficiary under the subcontract in its own name, to recover
from Hennessey the same relief with respect to breach of the
terms of the subcontract as might be available to White as
contractor. Reference is made to the observations of the
majority in Trident General Insurance Co Ltd v. McNiece Bros Pty
Ltd (1988) 165 CLR 107 and to Burleigh Forest Estate Management
Pty Ltd v. C.I.G.N.A. Insurance Australia Ltd (1992) 2 Qd R 54.
On the facts of this case, so it is said, the promises of
Hennessey are expressly given in favour of Eagle Star and on the
face of the documents Eagle Star is the beneficiary of the
promises of Hennessey to be found in the subcontract.
It is contended for Hennessey that there is no privity of
contract between Eagle Star and Hennessey and that there is
nothing in this particular subcontract to distinguish it from any
other subcontract and that the general rule is that a contracting
party, who is not a party to a subcontract may not sue a
subcontractor but must look to the person with whom he is in
direct contractual relationship should the work done by a
subcontractor under the subcontract not satisfy the contractual
obligations imposed upon the contractor under the head contract.
Every case, of course, must be determined on its own facts.
There may very well be subcontracts made where upon the facts and
in the circumstances of that particular contractual arrangement,
a subcontracting party does not make promises for the benefit of
-- 43 of 56 --
38
a party to the head contract, who is not also a party to the
subcontract.
On the cases however to which I have referred and having
regard to s.55(3) there are clearly cases where a person not a
party to a subcontract may be a beneficiary under that
subcontract. The question is whether this is such a case.
In my view, upon its express terms and upon the events
leading to the making of the subcontract (including the variation
of the period of "guarantee" from 15 years to 10 years) the
subcontract between White and Hennessey may be characterised as
one in which Hennessey makes promises for the benefit of Eagle
Star. Expressed in the language of s. 55 of the Property Law Act,
Hennessey as promisor for valuable considerable moving from White
as promisee, promised to provide and fix glass which complied
with the requirements of the long specifications, to which I have
referred, for the benefit of Eagle Star as beneficiary. Eagle
Star accepted the benefit of that promise and consequently is
able to enforce against Hennessey the contractual obligations
imposed upon it by the terms of the long specifications.
It is clear that the specifications under the subcontract
were performance specifications. Both Eagle Star and White
relied upon the knowledge and skill of Hennessey and its experts
in the design and provision of the glass curtain wall to be
constructed on the building and it was of critical importance
that Hennessey as subcontractor, as well as exercising skill and
taking care in the performance of its subcontract work give a
"guarantee" (more precisely "make a warranty") to Eagle Star as
to the quality and performance of the glass curtain wall it
-- 44 of 56 --
39
erected for Eagle Star as subcontractor of White. Initially the
period of warranty under both contract and subcontract was for
15 years and it was at the express request of Hennessey that
Eagle Star agreed to a reduction of this period to 10 years.
The plaintiff claims against the second defendant as a
party entitled pursuant to s. 50 of the Property Law Act to
enforce a promise made by the second defendant to the first
defendant. I find that subs-s. 002-01 and 002-09 in the long
specifications are promises by Hennessey for valuable
consideration moving from White to do the things therein
specified for the benefit of Eagle Star which have been accepted
by Eagle Star. Upon that finding the settlement of the action
between the plaintiff and White is a matter res inter alios acta.
I have already referred to the material contained in the quantum
schedule which is ex.102B. In the action between Eagle Star and
Hennessey I find established the items A to I (inclusive) and
this sum amounts to $544,061.06.
I find that the 24 panels which have failed were supplied
and fixed in breach of the second defendant's obligation to
provide and fix glass panels free of defects which would
interfere with appearance or service and that Eagle Star suffered
damage as a result.
With respect to Item J the finding which I have already
made that this was a reasonable sum to include in White's
settlement of the claim by Eagle Star is not it seems to me of
itself sufficient to justify a finding, that the sum of $254,500
is the proper assessment of damages for the plaintiff with regard
-- 45 of 56 --
40
to the cost of investigation of glass panels which will, but have
not yet failed, and the cost of their replacement.
For the reasons I have already given, I assess this item
of damage against the second defendant in the plaintiff's action
in the sum of $237,958. In total therefore, I assess damages in
the plaintiff's claim in contract in the sum of $782,019.06.
4. Owner's Claim against Subcontractor in Negligence
With respect to the plaintiff's claim against Hennessey in
negligence, the conclusions I have reached on the plaintiff's
claims in contract and that of White for a contractual indemnity,
are of no assistance. I note initially that the plaintiff, while
not abandoning its claim in negligence, did not attempt to argue
the matter at any length. Because it is at least formally an
issue that was not abandoned, I will deal briefly with it.
The plaintiff's abandonment of its claim in negligence
against its architects is irrelevant to its claim not abandoned
against Hennessey. In any event, the case against the
plaintiff's architects involved their duty of care to the
plaintiff when they procured the services of Hennessey, being one
of a number of glass suppliers and fixers who tendered for the
work involving the meeting of a performance specification. The
architects did not hold themselves out as being expert in either
the characteristics of glass to be used for curtain walling
purposes or in the manner of the fixing of that glass to the
building. The architects did specify in the long specifications
(ex.142), inter alia, that-
"Glazing shall be in safety glass of thickness
complying with the requirements of AS1288 using the
designed wind pressures set out in appendix "A" in
section 010-09 'Glass Generally- Glazing'"
-- 46 of 56 --
41
Although in subsection 06 Installation - 01 Schedule of Glass
after specifying five types of glass, it was noted -
"The above glass is PPG and is indicative of the
colours and thermal properties required.
The type and thickness of safety glass required will
comply with the previously mentioned codes having
regard for the wind loadings as set out in
appendix A.
All tenderers must submit a conforming tender but
are requested to submit an additional tender
including for laminated glass of similar colour and
thermal properties.
In addition to the above tenderers may submit a
further tender based on alternative brand glass
possessing similar colour and thermal properties as
that nominated."
That specification, of course, must be read as generally
subservient to and as not permitting departure from the
requirement under s.010- 09 Glass Generally- Glazing, that the
glass "shall be free from cracks, scratches, bubbles, blisters
and other defects which will interfere with the appearance or
service".
It is perfectly clear upon the evidence that it was
Hennessey who obtained for its own purposes, the advice of an
expert from Cal Asia who had experience in the construction of
glass curtain walling of the kind contemplated by the architects
which was innovative, at least insofar as construction of
commercial buildings in Australia was concerned.
Whatever may have been the duty of care imposed upon the
architects, it is the plaintiff's contention that there was
certainly a duty in tort as well as in contract imposed upon
Hennessey, given the width of choice permitted to it under the
express terms of the tender when it knew that both Eagle Star and
-- 47 of 56 --
42
the architects were relying upon its expertise in connection with
this aspect of the building, to use reasonable care when
selecting glass to avoid providing and fixing glass to the
building, which was known by reasonably well informed persons
with experience in the glass trade to have the characteristic of
spontaneously failing for reasons of the sort that had been set
forth in Australian publications from 1961 onwards and indeed,
had been referred to in some American literature from the early
seventies.
It is abundantly clear that other glaziers, particularly
J James & Co, had indicated that they were not keen on selecting
and applying toughened glass to high rise buildings. The
evidence is silent as to what led to this unwillingness, although
one might be forgiven for strongly suspecting that that firm knew
something of the events concerning the ICI building in Melbourne
in 1961 and the Glenfell building in Adelaide in the 1970s. Both
buildings were large buildings, innovative no doubt for their
time, relying upon the use of extensive glass panelling and both
failed. It is hard to imagine that in a competitive industry
involving the application of glass panels to large structures,
the characteristics of toughened glass experienced in those
buildings would not have come to the attention of other glaziers
in Australia whether directly involved or not. However, the
evidence does not establish that the articles written by persons
who had investigated this phenomena in connection with the
Melbourne and Adelaide buildings had even achieved wide
distribution in the trade circles in which Hennessey operated and
competed. I infer on the evidence generally that manufacturers
-- 48 of 56 --
43
of toughened glass had a commercial interest in refraining from
conceding too readily that unavoidable defects resulting from
nickel sulphide inclusions sometimes but not always led to
failures of toughened glass. Because Hennessey had obtained and
presumably relied to some extent at least upon the expert advice
of Cal Asia, an American organisation with experience in the
erection of glass curtain walling of the sort which Eagle Star
proposed, perhaps it saw no reason to raise the matter or give
consideration to it, if it were not adverted to by experts with
Cal Asia.
However, there is clearly to be found in the literature
circulated by PPG and by other glass industry organisations,
reference to certain dangers in the use of toughened glass which
might be avoided by the use of heat soaked glass, whether
toughened or not.
The plain fact is, upon the evidence, that there were other
types of "safety glass" which could have been selected and which
probably would not have resulted in panels which failed
spontaneously at significant heights above public areas when
applied to the external portions of the building. Had the
toughened glass in the present case been heat soaked, the
evidence strongly suggests that the problems which did arise in
this case would not have arisen or at least if there had been any
failures they would have been minimal. Similarly, if safety
glass had been prepared from laminated glass, which was either
heat strengthened or not, there would have been a conforming
tender in respect of such glass.
-- 49 of 56 --
44
It is clear from the evidence of Mr Donovan that had Eagle
Star been advised by people who knew of the tendency of some
toughened glass to spontaneously fragment over a period of years
after the building had been completed, it certainly would not
have used that type of glass.
In my view, the fact that Hennessey once its tender was
accepted took upon itself the obligation to use its skill as a
glazier to comply with the performance specification which it
submitted, does not lead inevitably to the conclusion that it
owed any duty in tort not to submit a tender or in effect make
an offer which if accepted would lead to its supply of a type of
glass which contained inherent defects - particularly when its
tender would to its knowledge be considered by Eagle Star's
architects. I am unpersuaded that Hennessey owed the owner of
the building a duty of care when tendering to supply glass to be
manufactured by a reputable manufacturer to advise either the
architect, or Eagle Star in this case, of any inherent
self-destructive characteristics which some, but not all glaziers
believed the glass proposed might have even if it was aware, or
should have been aware of those views so that persons could be
fully informed of those beliefs before considering the tender it
submitted.
It is clear upon the material, and it must have been clear
to Hennessey at all relevant times, that it was submitting a
tender to comply with a performance specification for the
erection of a glass curtain wall, where both the architects
concerned and the building developer or owner, Eagle Star, were
relying upon it to select the glass and all the materials
-- 50 of 56 --
45
necessary to fit it to the building as an exterior wall, and
indeed to design the framework etc to be used to hold the glass
with glue etc for that purpose.
If Hennessey in fact knew of the inherent characteristic
of the toughened glass to be supplied by PPG to fail
spontaneously, even if it was not aware of the scientific
explanation for such spontaneous failure, the question is was
there a duty placed upon it in the circumstances of this case to
bring that fact to the notice of White, W. Job & Associates and
Eagle Star when it made its offer to supply and fix toughened
glass when the specifications imposed a contractual obligation
that the glass have no defect which interfered with appearance
or service and when the specifications also imposed a warranty
against such defects for a period of 15 years (later reduced to
1 0 years).
Mr Hennessey, who seems to have been personally involved
with this matter, was not called to give evidence on behalf of
Hennessey.
What knowledge of nickel sulphide inclusions in toughened
glass and their effect Hennessey gleaned from glass manufacturers
both in Australia and overseas in printed material distributed
to glaziers in Australia before 1985-86 has not emerged in the
evidence.
Even upon the assumption that before its tender was
accepted, Hennessey was under a duty to advise Eagle Star or its
architects of any knowledge it had, or ought to have had, about
possible defects in the PPG toughened glass it offered to supply,
the liability of Hennessey to the plaintiff in negligence upon
-- 51 of 56 --
46
the evidence in the case would depend substantially upon whether
it ought to have known of the self destructive characteristics
of some toughened glass prior to the time it submitted its tender
for acceptance.
A difficulty in the way of the plaintiff is that a good
deal of evidence was called to show that the architects in this
case ought to have been aware, or at least would and should have
become aware of this characteristic of toughened glass before it
was supplied and fixed to Eagle Star's building. No evidence was
called that they did know about it. All the persons called who
had been connected with the architect at this time, gave evidence
that they did not in fact know about this particular
characteristic of toughened glass in spite of the fact that they
kept up subscriptions to various professional journals touching
on developments etc in the building industry and architectural
profession.
To succeed in negligence against Hennessey with respect to
the failure of glass because of nickel sulphide inclusions
assuming a duty in tort did exist, it seems to me the plaintiff
must show Hennessey ought to have known of the characteristic of
toughened glass to fracture spontaneously even if unaware of the
reasons made public by Mr Ballantyne in the early sixties and the
reasons given in various publications in the 1970s. There is no
evidence that such information was probably contained in
literature which would be available to glaziers but not available
to architects. There is evidence that some glaziers were aware
of "problems" with toughened glass - Pilkington, Comalco and H. H.
Robertson. However, opinions on this matter varied. All the
-- 52 of 56 --
47
evidence indicates that the archi teet in this case had no
knowledge of the work published by Mr Ballantyne because it had
not been published in a way to bring his conclusions to the
knowledge of people generally in the archi teet ural profession and
building industry but only as a paper which could be purchased
through CSIRO apparently by somebody who had heard or knew about
it.
One evidentiary problem in the way of the plaintiff
recovering in respect of the spontaneous fracture of panels in
my judgment is the absence of satisfactory evidence that at the
relevant time Hennessey ought to have known of that particular
characteristic of toughened glass. There was no evidence
whatever led to show that at the relevant time persons supplying
and fixing glass curtain walls in Brisbane or elsewhere in
Australia for that matter ought reasonably to have known of that
characteristic of toughened glass which had not been heat soaked,
although upon the evidence there were several large organisations
then carrying on business similar to and in competition with
Hennessey that had reservations about the use of such glass
unless heat soaked. The plaintiff led no evidence whatever as
to the availability of this information to persons carrying on
the sort of business that Hennessey was carrying on. The only
evidence from which arguably such an inference might be drawn is
that given by the architects Parker and Hartog. I would be
unprepared to draw such an inference from that evidence because
it is not sufficient in my judgment to demonstrate that at the
material time glaziers generally accepted as a fact the
conclusions reached by Mr Ballantyne. It was a time when
-- 53 of 56 --
48
opinions of people in the trade varied and indeed some rejected
the suggestion that the glass was defective.
Evidence called by the plaintiff on the question of
negligence seems to have been directed to the duty of care owed
by architects. Whatever finding against the architects on the
issue of negligence may have been open upon the evidence, in my
judgment there was not sufficient evidence led to support a
finding of negligence against Hennessey (even if it were open in
law to do so).
In my judgment in making the offer which conformed with the
specification provided, Hennessey owed no duty of care to the
plaintiff in tort to advise it or its architect of the danger of
inherent defects in toughened glass, which possibly or even in
all likelihood would result in spontaneous failure of the glass.
I have held Hennessey to be liable to the plaintiff in
contract, pursuant to s.52 of the Property Law Act. I am
comforted by the observations of the Judicial Committee in Tai
Hing Cotton Mills Ltd v. Liu Chong Heng Bank Ltd (1986) AC 80 at
p.107 in concluding that there was no duty of care upon Hennessey
as offeror in submitting to White its tender for the performance
of subcontract work in accordance with specifications provided
to it by Eagle Star's architects. Authorities dealing with
obligations in tort which run parallel with those in contract are
of little assistance in this case which deals with obligation in
tort arising in precontract negotiations resulting in the making
of an offer.
The plaintiff's claim against Hennessey in negligence for
loss it suffered as a result of the scratching of the 24 panels
-- 54 of 56 --
49
of glass is in a different category from the claim with respect
to the offer to supply and fix glass with inherent defects in it.
With respect to the scratching of the glass, it is more probable
than not, in my view, on the whole of the evidence that the glass
was scratched by employees of Hennessey in the course of working
on the installation of those glass panels. The damage, even on
the assumption that it was merely economic damage, having regard
to the relationship between Hennessey and the plaintiff, is
actionable at the instance of the plaintiff because there is
sufficient proximity between them. In this respect, I apply
Caltex Oil (Australia) Pty Ltd v. The Dredge "Willemstead"
(1975 - 1976) 136 CLR 529. The damage suffered as the result of
the scratching I have already assessed in the sum of $77,346.
In light of the judgment, I propose to give in favour of
the plaintiff against Hennessey in contract, it is unnecessary
for me to specifically give judgment against it in tort. The
quantum of damage with respect to the scratching of the glass is
the same whether it be pursued in contract or in tort.
The plaintiff is entitled to judgment against the second
defendant in the sum of $782,019 together with interest pursuant
to S.72 of the Common Law Practice Act at the rate of 11 per cent
per annum for a period of 2.25 years upon $466,715 of that sum,
which is $115,512 with costs to be taxed.
I give judgment for the plaintiff against the second
defendant in the sum of $897,531 with costs to be taxed.
I give judgment for the first defendant against the second
defendant for the sum of $938,561 plus the amount of the
plaintiff's costs against the first defendant to be taxed on a
-- 55 of 56 --
50
party and party basis. I order the second defendant to pay the
first defendant its cost of this action including its costs of
its third party proceedings against the second defendant to be
taxed.
-- 56 of 56 --