Bird, Re [1992] QCA 339 [1993] 2 Qd R 130
IN THE COURT OF APPEAL
[1992] QCA 339
SUPREME COURT OF QUEENSLAND
Appeal No. 90 of 1992
BETWEEN:
NICK FAVOT PTY. LTD.
(First Plaintiff) First Respondent
- and -
GLEN BIRD and KAREN BIRD
trading as BIRD'S PLUMBING
(Second Plaintiffs) Appellants
- and -
GROSSMAN BUILDERS PTY. LTD.
(First Defendant) Second Respondent
- and -
QUEENSLAND AMBULANCE SERVICE
(Second Defendant) Third Respondent
McPherson J.A.
Davies J.A.
Moynihan J.
Judgment of the Court delivered on the seventh day of October
1992
LEAVE TO APPEAL GRANTED. APPEAL ALLOWED WITH COSTS. ORDER
MADE ON 23 APRIL 1992 DISMISSING APPLICATION WITH COSTS SET
ASIDE. IN LIEU ORDER THAT APPLICANTS BE JOINED AS PARTIES TO
ACTION NO. MISC. 1/1992, DISTRICT COURT, TOWNSVILLE BETWEEN
NICK FAVOT PTY. LTD. AS PLAINTIFF AND GROSSMAN BUILDERS PTY.
LTD. AS FIRST DEFENDANT. FURTHER ORDER THAT RESPONDENT PAY
APPELLANTS' COSTS OF AND INCIDENTAL TO THE APPLICATION.
RESPONDENT TO HAVE CERTIFICATE UNDER THE APPEAL COSTS FUND
ACT.
CATCHWORDS: BUILDING AND ENGINEERING
CONTRACTORS - SUBCONTRACTORS’
-- 1 of 15 --
CHARGES -
appellants/subcontractors served
notice of claim on employer but
failed to bring action within
time - whether fatal to joining
in action brought by another
subcontractor - whether
appellants’ charge extinguished
by lapse of time - whether s.15
dominant provision.
Counsel: C. A. White for the appellants
C. Carrigan for the respondents
Solicitors: Cooper Grace & Ward t/a for
Nehmer Davenport Dean McKee,
Townsville, for the appellants
Connolly Suthers, Townsville,
for the first respondent
Wilson Ryan & Grose, Townsville,
for the second respondent
Hearing date: 21 September 1992
-- 2 of 15 --
IN THE COURT OF APPEAL
SUPREME COURT OF QUEENSLAND
Appeal No. 90 of 1992
Before McPherson J.A.
Davies J.A.
Moynihan J.
BETWEEN:
NICK FAVOT PTY. LTD.
(First Plaintiff) First Respondent
- and -
GLEN BIRD and KAREN BIRD
trading as BIRD'S PLUMBING
(Second Plaintiffs) Appellants
- and -
GROSSMAN BUILDERS PTY. LTD.
(First Defendant) Second Respondent
- and -
QUEENSLAND AMBULANCE SERVICE
(Second Defendant) Third Respondent
JUDGMENT OF THE COURT
Delivered the Seventh day of October 1992
This appeal raises a question under the Subcontractors’
Charges Act 1974-1979 that has previously been the subject of
decision by Douglas J. in Re Queensland Tiling Service Pty.
Limited [1978] Qd.R. 142 and by Kneipp J. in Ex parte
Collinsville Buckhoe Truck Hire [1985] 1 Qd.R. 233.
Essentially the matter for this Court is whether the
interpretation of the Act adopted in those two decisions is
-- 3 of 15 --
2
correct.
The appellants carry on in partnership a plumbing
business known as Bird’s Plumbing. Between June and October
last year they did plumbing work and supplied materials for an
ambulance station and residence being built for Queensland
Ambulance Service (“QAS”) at Black River. QAS was the
building owner, or, as the Act calls it, the “employer”. The
head contractor, which had agreed with QAS to construct the
building, was Grossman Builders Pty. Ltd. It in turn engaged
the appellants to do the plumbing work.
The appellants are still owed $47,000 for plumbing work
done on the building. Unfortunately the head contractor is
now insolvent and in liquidation. On the other hand, a sum of
$44,045 payable by QAS to the head contractor under the
construction contract has been paid into court to abide the
determination of claims of subcontractors asserting the right
to charges under the Act. Apparently the claims of all
subcontractors total some $97,427, of which the appellants’
claim of $47,000 is alleged to be part.
A subcontractor making a valid claim to a charge under
the Act on money payable to his head contractor is required to
give notice to the employer by whom the money is payable. The
notice must specify the amount and other particulars under
s.10(1)(a). Notice of having made the claim is to be given to
the head contractor: s.10(1)(b). If notice is not given
-- 4 of 15 --
3
under s.10 the charge does not attach: s.10(4). The
consequence of giving notice of claim of charge is that the
person to whom the notice is given is bound to retain a
sufficient part of the money payable under the contract to
satisfy the claim: s.11(1).
In the present case the appellants on 28 October 1991
duly gave their notices under s.10 both to the building owner
or employer QAS and to the head contractor Grossman Builders
Pty. Ltd. A number of other subcontractors also did so. One
was the first plaintiff Nick Favot Pty. Ltd. (which is the
first respondent on appeal), which gave its notices on 1
November 1991. Section 12(1) of the Act provides that a
subcontractor may recover the amount of the charge from the
person by whom the money subject to the charge is payable. An
action to enforce the charge was on 5 November 1991 commenced
by the plaintiff Nick Favot Pty. Ltd. against both the
employer and the head contractor. The action, which was
instituted in the Magistrates Court at Townsville, has since
been removed into the District Court and consolidated with
another such action transferred into that court.
Section 15(3) of the Act provides:
"(3) Every charge shall be deemed to be extinguished
unless the subcontractor duly commences a proceeding
under this section to enforce it."
What is meant by duly commencing a proceeding "under this
section" is to be gathered from s.15(1). Section 15(1)(a)
-- 5 of 15 --
4
provides, so far as material, that a proceeding in respect of
a charge under the Act is, in the case of a claim of charge in
respect of retention money only, to be commenced within four
months after the retention money is payable. In all other
cases, says s.15(1)(b), the proceedings:
"... shall be commenced within two months after
notice of claim of charge has been given pursuant to
section 10 and no later."
Section 15(1)(c) adds that a proceeding in respect of such a
charge "shall be brought by way of action".
Here no action as such was ever brought by the
appellants, whether within the period specified in s.15(1) or
otherwise. If s.15 was the only relevant provision, then the
conclusion would follow that the appellants' claim to a charge
under the Act must fail. By virtue of s.15(3) the charge
claimed would have been extinguished because of the
appellants' failure duly to commence proceedings under s.15 to
enforce the charge.
Section 15 is, however, not the only provision bearing on
the matter. There is also s.12(3), which is in the following
terms:
"(3)(a) An action to enforce a charge under this
Act may be brought by or on behalf of any number of
subcontractors claiming charges.
(b) Every action brought by a subcontractor to
enforce a charge shall be deemed to be brought on
behalf also of every other subcontractor who has
given notice of claim of charge pursuant to section
10 and who in accordance with rules of the Court and
-- 6 of 15 --
5
this Act becomes a party to the action. Subject to
any rules of the Court, every such subcontractor may
become a party at any time before the date appointed
for the hearing or any adjournment thereof (whether
or not he has given a notice of claim of charge) by
filing in the Court and serving on all other parties
in the same manner as if he were commencing the
action a statement of claim endorsed with a request
that he be joined as a party in the proceedings."
Section 12(3) is concerned with cases where, as so often
happens, there are many subcontractors interested in enforcing
a charge against money payable under the contract. In that
event an action may be brought by or on behalf of any number
of subcontractors who claim charges: s.12(3)(a), and
s.12(3)(b) expressly deems "every action" brought by a
subcontractor to enforce a charge "to be brought on behalf
also of every other subcontractor ...".
The statutory provision in s.12(3)(b) imposes a number of
qualifications or conditions that must be fulfilled before the
action is deemed so to be brought. First, the deeming
process operates only in favour of subcontractors who have
given notice of claim of charge under s.10. The applicants
satisfied this requirement on 28 October 1991. Secondly, it
is necessary that every such subcontractor should, "in
accordance with rules of Court and this Act", become a party
to the action. Thirdly, the subcontractor must become a party
before the date appointed for the hearing - which can only
refer to the hearing of the action - or any adjournment
thereof; but he may do so at any time before that date.
-- 7 of 15 --
6
Under s.12(3)(b) the procedure for being joined is by filing
in the Court and serving on all other parties, in the same
manner as if an action were being commenced, a statement of
claim endorsed with a request that the subcontractor be joined
as a party in the proceedings.
In Re Queensland Tiling Service Pty. Limited [1978] Qd.R.
142 Douglas J. was confronted with a matter in which three of
four claimants had failed to give the requisite notice of
claim of charge under s.10. The fourth claimant (Pettigrew
Engineering Pty. Ltd.) had given notice but had failed to
commence proceedings within the time limited by s.15(1). All
four contended that, by reason of the provisions of s.12(3) of
the Act they were not obliged to comply with any of these
requirements. His Honour held that all of the claimants
failed. In the form in which s.12(3)(b) stood at the relevant
time, it did not contain, in reference to "every other
subcontractor", the qualifying expression "who has given
notice of claim of charge pursuant to section 10", which was
inserted by legislative amendment in 1976. His Honour
nevertheless concluded that giving notice of claim of charge
was essential to the efficacy of the claims. He reached that
conclusion because of the presence of the words "who in
accordance with rules of the Court and this Act becomes a
party to the action", which appeared in the subsection then
and continue to do so. He considered that no valid
-- 8 of 15 --
7
distinction could be made in the case of the claimant
Pettigrew Engineering, which had given notice under s.10 but
had not commenced an action within the time stipulated in
s.15.
On behalf of the claimants in that case it was argued
that, because of s.12(3), they were entitled to disregard
ss.10 and 15 if, despite their not having complied with the
requirements of those two sections, there was an action in
being by a claimant who had so complied. The argument was
specifically rejected by Douglas J. in Re Queensland Tiling
Service Pty. Limited [1978] Qd.R. 142, 145. His Honour seems
there to have held (ibid. at 146) that s.12(3)(b) was
available only to subcontractors who were still within the
prescribed times for giving notice and commencing an action
even if they had not yet done so.
It was this particular aspect of that decision that was
followed and applied by Kneipp J. in Ex parte Collinsville
Buckhoe & Truck Hire [1985] 1 Qd.R. 233. The circumstances of
the claimants in that case were indistinguishable from those
of Pettigrew Engineering in Re Queensland Tiling Service Pty.
Limited or of the appellants in this. Notices of claim of
charge had been duly given but actions had not been commenced
by claimants within the period of two months specified in
s.15(1)(b), although such an action had been duly commenced by
another subcontractor. The applications of all the claimants
-- 9 of 15 --
8
to be joined in that action pursuant to s.12(3)(b) were
dismissed.
Apart from the authority afforded by the decision of
Douglas J. in the earlier case, there were primarily two
reasons that led Kneipp J. to his conclusion. One was that he
considered it "more consonant than not with the scheme of the
legislation that s.15 should be read as the dominant
provision". He considered s.12(3)(b) to be "procedural only
and designed to avoid a multiplicity of actions, rather than
to give additional rights to the subcontractor" ([1985] 1
Qd.R. 233, 235). The other reason he gave was that if
s.12(3)(b) was interpreted as contended for by the claimants
in that case, "a charge which has been extinguished by the
operation of s.15(3) may be revived at any time thereafter by
the fortuitous circumstance that the subcontractor has found
that there is another action to which he can become a party"
(ibid. at 235-236). Such an interpretation would, his Honour
thought, be quite unfair to employers who should, he
considered, be entitled to assume that the charge had been
extinguished if, despite a notice under s.10, no proceeding
had been commenced within two months.
As regards the last of these matters, it is not easy to
see why an employer should suppose the charge to be
extinguished simply because a particular subcontractor, who
has given notice under s.10, has not also brought proceedings
-- 10 of 15 --
9
individually, or has not yet taken steps to be joined in
proceedings brought by some other claimant. Preventing a
multiplicity of proceedings seems to be the particular aim or
object of s.12(3). To that end it encourages, but does not
compel (" ... may become a party"), subcontractors to become
parties to existing proceedings rather than to start actions
of their own to enforce the charge.
An employer knows that once notice under s.10 has been
given by a subcontractor, it becomes perilous to pay the
contract moneys to the head contractor if at least one
subcontractor commences proceedings within the times specified
in s.15(1). That imposes no disadvantage on the employer, who
is amply protected if (as was done in this instance) he pays
the amount into court in accordance with s.11(5) of the Act.
The real hardship is suffered by the head contractor, who
fails to get his money. However, in most cases (of which this
is one) the head contractor is in practice already insolvent,
which is why the charge is claimed.
As for the scheme of the legislation, there appears to be
no compelling reason why s.15 should be treated as the
dominant provision. At least that is so where more than one
subcontractor has given notice of claim of charge under s.10
and one of them commences proceedings in accordance with the
time limits prescribed in s.15(1). In that event "A
proceeding in respect of a charge under this Act" in s.15(1)
-- 11 of 15 --
10
would include an action "brought on behalf also of every other
subcontractor" within s.12(3)(b); with the consequence that,
provided a claimant has given notice of claim of charge
pursuant to s.10 and becomes a party to the action pursuant to
s.12(3)(b), the limitations stated in s.15(1) apply to that
action in respect of that claimant. It is irrelevant, on this
construction, whether that claimant becomes a party to the
action within the time stated in s.15(1) for commencement of
the action.
If s.12(3)(b) does not have the effect stated above,
there would be little obvious or useful purpose for it to
serve. Its only function would be to provide an optional
alternative procedure for commencing proceedings within the
comparatively narrow limits of time prescribed in s.15(1)(a)
and (b). A more rational explanation is that it is designed
to ensure, so far as possible, that all claimant
subcontractors become parties to a single action (preferably,
no doubt, the first of those instituted), which has been
commenced within the time allowed by s.15(1), to enforce the
charge. The advantages of encouraging such a course is that
all claimants and all claims against the contract moneys
(which in the end are almost invariably paid into court) can
be assembled in a single proceeding in which the claims can be
administered and the funds in court distributed among all
those interested. The same policy is evident in s.13,
-- 12 of 15 --
11
providing for consolidation of separate actions that are
brought in respect of work under the same contract.
Against these considerations of interpretation and
convenience, the most that can be said is that the terms of
s.15(3) are strong. Section 15(3) provides that every charge
is extinguished unless the subcontractor duly commences a
proceeding under this section to enforce it. However, for
reasons which we have expressed, we think that the subsection
includes within actions duly commenced by a subcontractor
those actions which are deemed to be brought on that
subcontractor's behalf.
For all these reasons we consider that the interpretation
placed upon ss.12(3) and 15 adopted in Re Queensland Tiling
Service Pty. Limited and Re Collinsville Buckhoe and Truck
Hire cannot, so far as concerns the question arising on this
appeal, be sustained.
That would ordinarily mean that the appeal in the present
case should be allowed. As has previously been said, the
appellants gave the requisite notices under s.10 on 28 October
1991, even if they did not commence an action to enforce the
charge or apply to be joined as a party until well after the
period of two months under s.15(1)(b) had expired. The
application they made on 2 April 1992 was an application under
s.12(3)(b) to be joined as a party to the action already
commenced by Nick Favot Pty. Ltd. on 5 November 1991 to
-- 13 of 15 --
12
enforce a claim to a charge under the Act. On the authority
of the two decisions referred to, the learned judge of
District Courts refused the application of the appellants.
Logically, the consequence should now be that the appeal
should be allowed and the order below reversed so that the
joinder can be effected. The respondent, however, objected
that the order below was not final but only interlocutory, and
that leave had not been granted to appeal to this Court.
While acknowledging that it is a question of some difficulty
whether the order appealed from is properly regarded as final
or interlocutory, we have reached the firm conclusion that the
matter is one in which leave to appeal, now sought by the
appellants, should be granted. The circumstance that the
matter has, as was predicted at the outset, proved to require
a close consideration of the correctness of two decisions of
the Supreme Court in a branch of the law that frequently falls
to be applied in courts of this State - often in cases of some
magnitude - is we think sufficient to justify the granting of
leave to appeal in this case.
The orders to be made will therefore be as follows.
Leave to appeal is granted. The appeal is allowed with costs.
The order made on 23 April 1992 dismissing the application
with costs is set aside. In lieu thereof it is ordered that
the applicants Glen Bird and Karen Bird trading as Bird's
Plumbing be joined as parties to action no. Misc.1 of 1992 in
-- 14 of 15 --
13
the District Court at Townsville between Nick Favot Pty. Ltd.
as plaintiff and Grossman Builders Pty. Ltd. as first
defendant. It is further ordered that the respondent pay the
appellants' costs of and incidental to the application to the
District Court.
The case is a proper one for a certificate in favour of
the respondent under the Appeal Costs Fund Act. We
accordingly order that such a certificate issue.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QCA/1992/339