Alberton Investments Pty Ltd v Pine Rivers Shire Council [1993] QPEC 92
'_J
I .Q. c.::: 4''3>(09~
~- State Reporting Bureau
TRANSCRIPT OF PROCEEDINGS
(Copyright in this transcript is vested in the Crown. Copies thereof must not be made or sold
without the written authority of the Director, State Reporting Bureau.)
PLANNING AND ENVIRONMENT COURT
../ JUDGE O I SULLIVAN
p & E Appeal 79 of 1993
p & E Appeal 80 of 1993
ALBERTON INVESTMENTS PTY LTD
and
PINE RIVERS SHIRE COUNCIL
BRISBANE
.. DATE 14/12/93
JUDGMENT
Appellant
Respondent
1 o Ji/ h • (07) 217 4160 Facsimile: (07) 227 5532
4th Floor. The Law Courts, George Street, Brisbane. Q. 400 e ep one. - • •
-- 1 of 17 --
141293 T 2/JMK M/T CMS31/93 (O'Sullivan DCJ)
HER HONOUR: I publish my reasons. The matter is adjourned
until 9.30 a.m. on Friday, 4 February 1994.
2 JUDGMENT
10
20
30
40 "
(
50
60
-- 2 of 17 --
11
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P&E Nos. 79 & 80 of 1993
Before O'Sullivan DCJ
[Alberton Investments Pty Ltd v Pine Rivers Shire Council]
BETWEEN:
ALBERTON INVESTMENTS PTY LTD
Appellant
- and -
PINE RIVERS SHIRE COUNCIL
Respondent
REASONS FOR JUDGMENT - O'SULLIVAN D.C.J.
Judgment delivered:
Catchwords:
Counsel:
Solicitors:
Hearing Date(s):
14th December 1993
Appeal against conditions - rezoning -
buffer - parkland - cost of spillways
rehabilitation
Mr D. Gore QC with him ETC Howard
(Appellant)
Mr c. Hughes (Respondent)
Trilby Misso & Company (Appellant)
Shire Solicitor (Respondent)
25/08/93
-- 3 of 17 --
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P & E Nos. 79 & 80 of 1993
BETWEEN:
ALBERTON INVESTMENTS PTY. LTD.
Appellant
PINE RIVERS SHIRE COUNCIL
Respondent
REASONS FOR JUDGMENT O'SULLIVAN D.C.J.
Delivered the 14th day of December 1993
This is an Appeal against a number of proposed Conditions on a
proposed rezoning of two parcels of land at Johnstone Road,
Brendale. One proposed rezoning is from the "Rural" Zone to the
"Extractive Industry" Zone, and the other is from the "Rural"
Zone, partly to the "General Industry" Zone and partly to the
"Extractive Industry" Zone. I propose to deal with these
separately.
CONDITIONS - GENERAL INDUSTRY ZONE:
Condition 1 (ii) - An area of 10% of the subject site shall be
set aside for park purposes.
Mr Ryter, the Town Planner who gave evidence on behalf of the
Respondent, considered that parkland is necessary in general
industry areas for open space for use by employees for
-- 4 of 17 --
2
recreational purposes, for visual amenity and for recreational
uses which generate noise such as bike tracks. He had undertaken
some preliminary work indicating appropriate open space
pedestrian linkages. He referred to "requiring some park at the
subdivision stage".
I find that a condition along the lines of Condition 1(ii) may
be appropriate at subdivision stage, but I am not persuaded that
it ought to be imposed at rezoning stage. In reaching this view
I have considered Hervey Bay Developments Pty Ltd v Council of
the City of Hervey Bay (Unreported - Quirk DCJ - 10.8.93) and
Transcontinental Development Pty Ltd v Pine Rivers Shire Council
(1969) 25 LGRA 7.
Condition 3 - Park:
This proposed condition, as amended at the hearing, requires
park to be dedicated by the applicant at the time of sealing any
plan of survey.
I refer to my Reasons for Judgment in P & E Application 15 of
1993 delivered 26th August 1993.
There is nothing in the evidence at the hearing of this Appeal
which changes the findings I made in that matter.
I find that this Condition is not relevant or reasonably required
by the proposed rezoning.
-- 5 of 17 --
3
I accept that the combination of my finding in p & E Application
1 5 of 1 993, and this finding, will mean that the body of the lake
and th e foreshore area of the larger lake will be transferred to
the Respondent, but the balance of the same lake will remain in
the ownership of the Appellant.
Condition 5 - headworks:
The parties agreed that this proposed condition would be deleted
and replaced by the proposed condition which is Exhibit 23.
Condition 6(v) - buffer:
This proposed condition requires a buffer fence and landscaped
strip of not less than 3 metres along the eastern boundary.
Mr Kershaw, the Geologist who gave evidence on behalf of the
Appellant, considered that this condition is unreasonable in view
of the proposed uses on the "General Industry" zoned land,
namely, the manufacture of value added products of raw materials
transported from the "Extractive Industry" zoned land. There will
be processing plants and gravel works and so forth adjacent to
possibly a pipe works. If the condition is imposed, trucks would
need to leave the existing gravel works and travel on a public
road for 20 metres and then come back onto the "General Industry"
zoned land. He contended that although the two parcels of land
are in separate zones their activities are really of one type.
-- 6 of 17 --
4
Mr Ryter considered that the buffer is warranted from a town
planning viewpoint because it ·
is appropriate to have some
landscaping to soften he general industry use. I accept this
evidence.
Alternatively, the Appellant contended that any buffer should be
located on the "Extractive Industry" zoned land, rather than on
the "General Industry" zoned land.
Mr Ryter considered that in the "Extractive Industry" Zone what
might happen, in 8 years time or 30 years time, is an unknown
quantity. He considered that the buffer should be within the
0
General Industry" Zone because there ought to be some edge
provided now between the "General Industry" Zone and the
"Extractive Industry" Zone. I accept this evidence.
I was referred to Clause 77 of the Respondent's Town Planning
Scheme which states, inter alia:
"Subject to provisions of Part 7 hereof premises shall
not be erected or used for any purpose within the
service Industry or General Industry Zone unless the
following requirements are met:-
(5) Where land in any industrial zone is adjacent to
land in any other zone such land shall not be used or
buildings shall not be erected unless a buffer, fence
and landscaped strip of not less than ten (10) metres
in width where adjoining a residential zone and three
(3) metres in any other case is provided within the
industrially-zoned allotments along the common
boundary between the two (2) zones, unless otherwise
approved by Council .... "
I find that this Clause requires that there be a 3 metre buffer
-- 7 of 17 --
5
within the "General Industry" Zone.
However, in any event, Mr Ryter made it plain that he was not
relying on Clause 77, but rather on the difference in the nature
of the uses in the Zones as justifying the proposed condition on
town planning grounds.
I find that the proposed Condition is relevant or reasonably
required by the proposed rezoning, so long as it does not
preclude a gate for ingress and egress between the two parcels
of land.
Condition 7 - Noise:
The only issue concerning this proposed Condition was the point
of measurement of the level of noise, the Appellant preferring
measurement at the boundary of any other premises, rather than
at the property boundaries as stipulated in the proposed
Condition.
Mr Ryter conceded that both points are used by acoustics experts,
and he thought both are acceptable. He agreed that there may be
some administrative difficulties arising from the fact that some
of the receptors may be located in Brisbane City rather than in
the Respondent Shire.
The Department of Environment and Heritage Guidelines refer to
measurements "within the boundary of affected premises".
I find that the proposed Condition is relevant or reasonably
required by the proposed rezoning.
CONDITIONS "EXTRACTIVE INDUSTRY" ZONE:
Condition 3 - park:
Clauses (a), (c) and (d) refer to park and clause (b) refers
-- 8 of 17 --
6
to spillways. Clause ( d) defines "completion of extractive
operations" referred to in (b) and ( ) C •
Clause (a) refers to the transfer free of cost to the Council of
the lakes and surrounding areas shown on Figure 19 of Mr
Kershaw's report prior to the submission of the applications to
the Minister.
Clause ( c) refers to transfer to Council on completion of
extractive operations of the lakes and surrounding parklands in
a suitable state for park preparation. It also refers to the
removal of access roads, ramps and other extractive
infrastructure not required by Council.
Clause (d} states: " For the purpose of determining conditions
(b} and (c) above "completion of extractive operations" shall be
taken to be twelve (12) years from the date of rezoning. Council
may extend this period over some or all of the subject lands
should the need arise"
With respect to clauses (a) and (c), I refer to my Reasons for
Judgment in p & E Application 1 5 of 1993. There is nothing in the
evidence at the hearing of this Appeal which changes the findings
I made in that matter.
I find that these proposed Conditions are not relevant or
reasonably required by the proposed rezoning.
If clauses (b) and (c) are deleted, it follows that in so far as
clause (d) should also be deleted.
Clause 3 (b) - Spillways:
The proposed clause is as follows:
"Two (2) lake to river spillways, and a lake spillway
under the realigned Nolan Road, shall be constructed
by the applicant. Council will not require the
-- 9 of 17 --
7
immediate construction of these structures provided a
bond of $220,000 to cover future construction costs is
lodged •. Council reserves the right to require
construction of such structures or to construct them
at the applicant's cost should they be required for
floo~ or water quality control measures. If such
require~ents are _not imposed prior to completion of
extractive operations construction shall be undertaken
at that time".
Counsel for the Appellant submitted that the proposed Condition
is unlawful as none of the spillways are on land the subject of
the rezoning application.
Counsel for the Respondent submitted in reply that the lakes to
be created require interaction, but more importantly with the
river. The lakes require drainage and interaction with the
river, and the lakes will be formed by the extraction of sand on
the land the subject of the rezoning application.
I find that the proposed Condition is not invalid by reason of
the spillways not being on land the subject of the rezoning
application.
Mr Fiedler, an Engineer who gave evidence on behalf of the
Appellant, considered that the lake to lake spillway and the
downstream river to lake spillway are acceptable as they are for
the operation phase of extractive industry. At the end of the
extraction works, he computed additional works involving
anticipated costs of $10,000 and $25,000-$30,000 respectively.
The upstream lake to river channel would involve costs of
$25, 000-$30, 000. This is for a grass lined channel with minor
protected works. Thus, his total anticipated expenditure for the
3 channels or spillways is $60,000- $70,000.
Mr Joy, the
Respondent,
Engineer
contended
who
that
gave evidence on behalf of the
Mr Fieldler's calculations were
not persuaded that Mr Fieldler's
He preferred the system outlined
lacking in detail, and he was
proposals would be adequate.
in the Co-ordinator-General's Report entitled "Pine Rivers Sand
-- 10 of 17 --
8
and Gravel Extraction Study 1977" in which he had been involved
in writing. Mr Joy had not visited the site, and the only work
he had done was to compare Mr Fiedler's conclusions against the
general design guidelines that were established in the Co-
ordinator-General's Report.
Based on the Co-ordinator-General's Report Mr Joy estimated
spillways' widths of the lakes and, based on gabions and stone
pitching, he estimated that total costs would be of the order of
$200,000 - $220,000.
I consider that Mr Joy has relied on a general approach which may
or may not be suitable for this site. He said in evidence that
the Report was of a general nature and the authors could not come
up with specific configurations for particular lakes - they did
not know how the lakes were going to turn out, so they were
indicative only. He said in evidence that there is the
possibility that subsequent calculations could be done that would
indicate a spillway of lesser dimensions or lesser cost could be
required. He said in evidence that he would require more detailed
calculations of changes in water levels and velocities through
the spillways before he could be convinced that a grass lined
channel would be adequate.
Counsel for the Respondent submitted that in considering the
reasonableness of the proposed Condition regard ought to be had
to the fact that there is no allowance for inflation in the
figure of $220,00 for the proposed bond.
Mr Joy considered that Mr Fielder ought to have dealt in much
more detail with a number of matters, including what will happen
to the lakes during flooding events (both local and in river
flooding conditions) likely velocities of water during flood
conditions, overflow of water around the edges of the lake into
the lake, the likelihood of erosion during flooding and whether
the lakes are to be fresh or saltwater.
-- 11 of 17 --
9
I accept that the final configuration of the final lake levels
will have a major influence on the final shape of any outlet
works of channel works.
I accept the evidence of Mr Fiedler that the final layout and
water level requirements
future operating levels,
better technology.
of the lakes, both for existing and
should be subjected to study using
A number of possibilities were canvassed by Counsel for the
parties concerning a practical approach to the evidence of
Messrs. Fiedler and Joy. Counsel for the Respondent raised the
possibility that the applicant may be able to come back at some
later stage with an alternative which may well be cheaper, which
the Council would consider and if it were satisfied then the bond
would be reduced or released. Senior Counsel for the Appellant
raised two possibilities: re-formulation of the Condition so as
to require the provision of more information to substantiate what
form of spillways should be provided before the end of the life
of the project. This would leave open the question of the amount
of the security. Another possibility he raised is that the
Condition be re-formulated by the insertion of words such as
"unless the Respondent is satisfied that such works are not
necessary". This would leave open the question of whether the
appellant has any legal right to challenge the Council's decision
as to its satisfaction or otherwise. Another possibility is that
the Condition be deleted at this stage, for re-consideration at
the consent stage.
Counsel for the Appellant drew my attention to Condition 32 in
Permit 736 which requires a bond of $30,000 for the construction
of spillways during Stage 1. Mr Kershaw gave evidence that this
bond has been provided.
I find on the evidence that the appropriate design of the
spillways cannot be arrived at with any degree of accuracy or
certainty until later in the operation when the final
-- 12 of 17 --
10
configuration of the lakes is known with greater certainty.
Whether there is sufficient certainty at consent stage can be
reviewed at that time. If there is not, then it may be necessary
for a broadly-drafted Condition to be inserted to provide for
further design detail and calculations to be submitted by the
Applicant's experts. These are matters for consideration at the
appropriate time. I am satisfied on the evidence before me at
this hearing that the proposed Condition is relevant or
reasonably required by the proposed rezoning.
Counsel for the Appellant further submitted that proposed
condition 3 (b) is void on three grounds:
First, it is uncertain because it is not possible to identify at
this stage what is an appropriate form of construction.
Secondly, it is uncertain because the time for construction is
not clear.
Thirdly, the spillways related to some future use (park) of the
land.
I accept the first two of these submissions, and find that the
proposed condition is invalid by reason of them. On the question
of uncertainty, I have obtained some assistance from Television
Corporation v Commmonwealth (1963) 109 CLR 70, 71, which was cited
with approval in Kilpatrick v Logan City Council ( 1982) QPLR
74,76.
Condition 4 (d) - intervals for cross-sections:
The proposed condition refers to cross sections at 20 metre
intervals for the length of the proposed bund, to be obtained
from a field survey by a licensed surveyor.
Mr Kershaw considered that 50 metre intervals would be sufficient
because of the long straight stretches and the visible, flat
-- 13 of 17 --
11
ground. He considered that the work could be done as part of an
operational requirement, and should not require the engagement
of a licensed surveyor. The site foreman would be quite capable
of doing the work.
He explained that the 20 metre interval requirement, and the use
of a licensed surveyor, had been inserted in the proposed
Conditions for consistency with earlier Permits. He conceded that
intervals of 20 to 40 metres would be of the right order, and
said there would not be a great deal of difference between 40 and
50 metre intervals. He considered that leaving it to someone on
the site would not guarantee accuracy, and maintained that a
licensed surveyor, or a registered surveyor, should be required,
as is the case with the earlier Permits.
I find that a Condition which provided for 50 metre intervals,
and for the work to be done by a registered or licensed surveyor,
would be relevant or reasonably required by the proposed
rezoning.
Condition 4 (i) - hours of operation:
The Appellant sought, notwithstanding the failure to make this
clear in the EIS, hours consistent with those provided for in the
earlier Permits, namely 6 a.m. north of Nolan Road and 7 a.m.
south of Nolan Road. Mr Ryter considered that this was not
inappropriate.
I find that a relevant or reasonably required Condition would
provide for these commencement times.
Condition 4(k) - explosives:
11 shall not use explosives in the operations". The permittee
The Appellant sought to amend this proposed Condition, by adding
the words "No use of explosives without the written approval of
-- 14 of 17 --
12
the Shire Engineer".
There was no mention of explosi· ves • thin e Application and
accompanying EIS.
I was not convinced by the reasons advanced by Mr Kershaw as to
the necessity for this addition to the proposed condition.
The use of explosives is specifically precluded by the earlier
Permits.
I consider that the proposed Condition is relevant or reasonably
required by the proposed rezoning.
Proposed Rehabilitation Condition:
The Respondent submitted that an alternative to transfer of land
to the Respondent was a Rehabilitation Condition, to be imposed
at permit stage, along the lines of Exhibit 24, which is as
follows:
"Prior to the issue of any Town Planning Consent
Permit permitting the operation of an extractive
industry on the land to be rezoned, the applicant
shall provide:
(i) a detailed plan and report prepared by suitably
qualified persons specifying the post-extraction
rehabilitation of the site to the satisfaction of the
Shire Planner; and
(ii) detailed costings of the proposed rehabilitation
works and lodge a bank guarantee to the value of the
required works. The bond amount shall be reviewed by
Council every five (5) years to ensure the outstanding
cost of rehabilitation works are secured".
Counsel for the Respondent submitted that a Condition such as
this is warranted if the parkland Conditions are held to be
invalid.
The EIS included a discussion of rehabilitation. At page 26, it
states that a detailed landscape plan for the proposed workings
-- 15 of 17 --
13
will be submitted w1.· th the f th ur er consent application for
Extractive Industry. Figures 20 and 21 show rehabilitation for
the Nolan Road site and Scouts Crossing Road site respectively.
Condition 1 of the proposed rezoning to the "Extractive Industry"
Zone is as follows:
"The development of the site and subsequent
rehabilitation shall be generally in accordance with
the report prepared by David Kershaw dated 13 February
1991, submitted with the application unless varied by
any condition of this approval".
Senior Counsel for the Appellant: (i) there is already security
in the form of dedication of part of the land and in the bond
required by Condition 32 of Permit 736; (ii) as Exhibit 24 is
a new Condition, much better evidence than has been presented by
either side ought to be presented before it is imposed; (iii) the
proposed Condition adds nothing because in its terms it has
application at consent stage, not rezoning stage.
I accept submissions ( i) and (iii). As the matter is more
appropriately addressed at consent stage, it is unnecessary for
me to address submission (ii).
3. CONDITIONS FOR "EXTRACTIVE INDUSTRY" ZONED LAND:
Condition 2 - road widening:
This proposed Condition provides for Nolan Road to be widened by
3.0 metres along the entire frontage of Lot 2 on RP 36132.
Clause 63 (h) of Division 13 of Part 7 of the Respondent's Town
Planning Scheme prohibits extractive industry within 20 metres
of the alignment of a road.
Mr Ryter explained that Fermi t 7 36 required a realignment of
Nolan Road, and the purpose of proposed Condition 2 was to
-- 16 of 17 --
14
provide for consistency with this. The proposed Condition was to
ensure that extractive industries on the land north and south of
Nolan Road should not compromise the potential of that road link
in the future.
I agree with the submission of Senior Counsel for the Appellant
that the Condition should be re-formulated so that it makes this
clear: indeed Mr Ryter seemed to more or less concede this. If
this is done, then the proposed Condition, as re-formulated, may
be relevant or reasonably required by the proposed rezoning.
Condition 3 - Park:
The same considerations apply as those I have already discussed
in the context of the other rezoning Application.
I find that the proposed Condition is not relevant or reasonably
required by the proposed rezoning.
Condition 4 (b) :
This proposed Condition was abandoned by the Respondent during
the hearing.
Condition 4 (j) - noise measurement:
The same considerations apply as those I have earlier discussed
in the context of the other rezoning Application.
I find that the proposed Condition is relevant or reasonably
required by the proposed rezoning.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/1993/092