Capricornia Electricity Board v John M Kelly (Builders) Pty Ltd [1991] QSCFC 75 [1992] 2 Qd R 240
1 in: the supreme court of Queensland
VO )
FULL COURT
BEFORE:
Mr. Justice Shepherdson
Mr. Justice Williams
Mr. Justice de Jersey
BRISBANE, 18 JULY 1991
Appeal No. 85 of 1990
20
(Copyright in this transcript is vested in
the Crown. Copies thereof must not be made
or sold without the written authority of the
Chief Court Reporter , Court Reporting Bureau.)
BETWEEN : 20
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
-and-
JOHN M. KELLY (BUILDERS) PTY . LTD.
(Defendant) Appellant
30
40
JUDGMENT
MR. JUSTICE SHEPHERDSON: I will ask my brother Williams
to
be
deliver the first judgment.
MR. JUSTICE WILLIAMS: In my opinion the appeal should
dismissed with costs. I publish my reasons.
MR. JUSTICE SHEPHERDSON: I would ask my brother de Jersey 40
to read the second judgment.
50
MR. JUSTICE DE JERSEY: I would dismiss the appeal with
costs to be taxed for reasons which I now publish.
MR. JUSTICE SHEPHERDSON: I agree that the appeal should
be dismissed with costs to be taxed for the reasons given by
my brother de Jersey. I publish short reasons.
The order of the Court then is: the appeal is dismissed
with costs to be taxed.
60 60
G214— Govt. Printer, Qld.
l
[1991] QSCFC 75
-- 1 of 39 --
tC c V/0 76
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT Appeal No. 85 of 1990
BETWEEN :
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
AND:
JOHN M. KELLY (BUILDERS) PTY . LTD.
(Defendant) Appellant
SHEPHERDSON J
WILLIAMS J
de JERSEY J
Reasons for judgment delivered by Shepherdson,
Williams and de Jersey JJ on 18th July, 1991.
Shepherdson J agreeing with the reasons of de
Jersey J. All concurring as to the order.
"APPEAL DISMISSED WITH COSTS."
-- 2 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 85 of 1990
Before the Full Court
Mr Justice Shepherdson
Mr Justice Williams
Mr Justice de Jersey
BETWEEN:
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
- and -
JOHN M. KELLY (BUILDERS) PTY . LTD.
(Defendant) Appellant
JUDGMENT - SHEPHERDSON J.
Delivered the 18th day of July, 1991
CATCHWORDS
Counsel: Mr. Gotterson Q.C. with for the
Defendant Appellant
V. Copely Q.C. with A. S. Mellier for the Plaintiff
Respondent
Solicitors: Cooper Grace & Ward for the Defendant Appellant
Connolly Schirmer & Batts for the Plaintiff
Respondent
Hearing Dates: 15th, 16th May, 1991
-- 3 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 85 of 1990
BETWEEN:
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
- and -
JOHN M. KELLY (BUILDERS) PTY . LTD.
(Defendant) Appellant
JUDGMENT - SHEPHERDSON J.
Delivered the 18th day of July, 1991
I agree that this appeal should be dismissed with costs
for the reasons given by my brother de Jersey. I would add
that the construction placed on s. 251 (10) (e) of the
Electricity Act 1976 (as amended) may cause added cost to
Electricity Boards relying on its provisions.
However, the remedy lies in the hands of the legislature
and, if that particular sub-section is to be amended, the
draftsman may find guidance from the comments on selective
tender procedure in the reasons for judgment of my brother
Williams .
-- 4 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 85 of 1990
Before the Full Court
Mr. Justice Shepherdson
Mr. Justice Williams
Mr. Justice de Jersey
BETWEEN:
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
AND:
JOHN M. KELLY (BUILDERS) PTY. LTD.
(Defendant) Appellant
JUDGMENT - G.N. WILLIAMS J.
Delivered the Jay of July, 1991.
CATCHWORDS :
Contract - powers of Electricity Board to enter into contract
considered - Electricity Act ss. 102, 129, 251, 252 considered -
procedure of registering tenderers considered - held contract
enforceable - whether non-compliance with statute rendered
contract unenforceable considered.
Counsel: Mr. R.W. Gotterson Q.C. and M. Conrick for
Appellant.
Mr. K. Copley Q.C. and A. Mellick for Respondent.
Solicitors: Cooper Grace & Ward for Appellant.
Connolly Schirma & Batts for Respondent.
Hearing date: 15th and 16th May, 1991
-- 5 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 85 of 1990
BETWEEN ;
AND:
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
JOHN M. KELLY (BUILDERS) PTY. LTD.
(Defendant) Appellant
JUDGMENT - G.N. WILLIAMS J.
Delivered the day of July, 1991.
For reasons which he gave the learned trial Judge ordered
the specific performance of an agreement in terms of which the
respondent agreed to sell to the appellant two parcels of land
for $1.75 million. In so doing he overruled the appellant's
contentions that the respondent had no power to enter into the
agreement or alternatively that the respondent was in breach of
a condition of the agreement entitling the appellant to rescind.
On.the appeal the appellant argued that the learned trial Judge
erred in rejecting each of those defences. This was not the
usual simple contract of sale and it is necessary to record some
essential background facts.
At all material times the respondent was an Electricity
Board constituted pursuant to Division II of Part III of the
Electricity Act 1976-1989 ("the Act"). For some time prior to
1987 it had been the registered proprietor of a number of parcels
-- 6 of 39 --
2
of land situated in Bolsover Street and Alma Street, Rockhampton.
The land fronting Bolsover Street was described in the contract
as Lot 2 on R.P. 600141 being the whole of the land contained in
Certificate of Title Vol. 622 Folio 183 and Lot 1 on R.P. 619349
being the whole of the land contained in Certificate of Title
Vol. 387 Folio 103. As at October 1987 the headquarters building
of the respondent was erected on the latter site.
From about early 1985 the respondent was interested in
acquiring a new building as its headquarters. There were seen
to be a number of ways in which that object could be achieved.
A new building could be erected on one of the sites owned by the
respondent fronting either Bolsover Street or Alma Street; or the
building could be erected on some other site in the Rockhampton
area. In order to offset construction costs, depending on where
the new building was erected, some or all of the existing parcels
of land owned by the respondent could be sold; one possibility
was that the building contractor might take the surplus land in
part payment for the construction costs.
From the outset the respondent was aware that there were
constraints imposed on it by the Act, and it realised that care
had to be taken to ensure that the proposal ultimately accepted
complied with the terms thereof. At all material times the
Queensland Electricity Commission ("the Commission") was
responsible for administering the Act, and as early as 15th July,
1986 the respondent wrote to the Commission informing it of its
proposals and seeking advice or approval with respect thereto.
General approval to the respondent ' s proposals was given by the
Commission in a letter dated 5th August, 1986; the letter did
-- 7 of 39 --
3
observe that "meticulous care" should be taken in implementing
the final proposal to ensure that there was no infringement of
the statutory provisions .
Section 102 of the Act constituted the respondent a "body
corporate" which was "capable in law of . . . taking, acquiring,
holding, dealing with and disposing of real and personal
property". Section 129 conferred powers, functions and duties
on the respondent which are generally associated with the supply
of electricity to consumers; it is not necessary to refer to
those powers in detail, but note should be taken of (u) which
empowers the respondent to "do such incidental or consequential
acts and things as may be necessary or expedient for the exercise
and performance of its powers, functions and duties." Finally
in this regard reference should be made to cl. 4 of Schedule II
to the Act; it confers on the respondent the power to do what is
necessary for "the provision of an office". Again it is not
necessary to refer to other provisions found in that clause. In
the light of all that there can, in my view, be no doubt that the
respondent had the power to own land and dispose of it, and to
enter into a contract for the construction of its office
premises.
Part VII of the Act is headed: "Contracts by and Authority
for Works of, Electricity Boards". The sub-sections of s. 251
relevant for present purposes are the following:
"(1) An Electricity Board may enter into any contract
for any of the purposes of this Act applicable to
an Electricity Board.
(2) A contract entered into by any Electricity Board
shall be made as follows:-
-- 8 of 39 --
4
(b) A contract that, if made between private
persons, would by law be required to be in
writing signed by the parties, may be made
in writing signed by the General Manager;
• » •
(3) A contract so made as aforesaid shall be
effectual in law and shall bind the Electricity
Board and all other parties thereto and may be
varied or discharged in the manner in which it is
authorised to be made.
(8) Before an Electricity Board attempts to dispose
of land pursuant to a provision of this section
... it shall offer it to the Minister for Lands
for acquisition on behalf of the Crown in right
of the State or a Crown instrumentality, . . .
(9) Before any contract -
(a) for the execution of any work ... to the
amount of $20,000.00 ... or more;
(c) for the sale of land
is entered into by any Electricity Board, it shall,
three weeks at least before entering into the
contract, notify its intention to make and invite
tenders for the contract by public notice published in
such newspaper or newspapers and in such manner and to
such extent as in the opinion of the Electricity Board
will ensure that the notification of intention to
enter into a contract is likely to be seen by as many
people as possible who are likely to tender.
(10) The procedure referred to in sub-section (9) may
be dispensed with -
(a) where the Commission certifies that an
emergency exists or special circumstances
exist;
(b) where the General Manager of the Electricity
Board is satisfied that there is only one
source of supply for the goods that are the
subject of the proposed contract or,
alternatively, that every likely supplier in
Australia has been invited in writing to
tender;
(e) where tenders for a particular project are
being invited by the Electricity Board from
registered tenderers who were so registered
by the Electricity Board pursuant to an
advertisement inviting such registration;
(11) (a) In respect of a sale of land ... an
Electricity Board may, in lieu of complying
-- 9 of 39 --
5
with sub-section (9), comply with this sub
section.
(b) An Electricity Board may sell any land
. . . by public auction or private contract,
but no such sale shall be made by private
contract unless and until the land or
surplus goods or materials have been offered
for sale by public auction and not sold.
(13) Subject to this Act, an Electricity Board may
accept the tender that on the view of all the
circumstances appears to it to be the most
advantageous, ... or the Electricity Board may
decline to accept any such tender."
Section 252 requires a Board to obtain the approval of the
Commission before entering into any contract exceeding in value
the amount of $250,000.00, or, in the case of a sale, before
accepting a tender obtained pursuant to s. 251(9) other than the
highest tender conforming with the specification in the tender
documents issued.
Against that background the respondent proceeded as follows .
On 7th, 9th and 12th July, 1986 it caused an advertisement to be
placed in a local newspaper under the hand of its General
Manager; other newspapers also carried that advertisement. - The
relevant terms for that advertisement for present purposes were
the following:
"New Administration Building - Rockhampton
Registration of Interest.
The Capricornia Electricity Board invites interested
parties to register their interest in the development
of a new Head Office building in Rockhampton.
This building is envisaged to comprise not less than
6,000 square metres of useable floor area exclusive of
car parking. General information on the Board's
intentions on this project are available on request
from the Manager . . .
Registrations of interest should outline the company
organisation, details of incorporation, and
demonstrate:
-- 10 of 39 --
6
architectural and structural design skills and
experience appropriate to modern office
buildings;
project management skills which will be required
to be maintained through the construction period;
cost and time consciousness relating to building
projects.
II
The General Information available to all prospective
registrants the following was the most critical siection thereof:
"Organisations interested in entering into an
arrangement are to submit proposals containing
sufficient detail for initial assessment based on:
architectural and structural design skills and
experience appropriate to modern office
buildings;
project management skills which will be required
to be maintained through the construction period;
cost and time consciousness relating to building
projects.
On the basis of this information the Board will
determine a short list of up to five (5) organisations
who will be invited to proceed to Stage 2.
The Board reserves the right to accept or reject any
expression of interest without assigning any special
reason therefore."
The document then set out a "Schedule of Alternative
Schemes". Therein a number of proposals were mooted either for
construction on the Alma Street land, or some other site in the
Rockhampton district; the various proposals could be incorporated
with transfer of the Alma Street property to the builder as part
payment. The Schedule then went on: "Each of the above
proposals may include a further alternative to allow for the
transfer of the Board's Bolsover Street properties to the
developer as part payment."
-- 11 of 39 --
7
In consequence of those advertisements some 41 organisations
registered interest, including J.M. Kelly (Project Builders) Pty.
Ltd. - hereinafter referred to as "Project Builders".
From the 41 who registered an expression of interest, the
consultant architect appointed by the respondent "prepared a
short list of nine developers whom he considers would be
satisfactory as the constructors of the proposed new
Administration Building." At its meeting on 26th August, 1986
the respondent considered that submission and in turn decided
that five developers, including Project Builders, should be
invited to submit detailed designs and proposals. The respondent
wrote to the Commission on 29th August seeking its approval of
the selection of organisations who were being invited to tender,
but the Commission by its letter of 22nd September, 1986 pointed
out that it was not part of its function to comment on that
decision. But in that letter the Commission did indicate that
it was satisfied that the respondent was observing the provisions
of s. 251 (10) (e) of the Act in proceeding as it proposed.
By letter dated 5th November, 1986 the respondent advised
each of the five selected tenderers, including Project Builders,
of the position. Those organisations were told a "Design Brief"
would be forwarded when available. In fact the design brief was
sent to each of the five under cover of a letter dated 12th
February, 1987. Tenders were to be lodged by 27th March, 1987.
The letter informed the prospective tenderers that, if
unsuccessful, the respondent was "prepared to pay to the
developer a contribution towards the expenses incurred in the
preparation of his submission such contribution to be limited to
-- 12 of 39 --
8
the sum of Eight thousand dollars ($8,000.00) per developer."
Relevantly Appendix "B" to the design brief detailed alternative
proposals based on the transfer to the successful tenderer of the
Bolsover Street properties in part payment of the construction
price. Each of the organisations invited to tender submitted at
least one proposal; Project Builders in fact submitted five
alternative proposals each with a separate price. It is
interesting to note that in the summary of tenders prepared by
the respondent it described the tenderer simply as J.M. Kelly.
The only tenderer who indicated that it would consider purchase
of the Bolsover Street properties was Project Builders.
On 16th April 1987 the respondent wrote to the Commission
asking it to formally approach the Minister for Lands in
accordance with the provisions of s. 251(8). The lands referred
to in that letter were the two parcels fronting Bolsover Street.
The letter said it enclosed "valuations which comprehensively
described the lands and improvements thereon and place a combined
value of $2.25 million on the properties."
The tenders were considered at a meeting of the respondent
held on 28th April, 1987. The architect on that occasion
furnished a recommendation that two of the proposals should not
receive further consideration. In consequence a resolution was
passed that .those two tenderers should be notified that their
submissions would not receive further consideration and $8,000.00
should be paid to each to offset design costs. It was further
resolved that there be further consideration given to the
remaining three tenders . The matter was then taken up at the
meeting of the respondent on 13th May, 1987. A further report
-- 13 of 39 --
9
on the remaining tenders was tabled, and it was resolved that one
of the remaining three should be deleted and that tenderer also
paid $8,000.00. That left the tender from "J.M. Kelly" and a
tender from Kern Konstruction. There was a deal of discussion
concerning the "tender of J.M. Kelly". Finally it was resolved
that there be agreement in principle "that the lowest tender,
i.e. that of J.M. Kelly (Scheme D), on the Fitzroy and Alma
Street site, for a firm lump sum price of $7,050,600.00 ... be
proceeded with."
By letter dated 16th June, 1987 Project Builders informed
the respondent that it "would now confirm our offer" to purchase
the two Bolsover Street properties for $1.75 million. The letter
also referred to the Alma Street site, but that is not relevant
given what happened.
The respondent notified the Commission of its decisions
under cover of a letter dated 24th June, 1987. It stated that
the Board had "selected a submission by J.M. Kelly (Builders)
Pty. Ltd." which was the lowest priced tender. It also stated
that negotiations were taking place with the preferred tenderer
for the purchase of "existing C.E.B. land and buildings surplus
to the Board's reguirements ." The offer to acguire the two
Bolsover Street properties for $1.75 million was discussed at the
meting of the respondent on 30th June, 1987. A sub-committee
recommended that those offers should be accepted. The minutes
of the respondent record the following resolution:
"That it be recommended to the Queensland Electricity
Commission that, subject to negotiations with the
preferred tenderer for payment arrangements acceptable
to the Board, and subject to a valuation by the
Department of the Valuer-General indicating that the
negotiated sale price is satisfactory, the acceptance
-- 14 of 39 --
10
by. the Board of the offer by the preferred tenderer to
purchase the premises owned by the Board at 152 and
156 Bolsover Street, Rockhampton, for not less than
$1,750,000.00 be approved."
The next relevant step was taken by the Board on 24th
August, 1987 when it forwarded a telefax to the Commission
setting out details of the proposal accepted by the respondent.
It showed the appellant as the successful tenderer with a
construction price of $7,050,600.00, and proceeds of sale of the
Bolsover Street properties (paid at stage of practical completion
of the new building) as $1,750,000.00, leaving an overall project
cost (after other items were brought into account) of
$7,590,600.00. Throughout that document the only reference was
to the appellant. The Commission responded by letter dated 1st
September, 1987 giving the Commission's approval to the
respondent to "enter into two contracts with J.M. Kelly
(Builders) Pty. Ltd." to construct the building for
$7,050,600.00, and to sell the Bolsover Street lands for
$1,750,000.00. Then by letter dated 29th September, 1987 the
Commission noted that the construction contract would be with
Project Builders and not the appellant. Under cover of a letter
dated 22nd October, 1987 the respondent forwarded to the
Commission copies of each contract; that for the design and
construction of the new building with Project Builders, and that
for the acquisition of the Bolsover Street land with the
appellant. Approval for the respondent to enter into those
contracts was given by the Commission in its letter of 6th
November, 1987.
It will be seen from the above resume of facts that there
appears to have been confusion at various stages between the
-- 15 of 39 --
11
appellant and Project Builders. They were found by the learned
trial Judge to be "associated companies" and that was conceded
during argument on appeal . It would seem that the involvement
of the two separate companies was at the sole request of those
controlling and benefiting from the activities of the J.M. Kelly
companies .
On 28th October, 1987 the contract in question for the
acquisition of the Bolsover Street properties was executed.
Forthwith upon the execution thereof the purchaser was to pay a
deposit of $5,000.00, and the balance of purchase price was to
be paid "upon the expiration of" two calendar months from the
date notice of practical completion of the new administration
building was given under the contract relating thereto. The
learned trial Judge found that by agreement between the parties
the completion date was extended until 6th February, 1989. No
challenge was made to that finding on appeal. It is only
necessary that I refer to cl. 22 of that contract in detail; it
provided:
"The Vendor warrants that all provisions of 'The
Electricity Act, 1976-1980' which affect this sale and
purchase (and in particular the provisions of Section
251 of such Act) have been complied with and that all
necessary approvals required to be obtained by the
Vendor pursuant to the said Act have been obtained."
I mention that the construction agreement was executed on
29th October, 1987 between Project Builders and the respondent.
No further reference need be made to that agreement; construction
was apparently completed in accordance with the terms thereof.
The construction contract made no reference to the other
dealing with the sale of the Bolsover Street land; but the
contract of sale was made subject to and conditional upon the
-- 16 of 39 --
12
execution of the construction contract and Project Builders
bringing the new administration building to the stage of
practical completion. It would seem to follow that pursuant to
the construction contract the respondent was obliged to pay
Project Builders the full contract price, and then pursuant to
the contract of sale the appellant was obliged to pay to the
respondent the full purchase price of the land. The argument on
appeal proceeded on the basis that the full price pursuant to the
construction agreement had in fact been paid. Strictly therefore
in terms of the executed agreements the value of the Bolsover
Street land was not set off against the construction cost.
On 6th February, 1989 (the date of settlement according to
the finding of the learned trial Judge) the appellant's
solicitors wrote to the respondent's solicitors informing them
that the appellant was "not prepared to proceed with settlement
unless proper evidence is produced that the provisions of the
above Act (and particular s. 251 thereof) have been complied
with". The letter stated that it seemed to the solicitors that
the section referred to had not been complied with. It was then
asserted that in those circumstances the contract was "void and
our client has no obligation to proceed to completion." The
respondent's solicitors replied by letter of 9th February, 1989
maintaining that the contract was legal and valid. Enclosed with
that letter were letters of 10th June, 1987 from the Commission;
of 9th June, 1987 from the Land Administration Commission to the
Commission; and of 8th February, 1989 from the Commission. In
the last of those letters the Commission purported to certify
that approval to entering into the two contracts "was granted on
-- 17 of 39 --
13
the understanding that special circumstances existed in regard
to the sale of the two Bolsover Street properties and therefore
the provisions of s. 251(10) (a) of the Electricity Act 1976-1986
had effect and obviated the need to comply with the provisions
of s. 251(9) of that Act." In a further letter from the
respondent's solicitors to the appellant's solicitors of 7th
March, 1989, the latter were supplied with copies of various
documents said to evidence the respondent's assertion that s. 251
was complied with.
The learned trial Judge considered that there had not been
compliance with either sub-ss. (9) or (11) of s. 251. Clearly
he was correct in so concluding. Tenders were not called by
public notice either for the construction of the building or the
sale of the lands and therefore sub-s. (9) was not complied with.
There was no attempt to sell the land by public auction and
therefore sub-s. (11) was not complied with . Indeed so much was
conceded by the respondent. Its case at trial, and on appeal,
was that it was able to bring itself within the dispensing
provisions of sub-s. (10) (a) or (e) . The appellant did not
concede that sub-s. (10) applied where the transaction involved
the sale of land. In my view there is no validity in that
argument. Whilst sub-ss. (9) and (11) each specifically refer
to a procedure which may be followed where sale of land is
involved, sub-s. (10) by its terms says that the requirements of
sub-s. (9) may be dispensed with if one of the conditions
specified therein is satisfied. In those circumstances, as a
matter of statutory construction, I am of the view that
sub-s. (10) may apply to a transaction which involves the sale
-- 18 of 39 --
14
of land, or indeed which relates solely to the sale of land, by
a Board.
The learned trial Judge held that para, (a) was not
available to the respondent because it required the certification
to be given prior to the contract being entered into. That such
was intended can be readily appreciated when one looks at the
wording of sub-s. (9). It applies "before any contract" is
entered into, and the dispensation referred to in (10) (a) must
therefore relate to that point of time. Here the Commission did
not purport to certify prior to October 1987 that "special
circumstances" existed though it may well then have been of that
view. It purported to so certify only by its letter of 8th
February, 1989, but in my opinion it was then too late to do so.
I agree with the learned trial Judge in concluding that the
respondent cannot rely on para, (a) of sub-s. (10).
But the position with respect to para, (e) is, in my view,
more complex. The learned trial Judge concluded that there had
not been implementation of the (10) (e) procedure because "all"
of those who registered an interest were not invited to tender.
The learned trial Judge noted that the respondent was "selective"
in deciding that only five should be asked to tender. He was
certainly correct in making that finding. He went on: "But it
is not enough that the Board's arrangements conform to the spirit
of the legislation. And because not all 'registered tenderers'
were asked to tender, the letter of Section 251 has not been
satisfied." He noted also that the respondent's proposal had to
answer the description "particular project" before (e) would be
enlivened, but he did not expressly decide whether or not that
-- 19 of 39 --
15
requirement was met on the evidence. He went on to say:
"Sub-section (10) (e) envisages that where there are expressions
of interest by more than one 'registered tenderer' , all those
registered tenderers must be invited to tender. The mischief to
which sub-section (9) and (10) (e) are directed cannot be
adequately addressed unless such an interpretation of
paragraph (10) (e) is adopted." He had previously defined the
"mischief" by observing that the "evident intent of Section 251
is to assure, in the public interest, the integrity and fairness
of decisions by Electricity Boards to dispose of land and to
enter into other contracts of the classes specified." Finally
it should be noted that the learned trial Judge also specifically
adverted to the fact that the agreement for sale was made with
someone who was not a registered tenderer; it appears to me that
he would have found non-compliance with para, (e) on that point
alone .
Critical questions for determination on this appeal are
whether or not the learned trial Judge was correct in construing
para, (e) and in applying it to the facts. It is true that there
is no proper basis for implying words such as "some or all of"
before the words "registered tenderers" in para, (e); but for the
same reasons there is no warrant for implying the word "all"
there. If tenders must be invited from all those who registered
pursuant to the advertisement then that must be the consequence
of the words actually used in the context in which they are
found. Absent other considerations, a reference to "registered
tenderers" would normally mean all of those who were so
-- 20 of 39 --
16
registered. But the context here is important and must be
analysed more closely .
If the procedure in para, (e) of sub-s. (10) is adopted then
the procedure referred to in sub-s. (9) may be dispensed with.
The procedure laid down in sub-s. (9) is as follows:
(i) tenders are invited (called) by the Board causing
advertisements to be made in such manner and to such
extent as would ensure that notification of intention
to enter into a contract is likely to be seen by as
many people as possible who are likely to tender;
(ii) tenders are lodged in response to that advertising
based on information generally available to all who
are interested;
( iii ) tenders are accepted or rejected by the Board in
accordance with sub-s. (13).
In other words the procedure provided for in sub-s. (9) is
designed to obtain directly actual tenders for the Board's
consideration from as many people as possible who are minded to
submit a tender.
If para, (e) of sub-s. (10) is construed in the way accepted
by the learned trial Judge then the procedure would be as
follows :
(i) an advertisement would call for persons interested in
being invited to tender for a particular project to
register their interest with the Board;
(ii) the Board would then invite all of the persons who so
registered to submit a tender based on information
made available by the Board to them;
-- 21 of 39 --
17
(iii) the Board could then accept or reject such tenders as
were in fact received in accordance with sub-s. (13).
If that is so, then one may well ask what is the significance or
relevance of the preliminary step of registration; the same
practical result is achieved by following the simpler procedure
provided for by sub-s. (9). Looked at in that light it seems
rather nonsensical to provide that by taking the purposeless
additional step of registering interested persons the simpler
procedure referred to in sub-s. (9) is dispensed with.
But there is a significance given to para. (e) of
sub-s. (10) if that paragraph is read as providing for the
following procedure :
(i) an advertisement would call for persons interested in
being invited to tender for a particular project to
register their interest with the Board;
(ii) the Board would then investigate the registrants and
determine which of them, if any, had the capacity to
perform the work in question and was otherwise a
suitable tenderer;
(iii) the Board would then invite a number from the
registrants who satisfied those criteria (the selected
group) to submit tenders based on information made
available by the Board to them;
(iv) the Board could then accept or reject a tender
received in accordance with sub-s. (13).
That could well be described as a selective tender procedure.
The reasons for adopting such a procedure in certain cases are
obvious. Ordinarily an unsuccessful tenderer must bear the cost
-- 22 of 39 --
18
of tendering; in many large projects, particularly where the
tenderer is to some extent responsible for design, such costs
could be considerable. It could well be that the cost of
preparing a tender would deter some potentially suitable and
otherwise interested tenderers from making a submission. To
overcome those factors the proprietor will sometimes offer to
recompense unsuccessful tenderers thus ensuring tenders are
received from the best possible sources. In order to limit the
extent of its exposure to unsuccessful tenderers, the owner in
that situation generally adopts a selective tender procedure.
The alternative construction of para, (e) would permit that to
be done; here the respondent was minded to pay unsuccessful
tenderers a not insignificant amount ($8,000.00) to help defray
the expenses involved in submitting a tender.
Such a selective tender procedure is recognised in the area
of construction law. In Brooking "Building Contract" (First
edition) the topic is referred to in para. 2.1. The learned
author there says that "tenders may be sought either from
contractors generally or from selected contractors"; he goes on:
"If the contract is put out to public ('open') tender,
any interested contractor may bid. The system of
inviting tenders on the open market has been much
criticised by builders, who contend that it leads to
unreasonable price cutting and to the acceptance of
unrealistic bids from builders who are unlikely to
complete the work in a satisfactory way. In addition,
it has been said that the open tender system is
wasteful, in that the cost of preparing large numbers
of unsuccessful tenders must be reflected in the
general cost of building. The alternative to putting
a contract out to public tender is the calling of
tenders from selected contractors only. Where tenders
are to be called from selected builders only, the
selection may be made in various ways. The architect
may put forward half a dozen names to the proprietor
who will often wish to add to the list of contractors
known to him. A public invitation may be made to
-- 23 of 39 --
19
builders who desire to be invited to tender to
register with the architect and tenders are then
obtained from a number of those contractors who have
registered."
A statement to similar effect is found in Bailey "Construction
Law in Australia" at 22. It is true that in neither instance was
the author addressing public works contracts. There is also some
recognition of that practice in para. 798 of Vol. 3 of Halsbury
(Third edition). In the Fourth edition of Halsbury (Vol. 4
paras. 1149-50) there is a discussion of public works contracts
in the light of the directives issued by the Council of Ministers
of the European Community dealing with the awarding of such
contracts. Those directives provide for an "open procedure" by
which any interested contractor may tender and a "restrictive
procedure" by which contractors may tender only if invited to do
so by the authority awarding the contract. In the latter
situation the authority is to select those invited to tender on
the basis of information given at the time of registering the
request to participate.
Observations such as those are not determinative of the
proper construction of para. (e). But it is significant, in my
view, that apart from s. 251 there is a recognition in
construction law of a difference between an open tender procedure
and a restricted or selective tender procedure. Further, there
appear to be well recognised circumstances in which it is
considered preferable to adopt a selective tender procedure as
opposed to an open tender procedure. Given that background one
can consider whether or not the intention of the legislature was
to provide for an open tender procedure in s. 251(9) and for a
selective tender procedure in s. 251(10) (e).
-- 24 of 39 --
20
Ultimately, in my view, it is important to recognise that,
if all who register pursuant to an advertisement made pursuant
to para, (e) must be invited to formally tender, there is no
effective difference between sub-s. (9) and sub-s. (10) (e); all
the latter would do in those circumstances is add an additional,
but pointless, step into the procedure. If sub-s. (10)(e) is
construed as providing a selective tender procedure then it is
meaningful in the context, and there is a readily recognisable
reason for providing that if it is adopted there should be a
dispensation from complying with the procedure laid down in
sub-s. (9).
The real question becomes whether or not the paragraph can
reasonably bear the construction favouring a selective tender
procedure. As I have stated previously the paragraph must be
read in the context in which it is found in s. 251. Doing that
I prefer the construction which would give full effect to the
paragraph as an alternative procedure to that laid down in
sub-s. (9). Given the context I have come to the conclusion that
such a construction is reasonably open.
The learned trial Judge correctly, in my view, identified
the "mischief", to which the sub-sections are directed - the
importance of, in the public interest, assuring the integrity and
fairness of contractual decisions made by Electricity Boards.
But, in my view, those considerations may be satisfied if a
selective tender procedure is adopted. Any interested party may
register an interest. The terms of the advertisement (including
general information on the project made readily available by the
Board) must ensure that the specific procedure to be followed is
-- 25 of 39 --
21
known to all. Here it was made known that a short list of five
organisations would be prepared from those who registered an
interest. There is no question here but that tenders submitted
were received from those five organisations on a fully
competitive basis. In those circumstances I am of the view that
the "mischief" may be overcome by the implementation of a proper
selective tendering system.
It follows that I am of the view that the learned trial
Judge misconstrued para, (e) . The procedure adopted by the
respondent in my view complied with the requirements thereof,
notwithstanding that not all "registered tenderers" were invited
to submit a tender.
When one looks at the material in the record relating to the
"design brief" with respect to which tenders were invited, there
is no doubt that the tenders were "for a particular project".
It does not matter that a number of alternative proposals were
put forward by the respondent. In the context the expression
"particular project" is used to exclude from the operation of the
selective tender procedure, contracts, for example, for the
general supply of an undisclosed quantity of material over a
lengthy period of time.
If the contract for construction and the contract for sale
of land in this case were made by the respondent with the
registered tenderer whose tender was accepted there would be no
doubt but that the requirements of s. 251 (10) (e) had been
satisfied. In that event the respondent was not obliged to
comply with the requirements of sub-s. (9). But in fact the
registered tenderer was Project Builders, the entity with whom
-- 26 of 39 --
22
the respondent contracted for the construction of the building.
The appellant was not a tenderer . Does that mean that there has
not been compliance with para, (e) because the contract for the
sale of land was with the appellant. There is a certain
unreality, at least in a commercial sense, in saying that
"Project Builders" was entitled to the benefits (profits) from
its contract with the respondent, but its associated company, the
appellant, could take the point that it was entitled to avoid its
obligations under the interdependent contract to purchase land.
In a real sense the appellant was the nominee of Project Builders
to enter into a contract which was collateral to or
interdependent with the principal construction contract the
subject of the selective tender procedure employed by the
respondent. In those circumstances non-compliance with para, (e)
on the ground of identity of the contracting parties is not
established.
I would therefore conclude, contrary to the views of the
learned trial Judge, that there was compliance in all respects
with s. 251(10) (e). In consequence no ground is established for
concluding that entering into the contract of sale of the land
was beyond the power of the respondent, or that the contract was
invalid by operation of s. 251.
If, however, I am wrong in the construction I prefer with
respect to s. 251(10) (e) I would conclude that the contract was
specifically enforceable for the reasons given by the learned
trial Judge and by my brother de Jersey in this Court. I have
had the advantage of reading what de Jersey J. has written on the
question whether or not non-compliance with s. 251 made the
-- 27 of 39 --
contract unenforceable. I agree with all that he has said on
that point. I also agree with what he has said specifically with
respect to the arguments of the appellant based on cl. 22 of the
contract.
I agree that the appeal should be dismissed with costs.
23
-- 28 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 85 of 1990
Before the Full Court
Mr. Justice Shepherdson
Mr. Justice Williams
Mr. Justice de Jersey
BETWEEN :
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
AND :
JOHN M. KELLY (BUILDERS) PTY. LTD.
(Defendant) Appellant
JUDGMENT - de JERSEY J .
Delivered the 18th day of July, 1991
CATCHWORDS :
Counsel: Mr. Gotterson Q.C. for the Defendant Appellant
V. Copley Q.C. with A.S. Mellier for the
Plaintiff Respondent
Solicitors: Cooper Grace & Ward for the Defendant Appellant
Connolly Schirmer & Batts for the Plaintiff
Respondent
Hearing date: 15th, 16th May, 1991
-- 29 of 39 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 85 of 1990
BETWEEN :
THE CAPRICORNIA ELECTRICITY BOARD
(Plaintiff) Respondent
AND :
JOHN M. KELLY (BUILDERS) PTY . LTD.
( De fendant ) Appellant
JUDGMENT - de JERSEY J.
Delivered the 18th day of July, 1991
The learned trial Judge decreed the specific performance
of a contract dated 28th October, 1987, by which the
respondent agreed to sell its land at Bolsover Street,
Rockhampton to the appellant for $1.75 million. The contract
was due for completion by 6th February, 1989 (an extension to
that date having been agreed upon), but the appellant declined
to complete.
The learned Judge rejected the two defences upon which
the appellant relied in resisting specific performance. They
were, first, that because the contract was not made in
compliance with s. 251(9) or (10) of the Electricity Act, it
was unenforceable; and secondly, that the appellant was not
obliged to complete the contract because of the respondent's
breach of cl. 22, which was an essential term. In this Court,
the appellant challenged his Honour's rejection of both those
defences .
As to the first matter, the respondent is an Electricity
-- 30 of 39 --
2
Board constituted pursuant to the Electricity Act, and s. 251
of that Act regulates the manner in which it may enter into
contracts for the sale of land such as this. Sub-sections 9
to 11 are particularly relevant, and I will set them out.
"(9) Before any contract -
(c) for the sale of land
is entered into by an Electricity Board it
shall, three weeks at least before entering
into the contract, notify its intention to make
and invite tenders for the contract by public
notice published in such newspaper or
newspapers and in such manner and to such
extent as in the opinion of the Electricity
Board will ensure that the notification of
intention to enter into a contract is likely to
be seen by as many people as possible who are
likely to tender.
(10) The procedure referred to in subsection (9) may
be dispensed with -
(a) where the Commission certifies that an
emergency exists or special circumstances
exist;
(e) where tenders for a particular project are
being invited by the Electricity Board from
registered tenderers who were so registered by
the Electricity Board pursuant to an
advertisement inviting such registration;
(11) (a) In respect of a sale of land ... an
Electricity Board may, in lieu of complying
with the subsection (9), comply with this
subsection.
(b) An Electricity Board may sell any land ...
by public auction or private contract, but no
such sale shall be made by private contract
unless and until the land ... (has) been
offered for sale by public auction and not
sold. "
The respondent did not comply with sub-s. 9 or sub-s. 11.
-- 31 of 39 --
3
At the trial, it sought unsuccessfully to rely on sub-s. 10.
The learned Judge held that sub-s. 10(e) was not satisfied
because the respondent did not invite tenders from all
tenderers who had responded to an advertisement for
expressions of interest; and he held that the Commission's
written certification as to the existence of "special
circumstances" was insufficient for the purposes of
sub-s. 10(a) because it did not precede the contract.
This is a convenient point at which to recite briefly the
facts relating to those matters.
The respondent wanted to build additional office
accommodation in Rockhampton. Because much of the initiative
in working out suitable proposals was to be left to the
tenderers, the respondent took the view that the usual
tendering process under the Act would be too rigid. It
therefore decided not to call for tenders in the usual way,
but to invite "expressions of interest". The respondent would
then ask those who had submitted the most attractive proposals
to put in tenders. The respondent called for interested
persons to register their interest, by three separate
advertisements in July, 1986, and there were 41 responses.
Five of those who responded were invited to tender. (Persons
registering their interest were able to obtain a document
headed (ex. 16) headed "General Information on the Board's
Intentions", and in that document the respondent had made it
clear that it would seek tenders from only five of those who
responded .)
Concerned that it might not be complying with s. 251, the
-- 32 of 39 --
4
respondent took up that matter with the Queensland Electricity
Commission. Acting in good faith, the respondent fully
disclosed its intentions to the Commission. By letter of
22nd September, 1986 the Commission endorsed the respondent's
proposed procedure, expressing the view that it did comply
with s. 251(1)(e) .
The respondent ultimately accepted a tender by J.M. Kelly
(Project Builders) Pty. Ltd. (one of the five chosen
companies) to construct the building for $7 million. Part of
that tenderer' s proposal was the appellant' s purchase of the
land which is the subject of this contract. (The possibility
of such a purchase had been mentioned in the call for
registration of interests.) On 1st September, 1987, the
Commission approved the respondent's entry into contracts with
the appellant. The subject contract with the appellant is
dated 28th October, 1987.
On 8 th February, 1989 the Commission wrote to the
respondent saying that that approval bad been granted on the
understanding that special circumstances existed, so that
sub-s. 10(a) applied, with no need for compliance with
sub-s. 9. That is the certification which the learned Judge
held insufficient because it was made subseguently to the
respondent's' entering into the contract, and I agree with that
conclusion.
I revert to the question of the proper construction of
subs. 10(e). I agree with the learned Judge's conclusion that
to satisfy that paragraph, the Board had to invite tenders
from all registered tenderers, registered that is by the Board
-- 33 of 39 --
5
on the basis of the response to the call for registration of
interest. The words "some or all of the" do not precede the
reference to "registered tenderers" in para. (e). I do not
think that the paragraph sanctions the Board's selecting from
those who have registered an interest, some only to be the
persons to be invited to tender. The natural meaning of the
paragraph is made clear if one reads in the words "all of the"
before "registered tenderers". But I emphasise that I
consider that that is the natural meaning without one's having
to read in those words. The learned Judge said that such an
interpretation properly took account of the "mischief" to
which the sub-sections are directed, presumably the
achievement of impartial treatment for all persons who may be
interested in tendering, and the avoiding of a preliminary
selection (pre-tender) from interested parties perhaps on the
basis of insufficient information. Accepting for the sake of
argument that that was the mischief to be avoided, then those
problems would be avoided on this construction of the
paragraph. I appreciate that in calling for expressions of
interest, the Board made it clear that it may invite tenders
only from some of those who responded. But the question
remains whether it was entitled to do that, in conformity with
sub-section 10(e), and I have reached the conclusion that it
was not .
Having held that the respondent failed to comply with
s. 251(9) and (11), and that sub-s. (10) was not satisfied,
the learned Judge went on to hold that that non-compliance did
not make the contract unenforceable. He said, first, that
-- 34 of 39 --
6
there was no reason to doubt the respondent ' s power to enter
into the contract, that being accorded by s. 102(1 )(b). The
defect was confined to the manner in which it did so. As to
the significance of that deficiency, he pointed to the absence
from the Act of any prescription of the consequences of a
failure to comply with such requirements, save the general
criminal sanction (s. 419) (as to which see Doug Rea
Enterprises Ptv. Ltd, v. Hvmix Australia Ptv. Ltd. (1987) 2
Qd.R. 495, 506). By contrast, the Act does specify that
non-compliance with other requirements avoids consequent
agreements: s. 172(2) and (3). The draftsman could easily
have made similar provision as to invalidity for
non-compliance with s. 251, but has not done so, and I should
say that I regard this as of great significance. The Judge
then referred to a number of practical matters tending to
support the view that a contract should not be considered
unenforceable in the event of non-compliance with s. 251: the
absurdity of such a result were the non-compliance to arise,
say, from seeking tenders from 40 but not 41 of the
registrants, or if the Commission - prior to contract - formed
the view that the "special circumstances" referred to in
sub-s. 10(a) existed, but inadvertently failed to certify in
writing to that effect. He concluded that one could not
discern, "from the language of the Act or a consideration of
its objects", a prohibition on the subject contract.
Mr. Gotterson Q.C., who appeared for the appellant,
submitted that the learned Judge did not properly apply A.B.C.
v . Redmore Ptv . Ltd . (1989) 166 C.L.R. 454. His Honour
-- 35 of 39 --
7
referred to that decision merely as authority for the
proposition that in determining the consequence of
non-compliance with statutory requirements, one should look to
the legislative intent discernible from the language of the
immediately relevant provisions in the context of the whole
Act. There was nothing objectionable about that.
Mr. Gotterson's submissions focused on the words of
s. 251(9), "Before any contract ... is entered into". Those
words, in setting a temporal sequence, are not in my view
determinative of the result of a failure to comply with the
specified procedure. He also submitted that compliance with
the prescribed steps was essential to the existence of the
power to contract . One notes however that the power to
dispose of land emerges from s. 102 (1 ) (b) ( iii). See also
s. 129(u). Section 251 merely regulates the exercise of that
power. He then referred to the location of s. 251(9) within
the Act. It occurs amongst other provisions regulating the
manner of contracting. The power to dispose of land is, as I
have said, in another part of the Act, and it is not correct
to say, as was submitted, that Part VII - where s. 251 is
located - includes the sections conferring the relevant power .
Mr. Gotterson also submitted that sub-ss. 10 and 11 would
be unnecessary were non-observance of sub.s. 9 not to vitiate
the contract. Providing alternative procedures to meet the
same object may perhaps be seen as emphasising the importance
of achieving that object. On the other hand, providing
alternatives may itself be an indication that no particular
method is critical. Those matters aside, however, this
-- 36 of 39 --
8
feature alone does not mean that non-observance of the
mechanism invalidates the contract.
Mr. Gotterson relied on Hunter Bros, v. Brisbane City
Council (1984) 1 Qd.R. 328, where non-compliance with the
Council' s tendering procedure resulted in the invalidity of
the resultant contract. Notwithstanding the prohibition in
the statute or by-law, the question of the validity of the
contract entered into contrary to such a prohibition falls to
be determined by reference to legislative intent, expressly
declared or implicit. In that case, Connolly J. concluded
that compliance with the precise procedure was mandatory.
Here, for reasons I think compelling, His Honour took a
different view.
I respectfully adopt the learned Judge's reasoning in
relation to-the first defence.
The second defence relied on by the appellant in
resisting specific performance is based on cl. 22 of the
contract, which is in these terms:
"The vendor warrants that all provisions of 'The
Electricity Act 1976-1980' which affect this sale
and purchase (and in particular the provisions of
s. 251 of such Act) have been complied with and that
all necessary approvals required to be obtained by
the vendor pursuant to the said Act have been
obtained."
Having concluded that the respondent did not comply with
s. 251 of the Act, the learned Judge had to determine whether
cl. 22 was art essential term, such that the appellant could
rely on the breach for a determination of the contract.
The question he asked (while mentioning D.T.R. Nominees
Ptv. Ltd, v. Mona Homes Ptv. Ltd. (1978) 138 C.L.R. 423) was
-- 37 of 39 --
9
whether the appellant would have entered into the contract if
not assured of performance of the respondent's promise that s.
251 had been satisfied. He acknowledged the importance of
that promise in minimising the risk of challenge to the
contract prior to the appellant's obtaining an indefeasible
title on registration following settlement. Supporting a view
that cl. 22 is a condition, is the circumstance that a breach
would ordinarily sound only in nominal damages. But His
Honour identified three "countervailing factors": that the
language of the clause is "the language of warranty"; that by
contrast, another provision of the contract makes it "subject
to and conditional upon" certain matters (cl. 1B), and yet
another gives an express right of termination in certain
circumstances (cl. 12); and that the protection given by cl.
22 had no apparent relevance after the registration of a
transfer.
As to the first matter, Mr. Gotterson referred to Oscar
Chess Ltd. v. Williams (1957) 1 W.L.R. 370, 374 where
Denning L.J. distinguished between the ordinary and technical
meanings of "warranty". His Honour's point was nevertheless
of some . relevance. He has not given it decisive
significance - neither would I.
The learned Judge also referred to the statement in Ankar
Ptv. Ltd, v. National Westminster Finance (Australia) Ltd.
(1987) 162 C.L.R. 549, 556 to the effect that where "other
considerations are finely balanced", one should not be "too
ready" to construe a term as a condition, because there is a
"preference for a construction that will encourage performance
-- 38 of 39 --
10
rather than avoidance of contractual obligations".
Mr. Gotterson submitted that his Honour did not properly
apply the principle referred to in Ankar. The contention was
that the "preference for a construction that will encourage
performance rather than avoidance of contractual obligations"
requires the performance by the plaintiff of its obligations,
including the obligation in cl. 22, and precludes the
avoidance by the plaintiff of its contractual obligations.
Taken to that point, the contention rather begs the question.
The important qualification expressed in Ankar in that "other
considerations be finely balanced". Mr. Gotterson's
contention was founded on the feature that damages for breach
of the obligation under cl. 22 could never be an adequate
sanction. I do not consider the circumstance that breach
could attract only nominal damages means that the relevant
considerations are not "finely balanced". There are other
relevant considerations, as referred to in His Honour's
analysis. I regard the second of His Honour's "countervailing
factors" - that the contract accords an express right of
termination in one case (cl. 12) and in terms makes it
"subject to and conditional upon" certain matters in another
(cl. 1B) - as of great significance. In the end there is, for
the reasons given by the learned Judge, the "fine balance"
which gave operation to the approach suggested by Ankar.
I adopt the learned Judge's reasoning with respect to the
second defence.
I would therefore refuse the appeal with costs to be
taxed .
-- 39 of 39 --
Official source: https://www.sclqld.org.au/caselaw/QSCFC/1991/075