Draftcorp Drafting Service Pty Ltd v Townsville City Council [1993] QPEC 81
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P&E 17 of 1993
Before Judge Quirk
[Draftcorp Drafting Service Pty Ltd v Townsville C.C.]
BETWEEN:
Draftcorp Drafting Service Pty Ltd
Appellant
Townsville City Council
Respondent
REASONS FOR JUDGMENT - QUIRK D.C.J.
Judgment delivered:
Catchwords:
Counsel:
Solicitors:
Hearing Date(s):
10.11.93
s. Ure - Appellant
N.M. Cook - Respondent
Boulton, Cleary & Kern - Appellant
Barabara Bogiatzis - Respondent
5.11.93
-- 1 of 5 --
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT BRISBANE
QUEENSLAND
P & E Appeal No. 17 of 1993
BETWEEN:
DRAFTCORP DRAFTING SERVICE PTY LTD.
Appellant
TOWNSVILLE CITY COUNCIL
Respondent
REASONS FOR JUDGMENT - QUIRK o.c.J.
Delivered the day of November 1993
In this matter I have to rule whether or not the appeal is
competent. On the 30th June 1993 an application for Town
Planning Consent was submitted to the respondent Local Authority
by the Appellant. On the 7th July 1993, the respondent wrote to
the appellant advising:
"That the consent application form has not been signed
or dated by the current owner of the subject land, Bajool
Land Co. Pty. Ltd .... therefore, Council cannot proceed
with processing of this application for Town Planning
consent until such time as this requirement has been fully
complied with ... 11 •
on the 20th July 1993, the owner's written authorization of
the application for Town Planning consent was furnished to the
respondent. In the meantime, the public notification procedures
required by the Act had been initiated and on 3rd August 1993,
a statutory declaration that these procedures had been undertaken
was lodged with the respondent.
a:
-- 2 of 5 --
2
The respondent has not made a decision on the matter and,
on the 5th October 1993, a "Deemed Refusal" Appeal was lodged
pursuant to s.4.13(10) of the Act.
The respondent has taken the attitude that the appeal is
incompetent in that the application, as submitted, was null and
void not being accompanied by the owner's written authorization.
Consequently, the advertising procedures were not carried out in
accordance with the Act and these difficulties were not remedied
by the later production of the written authority. It was
submitted that there was no application with which the Local
Authority was required to deal and there has been no basis for
a "Deemed Refusal" Appeal pursuant to s. 4.13(10) of the Act.
Section 4. 1 ( 2) does appear to distinguish between the
"lodgment" of an application and its being "taken to be duly
made" suggesting that the latter situation may be postponed until
the requirements of the Act have been met. It is by no means
clear to me that the particulars referred to in s.4.1 (2)(b)
include the written authorization of the owner of the land
referred to in (4.1 (2) (d)) but as this matter was not argued by
the appellant I will not pursue it.
The period of forty days within which the Local Authority
must decide the application runs from the receipt of the
statutory Declaration ( 4. 13 ( 4) ) . In this case when the Statutory
Declaration was furnished to the Local Authority the owner's
written authorization had been submitted so it could not, at that
point, be said that the application had not been "duly made"
within the meaning of 4.1(2) (d).
-- 3 of 5 --
3
The Respondent's concern is however that the public
notification proceedures were commenced prior to the
application's having been "duly made". An applicant is required
to commence the public notification "not less than two days after
lodging the application" (s.4.12(3)). I point out that the
section refers to "lodgment" rather than the time at which the
application attains the status of having been "duly made", a
distinction which has already been referred to in the context of
s. 4 . 1 ( 2) and which was adverted to in another setting in
Brisbane city Council v. Mainsall Investments Pty. Ltd. (1989)
2 Qd. 204 at 213.
I am unable to see that the public notification procedures
which were initiated "not less than two days after lodging the
application" were invalidated by the late furnishing of the
owner's written authorization. I am satisfied that, when time
commenced to run for the purposes of s.4.13 (10). The application
was otherwise "duly made".
I'
If I am not correct in any aspect of this construction 1,
exercise, it seems to me that there could hardly be a better case
for the exercising of the discretion to provide relief from any (
non-compliance which is provided by s. 7 .1 ( 3) ( e) . The only
concern appears to be with the initiation of the public
notification proceedures and, at the very worst, these
proceedures had commenced too soon. It does not seem to me that
it could be sensibly suggested that any non-compliance with the
Act's requirements has adversely affected the awareness of the
public of the existence and nature of the application or
-- 4 of 5 --
4
restricted the opportunity of the public to exercise the rights
conferred by the relevant provisions.
In all of the circumstances, I rule that the appeal is
competent.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/1993/081