Eamon Pty Ltd, Rador Pty Ltd & Blackedged Pty Ltd v Sanwa Home Australia (Formerly Balfield) Pty Ltd [1992] QCA 1
[1992] QCA 001
IN THE COURT OF APPEAL
OF THE SUPREME COURT
OF QUEENSLAND
Before The President
Mr Justice McPherson
Mr Justice Davies
NO. 690 OF 1991
BETWEEN:
EAMON PTY. LTD.
(First Plaintiff) First Respondent
AND: RADOR PTY. LTD.
(Second Plaintiff) Second Respondent
AND: BLACKEDGED PTY. LTD.
(Third Plaintiff) Third Respondent
AND: SANWA HOME AUSTRALIA (FORMERLY
BALFIELD) PTY. LTD.
(Defendant) Appellant
REASONS FOR JUDGMENT OF THE COURT
Delivered the 31st day of January, 1992
PRACTICE - STAY - Application by purchaser ordered to
perform contracts for stay of execution pending appeal to
High Court - whether Court has jurisdiction - whether
balance of convenience favours stay - whether stay ought be
granted in exercise of wider discretion.
Counsel: Mr D.F. Jackson Q.C. with Mr Sullivan for the
applicant
Mr O'Shea for the respondent
Solicitors: Morris Fletcher and Cross for the Applicant
Corrs Chambers Westgarth for the Respondent
Hearing date 28th January 1992
-- 1 of 5 --
IN THE COURT OF APPEAL
OF THE SUPREME COURT
OF QUEENSLAND
Before The President
Mr Justice McPherson
Mr Justice Davies
NO. 690 OF 1991
BETWEEN:
EAMON PTY. LTD.
(First Plaintiff) First Respondent
AND: RADOR PTY. LTD.
(Second Plaintiff) Second Respondent
AND: BLACKEDGED PTY. LTD.
(Third Plaintiff) Third Respondent
AND: SANWA HOME AUSTRALIA (FORMERLY
BALFIELD) PTY. LTD.
(Defendant) Appellant
REASONS FOR JUDGMENT OF THE COURT
Delivered the 31st day of January, 1992
The Applicant is a purchaser which has been ordered to
perform three contracts. A Judge of the Court declared that
the contracts are valid and subsisting and ought to be
specifically performed and carried into execution, an appeal
was dismissed by the Full Court and another Judge of the
Court subsequently made ancillary orders, including orders
for completion on 3rd February, 1992, and giving leave to
any party to give a notice making time of the essence.
The Applicant then changed solicitors and lodged an
application for special leave to appeal to the High Court of
Australia against the decision of the Full Court. The
application for special leave to appeal will not be heard
until April, 1992. The present application is for a stay of
execution of the judgment of the Full Court and the
-- 2 of 5 --
ancillary orders (which remain unchallenged), pending the
determination by the High Court of the application for
special leave to appeal.
The present application faces a number of obstacles which it
is unnecessary to consider. Thus, for example, the source
of this Court's jurisdiction and power to grant the stay was
not demonstrated, but appeared to be asserted to be either
sub-section 4(6) of the Judiciary Act, 1876, or the Court's
inherent jurisdiction: Jennings Constructions Ltd. v.
Burgundy Royale Investments Pty. Ltd. (No.1) (1986) 161 CLR
681. It was also contended without authority (unless the
proposition is implicit in the judgment in Manfal Pty. Ltd.
(In Liq.) v. Trade Practices Commission (1990) 65 ALR 256)
that the stay could be granted in respect of the ancillary
orders although the application for special leave to appeal
only relates to the decision of the Full Court. Nor was
authority cited in connection with the assertion that a stay
with an effective operation could be granted in respect of
the declaration that the contracts ought to be specifically
performed and carried into execution.
If such problems be put to one side and it also be assumed
in favour of the Applicant that it has a sufficient
prospect of success in the High Court, it remains for it to
demonstrate, at the very least, that the balance of
convenience lies in favour of granting the stay. More may
be necessary if, as is sometimes suggested, a stay should
only be granted in exceptional circumstances.
It was not submitted by the Applicant that the balance of
convenience favours every purchaser ordered to perform a
contract by a date which will pass before an appeal is
determined. The additional consideration in this instance
was said to be the ancillary order giving leave for a party
to give a notice making time of the essence. It was
submitted that, in such circumstances, if the applicant
completed the contracts on 3 February in accordance with the
ancillary orders, the High Court proceedings would be
-- 3 of 5 --
nugatory if the applicant was granted special leave to
appeal and succeeded on the appeal because the Applicant's
"voluntary" completion of the contracts would preclude the
grant of effective relief by the High Court.
The Court was told that no authority could be found either
in favour of or against this rather surprising contention
which seems neither logical nor correct in principle.
Indeed, the Applicant's premise implicitly contradicts its
need for a stay, at least at this time. If the Applicant is
not obliged to perform the contracts until a time for
completion is effectively established by a notice making
time of the essence, the operation of the ancillary orders
need not be stayed in order to protect the Applicant's
possibility of an effective judgment in the High Court. If,
on the other hand, the Applicant is obliged to complete the
ancillary orders either on 3 February or on whatever date is
fixed by a notice making time of the essence, then its
position is no different from any other purchaser obliged to
complete in accordance with an order of the court
notwithstanding the existence of an appeal. If it parts
with the purchase moneys on settlement it will receive in
return a title to the land purchased. In either event, a
stay is inappropriate.
The conclusion that the application should fail is
reinforced by other considerations if a wider discretion is
involved.
For example, some of the ancillary orders, including the
order fixing 3 February as the date for completion, were
made by consent or at least without objection. Further,
some of the obligations imposed upon the Respondents by the
ancillary orders have already been performed. In
particular, the hotel formerly situated on the subject land
has been demolished by the Respondents in accordance with
the terms of the contracts and the order. It is unnecessary
to pursue other matters, such as the Court's continued
control of the performance of the contracts, including the
-- 4 of 5 --
time for completion, and its power to determine what, in all
the circumstances, is a reasonable period if a notice is
given purporting to make time of the essence.
The application is dismissed, with costs.