Felixstowe Pty Ltd v Council of the City of Gladstone [1993] QPEC 3
IN THE PLANNING AND ENVIRONMENT COURT
HELD AT GLADSTONE
QUEENSLAND
P. & E. Appeal No. 1 of 1992
BETWEEN:
FELIXSTOWE PTY. LTD.
Appellant
COUNCIL OF THE CITY OF GLADSTONE
Respondent
REASONS FOR JUDGMENT O'SULLIVAN D.C.J.
DELIVERED THE J.:7 JI._
The Appellant appeals against the refusal of the Council
of the City of Gladstone of a claim for compensation for
injurious affection relating to land described as Lot 2 on
v
Registered Plan No. 15152, County of Clinton, Parish of
~ Gladstone ("the land").
The land was re-zoned from Residential "A" (High Density)
to Residential "A" (Low Density) under the Town Planning
Scheme of the Respondent gazetted on 15 June 1991 ( "the
prescribed date").
On 12th March 1977 the land had been re-zoned to
Residential "A" ( High Density). This re-zoning had been the
subject of a Deed dated 12 March 1981 between the Appellant
and the Respondent which provided for 162 units in accordance
with a plan of development ( "the Deed").
Deed is as follows:
Clause 9 of that
-- 1 of 17 --
2
"Notwithstanding anything herein contained arid
without prejudice to the Council's rights hereunder if
the Developer shall fail in its obligations hereunder
with respect to the development of any part or parts of
the said lands in accordance with the plans attached
hereto and such failure to develop shall continue for a
period of one year then the Council shall have the right
without any further reference to the Developer to apply
for the re-zoning of the said part or parts so
undeveloped to the original zoning of Residential "C", as
herein set out or such similar zoning as may be
applicable under the Council's Town Planning Scheme from
time to time for Residential Development and in the case
of such re-zoning being granted the Developer shall not
be entitled to any compensation in respect to such re-
zoning whether on account of injurious affection or
otherwise howsoever."
The Respondent gave the Appellant various extensions of
time for the commencement of the proposed development.
Building approval for the construction of 1 2 units was
granted by the Respondent to the Appellant on or about 25 July
1990.
A new Town Planning Scheme was gazetted for the whole of
the City of Gladstone on 15 June 1991 ("the new Scheme").
Pursuant to the new Scheme the land was zoned Residential "A"
( Low Density) . Pursuant to the Table of Zones a dwelling
house is a permitted use in that Zone and as far as is
relevant in this appeal, cluster housing development is a
consent use. The Statement of Intent for the Residential "A"
Zone in the new Scheme is as follows:
"The intent of this zone is primarily to accommodate
detached dwelling houses at low densities to the general
exclusion of other land uses, but may include specific
uses associated and compatible with these residential
areas."
The Appellant made a claim for compensation pursuant to
s.3.5 of the Local Government (Planning and Environment) Act
1990-92 {"the Act") which was received by the Respondent on 28
-- 2 of 17 --
3
October 1991. By letter dated 23 December 1991, the
Respondent rejected the claim, relying on clause 9 of the
Deed. The appellant appeals against that decision.
Pursuant to s.3.5(8)(a) of the Act, compensation is
assessed as follows:
"The amount of compensation is (subject to
paragraphs (b), (c) and (d)) to be an amount equal to the
difference between the market value of the interest
immediately after the time of the coming into operation
of the provision of the planning scheme by virtue of the
operation whereof the claim for compensation arose and
what would have been the market value of that interest if
the provision had not come into operation."
The value of the land if the new Scheme had not come into
operation was agreed by the parties at $569,250. In contrast
the market value of the land immediately after the time of the
coming into operation of the new Scheme was in issue. The
values contended by the Respondent's witnesses were $7,000
(Roffey) and $6, 634 (Jorgensen), representing the value of 2
units (161 multi-units prior to the new Scheme and a 159
cluster housing development under the new Scheme.) The value
contended by the Appellant was $167,000, representing the
~ value of the land developed as a 46 lot residential
/
subdivision.
The market value of land at the prescribed date is
arrived at by applying the tests enumerated in a long line of
authorities, including the well-accepted approach in Spencer v
The Commonwealth of Australia (1907) 5 C.L.R. 418 at 441 per
Isaacs J:-
"The market value cannot exceed what such a prudent
purchaser would be prepared to give him. To arrive at the
value of the land at that date, we have, as I conceive,
to suppose it sold then, not by means of a forced sale,
but by voluntary bargaining between the plaintiff and the
-- 3 of 17 --
4
purchaser, willing to trade, but neither of them so
anxious to do so that he would overlook any ordinary
business consideration. We must further suppose both to
be perfectly acquainted with the land and cognizant of
all circumstances which might affect its value, either
advantageously or prejudicially, including its situation,
character, quality, proximity to conveniences or
inconveniences, its surrounding features, the then
present demand for land, and the likelihood, as then
appearing to persons best capable of forming an opinion,
or a rise or fall for what reason soever in the amount
which one would otherwise be willing to fix as the value
of the property."
Other authorities are of assistance to the particular
issues raised in this appeal.
In Gallagher v. Brisbane City Council (1975) 2 Q.L.C.R.
368 (at p.381), the Court said:
"But if the highest and best use on the said date is
a permitted use by consent, the view we hold is that only
in exceptional circumstances, if at all, would its
present value not exceed, to some extent, its permitted
use a 'as of right' value. The amount by which it does
exceed this last mentioned value will depend, among other
things, on the time lapse between resumption date and the
consent date."
In N.L. Horner & Horner Investments Pty. Ltd. v. Brisbane
City Council (1983) 9 Q.L.C.R. 3 (at p.10), the Court adopted
Gallagher and said:
"However, the task imposed upon me by the Act, is to
seek to place a value on the claimant's land on the basis
of the highest amount they would reasonably be expected
to receive from a hypothetical prudent purchaser. In
doing so I must weigh all the potential which the land
possesses in the claimant's hands, and although I must
have due regard to the current zoning I must not use such
zoning to deny the claimants a higher value if a prudent
purchaser would be prepared to offer on the basis of the
probabilities or possibilities of a higher zoning."
In Gill v. Queensland Ambulance Services Board (1988-89)
12 Q.L.C.R. 186, the Court said (at p.198):
"In testing a matter of this kind a hypothetical
sale must be envisaged in accordance with Spencer's case
and the possibilities and probabilities of obtaining an
amendment of the plan given due consideration."
-- 4 of 17 --
5
Town planning evidence was given by Mr Schomburgk for the
Appellant and Messrs Warren and Bell for the Respondent. Mr
Bell was the Respondent's Town Planner prior to Mr Warren and
later a Consultant Town Planner for the Respondent.
The substantive difference in the town planning evidence
was the highest and best use of the land immediately after the
new Scheme came into operation: specifically, whether it was
a residential subdivision (Mr Schomburgk) or cluster housing
t (Mr Warren) .
Mr Schomburgk adopted a minimum lot size of 600 m2 in the
Residential "A" Zone. He considered that Section 7. 9. 4 of the
Scheme, and the Table to which it refers, gave no guidance as
to density in the Residential "A" Zone, other than it being
within the phrase "all the other zones as determined by
Council."
Mr Warren considered a minimum density of 300 m2 for
' group title cluster housing in the Residential "A" Zone was
appropriate. He based this on two duplex dwellings being two
dwelling units on one 600 m2 allotment, each dwelling unit
being on an allotment of 300 m2 . He also referred to the June
1992 amendments to Clause 10. 13. 1 of the new Scheme which
changed the minimum area for Residential "A" from 600 m2 to
300 m2 .
The Respondent sought to give some weight to three
factors, namely, that in 1981 the land was earmarked for
cluster housing development; that cluster housing is also
supported by the Strategic Plan; that the 1981 zoning was in
the face of objections.
-- 5 of 17 --
6
Mr warren considered the Respondent would have given
consent immediately after the prescribed date for a cluster
housing development. He referred to a grant under the
Residential Regulation Review Program which the Department of
Housing and Local Government approved for the Respondent in a
letter to it of 16 January 1991. This grant was to enable the
Respondent to consider innovative developments. This,
together with his figure for likely density for Residential
"A", and section 1 . 3. 1 . 1 of the new Scheme led him to believe
that consent would have been given.
Mr Warren said that if cluster housing development had
been proposed in June 1991 he, as Town Planner for the
Respondent, "would have felt comfortable in supporting such an
application to the Council".
Mr Warren gave evidence that if a purchaser had asked him
after the prescribed date: "what can I do with this site?" he
would have answered along the lines of: if you can make an
application for cluster housing development which you can
demonstrate to me will work, I will probably recommend it to
Council. He would have also have added the comment: I can't
guarantee that the Council will accept my recommendation
al though my recommendations as a generalisation tend to be
followed.
Mr Warren said that he did not believe he would have been
in a position to convey to a purchaser that the down-zoning
was in the face of the Council's consultant's recommendation;
that matter would have been dealt with in a special meeting.
-- 6 of 17 --
7
Mr Warren gave evidence that since his time with the
Council (approximately December 1989) there had been no
cluster housing developments of the scale of the proposed unit
development on the land.
Mr Schomburgk referred to the consent uses in the
.
Residential "A" Zone. He considered that the minimum area for
Residential "A" of 600 m2, in conjunction with the Statement
of Intent for the Residential "A" Zone, meant that it was
likely that Council would not allow a cluster housing
development which provided a density in excess of that which
might be provided by a conventional residential subdivision.
Mr Bell was asked by the Respondent to consider the
Appellant's Objection to the re-zoning of the land as
Residential "A" (Low Density) under the new Scheme. It was
his recommendation that the land be rezoned to Residential "B"
(Medium Density) under the new Scheme. His recommendation was
contained in a report to the Council as follows:
"The-zoning of Lot 2 on R.P. 15152 (multi unit site)
be upheld in part with land being rezoned to Residential
B which better reflects the proposed scale of development
than unit density proposed in the original application."
This recommendation was not adopted by the Respondent, as
shown in Item 12 in the Minutes of the Special Meeting of the
Respondent held on 7 December 1990, which is as follows:
"That the objection be upheld in part as per the
Consultant's recommendation except for land described as
Lot 2 on R.P. 15152 and that such land remain as
advertised viz. Residential A."
Mr Warren disagreed with Mr Bell's recommendation because
he considered that the unit development which could be
achieved under the Residential "B" Zone was in excess of what
-- 7 of 17 --
8
was approved under the Deed. He said that the densities for
units in the Residential "B" zone were one unit per 250 m2 .
This would enable a development far in excess of 145 units on
the land.
Ms Finster, an Architect/Town Planner, was engaged by the
Respondent to provide drawings for cluster housing. These
were tendered to the Court and showed 159 units. She had been
provided with design parameters by Mr Warren. Her cluster
housing development was based on an assumed minimum density of
300 m2 per allotment.
It is likely that a prudent purchaser would, on making
enquiries of the Respondent be made aware of the building
permit for 12 units issued to the Appellant on 13 November
1989. Mr Warren said he considered he had to treat this
building application as as-of-right in the Residential "A"
Zone. Mr MacKenzie-Forbes, a Director of the Appellant, said
that the Appellant did not proceed to use the building permit
because the back-zoning meant that the land could not be used
as security.
It is likely that a prudent purchaser would, on reading
the relevant Town Planning Scheme, find little guidance
especially from section 7. 9. 4 and the Table accompanying it.
It was suggested that he would therefore make enquiries of the
Respondent. He might become aware of the Council Resolution
of 7 December 1990 (which I have quoted above). Mr Warren did
not say that he would explain the background of this
Resolution to him. Senior Counsel for the Respondent
submitted that the Resolution ought not be construed as
-- 8 of 17 --
9
preventing a consent for cluster housing. I consider that
such an inference would not be made by a prudent purchaser and
he would take the Resolution at face value. · I consider that
he would focus on the most recent event, namely, the
backzoning.
I consider that if a prudent purchaser came to know of
the Respondent's decision to back-zone the land he or she
would place a high risk on gaining the Respondent's consent
' for a cluster housing development, and consider it more
probable than not that the use of the land would be for a
conventional subdivision.
Mr Schomburgk considered the possibility of Greenstreet
housing or Australian Municipal Code of Residential
Development ( "Amcord") for the land. He considered that the
whole concept of Amcord was to incorporate a mix of housing
styles in a development and, to be practicable, such a
) development should have a range of houses on various sizes of
allotments. He considered that a development along Arncord
guidelines would not be viable using 300 m2 allotments (unless
\J they were house and land packages) and prepared a plan showing
450 m2 minimum lot size and 59 lots.
Mr Warren gave evidence that he would support an
application for an Arncord-style subdivision, with conditions.
imposed. Mr Warren said his personal preference for the
land, however, was for cluster housing style development to
maximise infrastructure in the heart of the city.
I find on the evidence that it is more probable than not
that the land would not be used for an Amcord-type
-- 9 of 17 --
10
development; and a prudent purchaser would not pay a premium
for an Amcord-type development for the land.
The Valuers who gave evidence were Mr Brett on behalf of
the Appellant and Messrs Roffey and Jorgensen on behalf of the
Respondent. Both Mr Roffey and Mr Jorgensen assumed that the
highest and best use of the land was for a cluster development
of 159 units. They both assumed the highest and best use
under the old Scheme was a 1 61 unit development. Mr Roffey
considered that the risk of obtaining consent for a cluster
housing development was cancelled out by the risk occasioned
by reliance on Clause 9 of the Deed. Mr Roffey's valuation of
the land used comparable sales for similar developments to
arrive at a value of $3,500.00 per unit for the land. His
estimated compensation was therefore $7,000.00.
Mr Jorgensen found that "sales evidence would suggest
that a unit development site of the size of the subject
property has a market price of approximately $3,000 per unit
site." He added $634 being additional application costs to
arrive at a compensation figure of 2 units x $3,000 per unit,
plus $634 arriving at a figure of $6,634.00. Mr Jorgensen
gave weight to the 1981 approval and the extensions of time
granted thereafter as indicating a generous approach on the
part of the Respondent. I consider that while these matters
are relevant, they must be considered in the light of the
down-zoning especially as it was against the Appellant's
Objection and the Respondent Consultant's recommendation.
Mr Brett used comparable sales which had been achieved
generally in a number of estates in the vicinity. He also had
-- 10 of 17 --
1 1
regard to statistical information from the Valuer-General on
average sales prices, to arrive at a gross realization of
$30,000 per lot for the 46 lots in a residential subdivision
of the land. From that assessment he subtracted, as a
development exercise, the relevant costs associated with a
subdivision development, including a headworks contribution of
$2,100 a lot (a total of $76,600), and thus valued the land at
$167,000.
Mr Roffey also undertook the exercise of valuing the land
on the basis of the highest and best use being a Residential
"A" subdivision. He considered that only one sale, Watford
Street, for $190,000 was _comparable. Mr Brett valued that
land at $167,000. Mr Roffey applied the development costs
·from Watford Street to the land, thus arriving at a valuation
of $190,000.00 if a headworks contribution were imposed and
$276,000.00 if no headworks contributions were imposed. In
, cross-examination, Mr Roffey accepted that he did not take,
into account engineering and surveying fees of $15,000 which
may already have been expended on Watford Street, and possible
holding charges of $5,000 to $6,000 which would make a
difference.
There was no clear evidence of these fees and charges.
Mr Roffey was asked about various factors which made the
Watford Street sale not comparable. These included the fact
that subdivisional approval had been obtained prior to sale,
the Watford Street land was elevated with very good views,
Watford Street was in a generally newer suburb and was
approximately 4 hectares.
-- 11 of 17 --
12
I prefer Mr Brett's methodology where he used comparable
sales and cross-checked with statistical sales information
from the Valuer-General, arriving at a figure of $167,000.
A further difference in valuations arose depending on
whether a headworks contribution should be taken into account.
Messrs Jorgensen and Roffey were advised by officers of
the Respondent that no headworks contribution would be imposed
on a residential subdivision on the land.
The Respondent has a "Policy for the Determination of
Water Supply and Sewerage Contributions on Development
Application". Mr Warren gave evidence that he would have
recommended to the Respondent that, pursuant to this Policy,
no headworks contribution be payable as there would be no
increased demand on the water supply and/or sewerage services
if the land were developed for a residential subdivision.
Mr Brett's valuation of $270,000 was based on his opinion
that the prudent purchaser would only be prepared to proceed
on a basis that no headworks contribution was applicable if he
had an:-
" irrevocable undertaking from the local authority
that it is the fact that those headworks charges won't be
made, and beyond that an indication that other works
required for the consent won't in some way be perhaps
inflated or sought to offset those headworks charges, and
I say that not on any reflection on this Council, but
just in relation to Councils and the cautious and perhaps
suspicious nature of developers. A great concern of
developers is the possibility that a local authority will
seek contributions beyond those which would normally be
sought."
The test to be applied is that of a prudent purchaser
taking into account the possibilities and probabilities of
such a charge being imposed. I consider a prudent purchaser
-- 12 of 17 --
13
would make further inquiries to ascertain if a headworks
contribution would be imposed. If they had done so, they
would have been advised by the Town Planning Department that
they would recommend these charges not be imposed on the land
but this is not to say that the Council would necessarily
adopt those recommendations.
The Deputy Shire Engineer of the Respondent gave evidence
that he would tell an enquirer that the engineering department
' would recommend headworks be charged on a per lot basis.
The enquirer could obtain a copy of the Respondent's
Policy but I find that he would not find this document easy to
follow and it would not provide him with a clear answer.
Witnesses gave evidence that they were not aware of any
residential subdivisions where the Respondent resolved that
headworks not be levied.
I consider that a prudent purchaser would consider it
, more probable than not that the Respondent would impose a
condition requiring a headworks contribution. I find that a
headworks contribution should be taken into account in the
valuation of the land.
I assess the value of the land after the prescribed date
at $167,000.00. The before value has been agreed by the
parties to be $569,250.00.
If compensation be payable, I accordingly assess it at
$402,250.00. Counsel for the Respondent submitted that
compensation is not payable because the Respondent is entitled
to rely on Clause 9 of the Deed. Counsel for the Appellant
-- 13 of 17 --
14
submitted that the Respondent is not entitled to rely on
Clause 9, for a number of reasons.
The history of the dealings between the Appellant and the
Respondent is relevant. In a report to the Town Planning
Committee on 5th March 1986, Mr Bell recommended that:-
"(a) The Council is not willing to accept the charge
over the subject land;
(b) The Performance Bond is to remain at $30,000;
( c) The period for compliance with the terms of the
agreement is extended until 18th June, 1989;
(d) It is FURTHER RECOMMENDED that the applicant should
also be advised that the Council is prepared to
release the bond if the subject land is re-zoned to
Residential "C"."
Mr Bell said that he had Clause 9 in mind when he made
this recommendation.
On the 18th March 1986, the Town Clerk of the Respondent
forwarded a letter to the Appellant advising that the Council
would waive the $30,000 bond and return it to the owners on
the rationale that the bond was designed to guarantee the
construction of roadworks in Bowles Street and that "The
owners be advised that Council is presently reviewing its Town
Plan and consideration will be given to the desirability of
the existing zoning at that time".
Mr MacKenzie-Forbes gave evidence that following this
letter the Appellant received no further advices from the
Respondent until he attended a meeting with officers of the
Respondent on 15 March 1989. This meeting was attended by Mr
Gordon, the Acting Town Planner for the Respondent, and Mr
Woodman, the Assistant Town Engineer for the Respondent. Mr
MacKenzie-Forbes stated that there was never any suggestion
-- 14 of 17 --
15
during the meeting, by any Council officer, that the land was
liable to be back-zoned. It was around the date of this
meeting that the Appellant engaged various persons to prepare
a townhouse design and layout.
An extension of time was given to the Appellant to 18
June 1987.
There is a diary note dated 15 March 1989 which includes
the following: "They could see no problems in regard to
~ densities or zonings at this stage".
The Appellant lodged an application for building approval
for the first twelve units of the project. Building approval
was granted on 13 November 1989. The documentation tendered
in the Appeal indicates that at the time of this approval,
the Respondent did not mention to the Appellant any intention
to back-zone, either orally or in writing.
By letter dated 11 January 1990, the Respondent advised
, the Appellant that the proposed development of part of the
subject land for the erection of twelve houses required the
further consideration of the Appellant. The second paragraph
of that letter stated that: "Reference is also made to an
agreement between Felixstowe Pty. Ltd. (The 'Developer') dated
12/5/81 and varied by deed of variation executed by the
Council on 15/12/85."
On 10 July 1990, Mr MacKenzie-Forbes and Mr Comiskey, a
Director of the Appellant, had a meeting with Mr Warren. It
was agreed that at that meeting Mr MacKenzie-Forbes was
advised that a building approval would be issued once the
Appellant had given a letter in relation to external works
-- 15 of 17 --
16
associated with the first twelve units. At that meeting
there was no mention that the land was to be re-zoned back to
the Low Density Residential Zone. There was no indication
that the concept plans tendered needed to be submitted to the
Council before the scheme could proceed. Mr MacKenzie-Forbes
said that as he and Mr Comiskey left the meeting they noticed
the new Town Plan on display and discovered that the land was
about to be re-zoned. When they advised Mr Warren that they
had seen that the land was to be re-zoned, he replied that the
Appellant should lodge an Objection.
Mr Warren could not recall whether there were discussions
about whether development in accordance with the new concept
plan could proceed. He said the re-zoning was on display
prior to the meeting and he noticed the gentlemen looking at
it. After the meeting, there was some comment passed about
the re-zoning and he told them they could lodge an Objection.
I have perused all the documentation tendered in the
Appeal for the period from the execution of the Deed on 1 2
March 1981 until the prescribed date, 15 June 1991. I find
that it does not support the contention that the Respondent
considered the Appellant was in default of clause 9 of the
Deed, and it therefore had a right to back-zone the land.
It is not clear from the evidence that the Respondent's
1991 application for re-zoning of the land was the result of
the Appellant's default under the Deed or whether it was the
result of a general planning review, independently of the
Deed. Senior Counsel for the Respondent submitted that the
Respondent's decision not to accept the recommendation of its
-- 16 of 17 --
17
Consultant Town Planner "gives rise to the inescapable
inference that it decided to exercise the back-zoning right,
in accordance with its terms". I find that this inference
ought not be drawn. I find that the rezoning was not the
result of the Appellant's default under the Deed.
There was no evidence that the Respondent advised the
Appellant that it intended to exercise its right to back-zone;
indeed, the evidence which I accept is to the contrary,
namely, that Messrs MacKenzie-Forbes and Comiskey found out
about it when they saw it on public display at the offices of
the Respondent.
I accept that, pursuant to clause 9 of the Deed, the
Respondent was not required to advise the Appellant that it
intended to re-zone; indeed the clause states that "the
Council shall have the right without any further reference to
the Developer". However, this does not mean that the
Appellant had lost its rights to compensation if there was a
re-zoning independently of default under clause 9 of the Deed.
The exercise by the Respondent of its right to back-zone
without compensation pursuant to clause 9 needs to be clear
and unequivocal.
I find that clause 9 of the Deed does not deny the
Appellant the right to be compensated.
I assess compensation at $402,250.00.