Corbett, Corbett, Nashtown Pty Ltd, Fandoan Pty Ltd & Anor v Wright & Francey Pty Ltd & Ors [1991] QSC 353
IN
THE SUPREME
COURT
OF QUEENSLAND
Before
Mr.
Acting
Justice
Robin
BETWEEN:
ANDREW
NEVILLE CORBETT
AND:
JOHN
LAWRENCE
CORBETT
NASHTOWN
PTY. LTD.
FANDOAN
PTY. LTD.
AND:
CORBETT ENTERPRISES
WRIGHT
&
FRANCEY
PTY. LTD.
GEOFFREY
ALEC WRIGHT
GREGORY
WILLIAM EICHHORN
No.
1169
of
1989
First Plaintiff
Second
Plaintiff
Third
Plaintiff
Fourth
Plaintiff
Fifth
Plaintiff
First
Defendant
Second
Defendant
Third
Defendant
REASONS
FOR JUDGMENT
- ROBIN
A.J.
Delivered the
3rd
day
of
December,
1991
CATCHWORDS
Negligent misstatement inducing investment
in
marina system
-
Allegedly represented as "fully
engineered"
etc.
-
Whether
representations
made -
Whether
misleading
-
Reliance
-
How
far
cause
of
plaintiffs'
loss
-
Whether
windfall to plaintiffs
from
sale of
a
successor business goes
to
reduce
damages
-
Relevant
principles
of
law
as
to mitigation
- Law
Reform
(Tortfeasors Contribution, Contributory Negligence
etc.)
Act
s.
10
considered
Counsel:
Mr. Bowden
for
plaintiffs
Mr.
Carrigan for defendants
Solicitors:
Feez Ruthning for plaintiffs
Short Punch &
Greatorix for defendants
Hearing dates: 15-18, 21-25, 28-31 October, 1, 4-7, 12-15 and
18 November, 1991
-- 1 of 115 --
IN THE SUPREME COURT
OF QUEENSLAND
BETWEEN:
AND:
No. 1169 of 1989
ANDREW NEVILLE CORBETT
First Plaintiff
JOHN LAWRENCE CORBETT
Second Plaintiff
NASHTOWN PTY. LTD.
Third Plaintiff
FANDOAN PTY. LTD.
Fourth Plaintiff
CORBETT ENTERPRISES
Fifth Plaintiff
WRIGHT & FRANCEY PTY. LTD.
First Defendant
GEOFFREY ALEC WRIGHT
Second Defendant
GREGORY WILLIAM EICHHORN
Third Defendant
REASONS FOR JUDGMENT - ROBIN A.J.
Delivered the Third day of December, 1991.
-- 2 of 115 --
2
INTRODUCTION
·
This
is
an
action arising out of
an investment
by way
of
a
large
number
of contributions
by
the
plaintiffs
who
claim
their
money was
wasted.
It
went
into
a
business called
Offshore Marinas
Australia
(
"O.M.A.
II),
which
the
third
defendant
founded
in
1976. The
defendants' asserted
liability
to
make
good any
loss
is
based
on
a
series of continuing
negligent misrepresentations as to the merits of
a
marina
system
devised
by
the
third
defendant
and
said (for
example)
to
have been
"fully
engineered"
by
the
second
defendant; the
negligence
is
said to
be demonstrated because
the
plaintiffs
can prove
the engineering
of the
system
was
defective, as the
defendants should
have
known. The
plaintiffs
found
their
claim
on Lord Denning'
s
famous
dictum
in
Esso Petroleum
Co.
Ltd. v.
Marden
(1976)
1
Q.B.
801, 820:
"If
a man, who
has
or
professes
to
have
special
knowledge
or
skill,
makes
a
representation
by
virtue
thereof
to
another
-
be
it
advice, information
or
opinion
-
with
the
intention of
inducing
him
to
enter into
a
contract
with
him,
he
is
under
a
duty
to
use
reasonable
care
to
see
that
therepresentation
is
correct,
and
that
the
advice,
information
or opinion
is
reliable.
If
he
negligently
gives
unsound
advice
or
misleading
information
or
expresses
an
erroneous
opinion,
and
thereby
induces
the
other side to enter into
a
contract
with
him,
he
is
liable
in
damages."
As
examples
of
liability
for pre-contract representations
they
cited:
Halliday
v.
Johnson
(1985)
2
N.Z.L.R.
563;
Thompson
v.
Henderson
Partners
Pty
Ltd
(1989)
51
S.A.S.R.
431;
New
Zealand
Motor
Bodies Ltd v.
Emslie
(1985)
2
N.Z.L.R.
569;
Norris v.
Sibberas
(1990)
V.R.
161,
171;
and
Roots
v.
Oentory
(1983)
2
Qd.R.
754.
-- 3 of 115 --
3
The
defendants deny
that representations
were made
in the
glowing· and
absolute terms alleged,
and deny
reliance
(
for
reasons associated with timing
and
alternatively
on
the basis
that
it
was
the
first plaintiff's situation
and
activities
and/or expectations of
quick
profit
which
explained the
investments); they
deny
that
there
was
any
relevant
duty
of
care
upon them, and deny
that
the
plaintiffs lost
as
much
as
they claim,
or
(if
it
comes
to that)
anything.
They deny
that
the engineering of the
marina system
was
defective;
a
good
deal of the
evidence
was
devoted
to that issue.
The
history will
begin
to
emerge by
a
discussion of the
dramatis personae.
THE
PARTIES
Andrew
Neville Corbett
The
first
plaintiff,
when
the action
commenced
on
10th
April
1989,
was Andrew
Neville Corbett. Tragically,
he
died,
aged 50, on
1
st
June
1989 from
multiple inoperable
brain
tumours,
diagnosed
in
March,
after
he had been unwell
for
a
month
or
so.
Mr.
Corbett's estate
has
been
represented
in
the
action
by
his
brother, the
second
plaintiff.
He
qualified
as
a
dentist,
but during
the
1980's
became
interested in
various
commercial
ventures
to
do
with
mining,
especially for
gold,
metallurgical-type
processes
and
the
like;
he had
earthmoving
equipment.
The
O.M.A.
adventure
grew
out
of
his
earthmoving
activities,
specifically in
a
development
at
Repulse
Bay,
in
Queensland,
which
it
was
thought
might
include
a
marina.
The
prospect
of
co-operation
at
Repulse
Bay
brought
Mr.
Corbett
and
Mr.
Eichhorn
together
in
late
1986.
At
that
stage
they
I '
-- 4 of 115 --
4
got
on
well together; they became
partners in the O.M.A.
business
by
early
1987 and remained so
until late in the year
when
clashes
between them which can probably be blamed on
personality conflicts led to
Mr.
Eichhorn's exclusion.
Mr.
Corbett's
involvement
in the marina
industry switched
from
O.
M.A.
to Invincible
Marina Systems
Pty. Ltd.
("I.
M.
S.
")
in
1988
sometime. Speaking
broadly,
I
.M. S.
sold out
to
C. S
.R.
Humes
Pty. Ltd.
in
March 1989,
when
any
further
involvement
by
Mr.
Corbett
was
to
be
as
a
manager
or consultant for
that
company.
When
he
realised
he
was
suffering
from
a
terminal
condition,
Mr.
Corbett
opted
to
take treatment
based
on
steroids
which
would
not
impede
the progress of the
tumours,
but
would
give
him
the best available quality of
life
(
including
intellectual
function,
specifically)
for
whatever
time
he had
left.
He
did
not
remain
in hospital,
but returned
to his
home.
Perhaps remarkably, he
must have
devoted
a
good
deal of
his
energies
to
this
action,
recorded,
in particular.
This
was
lengthy
affidavit,
with
voluminous
to
having
his
evidence
done
in
the
form
of
a
exhibits.
Much
of the
drafting
was
his
own.
Master Horton Q.
C. made
an
order
for
his
evidence
to
be
taken
on
Commission
under
Part
2
of
0.
40.
Cross-examination
was
confined
to
some
extent
by
the Master's
order.
It
took
place
on
two
days,
on
13th
April
1989
before
Mr.
King-Scott
of
counsel
and on
18th
April before
Ms.
O'Reilly
of
counsel,
at
Broadbeach
Waters, presumably
in
Mr.
Corbett's
home. The
affidavit
is
ex.
1
before
me,
and
the
transcripts
of
Mr.
Corbett's
evidence
are
ex.
2
and
ex. 3.
-- 5 of 115 --
5
The procedure placed the defendants in
some
difficulty.
There were no
pleadings available
when
they had
to
conduct
cross-examination,
and they had very limited time within
which
to digest
hundreds
of
pages
of material,
and
to give
instructions for cross-examination.
I
am
alive to the
disadvantage created.
The
defendants are,
I
think,
entitled
to
some
compensating
indulgence, for
example
in
being allowed
to
adduce evidence
of matters, notwithstanding
that
they
were
not
put.to
Mr.
Corbett
in April
1989.
Evidence
was
presented
by
both
sides bearing
upon
the
ability
of
Mr.
Corbett
to
give
competent
or accurate
evidence
in
March
and
April
1989.
Unfortunately,
none
of the doctors
specially called
on
this
issue
saw
very
much
of
Mr.
Corbett
at
all.
Even
the general
practitioner,
Dr.
Hoffman, saw him
only
once
a week from
the
end
of
March
or early
April;
he had
not
previously
known Mr.
Corbett.
He
says
he
has
no
doubt
Mr.
Corbett
was
capable
of
giving
clear,
accurate
and
intelligent
evidence
on
the
13th
and
18th
April
1989.
The
specialists
who saw him
in
March
(
but not afterwards)
were
more
doubtful.
It
seems
to
me
that
it
is
appropriate for
me
to
read exs.
1,
2
and
3
with
that
medical evidence
in
mind,
but,
as
a
general
rule, to
accept
Mr.
Corbett's
evidence
as
competent
where
it
is
coherent
and
responsive
to
the question
being addressed.
That does
not necessarily
make
it
reliable.
The
transcripts
show
that
Mr.
Corbett
felt
himself
under
a
disability
in
respect of
reading.
He
wished
to
have
documents
read out
to
him, upon which
his
comments
were
sought.
I
have
a
clear
impression
that
his
chronology
is
-- 6 of 115 --
6
unreliable,
and
his ordering of events.
As
is also the case
with Messrs. Eichhorn and Wright,
I
think
he
is
unclear as to
what
transpired at
any
particular
meeting.
I
think he
is
unreliable as to
whether
particular
statements
were
made by
Mr.
Wright
or
by Mr.
Eichhorn,
and
that there
is
confusion
in
his
mind
between
things those
gentlemen
actually said,
and
Mr.
Corbett's
own
impressions,
or
paraphrases
of things said.
Even
in his affidavit,
Mr.
Corbett's failure to
adhere
to
a
sensible chronological order leads
to significant
confusion
and doubt
as
to
what
precisely
is
his
evidence. That assumes
importance
given
that
the
plaintiffs'
case
depends upon
their
having
a
state
of
mind
reliant
upon
the defendants'
representations
accompanying
each
commitment
of expenditure
of
funds
to
O.M.A.
over
more
than
a
year.
Nashtown
Pty. Ltd.
The
third
plaintiff,
Nashtown
Pty.
Ltd.
is
Mr.
Andrew
Corbett's
company.
No
attempt
has been
made
to distinguish
between
moneys
put
into
O. M.A.
by
it
and
Mr.
Corbett's
own
moneys. The
parties
were
content
with
that
approach.
Dr.
Corbett
The
second
plaintiff,
Dr. John Laurence
Corbett
had
a
distinguished
academic
career in
medicine,
whose
high
points
included completing
a
Ph.D.
at
Oxford
University
on
a
Rhodes
Scholarship.
He
specialised
as
a
neurologist
until
1985
and
then
launched
a new
career
in
business,
which
has
been most
successful.
From
his
point of
view
his
investment
in
O.M.A.
was
exceptional
in
the
sense
of
being
a
failure.
As
will
be
seen,
my
assessment
is
that
this
investment
may
well
have
been
-- 7 of 115 --
turned to profitable account,
Dr.
Corbett's business
skills
7
and
offers another instance of
in acton. His evidence
was
credible
and
reliable in
most
respects, this arising
from
his
use of very
full
notes of telephone conversations
which he has
kept over the years. Otherwise,
his recollection
was
imperfect
in
cross-examination
transcript.
some
respects, as
Mr.
revealed.
See pp.
110
and
Carrigan's
162
of the
Dr.
Corbett
was
rather aloof
from
the action
itself.
He
was
living in
the
South
at
all
relevant
times,
and
preoccupied
with
his
business
interests
which
involved
many
companies.
He
was
not
particularly interested in
the
O.M.A.
venture
which
was
too small
from
the standpoint of
some
at least
of the
entities
with venture
capital
in
which he had
influence.
It
may
be
accepted
that,
at
least
before the crash of
October
19th,
1987,
if
he
wished
to
make money,
he could
do
it
much
more
simply
and
quickly
on
the stock
exchange
than through
a
venture
like
O.M.A.
-
so
he
informed
the
third
defendant.
What
Dr.
Corbett
knew
of
O.M.A.
came
essentially
from
his
brother
Andrew,
the
first
plaintiff.
The
aspect of the
defendants'
representations
being repeated
by
Mr.
Corbett
aroused
little
controversy.
For an analogy
in deceit
cases
see Pollock
on
Torts
(15th)
220.
Dr.
Corbett
had
been
making
contributions
of
a
kind
to
O.M.A.,
according
to
Mr.
Corbett,
by
putting
him
in
funds
which
he
lacked himself
from
time
to
time,
to
meet
O.M.A.
liabilities,
from
fairly
early in
1987.
His
main
contributions
began
at
the
beginning
of
June,
1987.
r t
-- 8 of 115 --
8
Fandoan Pty. Ltd.
The third plaintiff, Fandoan Pty. Ltd. is a company of
the second plaintiff's. It played no active part in the
action. Its name surfaced in November 1987 as the vehicle
whereby Dr. Corbett would effectively take over sole control
of O.M.A. in a scheme which Mr. Corbett and Mr. Eichhorn
agreed to, but whose implementation has not really been
established. The plaintiffs have generated documents which
are consistent with a takeover at dates both before and after
November 1987. Some at least, of O.M.A. 's property passed
through Fandoan Pty. Ltd. to another Corbett Company,
Invincible Marina Systems Pty. Ltd. ("I.M.S."). Fandoan
Pty. Ltd. does not claim, in the action, to have been
damnified by reliance upon any conduct of the defendants.
They, however, contend that its participation makes it
necessary that the plaintiffs bring to account a substantial
sum of money obtained by I.M.S. when it sold a marina
"invention" to C.S.R. Humes Limited in March 1989.
Corbett Enterprises Pty. Ltd.
Corbett Enterprises Pty. Ltd., the fifth plaintiff, was
not a party as the action was originally constituted. It is
the second plaintiff, Dr. Corbett's company. The evidence
shows that he always had in mind that the fifth plaintiff
would be the one, among many companies of his, which should
invest in O.M.A. For the first couple of months, Dr. Corbett
made contributions, consistently with a notion that "he"
should put in up to $100,000.00 to acquire a certain equity.
Then the fifth plaintiff took over in August 1987, at a time
-- 9 of 115 --
9
when
the $100,000.00 figure had been reached. Dr. Corbett
wished to attribute all
of the contributions to the
company,
including
some
under obligations
which he undertook
in respect
of chattel leases in
October 1987.
The
defendants raised
no
objection. In the circumstances
I am
content to regard the
first plaintiff
as the investor,
and
to
accord
to
it
the
benefit of
any
cause
of action for negligent
misstatement
which Dr.
Corbett
may
have.
UNSATISFACTORY FEATURES
OF THE
EVIDENCE
Some
peculiar features of the
evidence given
at
the
trial
have
made
identification
of the facts
unusually
difficult.
Many
of the
significant
events
happened
four
and
a
half
or
five
years
before the
trial.
The
parties
who
gave
evidence
have
imperfect
recollection
and
appear
to
me
to
have
coloured
their
.accounts
in
light
of
their
personal
views
of the
rights
and
wrongs
of the
situation.
I
do
not find
any
of
them
deliberately dishonest.
Mr.
Wright and
Mr.
Eichhorn,
who
tended
to
say they
presented the
O.M.A.
system
to
the Corbetts
in
terms
of
its
being only
an
untested
"concept"
in
an
embryonic
stage,
claimed
to
be under
a
disability
because
of
non-access
to
O.M.A.
's
documents
after
November
1987,
when
Mr.
Eichhorn
was
excluded.
That
led to
Mr.
Wright's
excluding
himself,
in
sympathy.
On
the
plaintiff's
side,
Dr.
Corbett
was
isolated
from
events,
partly
by
circumstances,
partly
by
his
own
choice;
he
essentially
knew
only
what
his
brother
told
him; he
refrained
from
making
independent
inquiries.
I
am
unable
to
make much
of
the
many
claims
made
by
the
Corbetts
that
they
were
not
' <
-- 10 of 115 --
10
told or warned
of various matters; to
make a
case they must
rely
on
events which
did happen,
rather than events
which
did
not
happen. Andrew
Corbett's
evidence, necessarily given on
affidavit
and commission when
the action
was
very
new,
creates
particular
problems.
He
has been denied the opportunity to
have
his
say
on
the issues as
finally litigated.
( I
observe
that
the
plaintiff's
pleadings
have
largely taken
up
the parts
of his
affidavit).
On
the other
hand,
the defendants not only
have
not
had
a
fair
opportunity to
cross-examine
Mr.
Corbett,
they
are
at
a
disadvantage
in
making
submissions
as
to his
credit
since
I
have
not seen
and
heard
him
in the witness
box.
In
principle,
if
there
is
to
be
a
prejudice
to
either
side
from
Mr.
Corbett's
unfortunate death,
it
seems
to
me
it
ought
not to
work
against the defendants.
I
hasten
to
add
that
I
do
not consider
a
great
deal has turned
on any
discounting of
Mr.
Corbett's
evidence so
far
as the
outcome
of the
action
goes;
if
he had
appreciated the
need
for
it,
he
might have been
able
to
give evidence
useful
to
the
plaintiffs
as
to
the
relations
between
the businesses
of
O.M.A.
and
Invincible
Marina
Systems
Pty.
Ltd.
Mr.
Corbett's
evidence
was,
in
my
view,
coloured
by
his
personal
standpoint
just
as
much
as
that
of the other
parties.
Dr.
Corbett's
notes
of
phone
calls
and
other writings
I
take
as
reliable.
I
have found
the
documents
tendered very
useful,
and
take
them
as
a
reliable
indicator
of
events
and
attitudes
of
participants,
(except
where
doubt
or reservation
is
expressed
in
these
reasons).
-- 11 of 115 --
1 1
Two
particular reservations
I mention here.
The
evidence
shows·
that the dates of plans produced by
the
Computer Aided
Drafting
System employed
in
O.M.A.
's
business are not
reliable, in that details of
drawings
may
have been
altered
after
the date of
an
original
drawing, without the appropriate
later
date being incorporated.
Next,
the
plaintiffs set
considerable
store
by
recitals
in
"agreements"
dated 20th
May,
1987
which formed
part of
ex.
12,
Mr.
Corbett's
bundle
of
written material sent to influence
Dr.
Corbett.
One
says
"the
parties
(which,
I
interpolate,
would
include the
third
plaintiff)
have
jointly
developed
a
unique marina system".
The
second
refers
to
a
bridging
loan taken
out
"in order to
facilitate
the
immediate
commencement
of construction
on
various items
of
production
equipment".
The
second
and
third
defendants
have
signed both
documents;
Mr. Bowden,
appearing
for
the
plaintiffs
says
this
connects
the
defendants
in
some
way
to
.the
recitals
as
representations to
the Corbetts.
I
disagree.
I
find
that
these
documents (which
describe
transactions
apparently never
implemented) were drawn by
or
on
the
instructions
of
Mr.
Corbett,
and
are
more
fairly
regarded
as
representations
by
him.
He
has
signed
the
first
document
as
a
director
of
his
company,
Pocket
Valley Pty. Ltd.
(envisaged
as
transferee
from
the
third
plaintiff
and
the
second
and
third
defendants
of
the
marina system)
and
he
has
initialled
the
pages
(prior to
the execution
page)
of
the
second.
My
view
of
the defendants' signing
is
that
they
were
simply
obliging
Mr.
Corbett
by
completing
documents he
was
interested in
having
signed,
and
that
they
had no
intention or
-- 12 of 115 --
12
consciousness of
making
representations thereby. Dr. Corbett
could not have been influenced too
much by them; he'knew
that
the investors
whose
participation the
documents were
calculated to
implement were no
longer
interested.
A
document
of
some
interest is
· a
letter
of Proctor,
Doumany & Co.
of 12th February,
1988
to
Mr.
Eichhorn's
solicitors.
It
is part
of
ex.
31
and
purports to
be
written
on
behalf of
"Offshore Marinas", although
Dr.
Corbett
in
ex.
32 showed
little
interest
in certain aspects of the
letter,
which he seems
to
have
regarded
as
Mr.
Corbett's
affair.
The
letter
of
12th February
includes the
following
in
a
long
list
of
complaints about
Mr.
Eichhorn:
"3.
Your
client
made
certain
representations to
my
client
in relation to
the design
of
Offshore
Marinas,
and
upon
examination
of
your
client's
design, our
client
is
now
of the opinion
that
the design
simply does
not
work.
During
the
period
that
your
client
was
associated
with
Offshore Marinas,
he
received the
sum
of
$600.
00
per
week,
and had
the
free
use
of
a
number
of vehicles.
In the
three
months
prior
to
Christmas,
your
client
ran another business
and
attended.
at
our
client's
premises
for
limited
hours each day.
Our
client
is
presently
considering
its
rights in relation to
this
matter."
Dr.
Corbett
was
informed
of
this
allegation
but did not take
it
up,
perhaps because
he
was
negotiating
terms
with
Mr.
Eichhorn. This
is
the
first
and
only
suggestion before
action
that
any
of the
plaintiffs felt
the victim
of
any
misrepresentation. Neither
of
the Corbetts
struck
me
as
likely
to
be
reticent
if
he
harboured
any
such
feeling.
There
is
no
evidence
that
either
did,
certainly
none
of
a
complaint
to
any
of the
defendants.
Dr.
Corbett
did
not confront
Mr.
Wright
in
accusatory
mode
after
receipt of
Mr.
Gallagher's
-- 13 of 115 --
13
critical
report.
assistance with
in late
a
view
February 1988,
rather
to selling
an
O.M.A.
sought his
Marina
to
Mr.
Lubrano.
One
of the factors
which
I
take into
account
is
the
plaintiffs' failure to
demonstrate
the outrage
commonly
shown by
experienced business people
who
have
lost
a
lot
of
money
through
reliance
on
misrepresentations.
Mr.
Eichhorn and
his
Offshore
Marina
concept
The
third
defendant,
Mr.
Eichhorn, has
a
long
association
with boating
and
marinas, but
no
formal
engineering
or other
qualifications.
He
is
a
designer of
marina
layouts,
and
of
facilities
incorporated
in
marinas;
he
established
a
career
as
a
consultant
to
developers
interested in constructing
marinas,
and
over
the years
he
has devised
and
sought
to
promote marina
projects,
notably
an
ambitious
one
(
described
in
ex.
8)
at
Rose
Bay
in
Sydney
Harbour.
From
about
1976
Mr.
Eichhorn
had
been concerned
with proposals
for
marinas
in
various locations
in
North Queensland
and on
the
Gold
Coast.
The
name
"Offshore
Marinas"
describes
his
idea
of
housing
floating structures
offshore,
which
situations
where
suitable
land
was
marina
facilities
in
was
attractive
in
unavailable.
Other
projects
Mr.
Eichhorn
was
engaged
in
were
for
marinas
to
be
constructed
in specially
excavated
locations.
Lacking
drafting
skills,
Mr.
Eichhorn
engaged
the
services of
a
draftsman
who
drew up
layouts
and
other
plans
for
him.
In
1977
or
thereabouts,
he
met
the
second
defendant,
Mr.
Wright,
who
was
engaged
"to
do some
calculations".
Mr.
Wright
was
then
in
partnership
with
Mr.
Francey;
this
firm
"actually
prepared
the cross sections"
in
respect of
the
-- 14 of 115 --
14
components
of the marina systems.
To promote the system,
Mr.
Eichhorn needed
a more
professional presentation than
merely
his
own
sketches; he needed dimensioned plans
and what
came
to
be
called isometric drawings.
Mr.
Eichhorn's idea
was
to
have
a
modular system,
sections
(whose
appeal
based
on
prestressed concrete
deck
lay in
their
proposed
strength)
Initially,
these
floats
were
to
be
supported
on
floats.
concrete
boxes
or "coffins", the
lid
being the
deck
section.
The
cost
and
risk
of transporting concrete tanks
to
remote
locations
emerged
as
a
problem
when Mr.
Eichhorn
was
tendering for
development
of
a
marina
at
Port
Douglas.
Recalling
a
project
he
knew
in
Sydney,
Mr.
Eichhorn decided
to
change
his
system
by
replacing concrete tanks with closed
polyethylene tanks ("P.E.
tanks"),
on
a
number
of
which
the
concrete
deck
sections
would
rest.
Although
Mr.
Eichhorn
says
he
won
the tender the
marina
was
never
built;
he blames
the
difficulty
of obtaining finance
for
such an
isolated
and
unknown
place as Port
Douglas
was a
decade ago, and
a
deteriorating
economic
climate generally.
Mr.
Wright
helped
with
the engineering aspects
of
the
project.
His
firm,
Wright
&
Francey
is
shown
in
the Port
Douglas
Marina
tender
of
May
1982
(ex.
10)
as
consulting
engineers;
there
is
no
reference
to
them
in
the
accompanying
plans, but
Mr.
Wright
is
named
as
co-designer
of
a
catwalk
for
the
marina
in
plans
of
21
.
4.
83
forming
part
of
ex. 9.
By
this
date the
realisation
had
sunk
in
that
it
was
a
matter
of great uncertainty
whether
any
marina
project
could
be
got
up
and
running
and
that
paying
for
engineering
services in
connection with
proposals
that
might
-- 15 of 115 --
15
not get
anywhere was beyond Mr.
Eichhorn'
s
resources.
A
gentleman's agreement was made
between two men whereby
Mr.
Wright would
not charge for engineering services, but
if
any
proposal
went ahead, he would have an
equity. This
appears
to
have been
fixed
at
6
per cent, probably
by
reference to
some
scale of
charging.
Another
project
running
at
about
the
same
time
which
got
a
considerable distance
was
for
a
marina
in
the Brisbane River
at
Kangaroo
Point,
in
connection with
a
residential
development.
The
building did not
go
ahead,
after
an
unfavourable
outcome
of
Local
Government
Court proceedings;
that
put paid
to
the
marina
project.
However,
official
approval
of the
marina
was
obtained,
after
a
good
deal of
effort
by
Mr.
Eichhorn
and
Mr.
Wright and
various consultants
they brought
in.
Exhibit
83
contains the
approved
plans,
many
of
which have been
signed
by
Mr.
Wright
as personally
checked
by
him.
On
17th February
1982,
the Port of
Brisbane
Authority
wrote
to
O.M.A.:
"A
further
examination
has been
made
of the
basic
design
criteria.
In
summary,
the basic
design loads
were:-
1 ) Wind
load:
-
(a)
concurrent
with flood
-
34
metres/second
(b)
wind
only
-
46.5
metres/second
2)
Flood
velocities
of
3
metres/second
Tidal
velocities
of
1
metre/secondDebris loading
and
log
impact
is
includedas
part
of
flood loading.
3)
Maximum
berthing
loaddisplacement
vessel
metres/second.
of
a
impacting
28
at
tonne
.75
-- 16 of 115 --
16
4) Wave loads due to large passing craft.
5) Dead load and live load of 3 kPa.
6) Loading assumes a marina occupancy of 100% but
shielding is provided in certain cases of wind
and flood flow. Craft adopted is 50% sail and
50% power.
Load case combinations examined have been:-
i) Maximum wind plus tidal flow in the same
direction.
ii) Maximum wind perpendicular to the bank.
iii) Floor flow plus wind in parallel direction.
iv) Wave action on an arm
v) Berthing load on a finger.
vi) Mooring loads on piles (flood case).
Examination of the design indicates that the general
principles are acceptable al though some minor
modifications may be required and these can be
carried out during the detail stage. The above
would satisfy the Port of Brisbane Authority but the
design will need Section 86 approval which is
administered by the Department of Harbours and
Marine.
The Port of Brisbane Authority is prepared to offer
tenure subject to Section 86 approval being obtained
from the Department of Harbours and Marine."
Such an approval was obtained. It is in a letter of 11th
November, 1982 which I refer to elsewhere.
At this stage the marina system O.M.A. was promoting
consisted of "arm" units 1800 millimetres wide and 8880
millimetres long. A covered duct or channel to accommodate
services ran the length of each section. The 100 mm. thick
d~cks were to be of pre-stressed reinforced concrete, with
outside legs of 300 mm. resting on polyethylene tanks (seven
per section) . The arm sections were to be rigidly joined
together by post tensioning cables or rods in groups of three
and two. Berths for boats were to be provided by pairs of
opposed "fingers", either long (7520 mm) ·or short (5740 mm).
-- 17 of 115 --
17
These had a
flare at the
end
to
be fixed to the
arm and the
opposing finger
and
that fixing
was
to
be
a
rigid
cons·truction
by means
of post-tensioning rods passing through conduits in
diaphragms provided underneath the decks.
Each
rod
would
traverse the length of
two
flares
and
the interposed
arm.
The
fingers
were
a
metre
or
so
wide beyond
the flares,
and
the
decks
were
similar in
thickness,
and
as
to their
legs, to
the
arm
decks.
The
whole
was
to
be
supported
in the
water
by
standard closed polyethylene tanks,
whose
dimensions enabled
them
to
fit
end
to
end under
the fingers,
and
side to side
under the
arms
.
That
Mr.
Wright and
Mr.
Eichhorn envisaged
their
modules
being
rigidly
held together
by
post tensioning
of
three
arm
units
and
three
pairs of
opposed
fingers
likewise
rigidly
fixed
at right
angles
to their
arms by
post-tensioning
seems
to
me
inescapable.
This
would
produce
rigid
sections of
arms
(
or
widthways)
of
2 7
metres
in length,
or
thereabouts,
with fingers
rigidly
attached.
The
walkways
could
be
lengthened,
by
addition of other sections
up
to
27
metres
in
length,
joined
by means
of
hinges.
This
would
introduce
an
element
of
flexibility.
The
official
publication
on
14th
May 1981
of
Mr.
Eichhorn's
International
Patent
Application
(which
related to
a
floating
marina
consisting of
a
central
limb and
radiating
arms)
included the
following:
"
Preferably
one
or
more
of the
buoyant
arm
portions
comprise
a
plurality
of
outwardly·
extending
buoyant
finger portions
to
define
mooring
areas for
marine
vessels
adjacent
said
arm
portions.
Preferably,
the
plurality
of
joined
predetermined
intervals.
arm
portions
comprise
members
articulated
a
at
-- 18 of 115 --
Preferably, theplurality of
members
joining
means.
18
arm
portions comprise
a
joined
by
post-tensioned
Preferably, the post-tensioned joining
means
extends
from
the
main
portion to Join thearticulated
members
in
end
to
end
relationship
and
said
main
portion to said articulated
members.
Preferably the finger portions are retained in
opposed
relationship
on each
side of
an
arm
portion
by
post-tensioned joining
members.
Preferably the
main
portion,
arm
portions
and
finger portions
comprise
essentially
hollow
membersformed from
fibre
reinforced concrete.
Preferably
the
arm
portions
comprise
ductspositioned
in
the region
of the geometric
centre
thereof
to locate
the post-tensioned joining
means.
the post-tensioned joining
means
preferably
comprises
a
post-tensioned cable.
Preferably
the
means
for
anchoring
thestructure to
the
seabed comprises
a
plurality
of
anchors connected
by
an
extendable
shock
absorbinglinkage
to suitable positions
on
said structure to
permit
even
load
distribution
on
the
structure
regardless of
tidal
conditions and/
or direction of
waves
and
prevailing
weather."
The
system
I
have
described
may
be
contrasted
with
Mr.
Eichhorn's
original
idea of
an
all
concrete
system.
Mr.
Wright's
drawings
for
this
may
be found
in
various places
in
the evidence
-
for
example one drawn
in
April
1979
is at
page
14
of
ex.
ANC-1
to
Ex
1.
The
plaintiff
Andrew
Neville
Corbett claimed
it
was shown
to
him
with
other
documents on
24th
November, 1986
by
Messrs. Wright
and
Eichhorn;
the
plaintiff
John
Lawrence
Corbett
swore
another
one
was shown
to
him by
Mr.
Eichhorn
in
April
1987
(ex.
4).
Mr. A.
Corbett
says
that
one
(ANC-2,
page
102)
was
shown
to
him
on
28th
November,
1986.
The
fingers
were
designed
in
lengths
of
7500,
11250
and
15000
millimetres,
tapered
for
a
length of
7500
mms.
-- 19 of 115 --
19
in each case; the
arms were apparently envisaged in
15 metre
lengths.
The O.M.A.
product continued to
change, and
in particular
(after
the
plaintiffs' first
involvement) an
enlarged version
of the polyethylene tank system
was "drawn" (by
a
computer
assisted drafting facility)
and
named
"System 2";
the
hope
was
that
it
would be
effective in locations like
Sydney Harbour
where
conditions required
a
heavier
system.
As
for
System
1,
the fingers
were
redesigned, so
that
the
flares
ceased
to
have
any
further structural role
-
the post-tensioning fixing to
the
arm
was
thereafter to
run the
full
length of the fingers;
the notion of fingers being
made
longer
by
a
finger unit
extension of
5750
mm.
(to
be
attached
by
post-tensioning)
was
adopted;
the extension could
be
joined
to finger
units of
9500
mm.
or
7500
mm.
The
polyethylene tanks
were
redesigned
so as
not
to
leave
a
void underneath
the
decks, but
to
allow
room
for
a
central
services duct. In
this
respect,
another
revision of the
arm
design
led to
the "legs"
being
moulded
at
an
angle
to
form
channels,
in
which
services
could
be
run
along
below
the
edges
of the
walkway
deck,
rather
than
in
a
central
duct.
In
my
opinion
it
was
plain
to
anyone
considering
O.M.A.'s
documents
that
its
"system"
was
one
undergoing
revision pretty
well
all
the
time.
Mr.
Wright
an
The
second
defendant,
engineer
in
1972
and
Geoffrey
Alex Wright
graduated as
has
had
a
successful
career in
practice
since.
After four years
in
employment
with
a
firm
at
its
offices
in
Brisbane
and
the
Gold
Coast,
he
established
a
-- 20 of 115 --
20
partnership with his "boss", George Francey as from 1st
January, 1977. During that year he met Mr. Eichhorn, who "was
formulating the concept of an offshore marina". The
partnership Wright and Francey became O.M.A.'s consulting
engineers and gave engineering advice on various projects,
such as Trinity Bay (Cairns) , Port Douglas and a number of
bays in Sydney Harbour. Some projects proceeded further than
others. In 1984 the engineering practice came to be conducted
by the first defendant, Wright & Francey Pty. Ltd. Mr. Wright
described the engineering services he supplied up to 1984 in
this way:
"Well, in all cases one of the things we wanted to
do was to engage specialist consultants to assist
with the work becatise the general consulting
engineer tends to be a jack of all trades type and
he needs the assistance of specialists in particular
areas."
Mr. Wright, in giving evidence, sought to emphasise that
there never were any final plans drawn by him:
"Advanced but not completed working drawings were
prepared for Port Douglas and also the Kangaroo
Point marina in 1981 / 82, which was a job which did
in fact get approval to proceed; had a fairly
advanced set of drawings, certainly advanced enough
for submissions to the authorities, though they may
not have necessarily been the final edition to which
it would have been built."
(The plaintiff's experts said that drawings prepared with
Mr. Wright's participation were working drawings, in that they
contained sufficient detail, by way of dimensions and so forth
to permit construction. He, on the other hand, described even
the latest such drawings as "developmental drawings"
somewhere between concept plans and working drawings, and not
-- 21 of 115 --
21
appropriate to
use in construction, because
details
such as
concrete strength
and
concrete cover
were
not depicted.)
He
explained the
change
of relationship with
Mr.
Eichhorn
when
the
first
defendant
came
into
the picture as follows:
"At
that
stage,
I
recognised
that vast
amounts
of
money
could
be used
up
in
research
and development
and
it
is
not
fair
or, indeed, probably
possible to
fund
that
on
the fees of
a
conventional
client/consultant
job, so because
I
considered
that
the system
had
great potential
and
promise,
I
took
it
upon
myself
to divorce
the practice of
Wright
&
Francey Pty
1
td.
from
being consultant to
OMA
to
taking
a
personal
interest
and
putting in
my
personal
time
aside
from
the practice.
I
did use
from
time
to
time
some
of
the resources of thepractice.
Of
course,
the understanding
was
that,
were
a
job
to
proceed,
then
Wright
&
Francey Pty Ltd
would
be given
first
option to
be
the engineeringconsultant to
do
those
works
over
and above which
I
had done
personally."
Thereafter,
he
said
"Wright
&
Francey"
had
not
been
remunerated
on
a
professional fee basis.
Wright
&
Francey
Pty.
Ltd. had
no
files
with
O.M.A.
as
client,
although
there
were
a
number
of
such
files
from
the
days
of
the
partnership.
Mr.
Wright
said
his
interest in
the
O.M.A.
project
from
that
time
was
a
personal
one.
Mr.
Francey'
s
wishes.
He
attributed this at
one
stage
to
Mr.
Francey ran
one
of
Wright and
Francey
Pty.
Ltd'
s
offices,
Mr.
Wright
the other.
He
had
spare
space
in
his
company's
premises
which
he
made
available
to
O.M.A.
for
storage
of
its
documents.
From
1984,
he
participated
further in
O.M.A.
projects
proposed
for
the
Southport
Broadwater.
In
1986,
for
a
client
of
his,
he
was
involved
with
Mr.
Eichhorn
in investigating
a
proposal
for
a
marina
in the
Pioneer River,
Mackay.
Mr.
Wright
said
Mr.
Corbett
was
introduced
to
him
by
Mr.
Eichhorn
at
the
first
defendant's
premises
in
"late
October,
-- 22 of 115 --
22
early
November" 1986; they were given access to the O.M.A.
documents, and use of the meeting room. Mr. Wright was
introduced as an engineer, and even
if
nothing had been
said,
the
documents
made
his participation in O.M.A.
projects over
the years
quite
obvious.
One
of the
documents produced then
or at
a
later
meeting
was a
letter
of the
Department
of
Harbours and Marine
of
November
11th,
1982
which was,
inter
alia:
"I
am
directed to
inform
you
that in
pursuance
of
the provisions of section
86
of the
Harbours Act
1955-1982,
approval has
been
given
to the plans
deposited with the
Marine Board
by you
for the
construction of
a
marina
facility
and
associated
dredging
in
the
Brisbane River
at
Kangaroo
Pointsubject to the
following
conditions:-
1.
Maximum
loading
on pontoons
of
3kPa.
2. Maintenance
of
the
dredged
river
bed
profiles
under
the
marina
as
shown
on
the
approved
plans
will
be
the
responsibility of the
owner
of
the
marina
and
as
directed
by
the Port
of
BrisbaneAuthority.
3. Navigation
lighting
must be
provided
on
the
marina
by
the
applicant,
and must
be
to
the
specifications of
the
harbour Master,
Department
of
Harbours
and
Marine,
Brisbane.
4. Wall
thickness
of
hollow
steel piling
must be
not
less
than
8
mm.
5.
The
applicant
and
his
successors
must
comply
with
the
requirements
of the Port
of
BrisbaneAuthority
and
the
Brisbane City Council.
6.
This approval
is
subject to
the
granting
by
thePort of
Brisbane
Authority
to
the
constructingauthority of
a
lease of
the land concerned
for
the
purpose proposed.
Copies
of the
approved
plans are returned herewith.
I
wish
to
point
out
that
the
approval
or
do
not
constitute
a
ruling
on
structural
you
must
make
your
own
arrangements
adequacy
of
design
and work.
conditions
safety
and
to
ensure
-- 23 of 115 --
23
In the event of the transfer of the property at
some
future date, please furnish this
Department with the
name and address of the transferee."
I
find
it
difficult to accept
Mr.
Wright's assertion that
no
special
emphasis
was
laid
upon
that letter.
In
my
view,
those associated with O.M.A. regarded
this
as an important
official
endorsement, notwithstanding the disclaimer
which
forms
part of
it.
I
accept
Mr.
Corbett's
statement
that
he
thought the
letter
was
independent acceptance
of the
engineering
adequacy
of the
system,
likewise that
the Port of
Brisbane
Authority's
letter
of
17th February,
1982
led
him
to
think
that
as the
loads
referred to
were
acceptable
to
relevant
officers
of
that authority
and
the
Department,
the
O.M.A.
system must be
structurally
sound.
As
to the
first
meeting
between
Mr.
Corbett
and
Mr.
Wright
(put
by
Mr.
Corbett
in his
affidavit
as
on
24th
November,
1986)
Mr.
Wright
said in Exhibit
148,
a
considered
written
response
to
the
affidavit:
"In
relation
to
paragraph
7,
I
was
introduced
to
Corbett
in
late
1986 and
it
was
not
until
about
March, 1987
did
I
have
my
first
business
meeting
with
him.
This
initial
meeting
was
held
at
the
offices of
Wright and
Francey
Pty.
Ltd.
which
premises
were
later
occupied
by
OMA
when
Wright
&
Francey
Pty. Ltd.
moved
their office.
We
discussed
how
the
system
differed
from
other
systems
available.
I
said
that
the
concept
was
different in
that
it
used
more heavy and
rigid units
which gave
better
user
benefits.
It
provided
better
comfort
in
that
it
moved
less
in
the
water, could
be
positioned
in
less
sheltered
waters,
and
it
was
not
necessarily
dependent
on
being
located
by
piles.
I
explained
in
general
terms
what
I
saw
to
be
the
advantages.
Corbett
asked
some
sensible
questions
and
in
lay
terms
he
appeared
to
know
what
he
was
talking
about.
Eichhorn
was
trying
to
interest
Corbett
in
financing
the
project.
Eichhorn
had
previously
spoken
to
me
so
I
knew
that
Corbett
was
meeting
with
us
for
that
purpose.
Documents
were
shown
generally
to
him.
I
do
not
recall
whether
at
the
end
of
the
meeting
whether
it
was
resolved
to
have
a
further
meeting.
At
this
meeting
I
did
not represent
myself
as
a
-- 24 of 115 --
24
specialist expert in concrete structures but as anengineer regularly working
in this material.
I
do
recall
saying
that
it
was me
personally
who was
basically
responsible for the engineering aspects of the
development
of the
OMA
System.
I
did not mention Wright
&
Francey Pty. Ltd.
in this role.
At
the
second meeting,there
was
again
a
general discussion.
I
produced
some
files for Corbett to see
and
invited
him
to
look over
them.
I
did
this to
show
that
I
had done work
in the
area
and had always engaged
specialist consultants toassist.
I
said
something
like
the
intrinsic
design of
the
OMA
system should
make
it
superior to other
systems.
I
recall that
I
did not qualify this at
the time."
Mr.
Wright,
like
all
the participants,
had no
clear
idea of
which
events occurred
at
particular
meetings. In
the
end,
at
pp.
1135-36
of
the
transcript,
he
seemed
to
concede
that
there
were
a
number
of
meetings
before
March 1987 (
still
the
first
meeting he
recalled
"with
a
heavy
technical content
in
it")
and
two
in
November 1
986
when some
of the
documents
Mr.
Corbett
mentioned
"would
have been looked
at,
but
certainly
by
no
means
all
of
them."
Mr.
Wright
had
great faith
in
the
O.M.A. system
and
conceded he
said
nothing about
possible
shortcomings,
and
certain
things
about
its
advantages.
He
is
probably
right
in
his
impression
that
Mr.
Corbett's
interest
at
first
was
in
securing
a ·
marina
for
Repulse
Bay
and
that
an
interest
in
becoming
a
proprietor of the
O.M.A.
business
came
later.
Again,
it
is
obvious
enough
that
Mr.
Wright
did not
warn
Mr.
Corbett
off.
From
his
perspective, there
was
no
reason
to
do
that.
The
following
exchange
in
cross-examination occurred
in
relation to
the
time
when Mr.
Wright had
become
aware
of
Mr.
Corbett's
investment
of
funds:
"Did
you
ever
go
to
him
subsequently
and
advise
him
that
you
hadn't
done
all
your
engineering
calculations in
questions
about
the efficacy of
the system?--!
think
I
advised
him
of
that
on
the
very
first
day.
-- 25 of 115 --
25
You
think
you advised
him
of that
on
the very
first
day?-
-I said that the system was
under development and not
complete."
Mr.
Corbett's version of this subject
is in
paragraph
14
of
his affidavit:
"14. Wright
told
me
at
the meeting
that
he and
Eichhorn
had
selected the outside consultants
and
advisersreferred to in
paragraph 9(k)
above
in order for
him
to
be
able to provide
OMA
with answers
to
all
engineeringquestions
which needed
to
be
considered.
He
said that
the only outstanding engineering matters
needing
attention
were:-
(a)
Selection of
type
of sealant
between
butt joints
from
Reid's sealants.
(b)
Selection of the materials,
dimensions
and method
of
construction of the
hinges
between
arm
units.
•
(c)
The
precise specification of
anchor
harness."
Mr.
Wright's
account
(at
pages
1153-54
of the
transcript)
has
a
different
flavour;
it
suggests
that
items
(a),
(b) and
(c)
were mentioned
in
more
general
terms;
it
lacks
Mr.
Corbett's
implication
that
there
would
be
satisfactory
solutions readily
found;
it
suggests
these
were
not presented as the only
matters requiring
engineering
attention.
On
balance,
I
prefer
Mr.
Wright's
account
in
this particular.
The
plaintiffs
have
not
persuaded
me
Mr.
Corbett
is
correct.
On
the other
hand
I
cannot
find
Mr.
Wright'
s
stance
was
as
tentative
as
my
last
quotation
of
him
would
suggest.
There
are statements
attributed to
Mr.
Wright
by
Mr.
Corbett
which
I
cannot
find
Mr.
Wright
made,
such
as
the
O.M.A.
marina system
was
"ready
to fly"
or
was
"an
engineering
masterpiece"
or
"fully
engineered
as
a
heavyweight
system".
Indeed
the
plaintiffs
are in
difficulty in
establishing
that
Mr.
Wright
made
any
particular
representations,
except
on
the
-- 26 of 115 --
26
basis of his
own
evidence, or of
Mr.
Eichhorn's. In
my
view
it
is
not to the point that
Mr.
Corbett
makes many
statements
such as
"At no time during the
many
meetings which
occurred
with Wright and
Eichhorn,
was
it
suggested
that
any
substantive engineering matters
were
outstanding".
More
to
the point are statements
of
what
did
happen, such
as
that
Eichhorn
and Wright
some
time before the
former and
Mr.
Corbett
went
to
Hamilton
Island
on
26th September,
1987
"voiced
satisfaction that
drawings were coming
together as
planned."
It
is
noted elsewhere
that
Mr.
Wright
retained his belief
in the
system
throughout,
and
voiced
it
for
example
in
March-April
1988,
so
far
as the
deck
structures
were
concerned.
He
clings to
that belief
notwithstanding doubts
expressed
from
time
to
time,
for
example,
by
Humes
Limited
in
1982
(Exhibit
135, 134) by
Mr. Seymour
and
by
Patterson
arid
Britton
in
1987.
The
plaintiffs
in
their
written
submissions
claim:
(
f)
Eichhorn
had
copies
of
Wright'
s
calculations
which
would
be
a
most
impressive
weapon
when
attempting
to
convince
a
layman
as
to
the engineering
integrity
of
the
system:
...
The
statements
to
which
Andrew
Corbett
deposes:
(a)
must
be
read
in
the
light
of
each
other statement;
(
b)
must be
considered
having
regard
to
all
the
documents
before
him;
(
c)
must
be
considered
in
the
light
of
who
was
making
the statements
and where
those statements
were
being
made. The
totality
of the
documents
placed
before
Andrew
Corbett
on
the
occasions
in
1986
in
question
by
themselves
(
and
without
more)
carry
with
them
a
number
of representations:
-- 27 of 115 --
27
(a) that the system was viable for conditions to be
normally expected in Queensland, Northern Australia~
that is that it was fit for the purpose;
(b) that it was properly engineered, that is that it was
merchantable quality;
( c) that the system would be or could be a commercial
success.
They found themselves upon the following statement in
Brennan J. 's judgment in San Sebastian Pty. Ltd. v. Minister
Administering the Environmental Planning and Assessment Act
1979 (1986) 162 C.L.R. 341; 373:
"The plaintiffs in this case do not suggest that the
representation which caused their loss was merely that
the plan was feasible considered as a representation made
in isolation. That representation was made, if at all,
by implication from the statement that the Study
documents had been expertly prepared by the Authority,
from the fact that the Council had accepted the plan
therein contained and from the publishing of the Study
documents. It was the official origins and official
acceptance of the plan which at once gave it an
appearance of feasibility and engendered such an
expectation that the plan would be implemented as to
encourage developers to purchase land".
The submission overstates what the plaintiffs have
proved. However, I do find that in all the circumstances, so
far as the deck system proposed was concerned, Mr. Wright was
making representations to the effect of (b) in a situation
where a duty of care existed, in light of the requirements
identified in Shaddock & Associates Pty. Ltd. v. Parramatta
City Council (No. 1) (1981) 150 C.L.R. 255 and San Sebastian.
I consider that Mr. Corbett relied upon such a representation
when he put his and the third plaintiff's money into O.M.A.
(apart from an initial payment of $5,000.00). I consider that
the effect of the representation was repeated by Mr. Corbett
-- 28 of 115 --
28
to
Dr. Corbett (as
Mr. Wright might have
anticipated)
and
that
Dr. Corbett had
some
regard to
it
(along with other matters)
in investing.
The meaning
of the "representation"
by Mr.
Wright
was
not, in
my
view, simply
that rigidly
post-tensi_oned
aggregations of the
deck
would "work"
in practice, but that
this
had been
established in
conventional engineering terms
by
appropriate calculations
based
on
correct information.
Mr.
Wright
was
suggesting,
in effect, that the
consensus
of
competent
engineers
would be
that
the deck's
structural
integrity
could
be
demonstrated.
As
I
determine
in these reasons,
this
is
not the case.
The
"representation"
was
untrue
and
misleading.
Further,
I
consider
that
Mr.
Wright
made
it
negligently.
What
calculations did
Mr.
Wright
do
to establish
the
structural integrity
of the
deck and
finger
system? There
is
a
large
bundle
of calculations in relation to
Kangaroo
Point"
in
1981-82, done
in
batches
in April
1981,
December
1981
and
February
1982.
The
first
batch,
of eight
pages,
not
all
of
which
show
"calculations"
by
any
means,
are
essentially
designed
to
ensure
that
the
piles
proposed
would
restrain
the
marina
in
adverse environmental
conditions;
only
half
a
page
was
devoted
to
concrete
strength
and
to
show
that
the
proposed
degree
of
prestressing
should
accommodate
bending
moments
affecting
the
arms
supported
by wave
crests.
The December
calculations
(22
pages)
were
more
extensive
on
this
aspect
and
others;
they
were
made
to
satisfy
questioning
raised
by
the
Port of
Brisbane
authority
on
24th
September. See
ex.
137.
Similarly
the
1982
calculations
which
supplemented
the
-- 29 of 115 --
December work appear
Authority's letter of
29
to have been a
17th February, 1982.
response to the
The · arms under
consideration did not have a flat surface as moulded, rather a
depressed, central rectangular channel (to accommodate
services) was incorporated. The arms considered were 60
metres long, hinged between post-tensioned aggregations of
three twelve metre sections and two twelve-metre sections.
Mr. Wright claimed to have considered reverse moments, that is
hogging as well as sagging moments. The engineering evidence
shows to my satisfaction he did not do it adequately, and that
his calculations were deficient in other respects, such as in
failing to combine forces. He is not charged with negligence
in his calculations, of course, but in republishing them, as
it were, to Mr. Corbett. I think it is legitimate to say he
was not justified in relying on the soundness of his own
calculations made five years or so before, when his experience
as an engineer was more limited. He knew he could hardly
qualify as an expert in floating concrete structures.
likely he placed some faith on the official approvals.
Very
In my
opinion it was incumbent on Mr. Wright to consider whether the
changes made to the system after those approvals had any
effect on the value of the 1981-82 calculations. It does not
appear that he did so.
As to the other representations which the plaintiffs
allege against Mr. Wright, except where they are admitted by
him or proved by Mr. Eichhorn, I am not persuaded they were
made in the terms alleged, or any near approximation. I am
not particularly concerned about remarks having the quality of
-- 30 of 115 --
30
puffery, or remarks comparing the O. M.A. System favourably
with its competitors. These seem to me part of a "sales
pitch" which was essentially Mr. Eichhorn' s, even if
Mr. Wright endorsed them in some way or other.
Wright & Francey Pty. Ltd.
The writ endorsement indicated that the action was based
on misleading and deceptive conduct under the Trade Practices
Act (Commonwealth); this probably explains why the company,
which took over the second defendant's and Mr. George
Francey's engineering practice in 1984, was made first
defendant - it is a corporation, whose actions are potentially
capable of being brought within s. 52.
It is trite that nothing Mr. Wright did before 1984 can
be regarded as done as the first defendant's agent. He claims
that everything done after the first defendant's appearance
was done in his personal capacity. Such a claim is shown
articulated for the first time in the company's letter of
March 16, 1988, ex. 39. This does not mean it is necessarily
untrue, but it does mean the defence contention that the first
defendant cannot possibly be liable for anything which
occurred in 1986-87 should be closely scrutinised. There is
evidence of co-operative endeavours by the company and O.M.A.
in late 1986. Exhibit 23 is a letter of 1st October from them
jointly in respect of a proposed marina on the Pioneer River,
Mackay, signed by Mr. Wright and Mr. Eichhorn. The two men
are described, accurately enough, as the principals of O.M.A.,
and the company presents itself as the successor of the former
engineering partnership. The letter is on Wright & Francey
-- 31 of 115 --
31
Pty. Ltd.' s letterhead, but many of the pages enclosed bear
· the O.M.A. "logo". This document may signify no more than
that the addressee was the company's client. On 20th October,
1986 there was created ex. 156, another letter jointly signed.
Part of an attempt to promote a proposal for Sydney Harbour,
it says that Mr. Eichhorn's partner in O.M.A. is "Civil
Engineer Geoff Wright of Wright & Francey Pty. Ltd.". Again
that is equivocal. Not at all equivocal is ex. 65, a
submission of 27th March 1987 to the New South Wales Minister
for Public Works and Ports. This showed Messrs Eichhorn and
Corbett as "principal partners" and Mr. Wright as a partner.
Wright & Francey Pty. Ltd. is listed as a consultant, and
provided a six page report on its own letterhead, signed
"G.A. Wright, Wright & Francey Pty. Ltd.". The report states
that "Data on layout and design has been synthesised from many
and various sources. From the point of view of engineering
design, lack of precedent is not a great drawback". Overall
design parameters were said to allow an anticipated economic
life of 25 years, the intention being to design for a 50 year
return period of natural phenomena affecting the structure.
Various representatives as to the advantages of the system,
which must be taken to emanate from the first defendant,
follow. I have no doubt that this document was available to
Mr. Corbett. He was well accustomed to visiting the first
defendant's office and seeing O.M.A. 's product and prospects
and problems ( to the extent any was acknowledged) discussed
there, with Mr. Wright participating at least some of the
time.
-- 32 of 115 --
32
I accept the plaintiffs' argument that in matters of an
engineering nature, when Mr. Wright did or said things before
Mr. Corbett, he may be regarded as acting for the first
defendant. So far as the first defendant was to act,
Mr. Wright would necessarily be the actor; the company's
premises were used without any kind of disclaimer that it was
involved being established; the company paid Ray Murray, who
did a good deal of drafting for O.M.A. on the Computer
Assisted Drafting System which Dr. Corbett obtained on lease
( this was part of an arrangement whereby Mr. Murray and the
system were made available to do work for the company); the
company was presented as successor to the engineering
partnership; the expectation was that the company would profit
from consultancies with the clients if O.M.A. should succeed
in getting jobs. The expectation of benefit to the company is
clear. Some matters pointed to by Mr. Bowden, such as.·, the
first defendant's allowing its facsimile transmission machine
to be used by O.M.A. seem neither here nor there to me (they
may simply be a courtesy between neighbours); however, Mr.
Bowden has persuaded me that whatever reservations Mr. Wright
may have held, his actions were performed in the course of the
company's business - he relied upon Deatons v. Flew (1949) 79
C.L.R. 371, 381; Lloyd v. Grace, Smith & Co. [1912] A.C. 716
and Pennington's Company Law (5th) 126.
To the extent that Mr. Wright may be liable to the
plaintiffs herein, the first defendant is liable. The
plaintiffs have not suggested Mr. Wright played any role in
-- 33 of 115 --
33
negotiations to
do with the parties' relative equities in
O.M.A.
THE EXPERTS
Mr. Abraham
Of
the three consulting engineers claiming
special
expertise in
marine
structures
who
gave
evidence,
I
prefer
Mr. Abraham. The
qualifications
and
experience
of
all
three
impressed
me,
and
it
is
invidious
indeed
to
be
required to
distinguish
among
them.
The
consul
ting
experience
of
Messrs.
Abraham
and
Patterson
outstrips that of
Mr.
Gallagher,
and
their
views
command
the
greatest respect insofar
as
their
theory
is
combined
with long
practical
experience.
Of
these
three experts,
only
Mr. Abraham
impressed
me
as being
"above
the
battle";
the other
two were
very
much
advocates
for the
parties calling
them.
It
will
shorten these
reasons
appreciably
to indicate,
as
I
do,
that
I
accept
Mr.
Abraham's
reports
(ex.
80
and
ex.
81) and
his
evidence.
Mr.
Glynn
Mr.
Glynn,
called
as the
plaintiffs'
third
expert,
is
another
whose
evidence
I
accept
in
its
entirety.
The
defendants
advanced
no
reason
why I
should
not.
He
is
an
expert in
concrete,
albeit
not
in
marine
applications in
particular.
His
standpoint
is
that
adequacy
of
concrete
structures
should
be
considered
in
light
of
concrete
codes
adopted
by
the Australian
Standards
Association
and
general
theoretical principles,
regardless of special
contexts.
In
many
respects,
a
marine environment
is
more
hostile
to
a
concrete
structure
than
a
land
environment.
Mr.
Glynn,
like
-- 34 of 115 --
34
the
plaintiffs' other experts, establishes that the concrete
decks of the
O.M.A. System 1
marina
are theoretically liable
to
fail
under conditions
which should be designed against.
The
concession has
to
be
made
that calculations of various
forces
and bending
movements
in particular
have
their
limitations; these
may
be
illustrated
by my
observing
that
the
shape
of
a wave
is
taken as being
triangular
-
which
a wave
in
practice
is
not; further, the calculations typically
look
at
a
wave
as frozen
in
an
instant,
whereas
it
is
in
motion
-
the
appropriateness
of treating
a wave
as
static
may
be
questionable, but
it
is
the best
that
can be done
in
the
circumstances.
The
defendants
were
not able
to present
an
engineering
or physical theory
to
demonstrate
that
the
O.M.A.
System
concrete
decks
would
not
fail
in
design
conditions.
Mr.
Gallagher
Mr.
Gallagher,
a
consulting engineer with
many
years
experience
in
marine
engineering,
first
encountered
the
O.M.A.
System
in
late
November 1987
when Ray
Murray, an
O.M.A.
employee
(
and
a
former
employee
of his
own)
asked
him
to
do
some
buoyancy
calculations.
He
was
given
possession
of
drawings
relevant
to floats
and
arm
units.
His
investigations
showed
satisfactory
buoyancy
but
he
decided
he
"could
see
some
problems
with
in
the
system
. . .
it
was
just
feeling in
the
water."
As Mr.
Gallagher
told
it,
communication
of
this
to
Ray
Murray
with
the
suggestion
that
Mr.
Corbett
be
advised
led
to
Mr.
Corbett
on
22nd
January,
1988
commissioning
him
to
do
a
full
check
of
the
system.
There
was a
good
deal
of
contact
after
that,
culminating
in
the
report
ex.
35
which
-- 35 of 115 --
35
Mr.
Gallagher prepared, largely for the purpose of informing
Dr.
Corbett of his
views.
He made
suggestions as to
how
the
system could be
made
to
work, he
did "not see things as
black
light to
medium
grey
certainty". Similarly,
Mr. Abraham, who was
engaged by Mr.
Gallagher over
a
year
later, in his report of 27th April
1989,
made
suggestions as
to
how
the
O.M.A. system could be improved.
By
this
time
attention
was
being focussed
on
the
adequacy
of the concrete
and
finger sections.
I
find
Mr.
Gallagher
was
correct in
identifying
"double
tee" sections
as
an
unfortunate choice for
an
environment
in
which
there
can be
full reversal of
loadings.
It
seems
plain that
for
a
marina,
forces
such as
vessel
impact, winds,
waves,
currents
and
the
like will
not
operate
in
a
consistent direction.
A
particularly
troublesome
species of
load
reversal
is
experienced as
a wave
of
appreciable length
moves
under
and
along
a
finger or
arm.
When
the
member
is
suspended
at
or near
both ends
by
wave
crests,
it
will
tend
to
sag;
when
supported
at
about
its
centre
by
the
crest
of
a wave
of
sufficient
length,
it
is
said
to
"hog"
-
its
back
will
tend
to
break, as
Mr.
Gallagher put
it
(p. 188).
He
said
that
the
critical
wave
length, the
one
which
may
do
the
greatest
danger,
is
one
nine-tenths of
the
length
of
the
floating structure.
The
bending
moments
were
calculated
by
various witnesses using
different
assumed
conditions.
Mr.
Abraham's,
for
a
combination
of
two
15
metre
fingers
joined
through
a
two
metre
walkway
are conveniently
set
out
in
the
table:
-- 36 of 115 --
underprestress
under
prestress
and
wave
bending
moment
36
Finger without splay
Top Bottom
3.0 12.
2
12.6 34.0
-6.6 -9.6
Finger with splay
Top Bottom
0.4 13.5
5.9 32.8
-5.0 -5.9
Comparison
of the
middle and bottom columns shows
the dramatic
effect
of load
reversal.
The
stresses or
bending
movements
shown
as negative are tensile or "pulling"
stresses,
the
others are
compressive.
Mr. Abraham
says,
and
I
accept,
that
given
the strength of the concrete
(
allowing
for the pre-
stressing
and
post tensioning) the
compressive
stresses
of
34
and 32.
8
Megapascals
are
unacceptable,
and
that
any
tensile
stresses
are
unacceptable.
Mr. Abraham
allowed
that
relocation of
the post-tensioning conduits (not
easily
achieved
precisely in
manufacture,
he
said)
would
alleviate
the
situation,
but
I
cannot
find
that
it
would do
so
acceptably,
after
considering
the debate
on
the point
between
him
and
Mr.
Patterson.
Mr. Abraham
thought
15
metre
fingers
would
fail
under
horizontal
wind
or
berthing
loadings
postulated
by him.
As
for
the
arms,
he
calculated, for
an
arm
section of
27
metre
length in
the conditions
he
considered,
the
following
stresses:
Top
Bottom
Under
pre
stress
1.05
12.02
under
pre
stress
10.79
38.32
and
wave
bending
-8.69
-14.28
moment
-- 37 of 115 --
37
Again, the stresses were unacceptable, and again I am not
satisfied by Mr. Patterson that correcting an· eccentricity
between centres of gravity of the concrete and the
post-tensioning strands would make the position acceptable.
Mr. Patterson
The defendants' engineering expert, Mr. Patterson had a
different standpoint. At p. 742 of the transcript, he said of
Mr. Glynn:
"He is an engineer who believes that strict
compliance with concrete codes is certainly a
preliminary objective of any design structure and
that we should be providing adequate factors of
safety against failure which has the mentality of
the majority of structural engineers which is quite
a desirable attribute of structural engineers, my
point being that in the design of marina systems we
are operating a different part of the spectrum of
material performance. We are not looking or seeking
to provide structures with the high factors of
safety inherent in the Australian codes."
His cross-examination revealed more of his approach:
"Can we go to Exhibit 23, please? Whilst we are
dealing with this question, if you assume the rigid
structure - just make this assumption, please - if
you assume the rigid structure, the rigid raft
structure, three arms and six fingers, that
Mr. Gallagher has dealt with I put it to you that
you can not justify the engineering integrity of
such a system within design conditions for the State
of Queensland?-- For the State of Queensland.
Well, the sort of design conditions that Mr Abraham
deals with in his letter, the exhibit we were
looking at before, the 400 mm wave, the 1 kPa wind
condition, the berthing speed that we discussed,
those four components on the first page of his
letter?-- Yes. What I would call maximum
conditions, yes, I would probably have to agree that
if all of those conditions pertained to a site then
I probably wouldn't be trying to use 27 metre long
rafts.
Or even an 18 metre long raft?-- I probably would
be able to make an 18 metre long raft work.
-- 38 of 115 --
38
Not with
15
metre figures (sic)?--
Depends on the
actual
wave
conditions
you
are talking about
at thesite.
Dealing with the design
waves
we
are postulating
it
wouldn't work?--
If
you
are talking about the
maximum waves
of .4 of
a
metre on
paper
it
may
not
work.
It
wouldn't
work, would
it?--
No, you
cannot
draw
that
conclusion
just
because
on
paper the
stresses,
concrete
stresses
-
the marina won't survive.
Why
do you
say
that?--
Because
if
I
were
to
do
that
exercise for
a
marina
that
already
has been
built
and
is
operating
at
Abel
Point
I
could
quite easily
demonstrate
that
it
won't
work on
paper.
You
have done
those
calculations, haven't
you?--
Yes, and
the
stresses in
it
are
very
large.
You
have done
those
calculations for
Abel
Point,haven't
you?--
Yes.
May
the witness see
Exhibit
1 07? I
am
going
to
suggest
to
you
these
calculations are
wrong.
Do
you
understand
that?--
Yes.
What
you
have
done
here
is
this; this
is
a
documentwhich
you
have
prepared
to
demonstrate
that
the
Coppers'
Wharf
at
Abel
Point
does
not
comply
withthe
codes
and
the concrete
codes,
or
whatever,
and
with
fundamental
engineering
calculations
is
·
still
there
and
well able
to
withstand the
elements
for
two
years?--
Yes.
It
is
therefore
important
for
you
doing
these figures to
demonstrate
that
the
relevant
forces
are
beyond
the
codes
and
yet there
it
is.
It
is
a
marina
which
is
still
therein existence.
That
is
your
thesis,
isn't
it?--
Something
like that.
The
thesis
is
that
if
we
blindly
apply
the Australian
Standard
Codes
of Practice for
reinforced
concrete
to
marina systems
that
most
marinas
would
fail,
nevertheless, the
fact
is
these
marinasystems
do,
in fact,
work.
That
is
simply
all.
I
am
not
trying to
prove
that
the engineer
who
designed
this
marina system
was
incompetent
or
incorrect,
by
just
by
applying the
same
criteria
or
philosophy
Mr
Gallagher
has
applied
to the
OMA
concept
design
calculations
done
for
Abel
Point.
If
you
apply
that
to
an
actual
installation
that
has
been
installed
you
come
up
with
the
same
conclusion.
That
is
it
will
fail.
Nevertheless,
there
it
is
built.
It
is
working
and
that
is
my
experience,
that
is
what
happens."
-- 39 of 115 --
39
There
was
an issue as to the adequacy
of
Mr.
Patterson's
Abel
Point calculations
which
I
need
not resolve. In
my
view
the
outcome
of
this
case ought not to
depend on such an
issue.
I am
satisfied that
Mr.
Patterson's
philosophy,
in relation to
marinas,
was
against the conventional approach
of requiring
theoretical
demonstration of the soundness
of concrete
structures.
I
have
great regard for
his expertise;
he
is
a
principal
author
of
the Australian
Standard
for
Marinas
which
recently
came
into effect.
(
It
has
no
bearing
on
the issues
before
me.)
Mr.
Patterson, in turn,
expressed
unashamed
regard for
the
practical
people
who may
lack engineering
or
any
paper
qualifications,
but
who
are able to create
marinas
which
work
in practice.
Mr.
Patterson
is
not able
to
point to
any
particular
marina
structure
offending the
Gallagher-Abraham
standards
which
has
survived
for
any
great
length of
time
in
years,
to
suggest
that
it
would
last
20
or
30
years.
This follows
from
the
recency
of
the
installation
of the
examples
he mentioned. There
is
much
to
be
said for
Mr.
Patterson's
"can-do" approach.
He
could
well
be
right
that
marinas
designed
to standards
below
those
theoretically
defensible will
last
for
an
acceptable period of
time
and
may
gain
commercial
success.
His
approach
was
presented
by
Mr.
Carrigan as
an
"empirical"
Court
leads to the
plaintiffs'
one,
whose
acceptance
by
the
failing to establish that
the
engineering of
the
O.M.A.
system
was
defective.
In
my
opinion, the empirical
approach
is
not
the correct
one
in
the present
case
where
the engineering
adequacy
of
a
design
is
brought
into
question
in
the context of
the
-- 40 of 115 --
plaintiffs
being induced
40
to
buy
into
a
venture
by
representations along the lines that the engineering has been
carried out or
vouched
for
by a
consul ting engineer,
namely
Mr.
Wright. In
such
a
context the ability of the defendants
to
produce
a
theoretical justification
of the
system
in the
face of the
plaintiffs'
experts'
evidence
is
crucial.
The
defendants have
failed the
test.
Even Mr.
Patterson did not
defend
the
O.M.A.
system, so
far
as
it
depended on
rigid
elements
of
27
metres
of
walkway
including
six
15
metre arms,
or similar.
I
find
that
the
system
was
conceived
in that
way,
and
that
the proposition
that
it
was
all
along regarded as
a
modular system with
far
more
flexible
connections
must
be
regarded
as
a
recent invention.
That
"recent invention"
played
a
large part in
Mr.
Patterson's
defence
of the
O.M.A.
system.
I
repeat
my
regret that resolution
of the engineering
issues
has
led
me
to prefer
Mr.
Abraham.
An
irony
of
the case
was
that in
August 1987,
Mr.
Patterson's
firm,
Patterson
&
Britton, rejected
a
proposal
for
an
O.M.A.
installation at
Birkenhead,
in
Sydney.
This
was
explained
in
terms
of
the
client
being conservative,
and
wishing
to
have
a
proven
system.
It
all
points
to
the defendants'
inability
to
show
that
the
system
will
work.
Mr.
Wright's
expertise,
nature
and soundness
of
the
system
he
defended.
It
may
be
accepted (as
Mr.
Eichhorn says
it
in
ex.
125,
which
the
defendants tendered)
that
at
a
meeting
in
late
November,
1986
Mr.
Wright
told
Mr.
Corbett, as
to his
-- 41 of 115 --
41
expertise, at least that
he had many
years experience in the
building of concrete structures,
and
that
he had been working
with
Mr.
Eichhorn in the
development
of the marina system over
a number
of years,
had
participated
with
Mr.
Eichhorn with
respect to
a number
of
marina proposals,
and had been involved
with other consultants brought
into
advise
on
the
development
of
the
marina systems. In
my
opinion
this
suff icies to
establish that
Mr.
Wright
was
presented as
an
engineer with
appropriate
qualifications to
pronounce
on
the
adequacy
of the
system
and
to
access
when
consultation
with
particular
experts
was
necessary.
On
the point of the
structural
soundness
of
the concrete
arm
and
finger
decks,
Mr.
Wright
has
been
stoutly
defensive
of
the
design
at
all
relevant
times.
For
example on
15th
April,
1988 he
told
Mr.
Corbett
that
engineering
had been done
for
the floating parts of the
system,
but
remained
to
be done
in
respect of
tethering. Similarly
he
told
Mr.
Lubrano
about
this
time
that
he
had
done
sufficient
work
on
the
floating
units
and
their
connections
to
be
confident
of
their ability
to
meet
design standards
and
perform
in actual
operation
(ex. 71).
After
Mr.
Seymour
expressed doubts as
to
the
potential
engineering
problems
with the
O.M.A.
system
in
September and
October,
1987,
Mr.
Wright
said
the
best
way
of
countering those
doubts
was
to
do
further
calculations for
a
specific
marina
job. This
led
to
what became
known
as the
"Abel
Point Calculations"
of
October,
1987.
Five
pages
in
length,
they
were
regarded
by
Mr.
Wright
as
vindicating
the
design.
They
are
the
focus
of the
plaintiffs'
attack
on
the
,I
-- 42 of 115 --
42
engineering design of the O.M.A. system, which is claimed to
be defective. See paragraph 36 of the statement of claim, and
particulars (i) to (viii):
II ( i )
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
The design involved incorrect calculation of
stresses on the structure caused by vertical
wave moments and horizontal bending moments due
to berthing of vessels. There was a failure by
the designer to consider wave action on the
assemblies of arm and finger units of the
structure. There were mistakes in the
calculation of forces caused by horizontal
berthing loads;
The design failed to investigate or take
account of moment reversal due to wave action;
Different stresses (for example due to wave
action and berthing) were not combined in the
designer's calculations of the relevant
stresses on the structure;
The stresses on both faces of finger and arm
units of the structure were beyond the limits
permitted by AS 1481 Table 4.8.4.(2);
The stresses or tensions on the structure were
to high, making the joints likely to open and
close regularly exposing post tensioning
strands to the marine environment;
The minimum cover (prescribed by AS 1480 and AS
1 481 : Condition 4) for reinforcement and post
tension ducts of arm and finger units, and for
pretensioned strands for arm units, were not
specified or included in the design.
Contrary to AS 1481, no cement grouting of
ducts containing prestressing strand was
included in the design, and it was not possible
consistently with the design to grout such
ducts;
The design incorrectly chose a double tee type
of section for the arm and finger units instead
of a section which was symmetrical about a
horizontal axis such as a box or an I section."
Those particulars are, I consider, made out on the
evidence - Particulars (ix) to (xii) have not been. They are:
-- 43 of 115 --
II
(
iX)
43
The
anchoring system was
inadequate to
cope with the vertical
component
of anchor cable
forces;
(x) The
harness design
was
defect(ive) in that:-
(xi)
(xii)
(a)
it
provided for
a
connection point
some
900
mm
below
water
line
and
a
large rolling or heeling
moment was
induced
in
the
arm
unit;
(b)
it
provided for
bronze
corner pieces instead for
a
simpler harness
fabricated
from
SAF
2205
stainless;
There were
excessive
direct stresses
on
the
polyethylene tanks
which would
result in large
long
term
deflections of the
tank
walls
due
to
an
inability
to
withstand
stresses
from
the
concrete decks,
live
load
on
the concrete
decks
and
water
pressure loads;
Hinges were
of insufficient
thickness:
a
thickness
of
20
mm
was
prescribed
by
the
design
when
the
thickness
should
have
been
at least
26.9."
Particular
(
i)
alludes to rigid
assemblies
of
arms and
fingers post-tensioned together,
"rafts" typically of three
arms
and
six
fingers
. Mr.
Gallagher
made
ex.
77
which
is
amodel
of
this
arrangement.
Rafts
were
to
be
hinged
together
at
arm
ends
to
provide
longer
walkways
(arms)
as
required,
and
as
many
berths
at
fingers
as
might be
required.
The
engineering
evidence
was
pretty
well
unanimous
that this
arrangement
was
not
justifiable
in
engineering terms.
The
issue
was
first
raised
about
September-October
Mr.
Corbett giving
evidence
on
commission
said:
11
What
about
the
other
matters,
what
was
his
response
to
the other matters
raised
by
Seymour?--
One
of
the
other matters
was
that
Seymour
didn't
like
any
hinges
at
all.
Wright
said that
virtually
every
little
pin
on
the offshore
system
-
yeah,
the
off
shore
system
-
was
essentially
a
hinge and
he
couldn't
understand
Seymour's
reservation
on
that
ground, so
he
dismissed
that.
Then he
also
-
Seymour
said
that instead of
seeing
hinges
at
all,
1987.
-- 44 of 115 --
44
the system should be designed virtually without
hinges at all and just a great long - or joined
tendons. Eichhorn - sorry, Wright said that was a
silly idea because it virtually made the whole thing
just one and it would not be able to take the
forces."
He may have confused the positions of Mr. Wright and Mr.
Seymour, although not necessarily so: Mr. Wright at all times
envisaged the use of a certain minimum number of hinges.
At the trial, Mr. Patterson supported the O.M.A. system,
but on the basis of its being a modular system which could be
employed by using smaller post-tensioned aggregations, in
particular shorter arms - he said there might be not three,
but only two arms sections post-tensioned together between
hinges; there might be hinges at each 9 metre arm section, if
the wind and wave climate and likely berthing and other forces
in a particular marina location so indicated. It might even
be that the fingers should be hinged (if made up of more than
a single section) and hinged at the arms.
Mr. Gallagher's model, ex.
leave
78 illustrated such a
possibility. It would very little room for
post-tensioning which was universally accepted as a difficult
procedure to carry out effectively in a salt water
environment. It is obvious that the risk of salt getting to
the post-tensioning strands to cause rusting or corrosion (and
consequent expansion, with disastrous consequences for the
concrete decks) is highly significant. Mr. Patterson was
disposed to be sanguine about what might be achieved on any
particular job. Mr. Abraham, an engineer of comparable
experience called by the plaintiffs, was not. Drawings were
in evidence which showed that Mr. Wright was alert to these
-- 45 of 115 --
45
problems, and had made some
provision to protect
post-tensioning strands.
The
efficiency with which
his
precautions
would be implemented by workmen
assembling
a
marina
at
a
remote
site is
a
matter for conjecture.
This apart, the defendants' strenuous
efforts at trial,
notably through
Mr.
Wright and
Mr.
Patterson, to present the
O.M.A.
system as
offering the "floppy" ex.
78
alternative just
as routinely
as
the
rigid
one
in
ex.
77
(which,
indeed
no-one
on
the
defence
side
appeared
to
wish
to
defend) were
beside
the point in
my
view.
It is
irrelevant that
Mr.
Patterson
sees
a
possible
commercial
future for
a
flexible or
floppy
O.M.A.
system marina
in
circumstances
where
I
must
find that
the ex.
77
model
(albeit
perhaps with
relatively
shorter
fingers)
was
always
envisaged as applicable to the exclusion
of
alternatives
with
more
frequent
flexible
connections.
A
large
rigid
assembly
was
prized for
the
stability
it
offered:
it
would
be
far
less
responsive
to
movement
on
the
decks so
far
as
bobbing
about
in
the water
is
concerned.
I
asked the
defendants'
counsel
to
show
me
any
instance in
which
the
defendants before
trial
had
advocated
the
floppy
model,
or
any
equivalent.
The
challenge
was
not
met.
On
the contrary
everything
I
have
seen
supports the
view
that
the
rigid
ex.
77
model
is
what
Messrs.
Wright
and
Eichhorn proposed.
The
December
1981
Kangaroo
Point
calculations are
based
on
a 36
metre
"raft"
hinged
to
a 24
metre
raft;
the
October
1987
Abel
Point
calculations
refer to
"total
arm
length
130
m
i.e.
4
'raft'
sections".
The
following
month,
Mr.
Wright
wrote
to
the
Water Research
Laboratory
in
Sydney,
which was
being
-- 46 of 115 --
46
engaged
to perform dynamic model
tests
on the hydraulic
performance
of floating
marinas
referring to the "typical
'three rafts'
configuration, each with
six fingers off three
arm
units
hinged together
and
tethered
by
six cross
anchors and
four longitudinal anchors".
He
wrote
that "the
equivalent
of nine
deck
units,
each
made
up
as
a
rigid three-
arm
'raft'
will
be
required.
pairs of 9.
6 m
finger units".
Each
will
have
three
opposed
O. M.A. ' s
isometric
drawings
produced
by
the
C.A.D. system
are consistent
with such
rafts
being seen
as standard,
and
with longer
fingers,
if
required.
No
attention
whatever appears
to
have been
paid
to the
logical
possibility,
always
present,
that
in
any
situation
(except
a
job
of smaller
size
than
a
single "raft")
smaller
rigid
components
than
such
rafts
would
be used.
One
of the early
suggestions
came
from
Mr.
Gallagher
in his report
ex.
34
in
February
1988,
when
he
suggested
means
whereby
the
O.M.A.
system might be
salvaged.
Andrew
Corbett decides
to
invest
Mr.
Corbett
in his affidavit
swore
that:
"16.
As a
result
of
the meetings
with
Wright andEichhorn
and
my
perusal of the
documentation
I
felt
confident
that
the
OMA
system
was
sound and
was
a
feasible
business proposition
and
I
therefore
decided
to invest
money
in
the
project
and
to
thereby
acquire equity in
OMA.
17.
Eichhorn
and
I
agreed
that
I
would
have
47%
equity
in
OMA
by
contributing
the "seed
capital"
which would
allow
OMA
to attempt
to
attract
a
larger
investor.
18.
A
written
agreement
was
entered
into
on
20th
May,
1987
between
Nashtown
Pty.
Ltd.,
(my
family
company
and
third
plaintiff
herein)
the
Eichhorn,
Wright and
another
company
called
Pocket
Valley
Pty.
Ltd.
A
true
copy
of
this
agreement
is
now
produced
and
shown
to
me
and
marked
"ANCS".
Pursuant
to
the
-- 47 of 115 --
47
agreement all of the parties' rights in respect of
the OMA system were transferred to Pocket Valley
Pty. Ltd. and 100 shares in Pocket Valley Pty. Ltd.
were divided between Nashtown, Eichhorn and Wright
on a 47:47:6 basis.
19. I made or caused the third plaintiff to make
payments periodically over the months that followed.
A schedule of these payments is now produced and
shown to me and marked "ANC6". The total amount
contributed by me was $88,390.02."
The first item is $5,000.00 "cash" said to have been paid
on 19th November 1986. Next came $425.86 paid on 24th January
1987, said to be 25 per cent of a Telecom bill. Two similar
payments were made on 9th February 1988, when $360.00 was paid
to a service station for fuel. On the following day came the
contribution of $2,500 to O.M.A. This would seem to mark the
beginning of the contribution of "seed capital" and establish
a decision to invest - yet the sequence of paragraphs I have
set out could be thought to point to a date in May 1987. Mr.
Corbett when he was giving evidence on commission favoured the
view that he had not decided to invest in O.M.A. before April,
1987.
Mr. Carrigan, the defendants' counsel, attached great
importance to the timing. Mr. Wright said that he had no
"business" meeting with Mr. Corbett before March 1987 and that
that was the date of a meeting Mr. Corbett placed on 28th
November 1986. Mr. Wright was aware, thanks to statements to
him by Mr. Eichhorn, of something Mr. A. Corbett did not in
terms say, namely that Mr. Eichhorn was trying to interest Mr.
Corbett in financing the project; Mr. Wright regarded this as
the purpose of their meetings with Mr. Corbett.
-- 48 of 115 --
48
On
20th January
1987
registration occurred in the office
of the Commissioner
for Corporate Affairs of the
proprietorship of the business
name
Offshore Marinas
Australia
of
Mr.
Eichhorn,
Mr. A.
Corbett,
and Dr.
J.
Corbett as
from
1st
January 1987.
A
possibility
may
exist of
some
backdating.
No
reason appears for
doubting the genuineness
of that date,
and
the
plaintiff,
by
Mr.
Corbett's
affidavit,
supports
it,
bolstered
by
the
detail
of the relevant application
being
forwarded
by him on
16th January. In the
end,
this
document
persuades
me
that
the decision
by
Mr.
Corbett
to invest
and
become
a
partner in
O.M.A. was made
in
December 1986
or
January
1987.
A
pointer to
such
a
decision
then
is
Mr.
Corbett's
generous
decision to lend
Mr.
Eichhorn
his
Mercedes
motor
vehicle to drive
himself
and
children to
Sydney
for
Christmas 1986.
The
Christmas shut-down
or other factors
meant
that
O.M.A.
had
no
need
for
funds
for
some
weeks.
I
am
not
persuaded
that
the timing
of
the
initial
decision
to invest
is
particularly
critical,
from
the point of
view
of exonerating the
defendants
from
liability
if
they can
show
representations
by them
came
later.
None
of the
plaintiffs
ever
became
obliged
to contribute
moneys
to
O.M.A.
for
any
particular
time,
or in
any
particular
sum,
or
without
limit;
there
was
a
series
of
separate decisions
to
put
up more
money
each
time
a
need
arose.
In
that
way,
in
theory,
each
outlay
must
be
examined
in
the
light
of
the
circumstances
in
which
the
particular
plaintiff
made
it.
representations
may
have
been
made
in the
meantime.
Further
Equally
importantly,
Mr.
Corbett's
increasing
participation
in
the
-- 49 of 115 --
49
business
made him
ever better placed to inform himself and
guard his
own and
nis brother's interests,
and those of their
companies.
The
balance
of the evidence favours the
view
that
Mr.
Wright
made
relevant representations
commencing
in
November,
1986.
J.
Corbett decides
to invest
In paragraph
42
of his affidavit
Mr.
Corbett explains his
calling
on Dr.
Corbett for
funds
in
terms
of the necessity of
getting
working
capital to
undertake
a
job
at
Yap,
the
money
needed
"to
gear
up
to
full
production" being
beyond
his
resources.
Mr.
Corbett
was
said to
be
entitled
to
1
per
cent
of
the
business
for
each $7,000.00
invested,
this later
"improved"
to
1
per cent
for
each $5,000.00 so
that
Dr.
Corbett,
by
initially
investing
$150,000.00,
acquired
30
per
cent.
Dr.
Corbett's
understanding
was a
little
different;
he
thought
it
was
to
be $100,000.00
for
20
per cent
and
that
loan
funds
of
$50,000.00
were
to
be
made
available.
His
decision
to
invest,
made
before the
terms
were
finalised
(if
they ever
were
finalised),
was
made
at
or
very
soon
after
the
end
of
May
1987.
The
registration
of
the business
name
shows
him
as
a
partner
from
1
st
January
1987.
I
cannot conclude
that this
occurred
without
his
knowledge and
consent.
The
exhibits
include
(ex.
128)
a
form
appropriate
to
have
registered
a
change
in particulars
relating
to
a
registered
business
name.
It
is
not
dated,
nor
is
it
shown
to
have
been
lodged,
but
it
relates
to
O.M.A.
and
is
signed
by
both
of
the
Corbetts
and
-- 50 of 115 --
50
Mr.
Eichhorn. For some
reason
it
shows
the date of change as
1st
February· 1985. The document
is
shown by
facsimile
imprints to
have
existed
by
21st October 1987.
The
possibility of
Dr.
Corbett investing in
O.M.A.
existed
and
was
known
to
him
in
January
1987.
He
did not
commit
himself in
any
way
until
some
months
later.
Even
then,
he
retained the
right to decline
particular
requests of
O.M.A.
for
funds.
As
events turned out,
Dr.
Corbett
seems
to
have
left
the
practical
aspects of remitting
funds
and
assessing the
need
for
them
to his
accountant,
Mr. Sweeney.
Mr.
Eichhorn's
Evidence
Mr.
Eichhorn's
faith
in his
marina
design
and
his
ability
as
a
consultant
in
the
field
are
obvious.
He
is
an
enthusiastic
and
plausible
salesman;
the
documents produced
by
him
show
his predilection
for
exaggerated language
or
claims,
which
is
no
doubt
a
legitimate part
of
salesmanship
-
he
was'.
out
to get
clients;
he had
to
display
confidence
in
O.M.A.'s
product
and
services.
I am
sure
that
those
he
approached
were
aware
of
the "puffery"
involved.
They
may
not
have
appreciated
it
extended
to
describing
as
if
they
were
achieved
developments
which
were,
in truth, just
around
the corner.
Thus,
Humes
Limited
were
described as
fabricators of
O.M.A.
concrete
components,
with the implication
that
production
was
established,
before
O.M.A.
even
held
their
written
quotation.
This
is
less
a
sign of
dishonesty or
recklessness
than
of
Mr.
Eichhorn
adopting
a
hopeful
approach,
in
confidence
that
what
he
says
will
be
achieved
will
surely
happen.
-- 51 of 115 --
51
With
hindsight
and
the knowledge
that
O.M.A.
never built
a
single
marina,
it
is
astounding to read
Mr.
Eichhorn's
lists
of jobs about
to
be
won
or in prospect.
Once
again, that
seems
to
me
to
be optimism
in action, rather
than
misrepresentation.
Mr.
Eichhorn
certainly believed
that
some
jobs
were
very close to
being secured.
No
complaint
is
made
by
the
plaintiffs
of misrepresentation
on
this score.
Perhaps
Mr.
Eichhorn
was
naive.
He
does
not present as
a
realistic
hard-headed businessman,
like
Dr.
Corbett.
He
seems
to
have
had
little
interest
in the
details
of adjustments
in
the
O.M.A.
partners'
equity
which
greatly affected
him.
He
has
not pretended
to
engineering
skills,
but
relied
on
the
expertise of
Mr.
Wright and
other consultants
to establish
that
his
ideas
have been
feasible.
This
was made
clear
to
Mr.
Corbett.
I
do
not think
Dr.
Corbett accepted
at
face value
everything
Mr.
Eichhorn
said;
he
was
plainly
unconvinced
by
Mr.
Eichhorn'
s
presentation to
him
in
April
1987, and
his
doubts,
even
after
May
1987,
when Mr.
Corbett
had
made
his
own
presentation, are
referred to
in Exhibit
46.
In
my
opinion
Mr.
Corbett
would
not
have been
acting
reasonably
in
accepting
everything
Mr.
Eichhorn
said
as
the
literal
truth,
as
wholly
reliable.
It
has
to
be
recalled
that
the
context of
their
early
discussions
was Mr.
Eichhorn'
s
attempting
to
persuade
Mr.
Corbett
to
install
an
O.M.A.
marina
at
Repulse
Bay.
Mr.
Eichhorn's
recollection
of
events
in
1986
and
1987
is
not
entirely reliable, in
my
view,
at
least his
account
of
them
at
the
trial
is
not.
On
that
account he
presented
the
-- 52 of 115 --
52
O.M.A. project to Mr. Corbett as so speculative that no one in
his right mind would have wished to get involved. Thus, in
Exhibit 125, Mr. Eichhorn says that at the first meeting:
"I told Corbett that ... the exact physical capabilities of
the system were still somewhat unknown although the
mathematics were that the system was stronger and
cheaper, I believed, than its competitors ... I believed
that this system would last (20 years approximately). I
again told Corbett that the system had not been
constructed and that most of this was conjecture."
I do not believe that Mr. Eichhorn qualified his
statements as he claimed by indicating they were simply
matters of his belief, nor that he indicated anything was mere
conjecture, nor that he indicated the capabilities 9f the
system were unknown. I do not believe he gave the slightest
intimation that the system might not work. Throughout his
evidence Mr. Eichhorn presented the O.M.A. system as a mere
"concept". He did not present it to Mr. Corbett as such; he
is reconstructing the situation wrongly when he says, for
example, that Mr. Corbett said "that he liked the system which
we were developing", if that is intended to convey that the
system had not got much beyond the stage of being an idea.
I do not believe Mr. Eichhorn that Mr. Wright said of
Exhibit ANC 3 to Exhibit 1, the Harbours and Marine Department
"Section 86 approval" that:
"Harbours and Marine have not approved the marina system;
all they have approved is the installation of that system
at that particular site based on calculation~ provided so
far".
(In my opinion, however, the qualification in the document is
patent and Mr. Corbett acting reasonably ought to have picked
it up for himself.)
-- 53 of 115 --
53
I do not accept
Mr.
Eichhorn'
s
statement that
- "At
all
times, Corbett
was
being told that the
O.M.A.
system was under
development and going through continuing design changes and
alterations,"
if
that
be intended to
convey
that
O.M.A. was
still
without
a
product ready
for
the market.
An
allegation of
Mr.
Eichhorn's
which
is
wrong
is
that in
June/July,
1987 Andrew
Corbett suggested
putting
a
polyethylene tank
on
the
System
2
marina, which
was
until
then
a
coffin
type,
and
against
Mr.
Eichhorn's objection
and behind
his
back,
had.
O.M.A.'s
staff draft
up
such
a
tank
for
System
2.
Exhibit
65
shows
that
System
2
had
this
feature
by
March
1987
and
Mr.
Eichhorn
was
evincing his usual enthusiasm
for
it,
in
a
submission
to
a
Minister of the
New
South
Wales
government.
In
human
terms,
Mr.
Eichhorn
may
have
a
justifiable
grievance
against the Corbetts
arising
out of
his
exclusion
from
o. M.A.
in
November,
1 9 8 7 . They
went on
to
make money
through
I.M.S.,
rendering
his
option
to take
20
per cent of
O.M.A.
for
a
nominal
consideration
when
it
achieved
profitability
valueless.
It
may
be
that
a
sense
of resentment
has coloured
his
attempts
at
reconstructing
the
events
of
1986-87 and
led
to
some
carelessness.
I
do
not
think
he
was
deliberately
presenting
false
evidence,
but
his
account
is
unreliable in
a
number
of
important
respects.
Unfortunately,
great bitterness
and
hostility
between
Mr.
Corbett
and
Mr.
Eichhorn developed,
as
evidenced
by
the enclosure
to
Exhibit
31,
a
letter
of
12th February,
1988
of
solicitors
nominally
acting for
O.M.A.,
but
plainly
taking
instructions
from
-- 54 of 115 --
54
Mr.
Corbett. (I
may
say that
I
take this letter into account
in assessing
Mr.
Corbett's evidence. His
hostility to
Mr.
Eichhorn
is
of limited importance, since the thrust of his
evidence
was
to implicate
Mr.
Wright and
the
first
defendant,
at
a
time
when
the action
was
obviously conceived as
Trade
Practices
Act
proceedings.)
I
do
not
reject
Mr.
Eichhorn's evidence
in
its
entirety.
For
example,
I
accept
his
evidence
that
Mr.
Corbett
from
quite
early in
1987 was
active in
O.M.A.'s
affairs rather
than
Mr.
Corbett's indirect
suggestion, (see paragraphs
35,
63
and
67
of his
affidavit), that
he had
only
limited
involvement
until
after
September 1987.
I
accept
his
evidence
that
handwritten
costings for the
"Yap
project"
in
Exhibits
ANC
13
are
Mr.
Corbett's
not
Mr.
Eichhorn's.
Correspondence
in
that exhibit
shows
Mr.
Corbett
was
negotiating
a
joint
venture
for
O.M.A.
in
April,
1987.
Mr.
Corbett
is
wrong
in
paragraph
48 "in
suggesting
indirectly that
he
received
no wages from
O.M.A.
until after
October,
1987,
also in
stating that
O.M.A.
's
business
activities
ceased
in
December, 1987.
Unimpressive
aspects of
Mr.
Eichhorn'
s
performance
were
his
depiction
of
the
O.M.A.
system
as
a
mere
concept
or
idea;
this sat
most
unhappily with
documents
emanating
from him.
Unimpressive,
too,
was
a
tendency
to
resile
from
documents
signed
or ostensibly
prepared
by
him, and
to
blame
Mr.
Corbett
for
their
contents.
Generally, the
only sense
in
which
I
think
he
presented
the
O.M.A.
system
to
Mr.
Corbett
as
in
course
of
development
was
that
it
was
being
refined
or
improved.
He
presented
-- 55 of 115 --
55
O.M.A. as having, at all
times,
a
saleable product.
He
believed that
was
the case
and indeed
it
may
have been so.
Potential clients
were
interested in the product.
If
only
a
substantial contract for installation of
a
full
O.M.A. marina
had
come
about,
it
may
well
have been
satisfactorily
executed.
The
Corbetts accepted,
and
it
is
obviously the case,
that
a
good
deal of the
design
and
engineering
work
is site
specific,
and
cannot be
done
until
the
client's
requirements
of the
marina and
site
conditions are
known.
In
that
sense the
Corbetts cannot
have
thought the system
"fully
engineered".
Mr.
Corbett
would have
seen
for himself
a few
months
into
1987
that
it
was
not.
No
one can say
that
Mr.
Wright
or
some
other
engineer
would
not
have
provided
a
final
design
which would
have worked
in practice,
even
if,
theory,
it
seemed
structurally
as
a
matter of engineering
deficient
for the design
conditions.
Had Mr.
Eichhorn's salesmanship
been
more
successful
or
had
those
clients
who
wanted
O.M.A.
marinas been
financially willing or able to
commit
themselves,
O.M.A. may
well
by
now
have
been
very
successful.
Liability
of
Mr.
Eichhorn
The
liability
of
Mr.
Eichhorn
is
not
at
all
straight
forward.
following
Corbett:
The
statement
of
claim
alleges
against
him
only
the
misrepresentations
as having
beeri
made
to
Mr.
(a)
The
O.M.A.
System was
better
than
other
systems
for
the
construction
of
a
marina
which
were
then
available;
(b)
The
O.M.A.
System
was
a
lot
stronger
than
other
systems;
-- 56 of 115 --
56
(c)
The O.M.A. System was
lighter
and cheaper to build than
other systems;
(d)
The O.M.A.
System had
a
longer
life
than the system used
by
a
competitor, Pacific
Marinas.
If
statements in those terms were made,
I
consider they
were
in
a
context
where
"puffery"
was
legitimate,
and
to
be
expected,
and
that
they
were
not presented or
accepted as
scientific
or absolute
truths; in
my
view,
in context, they
would be
understood as expressions of opinion.
The
plaintiffs
do
not plead
and have
not
established that
those four
statements are untrue;
what
they
do
plead
(by an
amendment
during addresses)
is
that
the statements
should
not
have been
made
because
there
were
defects in the engineering design
of
which
Mr.
Eichhorn should
have been aware.
I
am
not prepared
to
find
Mr.
Eichhorn
liable
on
that
ground.
I
do
not regard
him
as ever
having claimed
engineering
expertise.
The
plaintiffs
plead,
in
addition,
that
everything
Mr.
Wright
did
was
done
as agent for
Mr.
Eichhorn,
(
as well as
agent
for
Wright
&
Francey
Pty.
ltd.).
Such
an agency
is
made
out
to
my
satisfaction,
largely
on
the
basis of
Mr.
Wright's
evidence,
which
was,
of
course, presented
on
behalf
of
Mr.
Eichhorn
as
well as
on
behalf of the
other
defendants. Generally,
Mr.
Eichhorn
was
there
when
Mr.
Wright spoke
to
Mr.
Corbett,
when
plans,
drawings
and
calculations
were
discussed
and
the
like.
Mr.
Corbett
was
very anxious,
I
think,
to
be
convinced
of the
merits of the
system
and
to participate
in
its
hoped-for
success, but
part
of
Mr.
Wright's function
was
to
serve
Mr.
Eichhorn's
interest
as
94
per
cent
owner
of
O.M.A.
by
-- 57 of 115 --
57
informing
Mr.
Corbett either as
a
prospective purchaser or
(later) as
a
pro·specti ve
partner, as to the features of the
system, and
its
merits in particular.
The consequence
is
that,
if
Mr.
Wright
is liable for negligent misrepresentation
so
is
Mr.
Eichhorn.
It
cannot help
him
that
he
may
have had
every reason to repose confidence
in
Mr.
Wright, and
in
a
moral
sense
may
be
blameless.
So
far
as
alleged
liability
to
Dr.
Corbett
and
the
fifth
defendant
is
concerned, the
plaintiffs rely
upon
what
Mr.
Corbett passed
on
of
Mr.
Wright'
s
representations,
and
in
addition
Mr.
Eichhorn's representations
in his
meetings
in
Sydney
in
April
1987
with
Dr.
Corbett.
These
are pleaded as
follows
in
para.
29
of
the
Statement
of
Claim:
(a)
The
first
and second
defendants
had
done
detailed
engineering analyses
and
calculations to
ensure
that
the
system
would
succeed;
(b)
The
system
was
now
the
most
advanced system
for
any
general
marina used
in
the
world;
(c)
All
which
was
needed
for
the
commercially
was
working
capital
product;
system
to
succeed
to
build the
first
(d)
The
"pay back
time"
would
be
short for
an
investor
as
the
system
was
already
fully
developed,
and
could
be
implemented
as
soon
as
the necessary
working
capital
was
available;
(e)
The
principal
competition
of
the
system
was
that
produced
by
Pacific
Marinas,
which
was a
lightweight
and weaker
system
and which
was
more
expensive;
-- 58 of 115 --
58
(f) The O.M.A. System was much stronger than other systems,
and it could withstand conditions of strong wind, waves
and currents which could not be tolerated by the Pacific
Marinas system or any other systems;
(g) The O.M.A. System would last for 20-30 years;
(h) The O.M.A. System was cheaper to produce than competitive
systems.
Again, the plaintiffs do not plead the falsity or
misleading nature of those statements, founding their claim of
negligence on the allegation that the engineering design was
defective, and that the defendants should have known it. The
lead-up to the meeting was a telephone call to Dr. Corbett by
his brother. Dr. Corbett's evidence in chief was:-
"You are aware of a marina system?-- In 1987 in
about April. I may have heard a little about it,
but the first time I heard in any detail was in
April.
From whom did you hear of the existence of this
system?--
From my brother."
"What did he tell you about that system?-- He told
me that he had been involved as a partner in a
business called Offshore Marinas since the latter
part of the previous year which would have been 1986
and he outlined roughly what the system was about.
He told me that it was a specialised design that
consisted of a concrete platform or a series of
concrete platforms joined together; that it floated
by means of some plastic tanks which were made into
a specialised shape and that this was a highly
engineered structure which made it possible to
manufacture a marina of much more modern design than
had been in existence before. He said that he had
become involved as an investor in this project after
discussions with a number of people. He
particularly mentioned a Greg Eichhorn who he said
had previously brought it to him, and that the
engineer who was involved in the project with whom
he also had discussions was a Geoffrey Wright, of an
engineering firm called Wright & Francey of Nerang.
He told me that the project had developed to a stage
-- 59 of 115 --
59
where the engineering work was complete, but there
was a lot of work available; that jobs were able to
be obtained but that the partnership had
insufficient money to be able to move to a
production phase and that in order to be able to do
that they needed money specifically for making
moulds and there were two types of moulds. There
was a type of mould for making plastic floats and
that he said was a rotational mould, and there was
another type of mould of which there would be a
number of units but these moulds were for pouring
concrete and particularly for pouring concrete in
what I was told was stressing beds which I
understand - I was told that cables would be put
through and tensioned so he said that this project
is one that he was involved in. He said that it had
become too big for him to be able to finance to the
necessary extent and he asked me whether I was
interested myself in being an investor in it or
whether I knew any groups that I could introduce the
project to which might potentially be investors.
How long did this conversation take - an hour, half
an hour?-~ Of that order. It was a reasonably long
conversation, probably less than an hour, maybe half
an hour.
How was it concluded?-- I told him that I was
unlikely to be involved or introduced personally
because I said at the time I was very committed with
my time more than anything but I said I did know a
number of companies and that I was - that were
potentially interested. I told him of one
particular company of which I was a director that
might be prepared to consider it and I suggested
that he send me more material about it.
Was it agreed that he would send you more material
or someone else would come and see you?-- He
suggested that the best thing was to have Greg
Eichhorn see me ... "
I accept that evidence, except that Dr. Corbett, in my view,
is shown to have had some connection with the business to the
point of having himself registered as a partner in January
1987. In general, I accept Dr. Corbett's evidence as to what
passed between him and Mr. Eichhorn at their meeting in
evidence in chief and cross-examination. Part of his evidence
-- 60 of 115 --
60
in chief after a description of the system and its history (as
per Mr. Eichhorn) was:
"In relation to the Rose Bay plans or the Taylors
Bay plans, did he suggest that any more engineering
analysis had to be done to build these things or did
he suggest-----?-- He made the point that there
were always some site-specific elements, in any
project there was some elements which would vary
from one location to another, of - for instance, the
number of floats would differ in one marina
application to another marina application.
Yes?-- The shape in which the pieces were fixed
together would vary from one marina development to
another marina development. One might be designed
for a lot of boats; one might be for a small number.
The Rose Bay one had a particular feature that it
was designed to have a boat facility and perhaps
restaurant, or a service facility in a central hub,
and that wasn't specific to every development. Some
marinas would not have a radial design with a
central hub and the method of fixing would vary to
an extent. One place might have deeper water than
another. They can't all have the same anchor
system. It would vary according to the size of the
marina. A big one would have a bigger anchor and a
smaller one a smaller anchor. He said there was
differences which applied from one location to
another, but the basic modules, the building blocks,
were common and that - he talked about arm units and
finger units, and these became modules which were
linked together in various ways according to the
requirements of a particular application.
Yes?-- Those, and the engineering designs in
general, he said, had been worked on for
approximately ten years. They had been approved by
various authorities and they were at a very
developed stage where the only thing needed was to
make the moulds and actually pour them, both in
concrete and plastic.
Did he mention to you who had done the engineering
analysis in these plans over the ten year period?--
Yes, he told me that Geoff Wright, of Wright and
Francey, had been the engineer who had taken his
own- his is Greg Eichhorn' s - conceptual designs.
He said it was his original concept and he said that
the engineering work and the detail drawings and the
calculations had - all of the detail engineering had
been carried out by Geoff Wright of Wright and
Francey. He said that there were other people who
had also been used. He made reference to quite a
-- 61 of 115 --
61
lot of other outside experts
who had been consulted
II
....Mr.
Eichhorn
told
Mr.
Corbett that the
1981 and 1982
Kangaroo
Point calculations
on Wright
&
Francey
letterhead
were
detailed engineering calculations that
were
part of the
verification
of the
system; he
referred to
Mr.
Wright's having
engaged
outside consultants as considered necessary.
Dr.
Corbett
went on:
"MR.
BOWDEN:
Did he
say anything about
the
need
for capital for this
business?--
Yes,
he
did.
What
did
he
say about
that?--
He
said
that
theproject
was
ready
to
roll,
that
it
had
reached
a
stage
where
there
was a
lot
of
work
which
- a
lot
of
orders; in other
words, which were
available orlikely to
be
available,
and
that
the
only
thing
necessary
to
be
able
to
take
advantage
of those
orders
was
to
put the
system
into
production
and
that that
needed
money. I
recall
a
particular
project
he
talked
about
was
Yap
but
he
talked
about
a
number
of projects,
but
he
said
that
the
money was
needed
particularly
to
make
moulds
and he
talked
about
the
same
sorts
of
moulds,
some
plastic
types,
and
the
rotational
moulds, and
some
concrete
moulds
for
making
the
arms and
fingers,
and
he
said
that
other
money
was
needed
just
for
running
the
company
but
he
said
that
the
profit
margins were
high.
He
said
that
the
cost of
this
product
was
of
the orderof
- I
think the figure
was
$4,000. There
appeared
a
figure of the order of
six
or
$7,000
which
the
Pacific
Marina
system
sold
for.
We
are
talking
about
the
entire
system
or
a
part
of
a
system?--
The
cost
of
a
berth.
Of a
berth
for
a
boat?--
Yes,
because
that
was
really
multiple.
He
said,
therefore, there
were
high
profits; that
we
could expect
profits
of
the
order
of
40
per
cent
-
30,
40
per
cent.
I
think
he
may
have
used
different
figures
at different
timesbut
40
per
cent
is
a
figure
I
have
in
my
mind.
So
he
said
there
was
a
lot
of
money
to
be
made
but
this
system
had
to
be
physically
produced
or
- when I
say
system,
the
components
had
to
be
physically
produced
and
until
the
money was
there to
actually
set
up
production, they
could
not take
advantage
of the
orders
which were
there.
Conversely,
as
soon
as
money was
there, there
was
a
lot
of orders,
in his
opinion,
to
be had.
-- 62 of 115 --
62
Did you
talk about
how much money might be needed?--
Yes, he did.
He
thought the figure
was
of the order
of
$100,000, perhaps
a
bit
more, but that
was
the
order of magnitude.
Well,
did
you make a commitment -
sorry, did
you
talk
about the ownership
of
O.M.A., who owned
what
at that stage?--
Yes.
He
said that the current
partnership consisted of himself
and
my
brother,
Andrew
Corbett,
and Geoff Wright.
I
believe
he
saidthat
Geoff
Wright's
interest in
it
at that
time
was -
it
might have been
1 0
per cent
or
it
might
have been
some
slightly different
per cent, but
it
was a
percentage
like that.
Perhaps
it
was
more.
I'm not
certain of that
exact figure, but
he
saidthat
how
this
operated
was
that
Geoff Wright had
become a
partner
because
he
believed
that
the
system
would have
a
lot
of
commercial
success, so
that
instead of
Wright
&
Francey
charging
fees,
or
Geoff
Wright
charging
fees,
they
would
receive instead
consideration
in the
form
of
equity
and
debenture.
So
the proposal
was
for
another party
to
come
in
and
to
have
equity,
in
which
case
everybody
else
would
dilute their
equity.
I
think
he
probably
said that
Mr.Wright had
a
higher equity
at
that
time
and
that
they
would
all
dilute
down."
Dr.
Corbett
and
his
partner(s) in
the
company
which
was
considering
an
investment decided
that
Dr.
Corbett should
go
to
the
Gold
Coast and
investigate further.
He
saw
his
brother,
who
had
many
more
documents
than
Mr.
Eichhorn
had
brought
to
Sydney:
"What
did
he
say
to
you
about
the
quality of the
system?--
He
said that
he
had
seen
that
same
material;
that
he
had
talked to
the
same
people;
that
he
had
satisfied
himself
that
Wright
&
Francey
was a
well-known
engineering
firm;
he had
talked
to
Mr.
Wright
himself;
that
he
was
convinced
from
those
events
that
it
was
what
it
was
claimed
to
be,
in
other
words,
a
very
up-to-date
modern
system,
well
engineered
and
ready
to
produce.
He
said
that
the
project
had
just
become
too big for
him,
that
he
wanted
to
remain
in
it
but
he
didn't
have
thefinancial
resources
to carry
it
through
because
-
well,
simply
that.
Did
you
make a
commitment
at
this
stage
to invest?--
!
went
back and
talked
to
David
Lance
again
and
we
decided
that
it
sounded
a
good
system
but
it
was
not
an
appropriate
investment
for
that
company,
so
I
-- 63 of 115 --
63
rang and advised that
we
wouldn't be able to put
-
we
wouldn't be able to put
money
into
it.
You
advised who?-- I
believe
I
advised
my
brother."
The
next approach
to
Dr.
Corbett
came a month
or so
later,
from Mr.
Corbett again,
and by
telephone. Attribution
of the phrase "ready
to roll" to
him
as well as to
Mr.
Eichhorn demonstrates
that
Dr.
Corbett
is
not
to
be
relied
on
entirely
as
to
accounts
of
words
used
-
he
has engaged
in
a
good
deal of reconstruction
just
as
have
Mr.
Wright and
Mr.
Eichhorn.
Of
his
brother
Mr.
Corbett
said:
"Can you
tell
us what
was
discussed?--
Yes, he
talked
about Offshore Marinas
again.
He
said the
system
was
ready
to
roll
and
first
orders
would
probably
be
received
very soon.
He
talked
specifically
of
a
job
at
the
Spit
down
on
the
Gold
Coast.
He
said
it
needed about
$210,000
to
$220,000
of
working
capital.
He
asked
me
whether
I
would
put
that
money
in or could.
He
said
there
was
a
high
profit
margin so
he
said that for
instance the Spit
job,
there
was a 30
to
40
per cent
profit
margin
available.
He
said
that
management
was
in
place.
He
mentioned
Greg
Eichhorn as
the
person
who was
thesenior
manager.
He
said that
all
engineering
was
final
except for
site
specific details
which he
called fine print.
He
summarised
the
fact
that
the
shareholders
were
himself,
Greg
Eichhorn, Geoffrey
Wright
of
Wright
&
Francey.
He
said that his
input
had been
supplying
cash
for the
previous
six
months
in
return for
equity;
that
Eichhorn
was
responsiblefor
the
calculations,
engineering input
details etc.
He
said
that
they
were
offering to
an
investor
20
per cent
of
the
project for the input of
the
sum
of
$140,000.
He
said
that
cash flows
and
financial
information
were
available;
that
the
money
that
they
were
seeking
would
be used
for
moulds
for
boats
which
was
particularly for
a
work
boat,
for
a
crane,
for
a
winch
platform,
and
for
a
plastic
moulder;
that
these
various items
would
be
available for
other
jobs
in
addition
to
the
immediate
questions
so
they
would
be
used
on
an
on-going
basis.
He
referred to
a
Qintex
project
at
Southport
Spit
with
20
berths,
a 350
job
at
Southport,
a
job
at
Jacob's
Well
for
108
followed
by
360
berths,
a
400
berth
marina
at
Mackay, a 75
berth
marina
at
Yap,
a
350
berth
marina
at
Hervey Bay.
He
specifically
said
when
research
and
development
was
finished
that
he
would.
send
me
information
and
in addition
he
-- 64 of 115 --
64
referred to
a
project at
Rose Bay
with
400
berths
and
at
Woolloomooloo
with
400
berths so he
- andthen reiterated his previous investment request of
whether
I would
reconsider.
Did you
reconsider immediately?--
He
had promised
to
send information so
I
asked
him
to
do
that
and hedid so and
I
then considered
that
information in
addition."
A
doubling of the capital said to
be needed
set
no
alarm
bells
ringing.
The
material
Mr.
Corbett sent
is
ex. 12.
Dr.
Corbett's description of his reaction to
it
included the
following:
"
Well,
I
took
it
to
show
that
the technology
which had been
described
to
me
and
the designs
and
the
system
was
in fact part
of the
company
and
that
the
originator,
Mr.
Eichhorn,
and
the engineer,
Mr.
Wright, had
in
fact
transferred
this into
the
entity that
I was
being
invited to join.
I
took
it
to
show
it
was a
very
advanced
stage
because they
were
specifically
what
the
document
headed
"Construction
and
supply
contracts current
position" indicated
in
various
parts.
I
took
it
to
-
from
the
fact
that
the
financial
summaries
referred
specifically to
production matters
that
it
was
consistent
with
what
I
had
been
told;
that
theproject
was
ready
to
be
put
into
production
and
I
took
it
to indicate
that
there
was
also
high
potential
because
the
profit
margins
being
indicated
were
in fact
high.
There
were
a
great
many
jobs,
10
I
think
listed
with
rather
large
numbers
of
marina
berths
from
memory
somewhere
between 2,000 and
3,000
as
a
potential
number
and
I
had been
told
that
the
expected
profit
per
unit
was
of the order
of,
well,
that
the competitor
was
selling
it
for
something
like
3,000
to
4,000 more.
Therefore
that
was a
high
profit
margin
per
berth.
It
was
confirmatory
of
what
I
had been
told
previously
and
was
consistent
with the information given
in
the
earlier
meetings.
What was
your
response
to
this particular
communication?--
I
decided
that
I
would be
prepared
to
put
money
into
it
and
I
told
my
brother
that
he
could
-
that
I
would
do
so
and
he
could pass
that
on
to
the
group
-
to
his partnership."
Mr.
Corbett's
covering
letter
was,
in
part:
"Essentially, in
order
to
get
'the
system'
in
the
water
to
enable
us
to substantiate
our claims
as
to
feasibility
and
superiority
over Wilkins
and
Davies
-- 65 of 115 --
65
and Pacific Marinas, we have reduced our normal
margin on the Spit job to effectively $200,000 on a
job of $700,000 cost to us ( 700K+200K-900K). Since
we only plan to execute a Contract whereby our
outgoings ($700,000) is incurred back to back with
cash drawdowns and also since we have loaded the
profits into stage one, we feel we are very safe
indeed and
our $200,000 profit on stage one is obviously about
50%.111
The cash commitments yet to be 'covered' are as
follows:-
1 x Rotational Moulding Machine Manufacture
1 x Mould for floats
Set concrete deck moulds
1 x Floating Winch Platform Construction
(Made by A.C.N. at about half cost)
2 x Workboats (rubber)
30 tonne Site Crane (Pin Jib)
Operations of Company for months of July,
August and September
50,000
5,000
65,000
12,000
16,000
30,000
35,000
$213,000
I have obtained approval from the other directors of
our shelf company (Pocket Valley Pty Ltd) to offer
your 20% @ $7,000 per per cent interest. This is
obviously $140,000. (See 2).
However, I am happy to sell your share to Balmoral
or a new investment company to be taken over by
Richard Tinsby since he has also expressed interest.
I would propose that such a 'sell on' if desired by
you be a $10,000 per share ( 100 shares in Pocket
Valley Pty Ltd).
In any case, I am extremely thankful for your
support in getting this off the ground and
appreciate that you are really only doing it for me
personally - we will all work very hard here not to
let you down.
In the meantime
finance to a loan
on my house so
liquidity."
I have an approval by Network
for $60,000 against a 2nd Mortgage
that we will not be short on
The penultimate paragraph, in my opinion, accurately
identifies fraternal support as one of the main considerations
moving Dr. Corbett. Another, undoubtedly, was the prospect of
quick profits from contracts which O.M.A. hoped to win. Those
-- 66 of 115 --
66
considerations were each quite as vital as any confidence
Dr. Corbett
may
have
felt
in the product and
its
engineering.
As
to that, in
my
view,
Mr.
Corbett, in his statements to
Dr.
Corbett
went somewhat beyond
the representations as to the
finality
of the engineering
which had been
made
to
him.
On
this
aspect,
Dr.
Corbett remained
sceptical.
I
set
out in
full
his
letter
of 4th June, ex.
46, which
limits
the reliance
Dr.
Corbett can claim
to
have placed
on
Mr.
Eichhorn's
representations
as presented
in
the cross-examination
at
pp. 104. 5:
II
Dear
Nev,
Dr. John
L.
CorbettSuite
4.1,
320
St.
Kilda
Road,Melbourne,
Vic.,
3004
Telephone:
699
1433
Thanks
for the info
on
the
marina
project in
your
fax
on
30th.
As
I
told
you,
I'm
absolutely
flat
out here
-
Kemtron
has loads
of
problems
still
and
I'm
just
too
busy
to
come
up
to
look.
It
all
seems
o.k.
but
it's
a
lot
of
money.
You'd need
to
triple
check
the
cost
calculations
and
projections
and
be
sure
they're
met.
Absolutely
essential
too
to
be
certain
you
can
rely
on
the engineer
you
already
known how
expensive
R & D
can
be and
I
want
to
be dead
sure
this
is
a
finished
project
needing
production
secondary only
-
not
R & D.
So check
it
with
Wright
to
be
sure.
Even
then, I'm
wary
without
seeing
it
and
beingable
to
understand
it
all
personally
-
but
there's
no
chance
I
could
leave here yet
-
I'
11
try
though
to get
up
ASAP.
Will
you send
me
more
info
meanwhile
-
esp.
more
on
the technical side
and
more
re
costs/markets/margins.
I
guess
I'll
back
you,
but
the deal
sounds
toosteep
even
if
the
project
is
good
- $140K
for
20%
=
$700,000
for
100%:
that's
a
lot
when
there
have
not
been
any
put
into
the
water
yet
-
even
with
the
engineering
work
done,
there's
bound
to
be
a
lot
of
fiddling
yet
before
it
settles
down.
Will
you
talk
-- 67 of 115 --
67
to your partners
and
try to improve the deal.
I'll
send you the 1st
$SK you want tomorrow
in the
meantime.
I'
11 need
better notice before other
payments though. But, be bloody
certain these
guys
are
O.K.
This
is
rushed
-
will
be
in
touch
v
soon.
Love,
John."
There
is
nothing to suggest
Mr.
Corbett
made
any
further
inquiries of
Mr.
Wright
or
Eichhorn
whose
purpose might have
been
identified to
them
as the reassurance of
Dr.
Corbett.
It
does
not appear
Dr.
Corbett
was
sent
"more on
the technical
side". Just
about the only
effect
of his
letter
was
to
improve what he
was
to get for his
money.
Instead of
20
per
cent for
$140,000.00 he
was
to get
up
to
30
per cent
at
$5,000.00
for
each
one
per cent, according
to
para.
43
of
Mr.
Corbett's affidavit.
(Dr.
Corbett says
at
p.
119
of the
transcript
the
ceiling
was
to
be
20
per cent, but
up
to
$50,000
was
to
be
provided as
a
loan).
By
the
time
Dr.
Corbett decided
to invest, the
representations of
Mr.
Eichhorn
had
receded
well
into
the
past,
and had been
overtaken
by
the
more
persistent
and
equally confident
representations
by
Andrew
Corbett.
Nevertheless,
it
was
open
to
Dr.
Corbett
to
place
reliance
on
what
Mr.
Eichhorn
had
said in
April,
and he
did
so,
relying
equally
on
what
his
brother told
him. The
plaintiffs
have
not
made
out
the
allegations of
para.
29
in their entirety.
The
"warranties"
or
assurances
of
success
in
(a)
and
(c)
or of
a
certain
20
to
30
years
of
life
are not established
(
in
the
sense
that
in
my
view
Mr.
Eichhorn
was
conveying
opinions),
nor
the
element
in
(d)
expressed
in the
words
"as the
system
-- 68 of 115 --
68
was
fully developed"
.
Further the allegation of the O.M.A.
system being cheaper than Pacific
Marinas (the only one with
which comparisons
are
shown
to
have been expressed)
to
manufacture are not
made
out.
There were
suggestions
that the
O.M.A. system, being heavier,
might be
more
expensive
to
manufacture, but
that
O.M.A.
could produce
to
sell at
a
price
competitive with
Pacific
Marinas.
29
and 107.
See
the transcript at
pp.
Mr. Bowden
has persuaded
me
on
the basis of authorities
such
as
Banque
Commerciale S.A.
v.
Ankhil Holdings Ltd.
(1990)
92 A.L.R. 53,
58-9,
Dare
v.
Pulham (1982)
148
C.L.R.
658
and
Gould and
Birbeck
and
Bacon
v.
Mount
Oxide
Mines
Ltd.
(1916)
22
C.L.R.
490,
517-8
that
it
is
not necessary
for the
plaintiff
in
this
case to "score
a
bullseye"
and
establish
the
representations
pleaded
to the
letter.
I
am
satisfied that
Mr.
Eichhorn
(
and
Mr.
Corbett
even
more
strongly)
effectively
represented
to
Dr.
Corbett
that
the
O.M.A.
system
was
developed
and
verified
by
engineering
investigations
and
calculations to
the point
of
being
able to
be
put
into
production
immediately.
Dr.
Corbett
was
fully
aware
the
system
had
never
been
tested,
and
that
further
engineering
work
was
necessary
on
all site
specific
questions
and
other
matters
such
as
the
design
of
concrete
moulds.
Such
a
representation
was
misleading
not
only because
the
engineering
was
such
as
would
not
command
general
acceptance
by
engineers
(which
is
the
foundation
of
Mr.
Wright's
liability
for
making
representations
in effect
to the
contrary) but
because
there
had been
no
detailed
engineering
-- 69 of 115 --
69
work
since 1981-1982 and there had been
significant changes in
the system by
the elimination
from
the
arm
unit deck of
a
central services channel and
a
radical redesign of the
shape
and placement
of the "legs" of the double
tee section
which no
longer
were
placed
at right
angles
and
at the
extreme edges
of
the
deck; they
were
recessed
and
placed
at
a
slant to afford
an
alternative location for services.
No
work
at all is
shown
to
have been done by
April
1987
to
attempt
to verify
the
structural integrity of the
system so revised.
Nor was any
work done
to establish
the
structural integrity
of the
"blown
up"
version of
this
revised
system
promoted
in
March 1987 by
ex.
65.
Mr.
Eichhorn ought
to
have
known
all
of
this
when
he
went
to
see
Dr.
Corbett, as indeed should
Mr.
Corbett
in
April
and
May
1987.
Mr.
Eichhorn
owed
Dr.
Corbett
a
duty
of care.
He
regarded
Dr.
Corbett as already
a
partner,
and
must
have
known
that
he had
little
personal
familiarity
with
O.M.A.
affairs;
he
volunteered
in
p.
125
that
their
"meeting
was
as
a
result
of
Andrew
Corbett's
request
to
me
to
go
down
to
Sydney and
discuss
with
John
Corbett
his investing
further
money
in
the
O.M.A.
System."
He
said:
"I
did
tell
John
Corbett
that
the
system needed
working
capital.
This
was
to
pay,
apart
from
other
matters, for
further
engineering advice
to
be
given
in
respect of
the
detailed
formulation
of the
marina."
This
last detail
was
not revealed
to
Mr.
Corbett;
Mr.
Eichhorn
does
not
say
that
it
was;
it
should
have been.
The
consequence
is
that
the matters
leaded
in
para.
29
lead
to
-- 70 of 115 --
70
liability in
Mr.
Eichhorn to Dr. Corbett and the fifth
plaintiff in principle.
Progress of the
O.M.A.
Business
Notwithstanding the
terms of
a
tenancy agreement running
from
1st April,
1987,
O.M.A. moved
into
new
premises
some
time
earlier
than
that date,
as
early as January according
to
Mr.
Torti.
They
had been vacated
by
the
first
defendant,
which
moved
across the corridor to
a
larger office.
O.M.A.
acquired
a
number
of
staff,
especially
skilled
draftsmen,
one
of
whom
was Mr.
Torti,
who was
engaged
to operate
his
own
Computer
Aided
Drafting
system. This enabled plans,
once
drawn and
stored in the
computer,
to
be
amended
readily
and
cheaply.
It
enabled
the
O.M.A.
System
2
plans
in
ex.
93, and
ex.
65
to
be produced
by
the expedient
of enlarging the
System
1
plans
and
changing dimensions.
Mr.
Torti's
evidence,
which
I
accept, included the
following:
"Well,
I
was
engaged
to
draw on
the
computer
drafting
system and
my
understanding
was
that
all
the
things
we
were doing were
leading
towards
a
final
product, so
a
design
and
development
over
that
period, probably going as
far
through
as
to
August
when I
finished.
You
said there 'design
and
develop'. In
this
period
I
was
ref
erring
you
to
from
January through
till
about
April.
What
sort
of
things
were you
designing
and
developing?--
Well,
in conjunction with
other
people
in
the
office,
anything
from
the
concretefingers
and
arms
through
to the polyethylene tanks,
stainless
steel
hinges, lengths
and
catenary
of
the
anchoring system
-
basically
the
whole
system.
In
this
period
you
mentioned
that
you
were
doing
some
work
on
the
arms
and
fingers.
Exactly
what
was
that
work?-- Well,
there
was
some
preliminary
sketches
there
with
basic
shapes
but
we
had
to
fine-tune
those
shapes
so
that
they
would
suit
moulding
so
that
we
could
design
the
reinforcing
which
had
not
been designed
at
that
stage,
showing
covers
to
the concrete,
concrete
mix,
the tension
-- 71 of 115 --
71
strands, so that all that stuff
would
actually
fit
in the shapes that
were required.
You
said 'concrete strands'
,
what
did you
mean by
that?--
Well, the stressing tables that
hold
-
the
system
is
post-tensioned together
and
the
numbers
of
strands, the size of
them, how
they are
anchored,
all that sort of thing.
And
this hadn't
been done
previously?--
No.
From
what
you saw?-- There had been
some
preliminary
working
but the
detail
and
the
actual
stuff
had
not
been
detailed.
And
this
is
what
you
mean by
design
and
develop
these?--
Yes.
You
said
you were
also
doing
in
this
period
something
to
do
with the
PE
tanks.
What was
that?--
Well,
again
there
was
an
overall
envelope
shown
on
the preliminary sketches but there
was no
detail,
no
ribbing
shown,
not
to
my
recollection
-
there
was
no
actual
dimensional
size,
thickness of the walls of
the tank,
mounting
points,
all
that sort
of thing.
And
you
said also
that
there
was
something
with
respect to
the hinges.
What----?--
Well,
there
was
just
a
notation
on
the preliminary sketch,
'hinge',
so
there
was
no
detailed
design
on
the hinges
to
take the
stresses
imposed
upon
it.
Also,
we
looked
at
the
type
of material
that
had
to
be
made
out
of
-
so
that
it
could
cope
with the
extreme
conditions
being
close
to
salt
water,
that
sort
of thing."
"You
are saying
that
you
are
doing
this
design
anddevelopment on
these
drawings
and
you
have
indicated
a
number
of matters.
Were
you
doing
them
over
in
a
corner, as
it
were,
by
yourself
or
were
other
people
working
in
conjunction
with
you
in
this
period
from
January through
till
April?--
No, I
couldn't
possibly
do
it
by
myself. Geoffrey
was
involved,
Greg
was
involved,
Andrew
Corbett
made
comment, you
know,
the
same
as
they
did.
It
happened
over
all
that
period
of
time.
Well,
first
of
all,
as
you
were
doing
these
drawings
to,
as
you
said,
the
arms,
the
tanks, hinges,
and
other matters,
who
did
see those
drawings
as
they
were done
on
the
CAD
system?--
Well,
each
individual
would
come
and
look
at
what
they
were
doing.
They
were
paying
me
for
doing
the
work,
so
they
checked on what
I was
doing.
I
would
askquestions
and
ask
them
over so
they
would
look
at
-- 72 of 115 --
72
the screen but also
we would
print out an actual
hard copy on paper and have a
meeting about
it
and
discuss
it
at least
once
a week.
What was
the involvement of
Andrew
Well, he
was
at
the meetings,presented. Quite often
he hadabout
how
the things should behinges, for
example.
Corbett in this?-
he saw what was
detailed
comment
made,
especially
And
what
about
in respect to
-
you were
doing
arms
and
fingers?--
He
had
input there, too; not the onlyinput.
It
wasn't his
say only, but
he
was
there.
He made comment
about
it.
You
said there that
he
had
-
that
when
you
came
there
-
basic
information or preliminary plans. In
terms
of the
detail
on them,
how much was
there?--
Very
small
amount.
It
was a
very conceptual thingrather
than
actual
thing.
You
talked
about the
involvement
of
Andrew
Corbettin seeing
these
documents and
the
CAD
system
during
this
period
from
January through
till
April.
How
often
was
he
at
the
office
of
OMA
in
that
period?--
Minimum
of
once
a
week,
but
quite often three or
four times
a
week.
He
like
to
come
in for
morning
tea,
for
example.
He
would
bring
a
cake,
for
example,
so
he
was
there quite often.
When
he
was
there,
did
he
do
anything
to
involvehimself
in
what
was
going
on?--
Certainly, yes."
"How
regularly
did
you
talk
to
Geoff Wright
about
your
drawings?--
Every
day.
Did
he
ever say
to
you,
"I'd
better
run-off
and do
some
more
calculations.',
or
something
like that?--
Yes.
How
regularly did
he do
that?--
The
drawing
process
was
one where
I
would
take
his
information,
draw
it,
he would
take
it
back, check
it,
and
then
I
would
have
amendments
to
make.
What
sort
of
information
are
we
talking
about?--
Covers
to
steel;
laps
to
steel;
the
shapes
of the
concrete
to
make
sure
they
fit
in
the
moulds and
when
you
tip
it
out
it
is
not
going
to
break;
that
sort
of
information.
At
what
stage did
you
start
getting
this sort
of
input
from
Mr
Wright?--
It
was a
gradual
process.
It
was
happening
the
whole
time
I
was
there.
-- 73 of 115 --
July.
73
This
is in January and February?-- Right through
till
August."
The
meetings
Mr.
Torti
spoke of
were mostly in June and
Minutes
of
some
are in
evidence (ex.
1
3, ex.
13
2,
ex. 133).
The
earliest
appears to
have been on 26th
May,
1987. There
was much
activity
throughout
1987 by
way
of
seeking contracts,
from
mid-January,
when a
tender
was
submitted for
supply
of
150
flotation
tanks for
a
marina
at
Yap
with
a
non-conforming
tender for
a
complete
O.M.A.
System
1
marina.
The
conforming
tender
was
ultimately
accepted
and
performed,
and payment
received.
Otherwise
the
hopes
of
Mr.
Eichhorn
and
Mr.
Corbett
were
repeatedly
dashed,
often
at
a
late
stage.
Dr.
Corbett
may
have been
instrumental
in
the
loss
of
a
contract for
a
marina
at
Hamilton
Island
by
his
insistence
on
a
condition
that
no work
would
be done
on
a
marina being
supplied
at
cost
(so
that
O.M.A.
would
have
a
prototype
to
show
off)
unless
a
letter
of
credit
to
secure
payment
was
established
first.
The
third principal
activity
of
O.M.A.
was
in
gearing
up
for
production.
Dr.
Corbett's
money
indeed
was
used
for
the
acquisition
of
a
moulding
machine
and moulds
for
PE
tanks
and
for
moulds
for
deck
sections.
The
first
$100,000.00
was
provided
by him by
23rd
July,
1987.
Thereafter the
fifth
plaintiff
became
the
O.M.A.
paymaster;
its initial
payment
of
$50,000.00
on
19th
August
brought
Mr.
Corbett
to
the
limit
of
his
proposed
contributions.
It
is
not
appropriate to
draw any
distinction
between
him and
his
company.
His
position,
indeed,
which
the defendants apparently accepted,
was
that
the
fifth
plaintiff,
rather
than
he, should be
regarded
as the
-- 74 of 115 --
74
investor.
From November
9th 1987, monthly payments from
Dr. Corbett personally
became due under
new
obligations
assumed by him
to
a
finance
company,
Hunter
BNZ
Finance.
They
related to
a
motor
vehicle leased for
Mr.
Eichhorn
(to
"liberate"
Mr.
Corbett's
Mercedes) and
a new
CAD
System
(
to
replace
Mr.
Torti'
s
which
doubtless departed with him).
The
date of the
chattel lease in respect of the
new
Computer
System
is
12th October,
1987.
The
fifth plaintiff
brought
in another $25,000.00
and
$20,000.00
on
27th October and
13th
November, 1987
respectively,
a
further
$15,000.00
in
December.
From
the
point of
view
of
Mr.
Eichhorn
and
Mr.
Corbett,
Dr.
Corbett
showed
his
toughness.
On
12th
November 1987
(ex.
147) he
insisted
on
taking over
100
per
cent of
O.M.A.,
entitlement to
use
the tax
losses
and
the
like.
Mr.
Wright
was
forgotten,
but
Dr.
Corbett's other partners
were
offered
restoration to
20
per cent
each
in
the
venture
once Dr.
Corbett
had been
paid
back
everything
he
put
in,
(with
interest
at
the
AMBA
rate
plus
2.5
per cent
according
to
a
later
document).
Mr.
Eichhorn's
objections,
expressed
in
ex.
131 ,
are
understandable,
but
he
and
Mr.
Corbett
agreed
in writing to
Dr.
Corbett's
harsh
terms
on
or
about
20th
November:
ex.
70.
Mr. Sweeney
justified
it
all
thus:
"After
having
spent
so
much
money,
it
is difficult
for
us
to
now
stop,
so
we
wish
to
ensure
that
we
have
adequate
control
on
the
direction of
the
company".
The
company
referred to
was
Fandoan
Pty.
Ltd.,
which
was
to,
and
at
some
point did, take
over
O.M.A.
-- 75 of 115 --
75
Dr. Corbett's wish to retain Mr. Eichhorn' s services,
which he obviously valued, failed. Mr. Eichhorn refused to·
work with Mr. Corbett for reasons given to Dr. Corbett and
hinted at in ex. 131. Forced to choose between the two,
Dr. Corbett preferred his brother. Mr. Eichhorn kept the
leased motor vehicle, with what justification it is difficult
to see. It was repossessed in about May 1988. Discussions
occurred between Dr. Corbett and Mr. Eichhorn with a view to
making other arrangements to replace those in ex. 70. One
proposal was that Mr. Eichhorn's family buy Dr. Corbett out at
a price which would allow him an interest return on his
investment. Nothing came of this, as the Eichhorn family
could or would not take up that offer. In the end Mr.
Eichhorn seemed willing to accept a resolution which would
leave him with the vehicle.
Before Dr. Corbett took over, there had been problems
emerging over and above the lack of contracts. He said that
about mid-September, he was given by Mr. Corbett or Mr.
Eichhorn figures which startled him, that the project might
need another $600,000.00 or thereabouts, which was a far cry
from the original $100,000.00 or $150,000.00.
If Mr. Eichhorn meant to suggest he had made mention of
sums of $750,000.00 or $1 million for development at a
significantly earlier time, I think he is wrong. Such sums
were mentioned in the context of getting System 2 into
production, alongside System 1. Dr. Corbett says he "became
very concerned and required a re-arrangement of the commercial
basis".
-- 76 of 115 --
76
In early
August 1987 Dr. Corbett
was
told
Mr. Eichhorn
was going to
be
in
Sydney from
the 12th to the 14th putting
O.M.A.'s case to
be considered for
a
marina job
at
Birkenhead,
Sydney
to the engineers Patterson
and
Britton. In
a
letter
of
18th
August
to
Mr.
Foster (ex.
21) which Dr.
Corbett said
he
was aware
of
at
the
time,
Mr.
Eichhorn wrote"
"In
this
regard
I am
puzzled
at
the
attitude
of
Patterson
and
Britton
who
are
overlooking Off shore
Marinas
Australia
System
1
for the
60
berth
1
st
stage
replacement
programme
at
Birkenhead Marina.
They
have
indicated
that
they
will
probably use thePacific
System,
as
we
would
not
have time
to
develop
our
System
2
and
prove
it.
Our
'System
1 '
is
infinitely
superior
to Pacific in physicalproperties
and
is
in production.
It
would seem
that
no
one has
the
confidence
in
their
own
ability
to
assess the
structural
advantages
of
our system
and
are sticking
with the
'devil
they know'."
The
letter
said
"We
are
meeting
severe
resistance
from
consultants
and
developers
alike,
the
general
comment
being
-
'
is
it
proven'".
The
letter
was
produced
during
a
process
of
O.M.A.
arranging
for testing of
models.
On
31st
August
1987
a
meeting
of various
parties
was
held
to
explore the
possibility
of
a
public
float
of
O.M.A.
Both
the
Corbetts
were
present,
also
Mr.
Sweeney
and
Mr.
Eichhorn,
and
Mr.
Sproates,
a
representative of
Wardleys,
who
was
charged with
a
large
development
at
Raby
Bay.
It
was
hoped
to
interest
Mr.
Sproates
in
an
O.M.A.
Marina
for
Raby
Bay.
Mr.
Sproates obtained
an
assessment
of
the
proposed marina
from
Wardleys'
consultant
engineer,
Mr.
Seymour.
His views
are
not
in
evidence,
but
it
is
known
they
were
negative.
Dr.
Corbett
met
him
on 20th October,
1987.
Ten
days
before,
Dr.
Corbett
and
Mr.
Eichhorn
had
discussed
Mr.
Seymour's
critical
attitude.
Mr.
Corbett said:
-- 77 of 115 --
77
"He
told
me
he had met Gerald Seymour who seemeddead-pan
critical initially of the engineeringdesign·but
he
said that
Gerald
Seymour
did not hav~
a good
reputation as an
engineer; that
he was
very
conservative.
He
said that there
had been problems
at
Raby Bay and
at
Newport Waterways which were
theresult of
bad
engineering
and
specifically theresult of
bad
engineering
from Gerald
Seymour
so
I
shouldn't
be
too worried about the fact that
he was
critical."
Mr.
Eichhorn
also said that
Mr. Seymour was
committed
to
the Pacific
Marinas System.
The
evidence does not record
what
Mr. Seymour
told
Dr.
Corbett,
who
said that
as
a
result
of
their
meetings he took
steps to
have
the
O.M.A.
System
independently
examined by
another
expert.
Dr.
Corbett
failed
to get
Mr.
Barlow,
a
Naval
Architect, to carry out
this
task,
or
an
engineering
group
called
Gatskar Holdings.
Mr.
Corbett
suggested
Mr.
Gallagher, as
a
local
engineer,
less
"cumbersome"
to
deal
with than
a
firm based
down
South.
Mr.
Gallagher reported
in writing
(ex. 35)
in
late
February
1988,
although
it
appears
he
had
a
good
deal of
communication
with
Mr.
Corbett
earlier.
It
is
rather
astounding
that
Dr.
Corbett did not
get into contact
with
Mr.
Wright.
this,
he
was
asked:
As
to
"Can
I
ask
you
this,
around
about
the
same
time
that
you
had
this
discussion
with
Mr.
Seymour
do you
know
whether
Mr.
Wright
was
approached about
the
engineering
integrity
of
these
documents,
of
this
marina?--
I was
told,
I
believe
by
both
Mr.
Eichhorn
and
my
brother
-
that
all
of these matters
had
been
discussed
in
detail
with
Mr.
Wright.
In the event,
were
calculations
prepared
1987?--
Yes.
you shown a new
set
of
by Mr.
Wright
in
October
Would
you
look
at
this
document? Are
those
the
October
1987
calculations
produced
to
you
at
or
about
that
time?--
Yes,
I
saw
these.
I
believe
I
saw
them
the next
month
rather
than
in
Octoberthough."
-- 78 of 115 --
78
These were the "Abel Point Calculations", ex. 17.
0.M.A.'s business continued in some fashion or other.
Mr. Corbett was wrong in saying it closed down in December
1987. In particular, Mr. Lubrano, who gave evidence, was
interested in 1988 in installing an O.M.A. Marina at Kangaroo
Point, and the Corbetts were willing to contemplate supplying.
See pp. 15-7 of the transcript. I expect Dr. Corbett was
rather overstating his reservations when he said in evidence
in reply:
"You said earlier today that with some qualification
you may have entered into the Lubrano transaction.
You didn't say what those qualifications may or may
not have been?-- The qualification that I had said
to Pete Lubrano is that there is a dispute about the
engineering and that I was not an engineer. I
wasn't going to say that there was nothing for him
to be concerned about, but that he had to deal - I
said, 'It's open to you to talk to Mr. Wright, form
you own assessment' and there was certainly - there
was one engineering interview which was negative -
very negative, but it didn't mean necessarily that
you could never construct a marina in any place, but
I said - because he was already somewhat down the"
track with this - putting forward a marina based on
that concept, so I said, "It's up to you.' What I
didn't wish to do is to pretend that it was
absolutely clear sailing."
Mr. Corbett was quite active, at least until 15th April
1988, in attempting to obtain Mr. Wright' s co-operation so
that, in Mr. Lubrano's interest, the achievement of a "Section
86" approval for a marina at Kangaroo Point (at a different
location) could be replicated.
The belief which seems to have been entertained at that
time by Mr. Corbett and Mr. Gallagher among others, that the
O.M.A. System could be salvaged, was, I think, a correct one.
(I am not suggesting that it would necessarily satisfy, say,
Mr. Glynn.) Instead the concrete coffin system (plans for one
-- 79 of 115 --
79
version of
which were lying about the off ice and known
to
personnel such as
Mr.
Torti)
commended
itself
to
Mr.
Gallagher
and Mr.
Corbett.
Its
further
marina
activities
were
in
some
way
taken over by
Invincible
Marina Systems Pty. Ltd.
Aspects
of
O.M.A.
's activities
were
closed
down
earlier
than
this to
an
extent
forced
by
circumstances. "Production"
activities,
for
example, manufacture
of the
PE
tanks for
Yap
and
test
pouring
of
deck
units,
had
occurred
at
premises
at
Molendinar.
After
some
dispute
Mr.
Eichhorn
(
or
a company
connected with
his
family)
was
established to
have
control of
these
premises,
rather
than O.M.A.,
which
was
required to
leave.
The
concrete
moulds
had
to
be
stored
somewhere and
they
went back
to
the manufacturer's premises,
where
they
still
remain,
subject to
some
parts
having
been
"cannibalised"
to
make
moulds
for
I.M.S.
The
sale to
C.S.R.
Humes.
Exhibit
43
is
a
deed
of
agreement
dated 6th
March,
1989
whereby
C.S.R.
Humes
Pty. Ltd.
acquired
from
Invincible
Marina
Systems
Pty. Ltd.
an
Australian Patent
Application
for
an
invention
entitled
"Floating
Marina System" and
all
rights
relating to
the invention
and
its
application in
commerce
in
any form;
it
also
acquired
various "items
set
forth in
the
Third
Schedule",
the
right to
the
name
"Invincible
Marina
Systems", covenants
restricting
competition
by
the
vendor
and
the Corbetts
and
certain
warranties as
to
title
and
entitlements to
deal
with
the
subject
matter
of
the
deed,
including the
"Design Data",
which
is
defined:-
-- 80 of 115 --
80
'Design Data' means
the particulars contained
in the Part
A and
Part
B
of the Third Schedule
and without in
any way
limiting the particular·s
thereof includes both the hardware and
the
software comprising the
computer programme
known
as
Computer Aided
Drafting
Systems
together with
all
computer
disks relating
thereto
and
all
instructions,
information,
and
processing data
relating thereto
whether on
computer
disk or hard copy."
The
Third Schedule
is:
II
THE
THIRD
SCHEDULE
PART
A
Existing
base
and
lid
mould and drawings
thereto;
One
Plotter
Houston
Instruments;
One DMP-50
Plotter
-
(Model
No. DMP-52MP,
Serial
No. C
548707-10033);
One
Power
Conditioner (Sola)
240
Volt;
One
Digital
Micro
VMS
(V4.5V);
Plans designs
and
technical
details relating to the
invention held
by
R.J.
Gallagher Engineers
of
70
Kennigo
Street,
Spring
Hill;
One
Sharp
FO20
Facsimilie
Machine;
One
Toshiba
VD-3301
Photocopier.
PART
B
One
Palette
Computer
(Hardware)
including:-
Aided
Drafting
One
Tektronix
terminal
(model
No.
4209);
One
Tektronix
mouse (model
No. 4M);
Additional
Warranty
(N2);
System
One
D.E.C.
Micro
VAX
2000 (Model
No. DH-625N1-
A3,
Serial
Number WF724052
58);
and
Palette
2D,
IPI,
SOD, PSO,
3D
and
CSI
Software"
In
respect of
the
"C.A.D." system, C.S.R.
Humes
was
to
take over
the
chattel
lease
under
which
Dr.
Corbett held items
from
Hunter
B.N.Z.
Finance
Limited.
For
all
of
this
C.S.R.
Humes
was
to
pay (and
it
did
pay)
to
the
vendors
$300,000.00 on
signing of
the
deed,
$150,000.00
on
30th June,
1989
and
$150,000.00
on
5th April,
1990;
it
agreed
to
employ
Mr.
Corbett
"in
a
managerial
capacity
for
a
-- 81 of 115 --
81
period of three
months from
the date of the signing" at
$5,000.00 ·per month and
to
a
consultancy
at
$600.00 per day as
required for the nine
months
following
(minimum payment
$2,000.00 per
month).
Mr.
Corbett
was
also entitled to
expenses
and
to
have an
office
provided
for
him
for six
months.
The
defendants claim
that the
$600,000.00 should be
set
off
against
any
losses the
plaintiffs
may
establish.
The
plaintiffs
claim
that
the transaction
has
nothing
to
do
with
the case.
The
defendants
came
to learn of
it
only
shortly
before
trial
and
obtained leave
to
amend
their
pleading
to
assert
the claim.
No
evidence
was
adduced by
the
plaintiffs
to
show
what
costs,
if
any, were
incurred
in
earning the
$600,000.00.
Commonsense
indicates there
were
expenses,
for
example
in
Mr.
Gallagher's
work.
The
only
mention
which
the
plaintiffs
ever volunteered
of Invincible
Marina Systems
was
in
Mr.
Corbett's
affidavit
when
information
from
Mr.
Threlfall
("of Invincible
Marina Systems")
was
said
to
show
that
O.M.A.
had
supplied
at
least
178
hours
of
a
draftsman'
s
time
using
its
C.A.D.
system
to
prepare
certain
drawings
pertaining to
roadworks
for
the
first
defendant.
No
claim along
these
lines
was
pursued
in
the action.
One
of the
exhibits to
the
affidavit refers
to
expenditure
by Dr.
Corbett
or
the
fifth
plaintiff
on
"I.M.S.";
at
that
time such
expenditure
was
apparently
being
claimed
against the
defendants.
It
is
a
matter
of
some
surprise to
me
that
Invincible
Marina Systems'
and
C.S.R.
Humes'
roles in
the story
were
not
mentioned
in
Mr.
Corbett's
affidavit,
nor
in
the
two
days
when
/'
-- 82 of 115 --
82
he gave evidence before Commissioners. Asked
his occupation,
he
said
he was a
dentist, but
had "done
a
variety of things in
recent years".
If
the
Deed
of 6th
March, 1989 had been
implemented, he would have been
acting as
a
manager
for
C.S.R.
Humes. I
cannot proceed on
the basis that
he was,
because
his
ill-health
may
well
have
led to the
employment
aspect of the
deed never being
implemented.
The
evidence
shows
that
Mr.
Threlfall,
employed
by O.M.A.
in
late
1987
at
Mr.
Eichhorn's
instigation
,
having
become
an
I.M.S.
employee
about
April
1988,
joined
C.S.R.
Humes,
with
the
C.A.D. System
in
March
1989.
The
details
of negotiations leading to the
Deed
of
6th
March,
1989
are
surrounded
in
mystery.
Presumably
Mr.
Corbett
conducted
them. Dr.
Corbett
would
appear
to
be
a
principal
beneficiary of the
favourable
outcome.
He
is
a
director
and
principal
executive
officer
of the
I.M.S.
company:;
its
beneficial
shareholder
is
recorded
as Corbett Constructions
Pty.
Limited,
but
Dr.
Corbett
agreed
that
at
all
times
since
1987
he
or his
brother
in
effect
owned
and
controlled
Invincible
Marina
Systems
Pty. Ltd.
(
formerly
Woodhill
Pty.
Ltd.),
likewise the
fourth
plaintiff,
Fandoan
Pty. Ltd.
He
agreed
that
from
November 1987
until
the
sale to
C.S.R.
Humes,
all
the
assets
of
O.M.A.
(meaning
its
plant
and
equipment)
were
"under
the
umbrella"
of
companies
controlled
by him
or
his
brother.
He
took
the
view
that
the
title
to
the leased
C.A.D.
system
and
all
it
entailed
.lay
in
the
lessor;
he
accepted
that
a
"marina
management
system"
was
no
part of
the
lease,
but
to
the extent
it
existed
was
intellectual
property
-- 83 of 115 --
83
of O.M.A. Dr. Corbett may be right that such a management
system was little more than a concept of Mr. Eichhorn's - the
evidence does not reveal - but O.M.A. documents emanating from
Mr. Eichhorn (such as ex. 16, p. 12) refer to it. It is
inescapable that it is one and the same as the "Marina
Management System" Dr. Corbett purported to assign to C.S.R.
Humes on 67th March, 1989 by ex. 48, which relates essentially
to the chattel lease.
The plaintiffs' case is
completely useless, and was
O.M.A. 's which C.S.R. Humes
that the
discarded,
might have
O.M.A.
that
ended
system
anything
up with
was
of
was
accidentally acquired. For example, the evidence shows that
Mr. Emmerson "cannibalised" O.M.A. concrete deck moulds which
had been returned to him for parts for I.M.S. moulds (allowing
I.M.S. an appropriate credit); those I.M.S. moulds have gone
to C.S.R. Humes.
More to the point is that ex. 95 shows C.S.R. Humes
received and that other evidence (of Mr. Threlfall) shows that
I.M.S. undoubtedly used at least one O.M.A. drawing. This was
an outline of the Marina Basin at Hamilton Island, including
depiction of an existing marina. I.M.S. staff used the C.A.D.
system to alter O.M.A.'s plan showing a proposed O.M.A.
installation by showing instead an I.M.S. installation. I am
of the view that the I .M. S. isometric drawings included in
ex. 95 were produced by the C.A.D. system and Mr. Threlfall or
Mr. Corbett or others from the O.M.A. isometric drawings
previously produced. Little may turn on that. The evidence
satisfies me that those involved in I.M.S. had available
-- 84 of 115 --
84
everything of
O.M.A.
's,
and not only what was
stored in the
computer
or prepared
by
the
C.A.D. system.
It
seems
to
me
not
to matter
how much was
discarded as useless, given
that
a
discriminating
judgment was
obviously brought
to bear
and
that
items considered to
be
useful
were
turned
to
account. C.S.R.
Humes
received
from
I.M.S.
most
of the items
listed in the
third
Schedule.
It
did not
become
entitled to
any
patent, but
did get
intellectual
property
which
Mr.
Lee
described as the
concept
of
a
floating
marina through use
of
hollow
concrete
tanks,
and was
obviously prepared
to
pay
$600,000.00
for that.
One
Third Schedule
i tern
not received
was
plans, designs
and
technical
details relating to the invention held
by
Mr.
Gallagher.
Asked
about
identification of
the property sold
to
C.S.R.
Humes,
Dr.
Corbett
said
he
thought they
were
buying
what
O.M.A.
had,
then
made a
correction to:
"what I.M.S. had,
it
was by
then
what
Invincible
had".
In
my
view
it
is
right to
regard
I.M.S.
as the successor
to
O.M.A.
and
as
having taken
over
all
of
O
.M.A.
's
property, including
intellectual
property.
The
parties
in this
action
have
been
extraordinarily
casual
and
imprecise
in establishing
their
commercial
relations
with
each
other.
To
an
extent things
were
left
flexible,
and
they
changed
over
time.
Equities of
the
participants
varied in
ways
which
are
hard
to
appreciate,
both
as
to
quantum and
as
to
rationale.
Company
structures
apparently agreed
upon
were
never
implemented.
The
parties
must have
had
confidence
that
when
the
need
arose
they
would
-- 85 of 115 --
85
reach a consensus as to what their respective rights were.
Even when they signed documents, matters seem to have been
left open for review. , I imply no criticism in this comment,
but once Dr. Corbett was heavily involved financially, I think
his accountant, Mr. Sweeney, was identified as the person who
would regularise things if necessary, by imaginative
accounting, including appropriate "back dating" of
transactions. One document Mr. Sweeney produced is ex. 62, a
depreciation Schedule of Fandoan Pty. Ltd., the fourth
plaintiff. In the statement of claim it claims nothing. It
was proposed at an early stage as the corporate entity through
which the Corbetts and Messrs. Wright and Eichhorn would
operate O.M.A. The depreciation schedule made up to 30th
June, 1 988 shows Fandoan acquiring a number of O. M.A. assets
on 1 st July, 1987 and others later in that calendar year,
which were disposed of at depreciated values on 31st January,
1988. A month later than this last date Dr. Corbett was
writing to Mr. Wright stating that Fandoan was still in
business trading as Offshore Marines Australia. The Recitals
in the Deed of 6th March, 1989 suggest Fandoan was prior owner
of the invention before I. M. S. and assigned to I. M. S. on or
about 19th April, 1988. There may be a good deal of fiction
in all of this, and one would not set too much store by the
dates. However, it seems to me proper, as against the
plaintiffs, to regard it all as consistent with the C.S.R.
Humes transaction being the ultimate realisation of the
plaintiffs' investment in O.M.A.
-- 86 of 115 --
86
The plaintiffs conceded that various credits might be
appropriately charged against them for values (such as those
shown in or derived from the depreciation schedule) for
particular items; they opposed allowing a credit for the whole
$600,000.00 or anything like it. The sum is not apportioned
anywhere, hence the need for the plaintiffs to proceed in this
way to place values on tangibles which were realised upon ·to
their benefit. They say that the intellectual property C.S.R.
Humes was really paying $600,000.00 for was I.M.S. property,
in no way derived from O.M.A. 's work, which was entirely
abandoned.
Mr. Gallagher, who was one of the plaintiffs' expert
witnesses, claimed to have "reinvented the wheel", that is,
started from scratch in devising the I.M.S. system which
C.S.R. Humes ultimately purchased. As noted above, it was a
"concrete coffin" system. It has obvious similarities with
Mr. Eichhorn's original idea. One must accept that it was the
O.M.A. system of prestressed, post-tensioned concrete decks on
hollow polyethylene floats which was uppermost in all minds in
1986 and 1987, and which offered the prospect of a profitable
market being tapped quickly, and also that System 2 as
contemplated after the Corbetts' involvement in running O.M.A.
began was a larger version of that System 1 . ( See the
drawings in ex. 93, dated February to July 1987) . However,
both the Corbetts from the outset had drawings of the original
concrete coffin system, which, in my view, undoubtedly
belonged to O.M.A. Dr. Corbett must have been referring to
that system at p. 29 when he spoke of the Rose bay proposal.
-- 87 of 115 --
87
I
accept that his recollection
now
is that concrete coffin
flotation tanks were not mentioned
(
see pp. 95, 104).
Mr.
Corbett
was
perfectly
aware
of the idea of concrete floats
(see ex. 2, p.
17) and
was shown a
large
number
of
documents
incorporating
them,
including patent
documents such
as those
in
ex. 100.
He
and
Mr.
Gallagher
"interrelated" (to
use Dr.
Corbett's
term)
in
developing the
I
.M. s. system.
I
think
there
can be no
doubt whatever
that
O.M.A.
records
which
the
Corbetts controlled
included plans of concrete coffin floats
and
plans incorporating other features of the
I.M.S. system,
such as
a
central
duct
provided
in
the
arm
deck
for
services.
This
last
was
prominent
in
O.M.A.'s
plans
for
Kangaroo
Point.
It
may
be
the explanation for the incorporation of provision
for
such
a
duct
when Mr.
Corbett redesigned
the
O.M.A.
flotation
tank
in
late
1987.
In
my
opinion
it
was
ideas
derived
by
Mr.
Corbett
through
his association
with
O.M.A.
that
inspired
those
features of
the
I.M.
S. system, which
is
not
at
all
to
say
that
such
ideas
originated
with
Mr.
Eichhorn:
he
freely
conceded
their
derivation
from
other
sources.
It
is
not
necessary
to
find
whether
Mr.
Gallagher
saw
O.M.A. drawings
containing these
features.
denials.
I
accept
his
Even
if
I
am
wrong
in
concluding
that
the
I.M.S. system
was
developed
on
the basis
of
a
specific or
general
knowledge
based
on
association
with
O.M.A.
which
both
Mr.
Corbett
and
Mr.
Gallagher (through
his
preparation
of his report
of
February
1988,
ex.
35)
had,
I
would
nevertheless
hold
that
the
operations of
I.M.S.
and
its
disposal
of
various
assets
-- 88 of 115 --
88.
pursuant to the deed of 6th March, 1989
represent part of
a
continuing transaction
whereby
the Corbetts and
·their
companies' investments
in
O. M.A.
were
realised.
Dr.
Corbett
did not think
it
appropriate to distinguish
between
O.M.A.
and
I.
M.
S.
when
he
prepared
a
list
of his expenditures
on
17th
January,
1989. See
ex.
ANC
14
to
Mr.
Corbett's affidavit.
Effect of
$600,000.00
received
from C.S.R.
- Humes
In
British
Westinghouse
Electric
and Manufacturing
Company,
Limited v.
Underground
Electric
Railways
Company
of
London,
Limited
[1912] A.C. 671,
the
House
of
Lords
considered
what
damages
were
available to
a
purchaser
of turbines
which
did not
perform
to the standards required
by
the relevant
contract in circumstances
where
the turbines,
after
being
used
for
a
time,
were
replaced
by
the
purchaser with
others
so
superior
that in the
outcome
the purchaser
was
ahead
financially.
A
number
of propositions
were·
stated
at
689-90
in
Viscount
Haldane's reasons
for
judgment, which were
agreed
in
by
the
other
Law
Lords:
1.
he
who
has proved
a
breach
of
a
bargain
is
to
be
placed,
as
far
as
money
can
do
it,
in
as
good
a
situation
as
if
the
contract
had
been performed.
2.
A
second
(principle)
imposes on
a
plaintiff
the
duty
of
taking
all
reasonable
steps to mitigate the loss
consequent
on
the
breach,
and
debars
him
from
claiming
any
part
of the
damage
which
is
due
to his
neglect
to
take
such
steps.
3.
Provided
the course
taken
to
protect
himself
by
the
plaintiff
was
one which
a
reasonable
and
prudent
person
-- 89 of 115 --
89
might in the ordinary course of a business properly have
taken, and did in fact take whether bound to or not, a
jury ... may properly look at the whole of the facts and
ascertain the result in estimating the quantum of
damages.
4. When (the plaintiff) has taken action arising out of the
transaction, which action has diminished his loss, the
effect in actual diminution of the loss he has suffered
may be taken into account even though there was no duty
on him to act.
Reliance was placed on two recent Privy Council
decisions, Erie County Natural Gas and Fuel Co v. Carroll
[1911] A.C. 105 and Wertheim v. Chicoutimi Pulp Company [1911]
A.C. 301 as two illustrations of these principles, in which
"the facts have been allowed to speak for themselves". At
691, Viscount Haldane, having referred to cases in which
certain "windfalls" .or benefits to plaintiffs ( such as
insurance proceeds) were excluded from consideration by way of
reducing what defendants had to pay concluded:
"I think the principle which applies here is that
which makes its. right for the jury or arbitrator to look
at what actually happened, and to balance loss and gain.
The transaction was not res inter alias acta, but one in
which the person whose contract was broken took a
reasonable and prudent course quite naturally arising out
of the circumstances in which he was placed by the
breach".
The outcome would have been otherwise had the transaction
producing a beneficial outcome been an independent or
disconnected transaction from that in which the breach
occurred.
-- 90 of 115 --
90
The approach in evidence
is
the laudable one
of ensuring
that
· damages
are compensatory only and do
not excessively
enrich
a
plaintiff at
the defendants' expense.
at
307.
See Wertheim
In Erie
County
at
119
appears
a
passage which
in
my
view
applies to
the $600,000.00
paid
by C.S.R.
Humes -
the facts
were
that
when
the
defendant wrongfully
cut off
gas supplies
to
which
it
was
entitled, the
plaintiff
established
new
works
as
a
source of gas supply:
"It
may
well
be
that
if
several reasonable butabortive attempts
had
been
made
to
procure
this
gas
thecost of these
would
have been
properly
treated
as
part of
the cost of ultimately obtaining
it,
but
that
question
does not
arise
in
the
case.
The
works
having
admittedly
been
sold,
something must have been
obtained
for
them.
It
is
clear that
if
the
defendants
are to
pay
for thecost of
making
those
works and
of
thereby supplying the
plaintiffs
with the
gas
the
works
produced
they
must
getcredit
for the
sum
for
which
these
works,
after
having
supplied the gas,
were
sold,
otherwise
the
plaintiffs
would
make
by
the defendants'
breach
of
contract
a
profit
equal to the price
obtained
on
sale.
It
was
therefore
the
business
of
the
plaintiffs
to
show how much
that
something was.
The
prima
f
acie inference
to
be
drawn
from
a
document
printed
in
the
record
is
that
$75,000
was
the
amount
of
it.
That
inference, unless rebutted,
should
in
justice
to the
defendants
be
acted
upon.
The
burden
of
rebutting
it
lay
upon
the
plaintiffs.
They
have,
in
their
Lordships' opinion,
failed
to
discharge
that
burden,
and
should
not
be
permitted,
by
leaving the
matters
in
obscurity,
to
recover
more
than they
have
lost.
The
plaintiffs
have
not
sued
for the
loss
of
their
contract.
They
have
only
sued
for the
damages
caused
to
them
by
the
temporary
deprivation
of the gas.
They
have
got the
substituted
article,
identical in description
and
quality,
have
used,
and have
failed to
show
that
it
has
not
in
the
result
been
obtained
by
them
free of cost.
They
are
therefore,
according
to
the
principles
established
by
the
authorities
already
cited,
only
entitled
to
nominal damages."
The
principles
emerging
from
British
Westinghouse
are
discussed
in
Halsbury'
s Laws
of
England
(
4th) 12:
1196
and
at
much
greater
length
in
McGregor
on
Damages
(15th) Chapter 7,
-- 91 of 115 --
91
especially, relevantly, paragraph
335
ff. It
was a
contract
case, but the
same
principles
have been applied in
tort.
In
Bellingham v. Dhillon
[1973] 1 Q.B
304, 309, Forbes
J
said:
"
Here however,
we
have no
question of
benevolence
or of insurance.
The
action of the
plaintiff
was
that of
a
reasonable
and prudent
man
of business.
It
was
his
duty
to mitigate his
damage
by
buying
this
equipment
just
as
much when
that
damage
arose
in tort
as
if it
had
arisen in
contract.
It
seems
to
me
that
when
the
plaintiff's
claim for
damages
is
based on
loss in his
business
so
that
a
detailed
examination has
to
be
made
of his
accounts
and
methods
of trading, there
should be
no
difference
on
this
point
between
actions in contract
and
tort.
The damages
in
either
case
are arrived
at
by
a
calculation in
essence
of
extreme
simplicity.
Take
the
profits
which
the business
would
haveearned
on
the hypothesis
that
the defendants'
wronghad
not
reduced
them, and
subtract
from
that figure
the
profits
which
the business
in fact
earned
after
the
wrong
had
been
suffered.
The
first
of these
mathematical terms
must be
hypothetical.
The
secondshould
be
actual
and
real.
It
seems
to
me
artificial
in the
extreme
to
say
that in calculating
the actual
profits
earned,
one
must
shut one's
eyes
to
a
profitable
transaction
if
the
wrong was
a
tortious
one
but
look
at
the
realities
and
take
them
into
account
if
the
wrong
amounted
to
breach
ofcontract.
The
principles,
and
their
application in
tort
were
adopted
by
the majority of the
Court
of
Appeal
in
New
South
Wales
in
Hoad v
Scone Motors
Pty. Ltd.
(1977)
1
N.S.W.L.R. 88.
They
were
also
applied
at
first
instance in
a
case
of
negligent misrepresentation,
which
Mr.
Bowden's
industry
unearthed,
but
their
application
by
the
trial
judge
did
not
survive
an
appeal.
In
Hussey
v
Eels
(1990)
2 W.L.R.
234,
the
pre-contractual representation
was
that
the
vendors'
house
property
had
not been
subject
to
subsidence;
it
was
made
negligently
and
the
plaintiffs,
relying
upon
it,
purchased
for
£53,250.
The
representation
was
made
in late
1983.
The
plaintiffs
then agreed
to
purchase
and
completed
in
February
-- 92 of 115 --
92
1984; subsequently they discovered
a
subsidence problem,
rectification of
which was
to cost
£17,000, which they did not
have.
They
decided to build another residence in the garden,
but failed to get planning permission in
August 1984 and
again
six
months
later,
on
the
ground
of "overcrowding".
They
commenced
action in
January
1986 and
in
August 1986
obtained
planning permission
on
a
revised application
which
contemplated demolition
of the
house and
erection of
two
dwellings
on
the
site.
They
sold
immediately
for
£76,094.00
net;
while
it
may seem
to
be an open
inference
that
all
of
their efforts
with the planning
authorities
were
directed to
enhancing
the property's
value for
resale,
the
Court
of
Appeal's reasons excluded
it.
The
plaintiffs
quantified
their
damages
in
accordance
with various theories
over the years,
increasing
their
claim with
each
amendment.
Eventually they
claimed
(
and
recovered
by
the
Court
of
Appeal
' s :czorder)
£17,000,
as
the difference
between
what
they
paid
in
1984, and
"market
value"
of
what
they obtained, given
the
subsidence
problem.
The
trial
judge
found
for the
plaintiffs
on
liability,
but
dismissed
the
claim
on
the basis of
the "windfall"
accruing
to
them
wiping
out the
loss.
This
outcome
was
sought
to
be
supported
on
the
appeal
on
two
bases
mentioned
by
Mustill L.J.
at
238:
"1.
The
plaintiffs
owed a
duty
towards
the
defendants
to mitigate
the
loss
resulting
from
their
purchase
of the
house
in
reliance
on
the
misrepresentation; the
sale
to
the developers
was
a
performance
of
this
duty;
the
result
of
this
mitigation
was
to
be
taken
into
account
in
computing
the
loss.
-- 93 of 115 --
93
2. Whether the re-sale
was
mitigation or not, thefact is that
when
the plaintiffs' dealings are regardedas
a whole
it
can be seen
that
they have suffered
no
loss."
The
first
basis
was
dealt
with as follows
at
238-9:
"The
breach compelled
the
plaintiffs
to
choose
between:
(a) continuing to live in
the
bungalow
despite
its
serious faults;
(b)
repairing
the
bungalow;
(c)
selling
the
bungalow and
land
and going
tolive
elsewhere.
If
the
plaintiffs
had chosen
to
pursue
either
of the
first
two
options,
it
is
inconceivable
that
they
would
have been
held
to
be
in
breach
of
any
obligations
towards
the defendants;
their
recovery
of the estimated or actualcost of
repair
(as
reflecting the difference
between
the
true
market
value
and
the price)
would have
followed
as
a
matter
of
course.
Given
therefore
that alternatives
(a)
and (b) were
legitimate, the proposition
that
the
plaintiffs
were under
a
duty
to
spend
more
than
two
years
in applications
for planning permission,
and
that
having
obtained
it
were
under
a
further
duty
to
move
out of the
home
in
which
they
had
hoped
to
live
and
to
buy
somewhere
else,
all
for
the
benefit
of
the
defendants
who
had by
their
actionable
wrong
put
them
into this
dilemma,
need
only
be
stated to
be
rejected.
British
Westinghouse
was
summarised
in
this
way
at
241:
"First,
the
conclusion
that
the
benefits
derived
from
the
purchase
of
superior
machinery
should
be
set
against the
two
elements
of
loss.
In
retrospect
it
is
hard
to see
how
the
contrary could
have
been
maintained.
The
purchase
amounted
to mitigation in the
narrower
sense, designed
to put
a
stop
to
the
continuing
loss.
To
compensate
the appellants for
the cost of
replacement
whilst
ignoring the
additional benefits
which
this
replacement
had
brought
would
have been
palpable
injustice.
The
second
aspect of the decision
concerned
the
element
of
over-mitigation
introduced
by
the
fact
that
the
respondents
had
brought equipment
with
a
greater
output than before
-
presumably
at
greater cost
than
if
exactly
equivalent
replacements
had
been
obtained.
Again, once
it
was
found
that
the
purchase
had
been
reasonably
made
the
conclusion
in
favour
of
theappellants
now
seems
inevitable,
given
that
the
act
which
constituted
the mitigation
and
the
act
which
was
said
to
-- 94 of 115 --
94
constitute the over-mitigation were
in the event the
same. Thus,
there
was no
question of the case being
·concerned with
a
chain of disconnected transactions,
and
so,
I
cannot follow the
judge
in treating the present
case as
directly
governed by
Westinghouse."
This led into
an
interesting
review
of
a number
of
authorities,
which
pointed, in
Lord
Justice Mustill's
view,
to
a
notion of continuity as providing
a
relevant
test.
His
conclusion, agreed
in
by
Farquharson
L.J.
and
Sir
Michael Kerr
was,
at
246:
"Ultimately, as with so
many
disputes
about
damages,
the issue
is
primarily
one
of
fact.
Did
the negligence
which
caused
the
damage
also
cause
the
profit
-
if
profit
there
was? I
do
not
think
so.
It
is
true
that in
one
sense
there
was
a
causal
link
between
the
inducement
of
the
purchase
by
misrepresentation
and
the
sale
2½
years
later,
for
the sale
represented
a
choice
of
one
of the
options with
which
the
plaintiffs
had been
presented
by
the defendants'
wrongful
act.
But
only
in
that
sense.
To
my
mind
the
reality
of the
situation
is
that
the
plaintiffs
bought
the
house
to
live in,
and
did
live
in
it
for
a
substantial
period.
It
was
only
after
two
years
that
the
possibility
of selling
the
land
and
moving
elsewhere
was
explored,
and
six
months
later
still
that
this possibility
came
to fruition.
It
seems
to
me
that
when
the
plaintiffs
unlocked
the
development
va:lue
of
their
land
they did
so
for
their
own
benefit,
and
not as
part
of
a
continuous
transaction of
which
the purchase
of
land
and bungalow
was
the inception.
Accordingly, although
I
acknowledge
that
the
plaintiffs
had
until
the
start
of the
trial
persisted in
a
claim
which
was
inconsistent
with the
one which
they
introduced
by re-amendment,
I
consider
that in fact
and
law
their
second
thoughts
were
correct,
and
that
the
proper
measure
of
damage
here
is
the difference
between
the contract
price
and
the
market
value
of the property
in
its
unsound
condition."
One
feature
worthy
of
mention
(
see p.
239
C-E)
is
that
the purchasers' "windfall"
may
have
been
more
apparent than
real.
They
were
not property
speculators,
but
a
couple
seeking
a home
to
reside
in.
When
they
resold
it,
it
was
to
acquire
a new
home.
The
general
rise
in
the
housing market
was
such
that
one
expert fixed
£80,000
as the
cost of
a
-- 95 of 115 --
95
comparable property at the time of the resale (which would
have left the purchasers almost even), another £90,000, which·
indicated a substantial loss for which they would have to be
compensated.
In the present case in my view there was a continuous
transaction such as the Court of Appeal contemplated. there
is no indication that the plaintiffs were necessarily
investing for the long-term. When the first plaintiff, Mr.
Corbett was pressing the second and/or fifth plaintiffs to
invest, the prospect of a quick withdrawal at a handsome
profit was one inducement presented. As it turned out, those
two plaintiffs effectively bought out Mr. Corbett and the
third defendant in November 1987; all three had co-operated to
consider a public float in August. I regard the C.S.R. Humes
payment as the outcome of the various investments made by the
plaintiffs. This involves a deal of piercing of the corporate
veil, but if that can be done to ensure that losses by private
companies as well as their proprietors are effectively brought
in against a defendant (Esso v. Mardon cf. Gould v. Vagellas
(1984) 157 C.L.R. 215) it can surely be done to bring in
credits that the defendant may justly assert. The plaintiffs'
preference was to collect whatever they were entitled to in
aggregate by a single judgment in favour of _the fifth
plaintiff.
Dr. Corbett was at pains, for example at pp. 88-89 .of the
transcript, to present O.M.A. as without assets of
significance and the I.M.S. company as a new enterprise with a
new invention of its own. It seems plain he knew little of
-- 96 of 115 --
96
the details except what
his brother (and perhaps
Mr.
Gallagher) told
him. However,
the allegedly "completely
different sort of
marina system" must have been presented to
him
before I.M.S.
was
involved.
He
said
he was asked
to put
some money
into
"a possible
way
to design
a
completely
different sort
of
marina
. . . . I
eventually agreed
and
that
different
technology
became - I
asked
for
it
to
be
put
into
a
separate
company
so
that
it
was
quite clearly
kept apart,
and
·
...
that
company became
Invincible
Marinas
Pty. Ltd."
(p. 88).
This
was
all
occurring
while
or
even
before the fourth
plaintiff,
Fandoan
Pty. Ltd.
was
presented as
running
O.M.A.
Exhibit
61
has
Fandoan
in
August 1988
purchasing tax
stamps
for
O.M.A.
employees from
July
1987.
The
recitals
in
ex.
43,
as
noted
elsewhere,
describe
Fandoan
as
owner
of the
new
invention
and
as assigning
it
to
I.
M. S. on
19th April
r
1988;
it
seems
to
follow
that
the
new
invention
was O~M.A.
's
intellectual
property,
or
was
something
Mr.
Gallagher,
assuming
him
to
be
the
inventor,
was
prepared
to
make
available
to
O. M:
A.
,
with
which
he had been
consul
ting
(
for
reward
payable
by
O. M.A. )
on
aspects of
marina
design
for
months.
The
plaintiffs
submitted
that
the
case
was
not
pleaded
as
one
about
mitigation of
damages,
and
should
not
be
treated
as
such.
They
claim
they
could
have
adduced
evidence
of the cost
of
avoiding
the loss
by
the
I.M.S.
enterprise.
There
may
well
have been
such
cost.
I
am
disposed
to
think
that
from
the
eve
of
the
trial
the
plaintiffs
were
fully
aware
that
the
defendants claimed
their
asserted
loss
was
to
be
reduced
by
-- 97 of 115 --
97
the $600,000.00; the defence was at pains throughout the trial
to present·the I.M.S. venture as implementation of a business
plan devised by Mr. Bruce for O. M.A. ( the defendants are
required by the statement of claim to pay for everything spent
on Mr. Bruce, as an O. M.A. expense) . I will hear the
plaintiffs should they wish to submit in light of these
reasons that an inquiry should be had as to the costs the
plaintiffs were put to in earning the $600,000.00 in question.
My present view is that it is immaterial to the outcome
in this case whether it is regarded as one of mitigation
(which happened to turn out favourably to the plaintiffs and
hence the defendants, as opposed to unfavourably to both
sides) or as one of balancing loss and gain to identify the
plaintiffs' final financial position.
As the evidence stands, in line with Erie County,
plaintiffs have not proved any loss.
Quantum apart from $600,000.00 from C.S.R. Humes
the
The defendants mounted little challenge
plaintiffs' asserted figures for their expenditure
to the
on O.M.A.
So far as the defendants relied upon a written list by Mr.
Eichhorn declining to accept certain items in the claim
because he was unsure, they have failed to impress me. I do
refuse to find established as an expenditure made in reliance
upon misrepresentations $5,000.00 paid by Mr. Corbett on 19th
November, 1986, for the reason that it preceded the dates of
the alleged representations. Rather, the defendants submitted
that nothing by way of damages ought to be allowed after, say,
December 1987. The plaintiffs having shut Mr. Eichhorn (and
-- 98 of 115 --
98
also
Mr.
Wright,
who
elected to stay loyal to
him)
out of
O.M.A.
in
November 1987,
the argument
runs,
it
was
not for the
plaintiffs to
go on spending
money. Mr.
Corbett indeed swore
in his affidavit that
the business
activities
of
O.M.A.
were
terminated in
December 1987.
Substantial expenditure occurred
after that
time, including about
half of the
fifth plaintiff's
outlays.
Mr.
Bruce
was
paid $3,673.75
in
March
and
April
1988,
Mr.
Gallagher
$10,384.00
on
30th
March,
1988.
Mr.
Threlfall
was
paid
wages
of
$1,828.00
two weeks
later.
$790.96
was
paid
for fuel
on
12th
April.
Those
sums
are part
of the
fifth plaintiff's
claim.
Mr.
Corbett
and
the
third
plaintiff
claim
for
wages
paid
to
Mr.
Threlfall
earlier
in
1988
and
wages
to
Mr.
Horsburgh
to
the
end
of
February
1988,
and
fuel
bills
in
March.
Some
of
the
later
payments
may
have
been
rendered necessary
by
reason
of
earlier
commitments
of
O.M.A.
They
may
well
have been
made
because
Dr.
Corbett
felt
that
morally,
if
not
legally,
he
had
made
himself sole
proprietor
of the
business of
O.M.A.
Certainly, the other
two
proprietors
of
the registered
business
name
had
dropped
out
of
the
picture,
Mr.
Eichhorn
effectively
under compulsion,
and
Mr.
Corbett
because
Dr.
Corbett
was
paying
him
out.
However
the
wages
payments
show
that
O.M.A.
(as
one
or
more
of the
plaintiffs)
was
still
active
until
the
interposition
of
the
I.
M.
S.
company,
apparently
in
April
1988.
It
is
right
to
allow
the
plaintiffs
to
bring
in
such
items only
on
the basis
of the
full
history of
I.M.S.
being brought
in,
including the
large
payments
it
received
in
1989.
As
for
Mr.
Gallagher,
his
invoice
for
the
sum
mentioned,
in
ex.
61
,
includes
a
further
-- 99 of 115 --
99
$735. 00
for
work
of
which some
certainly, if
not
all,
was
I.M.S. work.
In
my
opinion,
it
is artificial in the extreme
for the
plaintiffs
by such accounting exercises as segregating
this
account so as
to
claim only
O.M.A.
work,
to assert that
I .M.
S.' transactions are
a
res inter alios acta.
The 1988
payments
specifically referred to
can be
included
against the
defendants only as
part of
O.M.A.
's
working
to
change
its
business
and
its
products as required.
On
the
assumption
that
the
$600,000.00
(or whatever
part
of
it
represented
profit
to the
I.M.S.
or
its
proprietors)
is
brought
in
I
find the
plaintiffs
have proved
the expenditures
claimed, with the exception
of
the
initial
$5,000.00.
Adopting
the figure
in
Mr.
Bowden'
s
written
submission,
that
leads
me
to
find
net expenditure "in reliance"
on
the
representations
(as well
as in reliance
on
other
considerations)
of
$279,967.93.
It
would
be
more
accurate
to
say
"in
consequence
of"
rather
than
"in reliance
upon",
given
that
the
1988
payments
were
in large
measure
made
at
times
when
the
plaintiffs
were
not accepting
anything
the defendants
might have
represented
about
the
O.M.A.
system.
The
approach
I
have
taken
is
on
the indulgent
side, in
accepting
what
the
plaintiffs
have claimed,
for
example,
as
to
how Mr.
Corbett
allocated
his
telephone
bills.
I
note
they
have
shown
discrimination
in
withdrawing
a
couple
of
items
which
Mr.
Corbett's
cross-examination
on commission
suggested
were
indefensible;
more
important
to
my
attitude
is
the
lack
of specific
challenge
to
particular
items
by
the defendants.
-- 100 of 115 --
100
The
plaintiffs
claim interest, or preferably, further
damages
for the cost of
moneys
provided, described as
a
Hungerfords v. Walker
claim.
See
( 1989) 84 A. L. R.
119. The
claim
is particularised in
Schedule
3
to the
amended
statement
of
claim, and
is,
in
my
view,
made
out in principle.
It
is
based
on
interest
which
the
second and
fifth plaintiffs
have
foregone,
at
rates established
by an
affidavit
admitted
by
consent.
The
total interest
claimed,
in the
first
section,
about two-thirds of the
"cash spent",
is
as follows:
Interest
from
May 1989
to
September
1991
is
Dr.
Corbett
$75,369.32
$50,659.30
The
balances,
for
interest
before
May 1989
are
$24,710.02
Corbett
Enterprises Pty. Ltd.
$118,650.60
$
82,195.28
$
36,455.32
Having
regard
to the
C.S.R.
Humes
payments,
there
is,
in
my
opinion,
no
warrant
for
any
interest
or
Hungerfords
v.
Walker
damages
after
6th
March,
1989.
Accepting
and
apportioning
the
Schedule
figures,
as
I
have
done,
Dr.
Corbett
and
the
company
should
not
be
given
credits for the
April
1989
interest
of
$1,736.25
and
$3,161.43
respectively,
nor
for
80
per
cent
of
the
March
interest,
which
may
be
estimated
at
$1,205.27
and
$2,186.01,
respectively.
If
my
calculations
are
correct,
what
should
be
allowed
comes
down
to:
Dr.
Corbett
$21,767.40
Corbett
Enterprises Pty.
Ltd.
$31,107.88
I
have
not
embarked
on
the
exercise
of
working
out the
effect
on
the
Hunger
fords
v.
Walker
claim
of
my
being
wrong
about the
defendants' entitlement
to
a
credit
in
respect of
-- 101 of 115 --
101
the C.S.R.
Humes payment. Speaking generally, the figures in
Schedule 3, regarding
which
the defendants said
little
in
opposition,
.would
apply.
However,
in respect of the
1988
payments
singled out for special
mention
by
me
above,
the
plaintiffs'
"funds spent" should be reduced, and
"interest"
would
fall
accordingly.
it
seems
to
me a
similar
consequence
would
follow had
the defendants succeeded
in
their
submission
that this
was a
case for
Common Law
Practice
Act
interest,
rather
than Hungerfords v.
Walker damages.
The
first
plaintiff
formulated
his
claim
in
a
slightly
different
way
in
Schedule 3,
claiming
interest in
six-monthly
instalments. cutting off
the
claim
at
6th
March, 1989,
it
would
comprise:
$
152.51
to
31.7.88
$
946.72
to
31.1.89
and
$
238.42
(estimated)
to
6.3.89
for
a
total
of
$1,937.71
Things
are
worse
for
this
claim,
which
is
based on
$14,334.65
as the
balance
of
funds
spent;
I
have
already
ruled against
$5,000.00
of
that
sum.
$14,334.65
is
a
balance remaining
after
reimbursements
made
by
the
fifth plaintiff
among
others
(a consideration
which
may
bear
on
the
correctness
of
its
claims,
but
the
defendants
addressed
no argument
to
me
on
the
point,
and
I
have
not
pursued
it).
The
first
schedule
shows
that
the
underlying
sum
of
$88,193.03
in
fact
includes
payments
of
$8,650.00
or
more
made
between
12th
January,
1988
and
7th
March,
1988.
Their
inclusion
for
any
purpose
is
in
my
view
limited
to
the
extent
to
which
they
purchased
what
I.M.S.
brought
in
from
C.S.R.
Humes.
-- 102 of 115 --
102
Evidence
is lacking to
show
that
Mr.
Corbett or his
company,
the third plaintiff,
was
in
a
position to earn
interest at particular rates.
In
all
the circumstances,
I
would
not assess
either
of
them
as
entitled to
anything under
Hungerfords v. Walker. They
have not been
out of
pocket
in
substantial
sums
for significant
lengths of
time and
it
has
not
been demonstrated
to
me
that
I
ought
to exercise
any
discretion in
their
favour under the
Common Law
Practice
Act
provisions as to
interest.
Contributory
Negligence
There
is
no
plea of contributory negligence.
It
seemed
to
me
the
defendants
had
raised
the issue
by
the
conduct
of
the
trial
throughout,
and
in their written
and
oral
submissions
in address; these
emphasise
the close
connection
Mr.
Corbett
had
with the
activities
of
O.M.A.
from
early in
1987,
through
which he
must
have
become
aware
that
the' design
of the
marina system
was
undergoing
constant
development,
and
that
it
was
not
"fully
engineered"
or
anything
like
it;
he
made
no
attempt
to extricate
himself, but continued
to
put
in
funds
and
encourage
Dr.
Corbett
to
do
so
by
representations of
his
own
which
I
am
willing to
find
were
in
terms
more
confident
and
sanguine than
any proved
to
have
been
made
to
him.
I
asked
Mr. Bowden
to
address
on
the
subject of
contributory
negligence,
and
referred
him
to
Fleming on
Torts
(7th)
615.
He
raised
the pleading
point,
citing
Fleming
at
242,
but
appeared
to
concede
in his written
submission
received
by
me
on
20th
November
that
James
v.
McCarthy
(1958)
Q.W.N. 32
established
that
contributory
negligence
need
not
be
pleaded.
If
pleading
is
necessary,
I
would
allow
the
defendants
to
amend
appropriately.
-- 103 of 115 --
103
The
authorities cited
by Fleming
sufficiently establish
that contributory negligence
is available as
a
defence in
ap.
action for negligent misstatement, although, as the learned
author said,
its
practical
scope
is
obviously limited, since
it
will rarely,
if
ever,
apply where
reliance
is
foreseeable.
This case
is
extraordinary, in that
the
plaintiffs
do
not
assert that their losses
flow from
a
single disastrous
commitment made
in reliance
upon
a
representation or series of
representations.
Such
is
the usual case,
where
a
property or
business
is
acquired.
The
present
plaintiffs
put
their
money
into
O.M.A.
as
required,
and
retained
the
ability
to
say yes
or
no
to
each
request for
more.
They
present
a
picture of
misrepresentations continuing
to
be
made
which gave
them
confidence
to
continue
investing.
Much was
made,
for
example,
of
a
document
Mr.
Eichhorn produced
for
the
meeting
of
31
st
August, 1987.
Its
purpose
was
to benefit his
and
the
Corbetts'
interests
by
promoting
the idea
of
a
public
float
to
bring in
outsiders'
money. Not
surprisingly, there
is
a
lot
of
glowing
material,
full
of
optimism and
talk
of vast
marketing
programmes.
The
notion
that
the Corbetts
might
rely
on
it
to
make
further
investments themselves
rather
than
rely
on
their
inside
knowledge
as
proprietors of
the business,
actively
running
it
in
the
case
of
Mr.
Corbett,
is
ridiculous.
Mr.
Corbett,
while
not
on
the
spot,
was
entitled to
make
whatever
inquiries
he wished,
and
it
is
clear that
Mr.
Sweeney
was
authorised
to
and
did
make
inquiries
as
part of his
financial control.
I
will
say
a
little
about
the
authorities cited
by
Fleming
at
615.
-- 104 of 115 --
104
Yianni v.
Edwin Evans & Sons [1982] 1 Q.B. 438 was,
like
Hussey v. Eels,
an undisclosed subsidence case, brought by
purchaser of the affected property against
a
firm of valuers
and
surveyors; they valued the property
and
assessed
it
as
suitable for
maximum
lending.
They
admitted negligence
in
preparing
their
valuation report but
claimed the
plaintiffs
were
negligent in failing to
follow
their
building
society's
advice
in
its
mortgage
application
form and
other
literature
and
obtained
an independent survey.
( The
plaintiffs
attributed
their
failure to cost considerations).
said,
at
457:
Park
J.
"Finally
Mr.
Fernyhough
says
that
the
plaintiffs
should be
held
guilty
of contributory
negligence,
because they
failed to
have an independent survey;
made
no
inquiries
with the object of discovering
what
had been
done
to
the
house
before they decided
to
buy
it;
also
failed to
read the
literature
provided
by
the building
society,
and
generally
took
no
steps to
discover the
true
condition of the
house.
It
is
true
that
the
plaintiffs
failed in
atr
these
respects,
but that.
failure
.was
due
to
the
fact
that
they
relied
on
the defendants
to
make a
competent
valuation of the
house.
I
have been
given
no
reason
why
they
were unwise
to
do
so.
I
have
earlier
read the
paragraph
under
the
heading
'Valuation' in
the
building
society's
handbook which
Mr.
Yianni
did not
read.
No
doubt
if
the
paragraph
had
been
in
stronger
terms,
and had
included
a
warning
that
it
would
be
dangerous
to
rely
on
the
valuer's
report,
then
I
think
that
the
plaintiffs
might
well
have
been
held
to
be
negligent.
But,
in
my
judgment,
on
the
evidence
the
allegation of
contributory
negligence
fails."
In J.E.B. Fasteners Ltd.
v.
Marks
Bloom & Co
(1983)
1
All
E.R.
583
the issue
of
this
kind
was
resolved
on
the
basis of
causation.
The
defendants
were
accountants
who
certified
to
the
plaintiff
the
accounts
of
a
company
which,
as they
knew,
the
plaintiff
was
considering acquiring..
The
defendants
were
held
negligent
in
preparing
the
accounts. Inaccuracies
in
the
accounts
included
an
inflated
value
put
on
stock.
By
the
time
-- 105 of 115 --
105
of the takeover which eventuated, the plaintiff, having
inspected the stock, knew that the figure was inaccurate. The
trial judge held that the picture presented in the accounts
would encourage the plaintiff to take over the company, and in
-
that sense the plaintiff relied on the accounts, although they
were not of critical importance. The plaintiff believed that
certain commercial advantages would accrue from the takeover.
The Court of Appeal disapproved of the trial judge's approach
in separating the issues of causation and reliance, in
"finding reliance where no true reliance was". The trial
judge had been cognisant of an apparent inconsistency between
his finding of "reliance" and his finding on causation which,
in the circumstances, was adverse to the plaintiff. He said,
"the distinction as I see it is that you can be influenced by
something, even though if you had not been influenced you
would have acted in the same way".
said in the Court of Appeal at 587:
Of this, Sir Sebag Shaw
"What the judge is really stating as his underlying
meaning is that, while the content of the accounts
was observed and considered by Messrs John and Eric
Bufton, it did not in any material degree affect
their judgment in deciding whether or not to take
over BG Fasteners Ltd."
Stephenson L.J. at 588-9 explains neatly the approach of
the Court of Appeal:
"In such a case the cause of action is the same as
in all claims for damages for misrepresentation.
The representation must be false, and it must induce
the plaintiff to act on it to his detriment. If it
does, he relies on it; if it does not, he does not.
He may, of course, rely on other things as well.
What operates on his mind, or motivates him, or
influences him to act as he does, may be a number of
things, some operating more or less strongly, one
perhaps predominating, as the judge found here was
the fact .that the plaintiffs thought that Mr.
Godridge and Mr. Wigg, in the form of BG Fasteners
Ltd., would be the ideal vehicle to complement their
existing business (see [1981] 3 All E.R. 389 at
-- 106 of 115 --
106
301); another, not 'of critical
importance' as the
judge found
(at
301),
was
the false accounts in this
case. But, as long as
a
misrepresentation plays
a
real
and
substantial part,
though not
by
itself
a
decisive part, in inducing
a
plaintiff to act,
it
is
a
cause of
his loss
and he
relies
on
it,
no
matter
how
strong or
how many
are the other matters
which
play
their part in
inducing
him
to act."
This case
does
not, in
my
respectful
opinion, bear
on
the
matter of contributory negligence
at all.
Grand
Restaurants of
Canada
Ltd. v. City
of
Toronto
(1981)
123
D.L.R. (3d) 349, however,
is
a
straightforward
application of the Ontario equivalent of
s.
10
of
our
Law
Reform
(Tortfeasors Contribution, Contributory
Negligence
and
Division
of Chattels)
Act
of
1952.
disappointed purchaser of
a
restaurant.
The
plaintiff
was
a
Trainor
J.
embarked
upon
an
interesting
review
of pertinent judicial
and academic
sources
at
366:
"I turn
now
to
the question
of
whether
the
plaintiff's
conduct
was
such
as
to contribute
to
the
damages
that
he
claims
he
has
suffered. In the
words
of
Viscount
Simon
in
Nance
v.
B.C.
Electric
R.
Co.
Ltd
. [ 1 9 51 ] 3 D. L . R. 7 0 5
at
p.
711 , [ 1 9
51
] A. C.
601
at
p . 611 , 2 W. w• R . ( N . s . ) 6 6 5 ,
"al
1
that
is
necessary
to establish
such
a
defence
is
to
prove
that
the injured party
did not
in
his
own
interest
take reasonable care
of
himself
and
contributed,
by
this
want
of care, to
his
own
injury'
.Did
the
plaintiff
Grand
Restaurants Limited,
once
being
aware
of the existence of
prior
work
orders
stemming from
a
liquor licence application
since
withdrawn,
fail
to
exercise
such
reasonablecare as
would
have
led
it
to
discover the nature
of
the defects
set
out
in
the
1977
work
order
and
the
economic
risk
of
closing?
It
must be
remembered
that
contributory
negligence
does
not
require
any
duty
owed
by
the
plaintiff
to
the party
sued;
all
that
is
necessary
is
to
show
that
the
plaintiff
did
not,
with
respect
to
a
duty
owed
to
himself,
take
all
reasonable
care
to
avoid
or
mitigate
a
foreseeable
risk
or
harm:
Nance.
(supra),
at
p.
711
D.L.R., p.
611
A.C.; Clerk
&
Lindsell
on
Torts,
13th ed.
(
1969),
p.
587,
para.
993. Quoting
Denning
L.J. in
Janes
v
Livox
Quarries
Ltd.,
[1952]
2
Q.B.
608
at
p.
615:
-- 107 of 115 --
107
'A person is guilty of contributory
negligence if he ought reasonably to have
foreseen that, if he did not act as a
reasonable, prudent man, he might hurt
himself; and in his reckonings he must
take into account the possibility of
others being careless.'
At first blush, there is perhaps some difficulty in
finding that a plaintiff ought to recover damages
for negligent misrepresentation, which presupposes a
reasonable reliance on the advice of the defendant,
and then to have his damages reduced on account of
his reliance - a causa sine qua non of his injury -
being to some degree 'unreasonable' or excessive.
But as the learned authors of Clerk & Lindsell on
Torts point out, 'it needs to be emphasised that the
plaintiff's negligence is contributory to the damage
he sustains' (supra, at para. 991, citing Craze v.
Meyer-Dumore Bottlers' Equipment Co. Ltd., [1936) 2
All E.R. 1150 at p. 1151), and this I interpret to
mean that there is a distinction at law between
reasonable reliance as a necessary prerequisite to
ground liability, to constitute the cause of action
under Hedley Byrne, supra, and reliance in the
context of contributory negligence as simply a
factor going to the extent of the damages suffered.
Section 4 of the Negligence Act, R.S.O. 1970,
c. 296, provides:
'4. In any action for damages that is
founded upon the fault or negligence of
the defendant if fault or negligence is
found on the part of the plaintiff that
contributed to the damages, the court
shall apportion the damages in proportion
to the degree of fault or negligence found
against the parties respectively.'
In Charlesworth on Negligence, 5th ed.
para. 1028, the author states: (1971),
'In considering "fault" what must be
ascertained is the fault causing the
damage; this may not necessarily be the
same as the fault causing the accident
which in turn caused the damage.'
In the case of fault that contributes to the damage
suffered, reliance that is 'unreasonable' simply
goes to reducing damages otherwise recoverable by
the plaintiff; it does not go to cancelling the
prima facie liability of the defendant. I find some
analogy in case law which holds that even where the
defendant is solely responsible for the damage
suffered by the plaintiff, the plaintiff's damages
will nevertheless be reduced on the grounds of
contributory negligence where the plaintiff could
have taken steps to avert or mitigate the damages
-- 108 of 115 --
108
flowing from the defendant's tortious act: see
O'Connell v. Jackson, [1972] 1 Q.B. 270."
At
p.
368
Trainor
J. said:
"In the case
at
bar,
I
have found
that the city
was
negligent in failing to disclose the existence of
an
open
file
pertaining to
the property
which
was
the
subject of the
plaintiff's
inquiries.
However,
the
defendant's response
shoul.d
not
go
to absolving the
plaintiff
purchaser
from
the
duty
owed
to
himself
-
to
take
all
reasonable precautions of
a
purchaser.
The
city's
response
specifically stated
that
any
information
was
for the purchaser's
'convenience' only,
and would
not absolve
him from
any
future inspections or
demands
for
compliancewith
the Building
Code Act
, 1 9 7 4 •
The
plaintiff
relied
on
the apparent
absence
of
an
active
file,
but
a
prudent purchaser could
and
should
have done
more,
especially
if
he
was
concerned,
as
was
the
plaintiff,
with
the
premises'
compliance
with the
Building
Code
Act,
1974
in the context
of
any
future
liquor licence applications.
Moreover. had
the
plaintiff
specifically
asked
about the
prior
liquor
licence application
-
he
knew
there
had
been one-
he
would
have
found
out
above
the
work
order
and
the
active
file.
The
defendant's
counsel submitted
that
in
effect
the
plaintiff
failed to
ask
the pertinent
question,
and
in
particular
a
specific
question
related to
the
prior liquor licence
work
order.
There
is
no
question
that
the place
to
seekinformation regarding
work
orders, violations
and
active
files
attendant thereto,
·is the
defendantbuilding
department.
In
this
case,
however,
the
plaintiff
had
information about
a
prior
work
order
and
this,
combined
with
special
knowledge
of the
business
to
be
purchased, should
have
alerted
it
to
make
further investigation
or specific inquiries
that
would
have
led
it
to
the
information
the
non-
availability
of
which
provided
the genesis
of
this
lawsuit.
Pursuant
to
the provisions of
the
Negligence Act,
I
find the
parties
equally
at
fault."
Lastly
comes
Siman
&
Co.
(Pty.)
Ltd. v. Barclays National
Bank
Ltd.
(1984)
(2) S.Af.L.R.
888.
In the
final
outcome,
the
plaintiffs failed
because
their
loss
was
adjudged
to
have
been
caused
by
the defendant's
refusal to
arrange
forward
cover
for
a
foreign currency
commitment
(in
respect of
which
the
plaintiffs
had
not
sued)
rather
than
the defendant's negligent
misstatement
that
it
was
not
possible
in
the circumstances
to
-- 109 of 115 --
109
obtain such cover. Corbett J.A.'s
judgment
at
923
ff contains
the following:
"Contributory negligence
At
the conclusion of respondent's case in the
Court below,
respondent's counsel applied for
an
amendment
to the plea.
The
application
was
not
opposed and
was
granted.
The amendment
introduced
an
alternative
defence
of contributory negligence
in
the event
of the
Court finding
that plaintiff
( now
appellant) suffered
damage,
that
defendant
(now
respondent), represented
by Muir,
acted negligently
and
that
such negligence causally contributed to the
damage
suffered
by
plaintiff.
In
that
event
defendant averred
that
the
damage was
caused
partly
by
the
fault
of
defendant
and
partly
by
the
fault
of
plaintiff,
represented
by Melnick
and/or
Simanowitz,
and
prayed
that
plaintiff's
damages
be
reduced
in
accordance
with the provisions of
Act
34
of
1956.
A
prudent
or
cautious
person
in
the position of
Melnick and Simanowitz
may
well
have been
dissatisfied
with Muir's
advice and
queried
it
on
the basis
that
it
was
not
yet
15h00,
but the
question
is
whether
in failing to
do
so
Melnick and
Simanowitz were
guilty
of contributory negligence.
As was
said
by
CENTLIVRES CJ
in
Herschel
v.
Mrupe
1954
(3)
SA
464
(A)
at
474A:
'The
mere
fact that,
if
appellant
had
been
more
cautious,
she
would
not
have
incurred the
loss
is
not per
se
sufficient
to
prove
that
she
was
guilty of
contributory
negligence.
See
Fred Saber
(Pty) Ltd
v
Franks
1949
(1)
SA
388
at
406
(A).
I
The
explanation of
Melnick and
Simanowitz
for
failing to
query
Muir's
advice
was,
in
each
case,
because
the
recipient of
the
advice thought
that
the
processing
of
an
application
for
forward
cover took
a
substantial
time
and
therefore
that
at
14h30
it
was
too
late
for
this
to
be
done
by
15h00.
In
other
words,
that
at
14h30
the
market
was
for
practical
purposes
closed.
There
is
no
reason
to
doubt
thetruthfulness of
this
explanation.
Obviously
the
processing
of
appellant's
application
would
have
taken
some
time.
There
were
some
19
transactions
to
be covered
and
there
were
three
different
currencies
involved.
Moreover,
in
the course
of the
same
conversation,
Muir
stated
that the application
had
to
be
in
writing
and
that
he
could
not
deal with
the
matter
over
the
telephone.
This
meant
that
one
of
appellant's
representatives
would
have
to
go
to
the
bank
with
his
records.
If
one
further
takes
into
-- 110 of 115 --
110
account the facts that
Muir was
the acknowledgedexpert
on
the question of
forward cover and
that inthis respect Melnick and Simanowi
tz
were laymen,
that
Muir was
appellant's trusted
bank manager and
had been
helpful to appellant in the past
and
that,
even though (on
the evidence) there
would have been
sufficient
time
to
arrange forward cover, there
was
not
much
time
to spare
and
appellant's
representatives
would have had
to hurry,
I am
not
persuaded
that
Melnick and Simanowitz were
guilty of
contributory negligence
in
any
of the respects
alleged. This defence
must
therefore
fail."
I
express
my
appreciation of
Mr. Bowden' s
provision of
the following note
in his
submissions
upon
the authorities
I
have been
discussing:
"In 'Professional
Negligence',
Partlett
1st
ed.
(1985)
at
p.
227
the learned author takes the
view
that:-
'The
application of the defence
where
economic
interests
are
at
stake
does
not
raise the
same
considerations.
The
defence
should not
be
available in
these
cases.'
There
the
learned author
is
talking
about
contributory negligence.
Of
course
it
is
mainly
concerned
with
'professional'
negligence.
Partlett
at
p.
225
refers to
Meddick
v. Cutten
&
Harvey
111
L . S .
J.
S .
21
2;
11 3 L . S .
J.
S . 3 7 5 (
on
appeal
) .
There
at
first
instance
White
J.
held
that
a
client
was
not
guilty of contributory
negligence
when a
cheque
was drawn
for the
purposes
of
an
investment
in
such
a way
as
to
permit the
proceeds
to
be
converted
by
a
third
party.
The
judgment
accepts
that in principle
contributory
negligence
may
be
found
in
such
circumstances."
This
is
not
a
professional
negligence
case, as the note
recognises.
In
this
case,
my
view
is
that
any
damage
the
plaintiffs
may
have
suffered
may
fairly
be
said
to result
partly
from
their
own
fault,
within
the
meaning
of
s.
10.
In
particular,
they
are
saddled
with
the
failure
of
Mr.
Corbett
to
appreciate
(or
acknowledge,
once he
became
active
in
the
business)
how
far
from
fully
developed
the
O.M.A.
system
was.
In
my
view
it
is
not
right to
sever the
second and
fifth plaintiffs'
-- 111 of 115 --
1 1 1
position
from
his
and the third plaintiff's.
They have
all
made common
cause.
On some
basis not
made
clear,
Mr.
Corbett
and
the third plaintiff
have been reimbursed for the bulk of
their
expenditure of $88,193.03.
The
details are:
II
Reimbursements from
OMA
24.7.87
24.9.87
30.10.87
13.11.87
27.11.87
10,000.00
9,858.38
3,000.00
10,000.00
6,000.00
Reimbursement from
Corbett Enterprises
Pty Limited
19.
1 .
88
38,858.38
35,000.00"
Dr.
Corbett, too,
may
be
regarded as having
contributed
to his
and
the
fifth plaintiff's
losses.
His
evidence
at
p.
90
(recorded
in
rather
garbled fashion)
is
designed
to
cover
the
technical
requirements
of reliance or
causation or
until
the expenditure
of the
last
dollar.
I
cannot accept
that
Dr.
Corbett's reliance
extends anything
like
as
long as
p.
90
might
suggest.
Quite
apart
from
his
expectations
regarding
customer
enthusiasm
for
O.M.A.
products,
there
came
regularly
from
August
1987
signals
that
engineers
such
as
Mr.
Patterson's
firm,
followed
by
Mr.
Seymour,
would
not
repose confidence
in
the
system.
It
was
not reasonable
to
ignore
Mr.
Seymour's views
on
the basis of
Mr.
Eichhorn'
s
criticism of his
competence.
I
do
not think
that
the five
pages
of
"Abel
Point Calculations"
in
October
1987
would
serve
to allay
the
doubts
any
reasonable
investor
would
have
felt.
They
did not,
in
any
event,
because
the
plaintiffs
proceeded,
at
a
leisurely
pace,
to
obtain
Mr.
Gallagher's
-- 112 of 115 --
112
views.
(
It
may
be noted that
no claim
is
made
in the
pleadings regarding reliance
by
the plaintiffs
·on
the
Abel
Point Calculations.
They
are not said to constitute
a
representation themselves,
or to
have been
the subject of
any
relevant representation
by
Mr.
Wright.
However,
the
plaintiffs
appear
to rely
on
them
in
terms
of
a
professional
person's obligation to
use continuing vigilance to
check
for
and
correct errors in old
work. See
per
Sachs
L.
J.
in
Brickfield Properties
Ltd. v.
Newton
(1971)
1
W.L.R. 859, 873,
and Jackson and Powell.
Professional
Negligence (2nd
ed.)
51,
where
it
is
said that
an
engineer's
duty
is
a
continuing one.)
This
issue of contributory
negligence
is
not
strictly
necessary
to
consider, as
I
have found
the
plaintiffs
do
not
demonstrate
a
loss,
at
the
end
of the
day. Should
I
be
wrong
in that
view, and
should
the
$600,000.00
recovered
from
C.S.R.
Humes
in
March 1989
and
later
not
be
properly
brought
into
consideration, then
it
would be
necessary
to consider
at
what
point in
time
the
plaintiffs'
loss
from
their
adventure with
O. M.A.
can no
longer
be
said to
have been
caused
by
their
reliance
on
representations
by
the
defendants,
alternatively
to
consider
the extent
to
which
the
plaintiffs'
own
fault
resulted
in
their
overall loss.
Elsewhere,
I
have
indicated
my
view
that
the
cut-off
point
is
the
end
of
December,
1987:
the
defendants
made a
submission
in
those terms.
If
contributory
negligence
is
applicable,
the
situation
becomes
worse
for
the
plaintiffs,
insofar
as
I
would
assess
their
fault,
in
all
the
circumstances,
as equally productive
of
their
damage,
with the defendants'
conduct.
This
would
limit
the
plaintiffs'
recovery
to
half of
the
sum
of
$279,967.93
and
half
of
the
Hungerfords
v.
Walker component
assessed
by
me.
-- 113 of 115 --
113
Conclusion
Damages
is in
most
cases the
gist of
an
action in tort.
The
plaintiffs
have
established negligent misstatements
against the defendants, but not that
they suffered
damage.
"Negligence
is
a
cause of action
only
for
a
person
who
suffers
actual
harm by
reason of
it."
(
Pollock, p. 139).
An
admission
of negligence
accompanied by
a
denial of
damage
is
a
denial of the cause of action: J.R.
Munday
Limited v.
London
County Council [1916]
2
K.B.
331, 334.
The
consequence
is that
the
plaintiffs'
action
ought
to
be dismissed, unless
they persuade
me
that
the
door ought
to
be
kept
open by an
inquiry
(
as already
mentioned) under
O.
37:5,
O.
39:52 (which
appears
to
apply only
if
some damage
is
shown
to
have
been
incurred,
so
that
a
judgment
may
be
given)
or
on
some
other basis.
Costs should not
simply follow
the
event,
in
my
view,
given
that
the
plaintiffs
have succeeded
on most
of the issues
litigated,
and on
the issues
which
took
up
virtually
the
whole
trial.
These
reasons
have been
prepared· under unusual
pressure.
The
trial
of the action
itself
extended
beyond
the
term
of
my
commission, which
has continued
under
s.
3
of the
Acting
Judges
Act
of
1873,
and
precluded
my
participation in
gazetted
Civil
sittings
in
another
court.
I
have been
anxious
to
return to
that
work
to
satisfy
the expectations
of
litigants
whose
cases
have been
set
down.
I
mention
this,
being only too
conscious
of deficiencies in
what
I
have
written.
There
are
some
matters
the
parties
might
have
expected
to find
treated
at
greater
length,
including
some
of
the
legal
arguments
presented,
and
the
engineering evidence;
there
are others in
-- 114 of 115 --
114
which I
appreciate that
I
have been
repetitive.
However,
·
having reached the point of being ready to give judgment,
I
think
it
better not to delay merely
for the purpose of
expanding, pruning
or presenting
more
felicitously
what has
been prepared.
-- 115 of 115 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1991/353