Endihill Pty Ltd v Grasso Searles & Romano (a firm) [1992] QCA 352 [1993] 2 Qd R 136
IN THE COURT OF APPEAL [1992] QCA 352
SUPREME COURT OF QUEENSLAND
No. 1768 of 1990
BETWEEN: ENDIHILL PTY. LTD.
(Plaintiff) Respondent
AND: GRASSO SEARLES & ROMANO
(First Defendant) Appellant
AND: CLARKE & KANN
(Second Defendant)
JUDGMENT - THE COURT
Delivered the Fourteenth day of October 1992
These are an appeal and cross-appeal from a judgment
given in the Supreme Court for the sum of $256,857.41 and
costs. That was the primary judge's assessment of the
damage done to the plaintiff, now respondent, in consequence
of the negligence and breach of contract of the appellant
firm as solicitors for the respondent. In part, the damages
awarded are unchallenged; the admitted items total
$129,798.76. The appellant has argued that two items
included in the damages awarded against it, namely a
difference in the purchase price of a piece of land plus
interest and a difference in the cost of construction of a
building on that land, should not have been allowed. By the
cross-appeal the respondent contends that a balancing item
which the primary judge took into account against the claim,
namely a saving of interest on a loan, should not have been
allowed. To make comprehension easier, the appellant will
be called the solicitors and the respondent will be called
-- 1 of 17 --
2
the client.
The solicitors admitted liability at the trial, on the
basis that their negligence or breach of contract resulted
in a failure to settle a contract for sale of land which the
client had made as purchaser. That contract was dated 7
January 1986 and by it the client undertook to purchase land
at Shaw Road for $340,000; it had intended to build on the
land in the same year and rent the building out. The client
sued the vendor for specific performance and when the action
came on trial in December 1989 it was settled on certain
terms including that the client paid an increased price for
the land, the amount of the increase being $105,000; that
sum plus interest was included in the judge's award. The
client brought the action for specific performance and
agreed to pay the enhanced price, intending to construct a
commercial building on the land. It began to do so shortly
before the trial and the judge found that the increased cost
of construction would be $83,000 and awarded that sum too.
His Honour was of opinion that between June 1986, when
construction had originally been planned to begin, and
January 1992 when it actually began, the cost of
construction had gone up by that sum; it was common ground
that that figure should have been $86,000, in accordance
with the evidence of one Kilpatrick, which evidence his
Honour accepted. The total expected cost of the building
was said to be over $1m.
-- 2 of 17 --
3
It was argued for the solicitors at the trial and
accepted by the judge that the consequences of the
solicitors' mistake could not be regarded as having cost the
client the whole extra sum which the client had to agree to
pay to secure the land, plus the extra building cost,
without considering possible savings because of the delay.
The judge held that if the project had proceeded as the
client initially planned, the client would have had to
borrow a substantial sum to finance the purchase. As things
turned out, when the client in fact paid for the land in
1989 it had the money at hand and did not have to borrow;
so, his Honour held, there was a saving of interest on the
borrowing which would have had to be made and that was
assessed at $90,000. The client's cross-appeal challenged
the making of that allowance.
The submissions on behalf of the solicitors
concentrated on the assertion that the client lost neither
land nor building as a result of the solicitors' fault; it
got the land and was in the process of erecting the
building, but all that happened years later than originally
contemplated. In the meantime, the total of the money value
of the land and cost of the building rose, but not as fast
as the rate of inflation, however measured. According to
the argument for the solicitors, the case should be looked
at as one where damages had to be assessed for the
consequences of these transactions being delayed. As for
the client, its counsel in the outline of argument contended
-- 3 of 17 --
4
that had the client got the land and building in 1986 it
would have obtained a hedge against inflation and it was
suggested that the matter should be treated as one requiring
assessment of the value of loss of that hedge. In oral
argument, counsel for the client focused on a different
point, saying that in accordance with orthodox principles,
the courts disregarded, in general, past changes in the
value of money, when assessing damages. It was argued for
the client, in effect, that if the value of the land and
building were in fact equal to the moneys paid and to be
paid for them, still the judge's assessment was right. This
was said to be so because, so counsel contended, the
question of inflation - i.e. decline in the value of money -
should be ignored in such a claim as this; as we have
pointed out, the same party's written submission did not
invite the Court to ignore inflation.
Real property, like most other property, tends to
change in price as time passes, up or down. But on the
client's argument the delayed purchaser who pays a higher
price always sustains a loss to the extent of the additional
sum paid, even if that price merely reflects an increase in
the value of the property (in the money of the day).
Equally, on that view, the delayed purchaser would earn a
"profit" if during the delay the value and price both fell.
In order to deal with the matter it is necessary to
refer to some authority, but it must be said that neither
-- 4 of 17 --
5
side referred the Court to a decided case in which a closely
similar problem has had to be considered, nor have we found
any such case. The basic principle on which both sides
appeared to rely was that stated by Lord Blackburn in
Livingstone v. The Rawyards Coal Company [1880] 5 App.Cas.
25 at 39 and of course in other cases:
"... where any injury is to be
compensated by damages, in settling the
sum of money to be given for reparation
of damages you should as nearly as
possible get at that sum of money which
will put the party who has been injured,
or who has suffered, in the same position
as he would have been in if he had not
sustained the wrong for which he is now
getting his compensation or reparation".
In the present case, that involved a comparison of the
client's position, considered as having carried out its plan
to buy and build in 1986, as compared with the reality,
which was that it bought in 1989 and built in 1992. The
client was not obliged to pursue the specific performance
claim. It decided in its own interests to purchase the land
and erect the building, some years later than originally
intended. It is reasonable to infer that it took this
decision because it expected to make money. The question
is, as it appears to us, whether the client would have made
more money out of the initially contemplated transaction
than it made, in the events which happened, and, if so, how
much more?
A thorough analysis of the consequences of this change
-- 5 of 17 --
6
of plan would be rather complex. On the evidence, the
client formed at material times part of a small group of
companies controlled by Mr. G.A. Cavallucci. When it became
necessary to defer the Shaw Road project, Mr. Cavallucci
turned his attention to another major venture; he did so,
however, on behalf of another company in the group, not on
behalf of the client company. There was no suggestion that
the Court should assess damages on the basis of the loss to
the group as a whole as a result of the delay, but it is
relevant to note that there were transactions between the
companies in the group, having to do with the transactions
immediately in question, which would have complicated the
process of arriving at a comprehensive analysis of the
results of the delay. Neither of the parties suggested that
such a complete analysis should be essayed, but each argued
that certain consequences should be treated as relevant and
others irrelevant.
An example is provided by the interest saving referred
to above, amounting to $90,000. The judge introduced that
subject by saying in effect that the client suffered loss in
having had to pay out more for the land and the building
because of the solicitors' fault, but that a balancing
exercise is necessary. His Honour held that the interest
saving should be taken into account against the client. Mr.
Chesterman Q.C., who led for the client before this Court,
contended that this approach ignored the fact that whenever
the land was bought, money had to be supplied, the use of
-- 6 of 17 --
7
which involved a cost; if the money was borrowed the cost
was interest and if not the cost was the loss of the
opportunity to use the money in some other profitable way,
for example by lending it out. Therefore, it was said, the
judge should have made no allowance against the client for
the expenditure it would have incurred by way of interest,
had it bought the land in 1986.
It appears to us that it is proper to approach the
matter in the way suggested on behalf of the solicitors,
namely as raising a question of the cost of a delay.
Considering the results of the deferment as a matter of
principle, it is seen that the Court's task is to determine
how much worse off, on revenue and capital account, the
client was, as a result of the delay in getting the land.
On revenue account, the only item considered by the
judge was that just discussed, the $90,000 interest saving.
We think, with respect, that there is something to be said
for the criticism of the $90,000 allowance which was made
before us. Whether the money used in the purchase came, as
it did, from credit funds held, or had to be borrowed, there
was as a practical matter a cost of use of those funds for
the relevant period. But we find it unnecessary, because of
the conclusion at which we have ultimately arrived on the
whole case, finally to determine whether in the
circumstances there should have been an offset against the
$90,000, to take account of the loss of the opportunity to
-- 7 of 17 --
8
turn to other profitable use the funds which were paid in
1989 to make the land purchase.
Another revenue element which would on a full
accounting have to be taken into account is the interest or
opportunity cost of funds which would have been used in
erecting the building and another, the sums lost by way of
rental from the building over the period from 1986 to 1992.
These elements were not put forward as requiring
consideration and need no further discussion.
With respect to capital expenditure, one has to
consider the change in the client's capital position which
would have taken place had it been able to purchase the land
and build in 1986 and compare that with the change in its
capital position which ensued, or was likely to ensue, as a
result of the 1989 purchase and 1992 construction.
As to the former, there was nothing in the evidence to
show that the hypothetical 1986 capital expenditures would
have altered the client's capital position; that is, it was
no part of the client's argument that had it purchased and
built as planned in 1986 the result would have been an
immediate unrealised capital profit. It commonly happens
that the addition to a piece of land of a suitable building
increases the value of the land by substantially more than
the cost of construction, but it was not sought to be shown
on behalf of the client that that would have been so in 1986
-- 8 of 17 --
9
or that any such unrealised capital profit would have been
greater in 1986 than in 1992.
There was expert evidence, which the judge accepted
(Exhibit 41), that the land price paid in 1989 was
reasonable - that is, in conformity with the then value of
the land. Cavallucci in fact said the land was worth
$520,000 to him in 1989 - more than the client then paid for
it. There was, so far as we can see, no direct evidence as
to the relationship between the expected value of the
building whose construction began in January 1992 and the
cost of construction. But it would be unrealistic to infer
that the erection of the building was, from the capital
point of view, an unprofitable enterprise. Had the client
thought it would be, the client no doubt would have
refrained from engaging in it. Further, the solicitors'
case on this point is assisted by evidence which was given
that between 1986 and 1992, building costs rose quite
modestly, by a proportion substantially less than the
decline in the value of money.
The solicitors' counsel argued, as we have mentioned,
that the problem should be approached as an assessment of
the cost of delay and also argued that so approached, no
loss in any relevant respect was shown. That argument was
elaborated on by a suggestion that there had to be taken
into account against the increased nominal cost of (for
example) the land, a figure assessed as the decline in the
-- 9 of 17 --
10
value of money from 1986 to 1989. That appears to us to be
a way of assessing the cost of delay of dubious orthodoxy.
We have preferred to look at the matter on the basis of a
comparison of the capital and revenue positions arising from
the hypothetical transactions, on the one hand, and the
capital and revenue positions arising from the actual
transactions, on the other.
It appears to us therefore that, on the evidence, it
was not shown that the capital transactions actually made in
1989 and 1992 had any worse result than those which would
have been made in 1986. This makes it unnecessary to go
further into the comparison of the results from the revenue
point of view, since it is not submitted that, on a revenue
basis, the client was shown to have been disadvantaged by
the delay.
It was, in effect, submitted on behalf of the client
that the judge's treatment of the capital results of the
transactions was supported by the decision in Wroth v. Tyler
[1974] Ch. 30. There, damages were awarded in lieu of a
decree of specific performance where a vendor defaulted
under a contract for sale of a house. The damages were
assessed on the basis of the difference between the house's
value at the date of judgment and the price. Similarly, it
was argued here that the judge should have, as he did,
assessed damages on the basis of the price paid for the land
in fact, ignoring the circumstance that the money in which
-- 10 of 17 --
11
the price was paid in 1989 was worth less than a similar sum
would have been worth in 1986.
It is difficult to see how Wroth v. Tyler can be of any
assistance in solving the problem in the present case. This
was not a suit for specific performance, nor for damages in
lieu. It is true that a suit for specific performance was
brought by the client (not of course against the solicitors,
but against the vendor) but that suit did not produce a
decree nor a judgment for damages. The client simply
agreed, to settle the case, to buy the property at an
enhanced price which it no doubt thought it was then worth.
If Wroth v. Tyler were relevant in determining a claim for
solicitors' negligence delaying the carrying out of a
transaction, it might be argued to favour an approach taking
into account the rise in the money value of the subject land
during the period of delay, rather than the contrary
approach. The award made in Wroth v. Tyler certainly
included that rise in value; in contrast, here the judge
made an assessment of the effect of the delay which ignored
the rise in value. Similar comments may be made as to the
applicability of the decision in Johnson v. Agnew [1980]
A.C. 367, in which an order of the same kind as that in
Wroth v. Tyler was made. Counsel also referred to the
decision of the House of Lords in Birmingham Corporation v.
West Midland Baptist (Trust) Association [1970] A.C. 874,
but that was a compulsory acquisition case; the problem
there faced appears to be quite remote from the present.
-- 11 of 17 --
12
Some reference was made to the treatment of inflation
in personal injury cases. It is the practice to assess
damages for non-economic loss in the money of the day, so
that if an injury which would have produced a certain award
when it occurred is "worth" twice as much at the date of
trial, the latter sum is awarded. It is not easy to see
that the existence of this practice has any bearing upon the
proper method of determining the cost of a delay in entering
into a real estate transaction.
Something should be said of the contention that the
damages should have allowed for the loss of a hedge against
inflation. The value of the land and cost of the building
did not, over the relevant period, increase at any faster
rate than the decline in the value of money; the sum
claimed could reasonably be described as an inflation loss.
As we have mentioned an argument based on loss of an
inflation hedge was made in the client's written outline,
but not pressed at the hearing. Circumstances can perhaps
be postulated in which such an award would be justified,
where a purchase of specific property is delayed for some
years. It might be impracticable to turn the purchase money
to profitable use during the period of delay, making an
award of the kind sought here a proper one. No such case
was made by the client. It was in 1986 the owner of a very
substantial asset, a Hill End property which was
unencumbered and available to fund an investment; that was
-- 12 of 17 --
13
sold in 1988. Late in 1987 Cavallucci decided to turn his
attention to another major project, at Lutwyche Road, in
view of the delay in acquiring Shaw Road. Resources which
would otherwise have been applied to Shaw Road were used at
Lutwyche Road; the Hill End property was made available as
security and, in a practical sense, the client's capacity to
call on the services of Cavallucci himself and those of the
group's building company was diverted to the Lutwyche Road
project.
There was a significant lapse of time, it appears,
while the future of the Shaw Road project remained uncertain
and Lutwyche Road had not been determined on as a
replacement. No attempt was made separately to quantify the
inflation loss during that period, during which the client
had moneys on interest-bearing deposit.
To look at the matter more broadly, the client was not
run as a truly independent company, but was part of a group
controlled by Cavallucci and which was engaged in various
activities, some briefly and some more elaborately alluded
to in the evidence. The long deferment of the Shaw Road
project did not bring those activities to an end, but made
them different from what they otherwise would have been. It
was a matter for the group's controllers and, in particular,
Cavallucci to decide from time to time which assets in the
group should be deployed, and to what purposes. It was not
shown that from 1986, when building at Shaw Road was
-- 13 of 17 --
14
intended to begin, to 1992, when it did in fact begin, the
client's resources had to lie fallow or be held in reserve.
To the extent that such resources were not used to what
was, from the point of view of the client itself, maximum
effect, that was substantially due to decisions made in the
interests of the group and not to the solicitors' breach.
The sums the judge awarded in respect of the increased
price of the land and the increased cost of the building
should not be allowed, nor interest on the former. This
renders academic the propriety of the balancing item of
$90,000 which the judge thought proper to set against those
sums; it was not contended, nor did the notice of appeal
allow for the possibility, that there could be judgment for
a lesser sum than $129,798.76. There was a suggestion that
the judgment should be reduced by another $50,000, by reason
of a partial discharge of the solicitors' liability, but for
reasons which need not be set out, that has become an
academic point and was not really pressed.
The appeal will be allowed by reducing the sum for
which judgment was given to $129,798.76. The respondent
must pay the costs of the appeal; no application under the
Appeal Costs Fund Act 1973 has yet been made.
-- 14 of 17 --
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
No. 1768 of 1990
BETWEEN: ENDIHILL PTY. LTD.
(Plaintiff) Respondent
AND: GRASSO SEARLES & ROMANO
(First Defendant) Appellant
AND: CLARKE & KANN
(Second Defendant)
_______________________________________________
Mr. Justice Pincus
Mr. Justice Davies
Mr. Justice Moynihan
_______________________________________________
Judgment of the Court delivered on 14th
October, 1992.
_______________________________________________
APPEAL ALLOWED.
JUDGMENT BELOW VARIED TO THE EXTENT THAT
AWARD OF DAMAGES BE REDUCED TO $129,798.76.
RESPONDENT TO PAY COSTS OF APPEAL.
_______________________________________________
-- 15 of 17 --
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
No. 1768 of 1990
Before the Court of Appeal
Mr. Justice Pincus
Mr. Justice Davies
Mr. Justice Moynihan
BETWEEN: ENDIHILL PTY. LTD.
(Plaintiff) Respondent
AND: GRASSO SEARLES & ROMANO
(First Defendant) Appellant
AND: CLARKE & KANN
(Second Defendant)
JUDGMENT - THE COURT
Delivered the Fourteenth day of October 1992
MINUTE OF ORDER: 1. The appeal is allowed.
2. The judgment below is varied to the
extent that the award of damages is
reduced to $129,798.76.
3. The respondent must pay the costs of
the appeal.
CATCHWORDS: DAMAGES - MEASURE OF APPEAL -
Appellant/solicitors admitted liability
for failure of contract for sale of land
to settle - whether client would have
made more money from initially
contemplated transaction and if so how
much more - whether sums in respect of
increased price of land and building
ought be allowed.
Counsel: P.A. Keane Q.C., with him J.C. Bell for
the Appellants
R.N. Chesterman Q.C., with him Ms M.A.
Wilson for the Respondent
Solicitors: Corrs Chambers Westgarth for the
Appellant
Greves Creswick for the Respondent