Boral Resources (Qld) Pty Ltd & Anor v Council of the Shire of Albert [1994] QPEC 56
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P & E Application No. 13 of 1994
Before Quirk DCJ
[Boral Resources (Qld) P/L & Baral Resources (Tasmania) Ltd. v.
Albert S .C.]
BETWEEN:
BORAL RESOURCES (OLD) PTY. LIMITED and
BORAL RESOURCES (TASMANIA) LIMITED
- and -
COUNCIL OF THE SHIRE OF ALBERT
REASONS FOR JUDGMENT
Applicants
Respondent
Judgment delivered: 11 August 1994
Catchwords:
Counsel:
Solicitors:
Hearing Date(s):
C. Hughes for the Applicants
s. Ure for the Respondent
Neil O'Sullivan & Rowell for the Applicants
King & Co for the Respondent
5 August 1994
-- 1 of 6 --
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P & E Application No. 13 of 1994
BETWEEN:
BORAL RESOURCES (OLD) PTY. LIMITED and
BORAL RESOURCES (TASMANIA} LIMITED
COUNCIL OF THE SHIRE OF ALBERT
REASONS FOR JUDGMENT - QUIRK D.C.J.
Delivered the day of August 1994
Applicants
Respondent
This matter involves a point of construction brought before
the Court pursuant to s. 2. 24 (3) of the Act. The applicant
conducts an asphalt plant on land at Stapylton. Because of
various commercial pressures, the applicant wishes that the plant
operate without any restrictions regarding its hours of activity.
Whether this can be done without a further application for the
town planning authority's consent is a matter which is in
dispute.
To understand this dispute it is necessary to look at the
matter's history. The subject land is presently included in the
Extractive Industry Zone in the Town Planning Scheme. I am
informed that in the current Scheme an asphalt plant (a "medium
industry" as defined) is a discretionary use. The Extractive
Industry zoning of the subject land was first gazetted in 1980
and as part of the arrangements relating to the rezoning, the
applicant and the respondent executed a "development agreement"
dated 28th November 1979.
-- 2 of 6 --
(
2
Included in that agreement there was a clause which read as
follows:
"2 .. In ~he event of t~e Governor in Council approving the
appl 7cation (for rezoning) the applicant shall carry out,
provide and do or cause to be undertaken carried out
provided, done the things and works and m~ke or pay th~
payments or contributions offered by the applicant and
accepted by the Council set out and specified in the second
schedule hereto from the date of the approval of the
Governor in Council."
In the second schedule, Clause 1 provides:
"The applicant shall at all times observe the requirements
of the Town Planning Scheme and the By-laws of the Council
relating to Extractive Industry as may be amended from time
to time."
On 10th June 1982, the applicant made an application for
town planning consent for use of the subject land as;
"raw materials processing plant, concrete plant, asphalt
plant and ancillary works".
The application was conditionally approved by Council resolution
of 26th August 1982. The approval was expressly:
"Subject to compliance with the terms and conditions
contained within the development agreement previously
signed between council and the Readymix Group Limited on
28th November 1979 in connection with Rezoning Application
No. 182 .•. ".
It is contended by the respondent that this particular condition
is the source of the restriction upon the operating hours of the
asphalt plant.
It will be remembered that Clause 1 of the Second Schedule
required the observation, at all times, of "the requirements of
the Town Planning Scheme and the By-laws of the Council relating
to Extractive Industry as may be amended from time to time".
-- 3 of 6 --
3
Part V of the Town Planning Scheme sets out the
"Special requirements in relation to particular development
whether or not consent of the Council is required".
Clause 21 of Part V deals with;
"Extractive Industries and Temporary Quarries".
Sub-clause (9) of clause 21 provides:
"The following hours of operation of an Extractive
Industry, Temporary Quarry or any ancillary use shall be
complied with at all times provided that in specific
instances of exceptional circumstances the owner or
operator may make application to the Shire Engineer for
variation of these requirements.
Monday-Friday - 6.30 a.m.-5.30 p.m.
Saturday and public holidays - 8 a.m.-12 noon.
carting extracted or processed material or maintenance of
equipment only does not include operation of any other
quarry plant or processing equipment.
Sunday - nil."
It is noted that these restrictions relate only to the
operation of "an Extractive Industry, Temporary Quarry or other
ancillary use".
"Extractive Industry" is defined in the Town Planning Scheme as
being:
"Any land, building or other structure or any part thereof
used or intended for use for the purpose of carrying on an
industry involving extraction, storage, loading or cartage
of sand, gravel, turf, soil, rock, stone or similar
substances from land; the term includes a mine but does not
include crushing, screening, washing or other treatment
processes, or manufacture of products from such substances,
provided that the Council may consent to these ancillary
uses subordinate to the Extractive Industry established on
the land".
The evidence before me indicates that the asphalt plant does
not use material 1 on site and is neither an "Extractive
Industry" or a use ancillary thereto. Accordingly, sub-clause
(9) construed according to the ordinary meaning of its words
-- 4 of 6 --
4
could not be seen as imposing a restriction upon the hours of
operation of the asphalt plant.
The respondent submitted, however, that by reason of the
condition of approval of the asphalt plant refern~d to above, the
plant was burdened with restrictions imposed by the Town Planning
Scheme and the By-laws of the Council relating to Extractive
Industry even if such requirements or by-laws did not (according
to their terms) apply to the plant. To put it another way, the
respondent's submission was that the condition of approval in
some way gave to sub-clause (9) an operation wider than that
which would flow from the ordinary meaning of its words.
I am unable to accept such a submission. The condition of
approval of the asphalt plant required no more than "compliance
with the terms and conditions" of the development agreement. The
agreement itself required no more than observation of the
"requirements of the Town Planning Scheme and the By-laws of the
Council relating to Extractive Industry".
I might be noted that, at the time of its execution, the
development agreement did not appear to contemplate the asphalt
plant or its operation and in any event, Clause 2 appears to see
the Second Schedule as being concerned with the identification
of works to be done etc. and payments or contributions to be made
presumably associated with the land's transition to the
Extractive Industry Zone. To attribute, in that context, to
Clause 1 of the Second Schedule (when, as stated, it calls for
no more than the observation of certain identified requirements
of the Town Planning Scheme and By-laws) an operation which
-- 5 of 6 --
5
extends in an important way the ambit of those requirements is,
in my view, to go too far.
It was submitted that certain correspondence passing between
the parties suggested that the applicant had accepted that its
asphalt plant, by reason-; of the conditions of its approval, were
subject to restrictions in relation to hours of operation.
However I am here faced with an exercise in construction and, in
the circumstances, what others may have made of the provisions
to be construed, does not assist me greatly in that task.
In the circumstances as they have been presented to me, I
construe the relevant provisions of the Town Planning Scheme and
of the conditions of approval of the asphalt plant as not
restricting the hours of operation of the plant so long as it
continues to remain outside the ambit of an "Extractive Industry,
Temporary Quarry or any ancillary use" as defined by the Town
Planning Scheme.
With that qualification, I am prepared to make the declaration
sought in paragraph 1 of the application and it is accordingly
allowed to that extent.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/1994/056