Colber Constructions Pty Ltd v Spicer [1991] QSCFC 131
10
20
50
60
IN THE SUPREME COURT OF QUEENSLAND
FULL COURT
I) OCT/13 91
No. 54 of 1990
BEFORE :
The Acting Chief Justice (Mr. Justice McPherson)
Mr. Justice Shepherdson
Mr. Justice Williams
BRISBANE. 24 JULY 1991
(Copyright in this transcript is vested in
the Crown. Copies thereof must not be made
or sold without the written authority of the
Chief Court Reporter , Court Reporting Bureau.)
30
BETWEEN:
COLBER CONSTRUCTIONS PTY. LTD.
(Plaintiff)
-and-
WARREN GEORGE SPICER
( Defendant)
ORDER
Respondent
Appellant
40
MR. JUSTICE WILLIAMS: The respondent to this appeal is
a contractor who carried out engineering work at the request
of the appellant. The circumstances giving rise to its
engagement were somewhat unusual. The appellant obtained a
quotation from another contractor, Techdesyn, with respect to
the laying of 650 metres of sewerage line for a contract
price of $35,000. Ultimately the respondent took over that
work and it was agreed at the trial and on the hearing of the
appeal that there was a specific contract which related to
the laying of 650 metres of 150 millimetre diameter clay pipe
for $35,500.
In terms of that contract, the respondent was entitled
to an extra if rock was encountered in the course of carrying
out the work. Further, in the course of carrying out the
work, the extent of the work was varied and it was the
"//-=*/
10
20
30
40
50
Govt. Printer, Qld.
60
[1991] QSCFC 131
-- 1 of 7 --
1 respondent's contention that a total of 865.7 metres of 1
sewerage line was laid at the appellant's request. The
appellant paid the $35,500 but did not pay anything for the
extra work. In consequence, the respondent commenced an
action in this Court claiming $20,836.99 for work and labour
done and materials supplied plus interest.
The matter was remitted to the District Court and came
on for trial in that Court on 14 May 1990. That the claim
was for the cost of the extra work was made clear in the
pleadings; particulars set out in para. 7 of the statement of
claim included a detailed description of the work done and
the prices charged for the work.
By para .4 of the defence the defendant denied that the
plaintiff did any work for the defendant other than the work
which was the subject of the lump sum contract and for which
the plaintiff had been paid.
The learned trial judge accepted, in essence, the
evidence given by Mr. Berry, the principal of the respondent,
and a quantity surveyor, Mr. Luckins, called to support the
respondent's claim. On the hearing of this appeal it was
argued that the learned trial judge was not entitled to find
in favour of the respondent that extra work had been done
because the respondent had not discharged the onus on it of
proving the precise work that was done under the lump sum
contract .
In my view, there is no merit in the appellant's
contention in that regard. It was for the respondent to
prove that extra work was done and that could, in my view, be
established without defining precisely the work which had to
be done under the lump sum contract. In any event, the
Govt. Printer, Qld.
10
20
30
40
50
60
2
-- 2 of 7 --
1
10
20
30
40
50
60
1
10
20
30
40
50
60
evidence clearly establishes that an additional 215.7 metres
of sewerage line was laid. One can obtain that figure by
looking at the notations on the plans Exhibits 6 and 7.
Further, that is established by the express evidence of
Berry. I would refer in particular to Berry's evidence in
chief at pp.17 and 18 where he deals extensively with the
extra 215.7 metres of pipeline.
In my view, there was ample evidence on which the
learned trial judge could make a finding that the extra work
claimed was carried out.
Looking at the particulars in para. 7 (a) of the statement
of claim, the 335 cubic metres referred to in para.(l) was
established by the evidence of Luckins at p.122; the 48.38
cubic metres of rock referred to in para. (2) was established
by the evidence of Berry at p.19; and the 22 extra metres of
cast iron piping referred to in para. (4) was established by
the evidence of Berry at p.33. The prices set out in
para.7(b) were all confirmed by the evidence of Luckins from
pp.122 to 124. In addition, so far as the cost of the cast
iron pipe was concerned, further evidence relating to that
was given by Berry at p.33.
The only matter so far not dealt with is the quantum of
sand bed referred to in para.7(a )(5). That paragraph refers
to 38.83 cubic metres of sand bed and surround. Berry at
p.33 gave evidence that the Maroochydore Shire Council as a
standard practice required the piping to be laid on a sand
bedding and surrounded with sand. Luckins at p.124 gave
evidence that the reasonable cost of sand bed and surround
was $26 per cubic metre. The evidence does not specifically
establish that the sand bed and surround had to be of a depth
Govt. Printer, Qld.
3
-- 3 of 7 --
1
10
20
30
40
50
60
1
10
20
30
40
50
60
and width 600 millimetres by 300 millimetres. Further, at
p.36 in the course of his evidence in chief Berry was
specifically directed to the particulars alleged in para. 7 of
the statement of claim and gave evidence that the quantities
outlined in that paragraph were fair and reasonable estimates
and that the charges made were fair and reasonable prices.
In my view, in those circumstances, the learned trial
judge was justified in concluding that the quantum of the
claim for sand bed and surround had been established.
Given that resume, there was, in my view, ample evidence
to support the learned trial judge's findings. It should be
noted that he did not accept the respondent ' s case that it
was entitled to seven additional manholes which were said to
have a cost of $4,837. In that regard, the learned trial
judge said this:
"I disallow, however, a claim made by the contractor for
seven additional manholes at an average depth of 1.5 m -
seven by $691, totalling $4,837.37.
I consider that Mr. Berry was mistaken on this part of
the claim and that that part of the claim should be
regarded as being part of the original quotation between
Techdesyn and Mr. Spicer."
The mere recital of that passage in the judgment shows
that at all times the learned trial judge was conscious of
the appellant 's case and was taking care to ensure that he
only allowed items which were truly extras.
It was argued that there was some inconsistency between
His Honour's conclusions with respect to the manholes and the
other part of his judgment; but as the original contract was
unclear as to the number of manholes involved and as Berry
also made an error in initially identifying the seven
manholes which he was claiming as an extra, it seems to me
that the learned trial judge came to the conclusion that on
Govt. Printer, Qld.
4
-- 4 of 7 --
1
10
20
30
40
50
60
the evidence he could not be positively satisfied that the
seven manholes claimed were truly an extra. Looked at in
that light, there is no inconsistency. In any event, by
disallowing that amount, His Honour made a finding which
operated in the appellant's favour.
In the result, His Honour allowed $17,907.09 for extras
associated with the additional 215.7 metres of line. The
learned trial judge accepted the evidence of Berry and
Luckins that it was appropriate to allow a 15 per cent profit
margin for the operator. The reasons for judgment record him
saying that the quantum of that was $3,686.05, but that is
obviously a typographical error for $2,686.05. The total
recorded in the judgment of $20,593.14 is accurate for cost
of work plus profit margin.
Counsel for the appellant indicated that there was no
challenge to the allowance of $218.53 for the additional cost
of excavating through rock in accordance with the terms of
the original contract. He also conceded that there was no
challenge to the finding that the respondent was entitled to
retention moneys withheld amounting to $1,775. It follows
that, in my view, there was ample evidence on which the
learned trial judge concluded that the respondent was
entitled to the total sum of $22,586.67. His Honour allowed
interest at the rate of 18 per cent per annum on the amount
of the judgment for a period of four years from the date of
issue of the writ; there is no challenge to that.
In my view, the appeal should be dismissed.
I agree with what is about to be said by the learned
presiding judge with respect to the question of interest
subsequent to the date of judgment.
Govt. Printer, Qld.
5
-- 5 of 7 --
THE ACTING CHIEF JUSTICE: For the reasons delivered
by my brother Williams, I agree that the appeal should be
dismissed.
I would also order pursuant to s.73 of the Common
Law Practice Act that interest on the judgment amount be paid
at the rate of 18 per cent per annum in respect of the period
commencing on 14 May 1990 and ending on the date on which the
plaintiff received the whole sum of $42,116.65 or (at the
option of the plaintiff, to be signified to the Registrar) on
22 March 1991, there being deducted from that interest sum
the amount,if any, accrued by way of interest on the sum that
was paid into court, if and in so far as the plaintiff has
received, or will receive, that amount of accrued interest.
MR. JUSTICE SHEPHERDSON: On the evidence, the plaintiff
did prove that the lump sum sewerage contract was for 650
metres of sewerage line at a total cost of $35,500. Bearing
in mind that the defendant pleaded that, in effect, all work
the plaintiff did was the subject of a lump sum contract and
already paid for, the onus was on the defendant to prove
this. He represented himself at the trial before the learned
District Court judge and gave evidence. The learned trial
judge gave an ex tempore judgment at the conclusion of the
evidence. He preferred the evidence of Berry where it
conflicted with the evidence of the defendant.
At the outset of the appeal Mr. McHugh, for the
appellant, abandoned all grounds of appeal in which findings
of fact adverse to the appellant's case had been challenged.
The plaintiff's evidence, as pointed out by my brother
Williams, was such that the learned trial judge could
properly find the plaintiff's case was proven in respect of
l
10
20
30
40
50
60
Govt. Printer, Qld.
6
-- 6 of 7 --
1 the matters for which he gave judgment against the defendant.
I agree with the reasons of my brother Williams and the
order he proposes .
I agree with the order proposed by the learned presiding
j udge .
0 THE ACTING CHIEF JUSTICE: The order of the Court is
that the appeal is dismissed with costs.
' There will be an order for payment of interest in the form
in which I have already expressed that order.
1
10
20
30
40
50
60
Govt. Printer, Qld.
7
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QSCFC/1991/131