Cape York Space Agency Pty Ltd, Re [1991] QSC 326
.
,.
.
r-....
, .:, .
r.,
. .'
..
TRANSCRIPT OF PROCEEDINGS
State Reporting Bureau,
4th Floor, The Law Courts,
George Street,
BRJSBANE. 0. 4000
Tel.
(07)
227.4360
(Copyright in this transcript is vested
in
the
Crov.,n.
Copies thereof must not
be made
or
sold without the written authority · of the Director, State Reporting
Bureau.)
SUPREME
COURT
OF QUEENSLAND
CIVIL
JURISDICTION
BYRNE
J
No
722
of
1991
?r°'
IN
THE MATTER
OF THE CORPORATIONS
LAW
and
,_o
REVISED COPIES ,ISSUED
Court Rioporting Bureau
Date, 3 I I , o I
Cf
I
......
IN
THE MATTER
OF THE CAPE
YORK
SPACE
AGENCY
PTY LTD
BRISBANE
•.
DATE
28/10/91 12.05
P.M.
JUDGMENT
1
-- 1 of 13 --
(
10
20
30
40
50
60
281091
JUDGMENT
HIS
HONOUR:
This
is
an
application for
winding
up.
The
ground
is
that
the
company, Cape
York
Space
Agency
Pty
Ltd,
is
insolvent.
The
evidence
shows
that
the
company
is
indeed
unable
to
pay
its
debts as they
fall
due.
Insolvency
has
been
clearly
proved.
Amongst
others·,.
the
·
company's
debts
include
liability
for
unpaid
income
tax
in
an
amount
approaching $50,000.
The
principal
ground
relied
upon
by
the
company
to
avoid
the
winding
up
is
that
the
substitute
applicant
tacks standing to
seek
the
winding
up.
The
company's
contention
is that
the
applicant
has
failed
to
prove
that
at
material
times
it
has been "a
creditor"
of the
company.
In
May
1988
the
parties
entered into
a
form
of
written
agreement
for the provision of
services
by
the
substitute
applicant to the
company. The
document
envisaged
that
the
services
would
include
rnan~9ement,
engineering
and
consultancy.
The
service~
would be
provided~in accordance with the
terms
of the
document and
in phases.
By
section
B-1
the services to
be
provided
by
Kaiser, as
I
shall call
the
substitute applicant,
were
to
be
provided in
these phases: one, concept
validation
and
criteria
definition;
two, enhancement
of the concept.; three, basic engineering
and
project financing; and, four, implementation.
During the enhancement of the concept phase Kaiser
was
to
Govt. Printer, Old.
2
10
30
60
-- 2 of 13 --
(
10
20
30
40
so
60
281091 JUDGMENT
provide project
management and consultant engineering services
"as shall
be mutually devel,oped and agreed upon".
In respect of the third
phase,
that is
to say the basic
engineering
and
project financing.by section
B-4
of the
contract,
Kaiser
was
to provide "project
management
consulting
and
engineering services
as
shall
be
mutually developed and
agreed upon".
Section
B-6
made
a
general provision with
respect to the
way
in
which
the services
were
to
be
provided.
The
section provides
that
Kaiser
Engineers
shall
perform
"services"·
"in
accordance with
directions
received
from
time
to
time
from
the
client
and must
at all
times
act in
good
faith
to the
client".
"Services"
is
defined
by
the
agreement.
The
correspondence
which
the
parties
have exchanged
reveals
that
a
substantial
number
of consultancy
services
were
provided
by
Kaiser
to
the
company
between
phases.
It
isrthe·
liability
to
pay
for these services
which
is
in
dispute.
The
dispute
arose during the
course
of
Mr
O'Shea's
submissions
on
behalf
of the
company.
The
material
contained
in the
affidavits
read
before
me
otherwise demonstrates
that until this
applicatio
was.called
on
for
hearing the
company
acknowledged
a
very
substantial
liability
to
Kaiser in respect of the interphase
services.
On
19
September
1989
the
company
wrote
to
Kaiser's
managing
Govt. Printer. Old.
3
10
20
30
40
50
60
-- 3 of 13 --
(
10
20
281091 JUDGMENT
director.
The
letter
advised that progress of the Spaceport
Project at that stage relied
on
the resolution of
a number
of issues
which were then currently being drafted
by
the
company. The
letter
contained
this
advice:
"The
project
management
services as defined in our agreement with Kaiser
Engineers
Australia
Pty Ltd
since
May
1988
are for the
time
being not required.
This
instruction will take
effect
from
today's date."
The
letter
went
on
to
propose
that
consultancy
services
nevertheless
continue
to
be
provided
by
Kaiser.
Those which
were
not required
were
of
a
consulting engineering
nature.
The
letter
indicated
that
there
would be
"Preparation
30
attendance
forthcoming
and
the negotiations regarding the
supply of rockets
and ground
support
equipment
assistance in
the
submissions
of the proposal
to the
company
and
assistance
in presentations to
the prospective
'equity holders'."
The
letter
went
on
to
propose
that
these"consulting engineering
t
4b
seivi6es
only
be
paid for in
accordance with our
agreement~.
The
reference there in context is,
plainly
enough" :to
the
written
agreement
of
6 May
1988.
SCT':Je
presently
i.'1l1Tlaterial
qualification
was
added
.
.
,,
so
The
letter
went
on
to
suggest
that
work
on
sev~ral aspects of
the
project.should
be
reduced
to
the
lowest
possible level
consistent
with the
company's
maintaining
its
options
to
proceed with
the
work
according
to
its
latest
project
schedule.
The
letter
concluded
by
the
company's
expression
of
60
Govt. Printer, Old.
4
10
30
40
60
-- 4 of 13 --
( J
10
20
30
40
50
60
281091 JUDGMENT
appreciation for what
it
described as "outstanding performance"
of Kaiser "on
this project to ,date".
The
proposal in the
form communicated by
that letter
was
not
entirely satisfactory to Kaiser. Rather ·than
communicating
its
consent
to, th·e
prdposal,
by
its
letter
dated
11
October 1989,
Kaiser
acknowledged
receipt of
the
l~tter,
acknowledged
the
difficulties
being faced
by
the
company
and
its
current
needs
to
reduce
project costs
as
much
as
possible,
and
proposed
a
different
form
of relationship
for the provision of further consulting
and management
services.
The
letter
proposed
what
it
describes as c9-operation with
the
company
by
proposing
a
new
management
fee
and making
other
arrangements.
It
is
not necessary
for present
purposes
to
set
out the
details.
The
letter
concluded
by
asserting
that
before
some
cost
reduction
measures ~o
which
the
letter
referred)were
implemente
agreement
would
be
required
on
a
number
of
other aspects of the
proposal.
These
included the
company's':
approval
of
work
plan,
schedule
and
budget
defining
anticipated
activity
during
"this
interim period".
I•••'
'-·
The
letter
continued{after
setting
out
other
details
of
the
proposal)
:"On
the
assumption
that this
proposal
will
be
acceptable
to
(company),
I
have engaged John
Sulzbach
to
work
with
you
at
your convenience
to
establish
events
and/or
Govt. Printer, Old.
5
10
20
30
1
40
50
60
-- 5 of 13 --
281091 JUDGMENT
activities
which
will further define the interim period and
its
anticipated duration •••.
he
will
work
with you on
the
other conditions as well.
I
want
to assure
you
that Kaiser
10 10
20
30
40
50
Engineers
Australia Pty Ltd remains
totally
dedicated to
bringing
the-Cape
York
Spaceport Project to operational
reality.
We
share
your goals
and
will
continue to strive
with
you
to
achieve them."
For
the
company
it
is
said that
the consulting services
which
were
provided
after that
exchange
of
correspondence cannot
have been
provided pursuant
to the written
agreement
itself
and
may
well
have been
provided
on
the footing
that
Kaiser
was
accepting the
risk that
it
would
not
be
paid for further
work done
in the
interim; that
is
to say, before
a
plan
was
developed
and embarked
upon
in respect of
phase
3
of the
project.
Two
separate contentions
were
advanced
on
the
company's
behalf.
One
was
that
there
was
no
arguable claim
to
remuneration
for
work done
between
phase
2
and
phase
3
on
the footing
that
Kaise
had
accepted
the
risk that
it
would
not
be
paid
any
sum.
This
was
the
company's
primary
position.
The
alternative
was
that
Kaiser
may
wel
1
have
decided
to
take
on
the
risk
of
doing
further
'l,-
wor
....
,
such
work
to
be
relatively
minor
in
the
scale
of
the
project
as
a
whole,
until project
financing
was
obtained;
with
Kaiser's entitlement to
payment
in
the
meantime·
being
dependent
on
project
financing
ultimately
being
obtained.
(The
cijse
has
been·
~onducted
on bhe
.assumption
---=60=----+---------
--------------------
---------
- -
Govt. Printer, Old.
6
30
40
60
-- 6 of 13 --
(~
10
20
30
40
50
60
281091 JUDGMENT
that the necessary finance has not yet been obtained.}
Now,
it
might have been expected
that Kaiser
would
support
this application
by materia.l tending ;to establish directly
that
the services for
which
this
claim
is
made,
that is
to
say
those
between
phases
2
and
3
said to
have been
effected
at
the direction of the
company, were reque.sted in.
c.ircumstances
,·. '
~learly
showing
~ithe~_an express or· implied
obrigation
to
pay
for
it.
inference.
Govt. Printer, Old.
1
Unhappily
the matter
was
left
to
7
10
20
30
40
50
60
-- 7 of 13 --
( 281091 JUDGMENT
In an affidavit of Mr Robbins filed on 24 October, Mr Robbins
deposes that Kaiser "continued to provide services in accordan e
with the directions received from the company from time to
time as w~s required bys B-6 of the contract." The affidavit
10 10
20
30
40
50
60
goes on to assert that those consulting services included,
amongst other things, meeting with the supplier of rockets and
ground support equipment in Moscow in December 1989, preparations
for meetings with the supplier in Montreaux in March.1990,
meetings with a supplier in Brisbane in July 1990, and prepara ,ion~
20
for meetings with a supplier in November 1990.
No cross-examination was directed to Mr Robbins in respect of
these allegations; and it seems to me tha~ 1 in context,they
ought to be understood as indicating a series of directions
from the company to Kaiser to provide the services
actually rendered. The reference to s B-6 of the contract sees
to involve nothing more , than that the nature of the
services to be provided were those broadly contemplated for
30
the-contract, and that the services were to be provided in
good faith.
40
The affidavit of Mr Robbins goes on to assert that in the firs
half of 1990 Kaiser became concerned that it was owed
substantial amounts of monies by the company, and in mid July
forwarded a statutory demand to the company seeking payment of
a substantial sum of money. There was·a deal of
correspondence. On 27 July, some nine days or so after the
statutory demand had been delivered, the managing director
of Kaiser, and Mr M L Edwar<fs, the managing director of the company .
Govt. Printer, Old
8
50
-- 8 of 13 --
( , l
10
20
30
40
so
281091 JUDGMENT
signed -'a clocument which recorded their then understanding of
arrangements reached with respect to payment
by the company to Kaiser of ·its claims.
The letter rec.ords "that the payments ·· to
your company as invoiced amounting to some $770,000 •.• are
defined and agreed by management." The fourth paragraph of
10
the letter contained a promise by the company to pay to Kaiser
$25,000. This sum was described in the letter as representing 20
• \!
'hotional interest payment" and $150 j 000 ..irepresenting al 1 fees
which may be due and payable to your ~ompany to and including
31 July 1990 11 •
There have been subsequent communications between the company
and Kaiser which are only consistent with a distinct
acknowledgrnent by the company :::,fa liability to Kaiser for a
substantial sum of money in respect of the consultancy ind
other services to which Mr Robbins has deposed in paragraphs 10
and 11 of his affidavit. For example, on 31 August last year
Mr Edwards sent a facsimile transmission to Kaiser's maneging
director referring to the delay in implementing arrangements
which had previously been agreed for the payment of what is
obviously a large sum of money for the compromise of Kaiser's
claim for consultancy services.
More recently, on 8 May this year, the company's financial.
controller sent a facsimile transmission to Kaiser in which
this was said, "Obr equity d~bt transaction is proceeding to
Govt. Printer, Old.
9
30
40
50
-- 9 of 13 --
(
10
20
30
40
50
60
281091 -JUDGMENT
We
therefore propose that
CYSA
bring its
debt current in four
equal instalments, the
first
payable on
3
June 1991 and
thereafter
bi-monthly
until the agreed debt
is
discharged"
(my
emphasis).
The
affidavit of
Mr
GT Galt
filed
by
leave today
is
consistent
with the
view
that
the services for
which
the present claim
is
advanced were
provided
at
the
company's
direction
and
in
circumstances
in
which
the
company
must have
expected
to
pay
for
them.
It
is,
as
I
have
indicated,
somewhat
unfortunate
that
the conclusion
to
which
I
have
finally
come
is
more
a
matter of inference
than
direct
proof.
But
I
have
reached the
conclusion
on
the
balance
of
probabilities that
Kaiser
has
established
that
it
is entitled
to standing to prosecute
this
application
seeking the
company's
winding up.
The company
also raised against
Kaiser
a
case
that
the
debt
it
alleges
has been
extinguished
by
the
company's
cross-claim.
The company
wishes
to
set
up
this
cross-claim
as
an
equitable
set
off.
The
basis
of the_alleged
set
off
is
the
allegation
that
the
company
has
·suffered
a
considerable
loss.
The
loss
is
said to
derive
from
the taking of
documents
by
Kaiser
which
Kaiser prepared
for the
company
in
accordance
with
obligations
it
assumed
either
under,
the
contract of
6 May
1988
or
pursuant
to
the
subsequent
ftirections
which have
given
rise
to
the
claims
relied
on by
Kaiser today.
Govt. Printer, Old.
10
10
30
40
60
-- 10 of 13 --
( '
L
10
20
30
40
so
60
281091 'JUDGMENT
These documents are said to have become the property of the
company and to have been wrongfully taken away from the
company's possession by Kaiser. It is not necessary for
present purposes to express a view about the merits of this
·claim. That is because Kaiser, while denying that it has
unlawfully removed the company's documents,offers an
undertaking, the effect of which is to preserve the documents
pending a trial of the company's claim against it. It offers
a further undertaking that in the event that the company
establishes its title to the documents in question, Kaise:r·.~-
wil l deliver them up to the company.
In the light of those undertakings there is no prospect that
the company,could establish at an early trial an entitlement
to damages in .... a. substantial amount. In short, the alleged
cross claim is no basis for a conclusion that the applicant
is not entitled to maintain the application for a winding q,
order.
Only one other consideration remains. It was urged on behal
of the company that a winding up in any event should not be
ordered now on the footing that the delay for a month or so
would cause substantial prejudice to the company, but little
or no·• prejudice to the applicant. It is also pointed out
that·Kaiser is not support~d0by any other creditor in the
making of the application for ·the winding up order, and it
has been su.hni tted that other major creditors have ,.in the
past at least,supported an adjournment.
11
10
20
30
40
50
60
-- 11 of 13 --
10
20
30
40
50
60
281091 JUDGMENT
An
adjournment for
a month
is said to be
justified
by
material exhibited to
an
affidavit of
Dennis Allan
Mcilwraith.
Mr
Mcilwraith,
who was
the Chief Executive
Officer of Essihgtoh International Pty Ltd,
exhibits
a
:letter
of intent
with·
R W
-Beck_&
Associatei ih relation to the
Cape York
International
Space·
Port.
Mr
Mcilwraith deposes
to
having
been involved
in
commercial
dealings with
R W
Beck
&•\
Associates concerning.the
planned
construction projects in
various p~rts
of-
the
world,
including
a $225m
hydro-electric
scheme
for
Zagreb.
He
is
working
with
R W
Beck
in
relation
to other current projects.
He
deposes
to
a
belief that
R W
Beck
&
Associates
has
the
capacity to
arrange
project
finance
for the
Cape York
Space
·Port ~n
the
amounts
refe~red
to
in the
letter
of
intent.
The
letter
of
parties
-
obtairii'ng
intent
and
envisages
exchanging
the
information
..
and
attending
one
meeting
at least to
make
preparation
for
entering into
a
formal~
binding
agreement
to
design
and
provide
construction
management
finance
and
constructing the
Cape
York
Space
Project.
Under
the
terms
of the
letter
of
intent project
information
is
to
be exchanged.
The
letter
of
intent plainly
contemplates
that
very
substantial
sums
of
money
might
be
involved
to
advance
the p~oject.
Para
1
contains
this
agreement,
"It is
recognised
that
the required
financing
for the
CYSA
project
is
in
the order
of
$700m
Australian
to
be
secured only
by
the
12
10
30
40
60
-- 12 of 13 --
( < . '
'
10
20
30
40
50
60
281091 JUDGMENT
project.
II
In
my
opinion the prospect that the
company may
be able
to
raise
finance for the project
which,
if
obtainec;I, would
'·
,
•;
enable
it
to discharge
its
liab~lity to Kaiser
is
not
a
s1.:i'fficient
justification for
0deny-1-p.g
Kaiser
-its
prima
·
faci~ present entitlement
to.
have the
canpany wound
up.
There
will therefore
be
an
order
that
Cape
York
Space
Agency
Pty Ltd be
wound
up by
the
Court under
the provisions of the
Corporation
Law
and
that
Philip
Gregory
Jefferson
be
appointed
the
liquidator for the
purposes
of the
winding up.
The
order
will
be:
upon
Kaiser
by
its
counsel .undertaking
to
preserve
and
subsequently
to deliver to
the
respondent
all files
retained or
taken
by
it
in the event
that
a
Court
of
competent
jurisdiction
determines
the
titles
to
such
files
as
retained
by
the
respondent.
13
10
20
30
40
50
60
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1991/326