Beard v Wratislaw [1991] QSCFC 23 [1993] 2 Qd R 494
I
IN THE SUPREME COURT OF QUEENSLAND
fc
I Rsvised copies -ISSUED l
f Cour{ Reportin3 Bureau J
I Dat9: Z /</
FULL COURT
Mr. Justice McPherson SPJv/
Mr. Justice Derrington
Mr. Justice Moynihan
Appeal No. Ill of 1990
10 BRISBANE, 21 MARCH 1991
(Copyright in this transcript is vested in
the Crown. Copies thereof must not be made
or sold without the written authority of the
Chief Court Reporter, Court Reporting Bureau.)
10
^ •
BETWEEN :
JOHN DAVID BEARD, KENNETH JAMES EUSTACE,
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs) Appellants
- and -
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
20
30
JUDGMENT
MR. JUSTICE MCPHERSON: The Court in this and the
succeeding appeals this morning consisted of Mr. Justice
Derrington, Mr. Justice Moynihan and me. I would allow this
appeal with costs, set aside the judgment in the court below,
and instead give judgment for the plaintiffs for specific
performance of the contract referred to in the writ of
summons. I would also give judgment dismissing the
counterclaim with costs. I would order the defendant to pay
the plaintiff's costs, including reserved costs if any, of
the action. There should be liberty to the parties to apply.
I publish my reasons.
Mr. Justice Moynihan agrees with the orders I have
proposed. I publish his reasons.
MR. JUSTICE DERRINGTON: I would dismiss the appeal.
— Govt. Printer, Qld.
30
40
50
1
[1991] QSCFC 23
-- 1 of 51 --
I publish my reasons.
MR. JUSTICE MCPHERSON: . There will be orders in the
form that I have proposed.
10 10
20
30
40
50
30
40
(
50
60
— Govt. Printer, Qld.
60
2
-- 2 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT Appeal No. 111 of 1990
BETWEEN
JOHN DAVID BEARD. KENNETH JAMES EUSTACE
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs) Appellants
AND
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
MCPHERSON SPJ
DERRINGTON J
MOYNIHAN J
Reasons for judgment delivered by
McPherson SPJ, Derrington and Moynihan JJ
on 21 March 1991. Moynihan J agreeing
with the order proposed by McPherson SPJ
Derrington J dissenting.
"APPEAL ALLOWED WITH COSTS. JUDGMENT BELOW
SET ASIDE AND IN LIEU THEREOF ENTER JUDGMENT
FOR THE PLAINTIFFS IN THE ACTION FOR
SPECIFIC PERFORMANCE OF THE CONTRACT AND
ENTER JUDGMENT DISMISSING THE DEFENDANTS
COUNTERCLAIM WITH COSTS. ORDER THAT THE
DEFENDANT PAY THE PLAINTIFF'S COSTS OF THE
ACTION INCLUDING RESERVED COSTS IF ANY.
THE PARTIES TO HAVE LIBERTY TO APPLY"
-- 3 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 111 of 1990
Before the Full Court
Mr. Justice McPherson S.P.J.
Mr. Justice Derrington
Mr. Justice Moynihan
BETWEEN:
AND:
JOHN DAVID BEARD. KENNETH JAMES EUSTACE
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs)
BARBARA JOYCE WRATISLAW
(Defendant)
Appellants
Respondent
JUDGMENT - MCPHERSON S.P.J.
Delivered the Twenty-First day of March 1991
CATCHWORDS
Vendor and purchaser - Contract for sale of pastoral lease under
Land Act - At contract date lease under conversion to grazing
homestead perpetual lease - Parties aware - Subject matter of
sale - Duty to deliver transfer with "instrument of title" -
Meaning - Vendor's failure to provide instrument of title -
Whether default by purchasers in failing to tender Land Act
1962-1988, s.160; R.E.I.Q. contract (1982 ed.), cl. 2.
Counsel: J. Greenwood Q.C. with C. Carrigan for the Appellant
P. Keane Q.C. with B. Clarke for Respondent
Solicitors: Phillips & Lowes for Appellants
McCullough Robertson T/A for Morrow & Co. for
Respondent
Hearing dates: 11 and 12 February 1991.
-- 4 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 111 of 1990
BETWEEN :
JOHN DAVID BEARD. KENNETH JAMES EUSTACE
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs) Appellants
AND :
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
JUDGMENT - MCPHERSON S.P.J.
Delivered the Twenty-First day of March 1991
In 1988 the defendant (respondent to the appeal) was
possessed of the cattle property "Alkoomie", some 72 sq. miles
in area, located south-west of Cooktown. She held the property
as lessee from the Crown under the Land Act 1962-1988 having
acquired it in 1975 with her late husband as joint tenant from
persons who were assignees from one or more of the original
lessees from the Crown. The lease was a "pastoral lease", as
defined in the Act, for a term of 30 years commencing from
1 April, 1964 at a specified annual rental, so that at the time
with which these events were concerned the lease had a period of
only some six years or less to run. Its description or number
is PL 14-4623.,
Division I of Part VI of the Act authorises the Minister on
application by a lessee to grant a new lease of the whole or part
of a holding represented by a pastoral lease in substitution for
a subsisting lease that has not more than 10 years to run:
s.155(1). If the Minister approves the application, he is to
-- 5 of 51 --
2
determine the area of land in respect of which the new lease is
to be offered, as well as the tenure, term, and rental thereof:
s. 157(2). The Minister may include in the area offered any Crown
land in addition to the whole or part of the land contained in
the subsisting lease: s'. 157(3). A lessee electing to take
advantage of a decision of the Minister approving an application
for a new lease in substitution for the subsisting lease is
required to surrender the subsisting lease "and thereupon the
Governor in Council shall issue a new lease to him in accordance
with the decision of the Minister": see s.160(1). The new lease
is to commence on the quarter day next following surrender of the
former subsisting lease : s .160(2).
The defendant's lease satisfied the description in s. 155(1)
of the Act. In about March 1988 she applied for a new lease of
Alkoomie. By letter dated 7 April 1988 the Land Administration
Commission (LAC) Department, acting on behalf of the Minister,
offered a new lease of part of the Alkoomie holding as shown on
an attached plan, exclusive of a defined area of 760 ha. to be
included in Caloola, but inclusive of a defined area of 760 ha.
to be surrendered from Caloola. Caloola is the adjoining
property also leased from the Crown, and so was Crown land within
s.157(3). The underlying purpose of the contemplated exchange
of 760 ha. was to reduce problems arising from the shapes of the
two properties. To this end the letter of 7 April 1988 required
from the defendant an executed surrender document, together with
the instrument of lease in respect of Alkoomie, to be returned
to the LAC by 30 June 1988 so as to enable the new lease to
O
o
o
o
-- 6 of 51 --
3
commence from 1 July 1988. The tenure of the new lease was to
be grazing perpetual homestead lease.
The instrument of surrender dated 10 May 1988 was executed
by the defendant and received by the LAC on 23 May 1988. In due
course the instrument of lease, being the subsisting pastoral
lease no. 14-4623 commencing from 1 April 1964, was also received
there. There were some delays in preparing survey plans for
giving effect to the exchange of lands between Alkoomie and
Caloola; but in the end the plans were received on 24 February
1989. The new grazing homestead perpetual lease was executed on
30 March 1989. It is identified or numbered GHPL 14/231. In
accordance with s. 160(2) of the Act it is expressed to commence
from 1 July 1988.
In the meantime the defendant had agreed to sell the
Alkoomie property to the four plaintiffs, who are the appellants
before us. The contract (ex. 12) dated 15 August 1988 is in the
standard printed REIQ form (1982 ed.). It names the four
plaintiffs as purchasers but is in fact signed by only two of
them. This formed a ground of defence at the trial of the action
for specific performance in the District Court at Ca?rns. It was
disposed of by his Honour's conclusion that the two purchasers
who signed did so for themselves as principals and also as agents
for the other two: Basma v . Weekes [1950] A.C. 441. No
challenge to this part of the decision has been made on appeal.
Before us the principal question in dispute revolved around
the precise identity of the subject matter and the defendant
purchaser's obligations in relation to it. The contract ex. 12
gives the particulars of land sold as "vacant"; and the
-- 7 of 51 --
4
description as "P.H. 278", which is the number of the plan of the
area of the pastoral holding that is attached for the instrument
of lease. The county, parish and town are given, together with
the area of 72 sq. miles; the type of holding is "pastoral lease"
and the lease number 14/4623 appears next to it. The instrument
of title is said to be located at ANZ Bank, Mareeba.
On the face of the contract, what the parties agreed to buy
and sell was the pastoral lease commencing in 1964 from the Crown
in respect of the property known as "Alkoomie". By the time the
contract was executed, however, all parties were aware of the
steps being taken by the defendant toward renewal of the lease,
and its proposed conversion to grazing perpetual homestead lease.
The plaintiffs learned of the "adjustment" involved in the
exchange of land with Caloola only later, but it does not affect
their attitude. The contract is dated 15 August 1988. By that
time the pastoral lease had, as appears from an endorsement dated
30.6.1988 on the instrument itself, been surrendered. The
endorsement proceeds: "Now being GHPL 14/231 Cooktown". The
grazing homestead perpetual lease was, as I have said, not
executed until 30 March 1989; but, in accordance with s.160(2),
the new lease was required to commence on the quarter day next
following surrender of the former pastoral lease. That surrender
was, in turn, required by s. 160(1) to follow the lessee's
election to take advantage of the Minister's offer of a new lease
in substitution for the subsisting lease. As I have said, the
lessee's election reached the LAC not later than 23 May 1988.
The surrender took effect on 30 June 1988, and the term of the
new lease (the GHPL) commenced from 1 July 1988.
O
o
o
-- 8 of 51 --
5
Hence, at the date of the contract the leasehold interest
(pastoral lease no. 14/4623) agreed to be bought and sold had in
law ceased to exist. No one now suggests that this means that
the contract was invalid. Both sides of the transaction at all
times knew that the "conversion" to grazing homestead perpetual
lease was under way as part of a process of granting a new lease.
Mr M.J. Mead, who is one of the plaintiffs and their solicitor,
regarded them as buying a pastoral lease which was being
converted to a grazing homestead perpetual lease. On appeal
Mr Keane Q.C. was accepted that what the parties were buying and
selling was "a lease in the process of conversion". The reality
no doubt is that the parties thought of themselves as buying and
selling the Alkoomie cattle property whatever the title under
which it might be held. There was no dispute on appeal that
evidence was admissible of the state of knowledge of the parties
in order to identify that contractual subject matter: cf. Akot
Ptv. Ltd, v. Rathmines Investments Ptv. Ltd. [1984] 1 Qd.R. 302;
Dainfords Ltd, v. Tari Nominees Ptv. Ltd. (1984) Building Units
and Group Titles Cases 30-073.
Difficulties nevertheless emerge in applying the provisions
of the standard form printed contract to the state of affairs
resulting from conversion of the title. The date for completion
specified in Item Q of the contract was 15 February 1989. By
cl. 23 of the contract time was in all cases and in every respect
to be of the essence of the contract. By cl. 2, entitled
"Completion and Possession" -
"The balance of the purchase price shall be paid on
the date for completion stated in Item Q in exchange
for possession . . . together with a duly executed
transfer in favour of the purchaser capable of
-- 9 of 51 --
immediate registration (after stamping) in the
appropriate office free from encumbrances ... and
accompanied by the instrument of title except as
provided in clause 8 ..."
It is common ground that this date was by agreement extended to
1 March 1989 with time remaining of the essence. Clause 8 is
concerned, among other matters, with the case in which the
instrument of title to the land sold relates also to other land.
Because of the proposed "adjustment" with Caloola, this
presumably was (at least as regards pastoral lease no. 14/4623)
the case here. But no reliance was placed on cl. 8 either at the
trial or on appeal and it may therefore be disregarded.
As the original date for settlement (15 February 1989)
approached it became evident that the instrument of lease for the
new grazing perpetual homestead lease would not be available in
time for completion of the contract at that date. Correspondence
passed between the solicitors for the parties. In the course of
it or of accompanying telephone conversations the date for
completion was extended first to 22 February and ultimately to
1 March 1989, time remaining of the essence. A letter dated
22 February 1989 from defendant's solicitor advised that "the
replacement GHPL" was, according to the Department, expected to
issue "within the next few days". A proposal by solicitors for
the plaintiffs for an extension to 6 March 1989 met with a
rebuff, so that in the end completion remained fixed for the
agreed extended date of 1 March 1989.
By faxed letter of that date defendant's solicitor advised
that "GHPL 231 replacing P.H. 14/4623 in respect of Alkoomie
Station" had now been recorded in the register at the LAC, and
that the defendant's executed transfer would be accepted there
-- 10 of 51 --
7
for registration. Confirmation was given that the ANZ Bank
mortgage and the related release of mortgage were also held by
the Commission together with "the Lease P.H. 14/4623
(surrendered)". All of them were said to have been lodged for
registration "but would be available for inspection should you
require a search" . The letter proposed settlement at the LAC
registry at Brisbane at 2.30 p.m. that day, 1 March 1989.
Settlement and completion did not take place on that day.
Essentially this was because, as was explained in the letter
dated 1 March 1989 from plaintiffs' solicitor, the new instrument
of lease (GHPL 231) had not issued, "and [it] might take up to
12 weeks for such lease to issue". In fact, as I have more than
once said, it was executed on 30 March 1989. However that may
be, it was neither executed nor available for a settlement that
was fixed for 1 March 1989. In his letter the plaintiffs'
solicitor claimed that in consequence the defendant was not in
a position to settle in accordance with the terms of the contract
of sale. He went on to say that the plaintiffs as purchasers
nevertheless wished to finalise the contract and were prepared
to settle as soon as the defendant as vendor was in a position
to comply with those terms. A letter dated 2 March 1989 from
that solicitor confirmed that this was the attitude of the
plaintiffs. .Despite this, the defendant by a formal notice
(ex. 34) dated 2 March 1989 elected: (1) to terminate the
contract on the ground of the plaintiffs' failure to attend at
settlement and otherwise to complete the contract; and (2) to
declare the deposit of $16,200 to have been forfeited. The
plaintiffs did not accept this notice of termination but instead
-- 11 of 51 --
8
gave a counter-notice to the defendant insisting on performance
of the contract.
The principal question to be determined on this appeal is
whether the defendant was justified in terminating the contract
by reason of the plaintiffs' failure to settle on 1 March 1989.
This in my view depends entirely on whether under cl. 2 the
plaintiffs were bound to pay the balance of purchase price on
that day in exchange for the documents that the defendant was in
a position to offer. Those documents did not include any
"instrument of title" within the meaning of cl .2. The
surrendered lease P.H. 14/4623 was available for inspection at
the LAC registry; but it is not suggested that the defendant
either could have or would have delivered it to the plaintiffs
on settlement in return for the balance purchase price.
In the court below the learned trial judge recorded his
conclusion that under the contract what the plaintiffs were
purchasing was "the rights or expectations of rights which the
defendant would have to the land formerly incorporated in
P.H. 278 or P.L. 14/4623 at 1st March .1989". His Honour went on
to say that at that date they had an expectation that any dealing
with the land would be recorded on the historical register sheet
at the LAC "and thereafter recognised by the Department as a
dealing which would become effective after issuance of the
lease". His Honour concluded that the defendant was on
completion date doing all that was required of her by providing
access to such documents of title, consisting of the historical
register sheet and the surrendered lease, as at that date were
available to her. He considered that the plaintiffs were at the
O
()
o
-- 12 of 51 --
9
time of contract not concerned whether on completion "they got
a Pastoral Lease; a Grazing Homestead Lease, or something in
between. In fact on completion they were to receive something
in between but something which. . .would have resulted in the
plaintiffs receiving the transfer of the GHPL subsequently issued
to the defendant". In declining what was offered by the
defendant on 1 March 1989 the plaintiffs, as his Honour held,
declined to accept a performance for which they had contracted,
and the defendant was therefore entitled as she did to terminate
the contract.
In my respectful view his Honour's conclusion cannot be
sustained. Even accepting that what was being bought and sold
was "a lease in the process of conversion", the plaintiffs did
not agree to accept on completion date a "dealing" that would be
recorded on the historical register sheet at the LAC and
"thereafter recognised.. .as a dealing which would become
effective after issuance of the lease". Quite apart from other
considerations, it must be plainly borne in mind that "dealings"
with land under the Land Act do not attract anything like the
same protection as dealings with land under the Torrens system.
In the case of land under the Real Property Acts , title is by
registration ( Breskvar v. Wall (1971) 126C.L.R. 376, at 385-386)
and conveyance by instrument is effectual to pass title only when
registered and not before: see Real Property Act 1861-1988, s.43.
Nothing like that state of things prevails in relation to leases
and transfers of leases under the Land Act . In practice
something resembling the same procedure is evidently followed in
recording dealings under both systems; but the "historical
-- 13 of 51 --
register sheet" has nothing like the status of the Torrens system
register on which, by ss.33 and 44, the Real Property Act confers
qualities of conclusiveness and indefeasibility. Under the Land
Act particulars of leases under that Act, and of transfers "and
other dealings therewith", are by ss.226 and 227 to be recorded
in a register or registers; and in the course of these recordings
"priority of registration of the dealing" is to be maintained:
ss. 226(3) and 227(1). Nowhere, however, does the Act ascribe to
such registers or the entries in them any of the legal character
or consequences of a register or registration under the Torrens
system. It is to my mind not even clear that (assuming the
consent of the Crown as lessor) registration is necessary to give
effect to assignments or "transfers" of leasehold interests under
the Act: cf . Land Act , ss.286, 287. The problems of conveyancing
under the comparable Crown lands legislation in New South Wales
is considered by Stonham: Vendor and Purchaser, paras 464-477A
and 1802-1809, who considers the desirability in such cases of
requiring a common law conveyance. On any view of the matter,
therefore, the historical register sheet maintained by the LAC
was not an "instrument of title" within the meaning of cl. 2 of
the contract. It was no more than it purported to be - a
compilation of past dispositions of the land recorded in
sequence.
It is not, however, necessary to pursue these questions
beyond the point of showing that what the plaintiffs were here
being offered on settlement on 1 March 1989 was nothing like the
title that would result from registration of a comparable
transfer under the Torrens system. With the former instrument
-- 14 of 51 --
11
of lease P.L. 14/4623 already surrendered, and the new lease GHPL
14/231 not yet issued, it may be doubted whether at that date the
defendant was in a position to transfer to the plaintiffs even
as much as a leasehold interest in the land, as distinct from an
interest under what was at that stage a mere agreement for lease,
or something less. Section 160(1) of the Act does, it is true,
in terms impose on the Governor in Council an obligation to issue
("shall issue") a new lease to a lessee who surrenders his
subsisting lease under the provisions of that Division; but an
enforceable agreement for lease is for these purposes not
equivalent to a lease at law: see Hutchinson v. McGwen (1910)
10 S.R. (N.S.W.) 449, 454, 461; and, in any event, there is an
ominous provision in s.162 expressly precluding remedies and
excluding the jurisdiction of courts in respect of things done
under the Division.
Some of these difficulties may be overcome by accepting his
Honour's characterisation of the transaction as a contract for
the purchase of "the rights or expectations of rights" that would
be held by defendant in the Alkoomie property on 1 March 1989.
For my part I doubt if the contract of sale can be pressed so far
as to fit it into such a mould. Even if, however, that is too
narrow a view, it remains necessary to return to cl. 2 of the
contract in order to ascertain what it was that the plaintiffs
were bound to do on the date for completion, and what they are
alleged not to have done. Clause 2 requires payment on
completion date of the balance of price "in exchange for"
possession and a duly executed transfer in favour of the
purchaser "accompanied by the instrument of title". It is
-- 15 of 51 --
accepted that both possession and a duly executed transfer were
or could have been provided; what was not tendered was "the
instrument of title".
Mr Keane Q.C. submitted that "the instrument of title"
referred to in cl . 2 is the same as that described in the contract
particulars as being located at ANZ Bank, Mareeba. That was
admittedly pastoral lease no. 14/4623. Long before 1 March 1989
it had been surrendered, and on that date it reposed in the
office of the LAC. It is true that it was available for
inspection at that place; but, even if completion was to take
place there, by no stretching of language could that be said to
satisfy the requirement of cl . 2 that the executed transfer be
"accompanied by" the instrument of title. The transfer is
plainly intended to be delivered to the purchaser, and the
instrument of title is to accompany it. One compelling reason
among others why the purchaser might be supposed to want the
instrument of title is to enable him to raise finance by
mortgaging the interest transferred to him. Without the
instrument of title, he would be able to do so, if at all, only
with extreme difficulty.
The "duly executed transfer" that the defendant proposed to
deliver on 1 March 1989 therefore could not and would not have
been "accompanied by" the instrument of title. That is plainly
so if the instrument of title was the surrendered pastoral lease
no. 14/4623, of which the Commission had possession. It is
plainly also the case, if it was GHPL 14/231, for that instrument
of lease did not come into existence until it was executed on
30 March 1989. It was submitted that, in any event, the
12
-- 16 of 51 --
13
o
O
O
■*v-
O
defendant never at any time undertook to transfer the GHPL that
ultimately issued. That is by no means as clear to me as it
appeared to counsel for the defendant. The leasehold interest
in "Alkoomie" as defined in P.L. no. 14/4623 expressly includes
"all other rights, powers, privileges, terms, conditions,
provisions, exceptions, restrictions, reservations, and provisoes
referred to, contained, or prescribed in and by the" Land Act and
other Acts. The provisions of Division 1 of Part VI of the Land
Act relating to surrender and the issue of a new lease fall
directly within those terms, as does the "privilege" of the new
lease itself. If what the defendant sold was "Alkoomie" pastoral
lease or any new lease resulting from its surrender, then
arguably the instrument of title to accompany the transfer on
completion under cl : 2 was the instrument of title to the GHPL
that commenced on 1 July 1988. The defendant was not, on 1 March
1989, in a position to produce that instrument.
It is, however, in my view not strictly necessary to decide
whether the "instrument of title" referred to in cl.2. of the
contract was P.L. no. 14/4623 or the GHPL 14/231 that ultimately
issued. Whichever of these it was, the defendant did not have
it on 1 March 1989 and so was unable to deliver her transfer
"accompanied by" that or any instrument of title. I have already
concluded- that the "historical register sheet" was not in any
sense an instrument of title within the meaning of cl .2. It
follows that the defendant was not on that date in a position to
settle and complete the contract in accordance with cl. 2.
It may be said, and was submitted, that this state of
affairs was not due to any default on the part of the defendant.
-- 17 of 51 --
The delay in executing the new GHPL instrument seems to have
resulted from delay in preparing survey plans relative to the
land "adjustment" with Caloola. I am for present purpose content
to accept that the defendant was not responsible for that delay,'
and, in consequence, was not at fault in being unable to provide
the new GHPL instrument of title at settlement on 1 March 1989.
Such a conclusion no doubt suffices to protect her from
assertions of a breach of contract on her part and against
consequential claims for damages arising from that breach. It
affords no justification for her purported termination of the
contract by reason of the plaintiffs' failure to complete it on
1 March 1989. It was nevertheless submitted that the plaintiffs
had on their own part failed to tender performance on that date,
and that there was no evidence that they were then in a position
to do so. In my opinion, however, this overlooks a critical
element in cl . 2 of the contract. It does not impose on the
plaintiffs as purchasers an unqualified obligation of paying the
balance of purchase price on completion date. What cl. 2 does is
to require the balance to be paid "in exchange for" other things
including an executed transfer accompanied by the instrument of
title. It is settled that the obligations of purchaser and
vendor under a clause in that form are dependent, concurrent and
reciprocal: cf. Dainford Ltd, v. Juana Ptv. Ltd. [1986J 1 Qd.R.
396, 401-402; Sunbird Plaza Ptv. ltd, v. Maloney (1988) 166 CLR
245, 264-265; and see Secacious Ptv. Ltd, v. Fabrella (1989) Qld.
Sup Ct - Byrne J. : unrep.). The plaintiffs here were therefore
obliged to pay the balance purchase price only in exchange for
possession, transfer, and instrument of title from the defendant.
-- 18 of 51 --
15
The defendant was demonstrably unable on 1 March 1989 to"
accompany the executed transfer with an instrument of title.
Plaintiffs' solicitor was aware of this before the time for
settlement at 2.30 p.m., which was why (or one reason why) he did
not attend and tender on that day. Had he done so, he would have
been entitled to withdraw tender once he discovered that (as was
the fact) the defendant was on that day not in a position to
complete in accordance with cl. 2. The law does not compel a
contracting party to make a useless tender of performance; and
where, as here, it can be seen that such a tender would or could
have achieved nothing, the party failing to tender cannot by
virtue of that failure be treated as being in default.
When, as appears from the evidence at the trial, it is
evident that the defendant vendor was on 1 March 1989 not in a
position to complete the contract in accordance with cl. 2, she
did not thereby acquire a right to terminate the contract. That
was ’so whether her inability to complete was due to default on
her part or otherwise. She was accordingly not entitled to give
the notice of termination (ex. 34) dated 2 March 1989. Doing so
amounted to a repudiation on her part of the contract. It was
then no doubt open to the plaintiffs to accept that repudiation
and so bring the contract to an end. They chose not to do so,
and communicated that election to the defendant. The contract
therefore continues to subsist, and the plaintiffs are entitled
to specific performance of it unless some other ground of defence
appears .
Two other matters were raised. One, that the subject matter
of the contract was uncertain, has, I consider, already been
sufficiently dealt with in these reasons. I am content to regard
the subject matter of the sale as the defendant's interest in the
-- 19 of 51 --
"Alkoomie" property with the rights (including the GHPL)
resulting from a surrender of that interest. At the date of the
contract on 15 August 1988 those rights had already been
transformed into a grazing homestead perpetual lease of which the
term commenced on 1 July 1988. The obligation in cl. 2 took its
meaning from those circumstances .
The other matter raised on appeal concerned the provisions
of the special condition of contract making "this sale ... subject
to the consent of the Minister for Lands to the transfer of the
leaseholds held under the provisions of the Land Acts." In fact,
on 3 December 1988, Mr. T.E. O'Brien as delegate of the Minister
consented to the contemplated transfer. The terms, of that
consent were conveyed to the defendant by letter dated 8 December
1988, (ex. 30), which so far as relevant reads as follows:
"With reference to your letter of 6th November, 1988,
I wish to advise that upon prior recording and issue
of the Instrument of Lease of a new G.H.P.L. to issue
over surrendered Alkoomie P.H. 14/4623 Cooktown
District, a transfer as proposed will be allowed if in
order and lodged promptly, provided the terms of any
Contract for Sale executed do not contravene the
provisions of the Land Act 1962-1988 and the Contract
or a certified copy thereof is lodged here with the
transfer documents for filing in the records of the
Department. If no contract is entered into, the
Department should be advised accordingly."
The point is made that the condition requiring Ministerial
consent by 1 March 1989 was not fulfilled. In fact, the special
condition does not in terms require consent by that date. Clause
1 6 of the printed conditions provides that if such consent is not
granted by the date for completion, then either party may by
written notice terminate the contract, whereupon the deposit
becomes repayable. It may be thought that the defendant put it
out of her power to determine the contract under cl. 16 when on
1 March 1989 she insisted upon settlement and completion on that
-- 20 of 51 --
17
day. Her later notice of termination (ex. 34) is by its own
terms and recitals plainly not referable to cl. 16, and in
purporting to forfeit the deposit it is inconsistent with the
terms of the power or option conferred by that clause.
In the end, however, the question is whether the condition
as to Ministerial consent had, indeed, not been fulfilled by
1 March 1989. I find myself unable to read the letter ex. 30,
or the consent it conveys, in the sense contended for. The
consent given there is in terms a present consent to a transfer
in the future. For some time past it seems to have been a
practice of the Lands Department to approve of transfers in that
proleptic form: cf. Norton v. Angus (1926) 38 C.L.R. 523, at 527.
However that may be, it is in my view nonetheless a "consent to
the transfer of the leaseholds" within the meaning of the special
condition in the contract; and, if it is necessary to go further,
it was not a consent that was "not granted by the date for
completion" within the meaning of cl. 16 of the printed conditions
of sale. This being so, the defendant has no defence to the
plaintiffs' action for specific performance.
I would allow the appeal with costs; set aside the judgment
in the court below; in lieu thereof I would give judgment for the
plaintiffs in the action for specific performance of the contract
referred to in the writ of summons in the action, and also
judgment dismissing the counterclaim; and I would order that the
defendant pay the plaintiffs' costs of the action, including
reserved costs, if any. As there may be a need to fix a new date
for completion of the contract, there should also be liberty to
the parties to apply.
-- 21 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 111 of 1990
Before the Full Court
Mr Justice McPherson S.P.J.
Mr Justice Derrington
Mr Justice Moynihan
BETWEEN:
AND:
JOHN DAVID BEARD. KENNETH JAMES EUSTACE
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs) Appellants
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
JUDGMENT - DERRINGTON J.
Delivered the 21st day of March, 1991
CATCHWORDS :
Counsel: Mr Greenwood Q.C. and Mr Carrigan for appellants
Mr Keane Q.C. and Mr Clarke for respondent
Solicitors: Phillips & Lowes for appellants
McCullough Robertson town agents for Morrow & Co.
for respondent
Hearing date: 11 and 12 February, 1991
-- 22 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
Appeal No. 111 of 1990
BETWEEN :
JOHN DAVID BEARD. KENNETH JAMES EUSTACE
MAXWELL JAMES MEAD and CLIVE ALLERT
(Plaintiffs) Appellants
AND : BARBARA JOYCE WRATISLAW
(Defendant) Respondent
JUDGMENT - DERRINGTON J.
Delivered the 21st day of March, 1991
In 1988 the respondent was the lessee from the Crown of a
pastoral lease in the gulf country. Although it was due to
expire in 1994, she had applied to the Department of Lands in
1986 for a conversion of the lease to a Grazing Homestead
Perpetual Lease over the same area. After some negotiations, on
28 March, 1988 the Department gave its approval to the grant of
a Grazing Homestead Perpetual Lease subject to the excision of
part of the area of the old lease which was to be added to the
area of an adjoining lease held by a Mr Martin and the inclusion
in the respondent's lease of a corresponding area excised from
Mr Martin's lease. Naturally this arrangement required the
agreement of both the respondent and Mr Martin, which was
forthcoming, and their mutuality of action in the consequential
procedures .
The alteration to the boundaries of the respective leases
under the new arrangement required the attention of a surveyor
-- 23 of 51 --
and at the time of the approval this cost was usually borne by
the Department. However by a change in the Department's policy/
from 1 July, 1988 it required this cost to be met by the parties
concerned, in this case, the respondent and Mr Martin. However,
the respondent did not know of this immediately.
While this position prevailed, she entered into a contract
dated 15 August, 1988 to sell to the appellants what was
described in the contract document by the title of her original
pastoral lease. The date of completion specified by the contract
was originally 15 February, 1989, but this was later
progressively advanced to 1 March, 1989. Time was of the essence
of the contract. The contract also contained the term that the
balance of the purchase price should be paid on the date for
completion in exchange for, inter alia, the executed transfer
documents "accompanied by the instrument of title". However as
part of the process of obtaining a new lease she had already
executed a form of surrender of the old one and had delivered it
to the Department with the instrument of lease. These
circumstances were known to all of the relevant parties leading
the learned trial Judge to find, "that the parties meant by ex.
12 (the contract document) to contract for the defendant to sell
and the plaintiffs to buy the rights or expectations of rights
which the defendant would have over the land then or formerly
incorporated in P.H. 278 or P.L. 14/4623 at the date of
completion namely 15 February, 1989 or such date to which
completion might be extended". There is ample evidence to
support the view that the parties either directly or through
representatives all intended that the subject matter of the sale
-- 24 of 51 --
3
would not be the original pastoral holding but her interest in
that property to which the respondent would be entitled as the
result of her surrender of the old lease and the consequential
grant of a new one .
It has been argued pursuant to and in support of the trial
Judge's finding, that the subject of the sale was confined to the
bundle of rights of the vendor in the transaction with the Lands
Department as it would exist on the date of completion, and that
the reference to the "Instrument of Title" in the contract should
be interpreted as referring to whatever instrument of title
should happen to be available at the date of completion,
including that relating to the old Pastoral Holding if the new
instrument of lease were not available. But that cannot be so
because of the possible position, which must have been in
contemplation in these circumstances and which in fact because
the case, that at the relevant date the old lease would have been
surrendered and therefore unavailable and the instrument of lease
of the new holding would not yet have issued. In that case there
would be no instrument of title in existence to meet the
respondent's obligation to produce it on settlement. In those
circumstances, even if it could be produced by the respondent,
the old instrument would no longer be an instrument of title for
there would be nothing to which it could then evidence title.
It would be only an instrument of former title. And the papers
which the Department had produced towards the new grant did not
purport to be and could hardly be described as an instrument of
title .
-- 25 of 51 --
There are many features which may render it important and
even imperative to a purchaser to receive on settlement a
document which is clearly the instrument of title. This is one
of the reasons for the express term of the contract requiring its
production on completion of the sale. Realistically the only
instrument which could have been in the contemplation of the
parties in relation to this provision was the new instrument of
lease, and this strongly supports the conclusion that the subject
matter of the sale was the new lease. More particularly it was
not an unsettled "bundle of rights" having no instrument of
title.
Although it may not be conclusive, it is also manifest that
this was the view of what was intended which was adopted by both
parties in the period leading up to the date for completion for
as it will be shown the respondent sought and the appellants
granted an extension of time for completion on the express ground
that the new instrument of lease had not issued but was expected
to do so within the extended time. If it were believed that the
production of the new instrument was not required, this
arrangement would have been unnecessary.
By 8 September, 1988 both the formal applications of the
respondent and Mr Martin necessary for the exchange of land and
the granting of the new leases were in the hands of the
Department, and it advised both of them on 20 September, 1988
that they were required to have prepared and to pay for a
"compiled plan" of the properties showing the exchange of land.
They both believed that this required a full survey costing a
considerable sum and both protested to the Department. They were
-- 26 of 51 --
5
in error in their belief for the cost was moderate because no
field work was necessary and the Department advised Mr Martin to
that effect on 23 November, 1988. There is no evidence however
that it also notified the respondent and on 24 January, 1989 she
wrote to the Department seeking to withdraw from the exchange of
land. However before the Department could do anything about it,
she must have learned the true position and joined with Mr Martin
in instructing the surveyor to proceed, for the plans arrived at
the Department on 20 February, 1989 and it continued with the
original arrangement. However the approval of the grant of the
new lease to the respondent was not given by the Governor in
Council until 16 March, 1989 and the instrument of lease was not
executed by the Governor until 30 March, 1989, that is in both
cases, after the extended date for completion of the contract.
On the date for completion the respondent offered to settle
without producing any instrument of title claiming that as none
was available, there was no obligation on her part to produce
one, and that the appellants were required to settle without it.
The error in this is manifest because it is in conflict with the
contract. The obligation of the appellants to settle was
expressly interdependent and concurrent with the respondent's
production of the instrument of title: cf. Rvan v . Ferguson
(1909) 8 C.L.R. 731: Dainford Ltd v. Juana Ptv Ltd (1986) 1 Qd.
R. 396 at p. 401; Sunbird Plaza ptv Ltd v. Malonev (1988) 166
C.L.R. 245 and to the extent that the respondent might have been
excused from such production then to the same extent she was
disentitled from insisting on completion. Even aside from the
express provision of the contract, which should be the end of
-- 27 of 51 --
this point, as a matter of general law the vendor must produce
the instrument of title on completion: Donaldson v . Gray (1920)
V.L.R. 379, 383. Contrary to the above conclusions, the
respondent's argument is that this is impliedly overridden by the
agreement which she says is tp sell only the rights which she had
A
at the date for completion for which there was no instrument of
title. However, as it has been shown the subject matter was her
interest as lessee in the new Grazing Homestead Perpetual Lease
for which there was to be an instrument, and the strength of this
conclusion is further fortified by the above general principle.
Of course the latter may be modified by agreement, express or
implied (cf . McKeller v. Abbott (1891) 17 V.L.R. 215; Peter
Turnbull & Co. Ptv Ltd v. Mundus Trading Co. (Aust.) Ptv Ltd
(1954) 90 C.L.R. 235, 252-253), but the force of principle will
not easily be displaced by inference; and when there is an
express term consistent with the general principle it is
impossible to imply the contrary in the present circumstances.
It therefore may be safely said that in the present case the
completion of the sale could not take place without the
instrument of title, and in the circumstances that had to be the
title to the new lease. Consequently the respondent was not
entitled to require completion.
To the respondent's offer to complete on her terms the
appellants countered that as the instrument was not yet available
they were entitled to defer the date of settlement until it
became available. While they affirmed the contract, the
respondent purported to rescind it on 7 March, 1989 on the ground
of the appellants' alleged default in failing to settle on the
-- 28 of 51 --
7
O
O
o
u
date for completion. The appellants argue that the respondent
was under an obligation to produce the instrument of lease at
settlement on the date for completion, and that she was in breach
of this; alternatively that if her obligation were conditional
upon the availability of the instrument, she cannot rely upon
this because of her delay in obtaining it in breach of her
implied obligation to do all things reasonably necessary to
obtain it by the date for completion.
As all parties agree, there was a term implied from the
circumstances that the respondent would act promptly to do all
things necessary on her part to advance the process of obtaining
the interest which was the subject of the sale and all things
necessary for completion: cf. McFarlane v. Wilkinson (1927)
V.L.R. 359; Mav v . Daly 91927) S.A.S.R. 428; Gasiunas v. Meinhold
(1964) 6 F.L.R. 182. It is not acknowledged by the respondent
however that this duty extended to the advancement of the matter
towards the issue of the new instrument of lease but this is
clearly so because the contract spoke of the exchange of, inter
alia, the instrument of title for the purchase money on
completion.
This is not to say however that she was unconditionally
obliged to produce the instrument on settlement: cf. Hargreaves
Transport Ltd v. Lynch [1969] 1 W.L.R. 215 and Richard West &
Partners (Inverness) Ltd v. Dick [1969] 2 Ch. 424. Her implied
obligation in these circumstances was to do her best, but the
result was out of her hands. Nor was there anything about the
circumstances to suggest an implication that although the result
may have been in the hands of others, she was nevertheless
-- 29 of 51 --
8
prepared to assume the unconditional obligation such as may be
the case for example when a purchaser who is known to require
finance is still prepared to enter into a contract which is on
its face unconditional. In such a case an implication of a
condition in favour of that party qualifying the obligation to
proceed would not be justified, particularly as it would relate
to something extraneous to the agreement . But here the
unconcluded nature of the new grant at the time of contract and
the possibility of a similar position at the date for completion
are clearly factors which are interwoven into the terms of the
agreement itself. As it has been seen, it was necessary to refer
to them to determine the subject matter of the sale. It would
then be artificial to ignore them in interpreting the contract
to determine the respondent 1 s duties in respect of an essential
feature of the subject matter, that is, its instrument of title.
Although the facts are quite different, the process of
reasoning in Redapple and Howgate v. Helv (1931) 45 C.L.R. 452
per Dixon J. (as he then was) at pp. 470-471 is fortifying of
this approach. There as the parties knew the vendor was required
to take steps to have the instrument of title amended to conform
with the area sold but this was subject to acceptance by the
Office of Titles. It was held that the vendor was obliged to
take all proper steps but did not warrant the outcome of the
application. There is a certain measure of analogy here in
essential principle, though the exercise is always a matter of
the interpretation of what is implied by the terms of the
particular contract in the light of the particular facts of the
case under consideration.
')
-- 30 of 51 --
9
Her obligation to produce the instrument on settlement was
therefore conditional upon its becoming available to her pursuant
to the procedure which she was obliged to follow in order to
obtain it. While she was to use her best endeavours to that end
and the length of time allowed before settlement shows that the
parties expected or at least hoped that it would become available
by that time (cf. Walter v. Nelms (1954) V.L.R. 398 at p. 399),
the arrangement could not be construed so as to oblige her to
warrant the co-operation of other in the process, particularly
as to time. This restricted implication as to her obligation
follows, not from some factor personal to her and within her
control or accepted responsibility such as in the abovementioned
circumstances of a purchaser's obtaining finance which is not
made a condition of a contract, or where there has to be the
release of a mortgage over the title, but from the very nature
of the subject matter of this contract and the need for action
by others in order that settlement could take place at the date
for completion.
In some ways this position is analogous with that where a
contract such as this, requires the approval of the Minister, but
contains no provision on that subject. There is an implication
that the vendor will seek to obtain the approval, that neither
party will do' anything which might put the gaining of approval
in jeopardy, and if the vendor fails to obtain it the contract
will go off: Duncan v. Mell (1914) 14 S.R. (N.S.W. ) 333, 339;
Egan v. Ross (1929) 29 S.R. (N.S.W.) 382, 387; app Rawson v .
Hobbs (supra) per Kitto J. at p. 486. See also Hargreaves
Transport v ♦ Lynch ( supra) and Richard West & Partners
-- 31 of 51 --
10
(Inverness) Ltd v. Dick (supra). Further analogy may be drawn
with McFarlane v. Wilkinson (supra) where the same .general
circumstances obtained but because of the action of the purchaser
the consent was delayed until after the date for settlement and
after rescission by the vendor, time being of the essence of the
contract. The "transfer of title" which it was the vendor's
obligation to provide meant a transfer duly approved by the
authority, and it is from this obligation that the vendor's duty
to seek the approval was implied. In none of these cases was the
vendor' s duty found to be the obtaining of the consent as
distinct from dutiful pursuit of it, and of course the reason is
that the result was outside the vendor's control or impliedly
accepted responsibility.
So too in the present case, that the instrument of title to
be produced on settlement was the new lease was a matter of
implication from the circumstances that the sale was agreed in
the context of the vendor's application for a new title. That
implication does not stand alone. For example there is also the
implication of the vendor's obligation to do all things
reasonably necessary to that end, an implication incidentally
which would be otiose if her obligation were absolute in the
sense of her having to produce the instrument, that is, her
warranting the result. To say that these implications from the
circumstances mentioned, which are necessary to the
interpretation of the contract as to which instrument is to be
produced on settlement, include one imposing the warranting the
result of the circumstances, particularly as to time, is to go
too far. It is because the process of obtaining the new lease
O
O
o
-- 32 of 51 --
11
and instrument of title are so essentially part of its terms, for
example in the identification of the subject matter, that it must
be taken into account in the construction of the contract as to
related topics. The analogy as to the condition that the
vendor's obligation to obtain ministerial consent on settlement
is subject to his/her ability to obtain it after diligent
efforts, which is part of the implication that it is his duty to
pursue it, is obvious.
In Walter v. Nelms (supra) also the vendor of a business was
held by implication to be obliged to seek the owner's grant of
a new lease to the purchaser of the business when such a grant
was made an express condition of the contract. It was further
implied that this had to be effected before the date of passing
of possession of the business at which time there was to be
payment of a substantial part of the purchase money. It was
still further held that if no such grant were obtained by that
date, the contract terminated. This and other cases on the sale
of a leasehold interest which is expressly made "subject to the
lessor's consent" are not otherwise truly analogous because that
condition was expressly stated in each of the respective
contracts whereas here the first question is whether a comparable
condition should be implied at all; and those cases were directed
to the question whether the vendor had done all that was required
of him to have the condition fulfilled: see Day v. Singleton
(1899) 2 Ch. 320; Smith v. Butler [1900] 1 Q.B. 694; Lehmann v.
McArthur (1868) L.R. 3 Ch. 496.
For these reasons, it should be implied from the terms of
the contract itself that there was a requirement for the
-- 33 of 51 --
12
production of the instrument of new lease on settlement but that
it was conditional upon its availability. The next question is
whether the respondent is deprived of any right to invoke this
condition by reason of her conduct.
It is abundantly clear that she delayed for several months
in taking the action on her part necessary to the advancement of
the grant of the new lease and the issue of the instrument of
lease because she did not wish to undertake the expense which she
believed was necessary for the survey. In this she was not
justified in failing to carry out her contractual obligation,
even if her belief had been correct, for in no way did her
expense in performing it excuse her doing so: Thomson v .
Richardson 91928) 29 S.R. (N.S.W.) 221. Any unilateral error as
to expense on her part in entering into it could not have
qualified her objective obligation as required by the contract.
: However she argues further that her delay was immaterial
because Mr Martin, the other party to the exchange of area, had
not performed certain actions on his part which were also
necessary to the progress of the exchange, and that his delay
continued up to the time when arrangements were made for the
surveyor's production of the compiled plan which allowed the
Department to proceed to finality. If there were such delay on
his part which prevented the advancement of the transaction in
any case, then the respondent's failure to act reasonably or
promptly would nevertheless not have been productive of any delay
in the progress of the transaction. If however the delay were
attributable entirely to her own refusal to proceed, then a
comparison between the length of her delay and the period after
-- 34 of 51 --
the completion date to the issue of the instrument of title
demonstrates that the absence of the latter at the date of
completion was due to her own default. On that hypothesis she
would not be entitled to rely upon the unavailability of the
instrument as a basis of discharge of the contract for
non-fulfilment of the condition: Roberts v. Bury Commissioners
(1870) L.R. 4 C.P. 755; New Zealand Shipping Co. Ltd, v. Societe
des Ataliers et Chantiers de France [1919] A.C. 1 at 9; Smith v.
Wirth [1945] St. R. Qd. 59; Amalgamated Building Contractors Ltd
v. Waltham Holy Cross U.D.C. [1952] 2 All E.R. 452, 455.
Because the parties do not appear to have directed their
attention to this matter at the trial and the respondent did not
enter the witness-box there is but sparse evidence as to whether
Mr Martin was so responsible for the delay so that the instrument
of lease could not have been available in time in any case. The
respondent's delay was certainly established, but direct evidence
as to the co-operation of Mr Martin is limited. Although-the
Department wrote to him on 23 November, 1988 correcting his
misapprehension as to the extent and cost of the required survey,
however, as His Honour found:-
"a letter of 20th December, 1988 to the defendant and ■
Mr Martin on the Department's file shows that the
situation as per the plan was still unclear as far as
the defendant and Mr Martin were concerned .. .".
Moreover, according to Mr Hunter, who was the surveyor who
prepared the compiled plan in the end, instructions from
Mr Martin were not given until 9 February, 1989. This tends to
support the proposition advanced for the respondent on this point
on this appeal, which was not controverted in reply. It follows
that so far as the evidence goes it shows that irrespectively of
-- 35 of 51 --
14
the respondent ' s delay the matter could not have proceeded to the
grant to her of the new lease and the issue of the instrument of
title by the date for completion of the contract because of this
independent delay by Mr Martin. Consequently her delay had no
bearing upon whether the instrument of lease issued in time for
the date for completion of the contract, and so she is entitled
to rely upon the implied condition to her obligation to produce
it that it should be available to her to produce.
Before dealing with this further it is desirable to discuss
the effect of conversations and correspondence between the
solicitors for the parties commencing shortly prior to the
original date for completion and leading to various extensions
of that date. This is because by reason of these communications
the appellants claim waiver of and/or estoppel from her relying
upon the essentiality of time. Alternatively, it is argued, if
formerly the respondent had been under no obligation to produce
the instrument of lease on settlement, by these new arrangements
she promised, in consideration of the appellants' agreement to
extend time, to produce the lease on the extended date or
alternatively to extend the time further until it could be
produced .
Apart from the first occasion when the respondent's
solicitor obtained a short extension in order to make himself
acquainted with the details of the matter, the remaining
extensions were negotiated by agreement expressly because the new
lease had not yet been granted and, it is fair to say,
particularly because the instrument of lease was not yet
available but expected to issue shortly. If there were ever any
O
o
o
o
-- 36 of 51 --
15
C' !
o
o
u
doubt that, the issue of its availability aside, the instrument
of lease was required to be produced upon settlement under the
original terms of the contract, then it would have been dispelled
by these agreements for extension. This is because the very
reason for the agreement by the appellants at the request of the
respondent to extend the time was the unavailability of the
instrument, and these circumstances clearly implied such a
promise by the respondent in consideration of the appellants'
compliance; and if necessary it would have amounted to a
variation of the original agreement.
However, there is some confusion as to the precise terms of
this implied variation. The appellants claim that the respondent
thereby undertook without qualification to produce the instrument
of lease upon the extended date of completion, but there is no
such promise expressed or implied from the circumstances :
Cf. the approach taken by Dixon C.J. in Rawson v. Hobbs (1961)
107 C.L.R. 466 at p. 477 to the suggestion of an implied
promissory provision from the circumstances there. In particular
there is no reason to conclude that her promise was to do more
than produce the instrument of lease on the settlement only if
it became available to her by that time. It is clear that her
solicitor and she may have had the hope and expectation that it
would become available, but the matter was out of her control and
nothing which was said and nothing in the circumstances would
suggest that she was warranting that it would become available.
Rather the factors which have been discussed above favouring the
interpretation that her original obligation to produce the
instrument on completion was conditional on its availability
-- 37 of 51 --
16
operate here in the same way. That her promise was so limited
is clearly so if, as demonstrated above, her original promise was
also so limited for there was no reason why her promise in
respect of the extension should be different, and the later
circumstances do not suggest that she should enjoy any greater
confidence in the result than at the earlier stage. Further,
there is nothing in the communications to suggest any such
change.
Nor was there any implied agreement for an extension of time
for settlement beyond the agreed extended date, for her solicitor
had always made it expressly clear that the extension was limited
to that date and no further and that time was to remain of the
essence pf the contract. Nor was there any waiver or estoppel.
There was simply a variation agreement between the parties that
because the instrument would not be available at the time for
completion that was then set, the latter should be postponed in
the hope that it may become available by the postponed date and
the contract would not be frustrated. There were no further
implications supporting a. waiver or an estoppel, for the
*• %
* ?
postponed date provided both sets of parties with the mutual
advantage of opening the possibility that the sale could
continue. This is as far as it went. Consequently these
communications do not advance the appellants ' case .
The respondent has further argued that the condition of the
contract requiring the consent of the Minister to the transfer,
which it was her duty to obtain, was not discharged. The
foundation for this argument lies in the terminology of the
consent which was granted. That approved of a contract relating
-- 38 of 51 --
17
to the new Grazing Homestead Perpetual Lease which was yet to be
issued, and it is somehow argued that there could not be a
consent to a transfer in respect of a future interest. It is
difficult to understand why such an inhibition could possibly be
so. The future lease was clearly identified and no authority at
all nor even any argument was advanced as to why the consent of
the Minister could not be given in advance in respect of such a
holding. There is nothing technical about the consent of the
Minister and as it related directly to this transaction there is
no difficulty. That the consent referred to a sale to three only
of the purchasers is immaterial because the defect was the fault
of the respondent in any case. This would be an answer, if it
were necessary, to any complaint on her part as to the consent,
for it was her obligation to obtain it, and she can hardly rely
upon any non-fulfilment of a condition which was due to her own
breach: Roberts v. Bury Commissioners (supra); New Zealand
Shipping Co. ( supra ); Amalgamated Building Contractors ltd v.
Waltham Holy Cross U.D.C. (supra) .
In the result on the extended date for completion the
appellants were entitled to require the production of the
instrument of lease upon settlement but the obligation of the
respondent to produce it was conditional upon its becoming
available by that date. Consequently when that did not come
about neither party was in default and the contract went off
because of the failure of the condition.
This being so and time being of the essence of the contract
the appellants were not entitled to insist that the contract
should remain on foot to be completed when the instrument of
-- 39 of 51 --
18
lease should finally become available. Nor was the respondent
entitled to repudiate upon the alleged ground of the appellants '
default, for there had been no such default. She was not
entitled to settlement without the production of the instrument
of title. However she was entitled to terminate the contract for
the reasons stated above. She did terminate it on 7 March, 1989
when her notice of termination was received by the appellants.
By that date the instrument of lease had still not become
available so there is no question to be considered in that
respect. Nor is it material that the ground upon which she V_.v
purported to terminate was not available to her nor that the
reason which she gave was not justified: Shepherd v. Felt and ^ ^
Textiles of Australia Ltd (1931) 45 C.L.R. 359. Consequently her
termination of the contract was valid in its effect, and it
should simply be regarded as having failed so that the parties
should be restored to their original positions.
Although the reasons are different the conclusions reached
by the learned Judge at first instance were correct in respect ( J
of the orders and declarations which should have been made. The
appeal should therefore be dismissed.
-- 40 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 111 of 1990
Before the Full Court
Mr. Justice McPherson S.P.J.
Mr. Justice Derrington
Mr. Justice Moynihan
BETWEEN:
JOHN DAVID BEARD. KENNETH JAMES EUSTACE.
MAXWELL JAMES MEAD and CLIVE ALBERT
(Plaintiffs) Appellant
AND:
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
JUDGMENT - MOYNIHAN J.
Delivered the 21st day of March, 1991
Counsel: J.. Greenwood Q.C. with C. Carrigan for the
Appellants
P. Keane Q.C. with B. Clarke for the
Respondent
Solicitors: Phillips & Lowes for the Appellants
McCullough Robertson t/a for Morrow & Co.
for Respondent
11th and 12th February, 1991 Hearing Dates:
-- 41 of 51 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 111 of 1990
BETWEEN:
JOHN DAVID BEARD. KENNETH JAMES EUSTACE.
MAXWELL JAMES MEAD and CLIVE ALBERT
(Plaintiffs) Appellant
AND:
BARBARA JOYCE WRATISLAW
(Defendant) Respondent
JUDGMENT - MOYNIHAN J.
Delivered the day ^ * 1991
This case is a classic illustration of the dangers of using
a standard form contract in circumstances other than those for
which it was designed at least without careful drafting to
accommodate the particular situation. On 15 August, 1988 the
parties, with the respondent as vendor and the appellants as
purchaser, signed a contract on a standard R.E.I.Q. form. In the
place provided for insertion of "particulars of land sold" the
parties acknowledged the current use of the land was "vacant" and
its description was "P.H. 278 D.G.O. 0115". The description went
on to give the county, parishes and town for the holding.
Provisions for insertion of the volume and folio ( relevant:"to the
description of land under the Real Property Act) were left blank,
one imagines because the land in question was Crown leasehold and
those particulars were irrelevant. The area of land was said to
be 72 square miles. The land was said to be sold as leasehold
and the instrument of title was said to be located at "ANZ Bank,
-- 42 of 51 --
2
Mareeba". The type of holding was said to be "Pastoral Lease"
and the lease number given was 14-4023.
The purchase price was $162,000.00 with a deposit of
$16,000.00. The standard form made provision for the insertion
of a date of completion and 15 February, 1988 was inserted.
Clause 2 of the contract dealt with completion and possession in
*
these terms:-
"2. COMPLETION AND POSSESSION. The balance of the
purchase price shall be paid on the date for
completion stated in Item Q in exchange for
possession (such possession to be vacant except
for tenancies stated in Item M) together with a
duly executed transfer in favour of the Purchaser
capable of immediate registration (after
stamping) in the appropriate office free from
encumbrances except as set out in Item L and
accompanied by the instrument of title except as
provided in clause 8 and in the case of the land
being subject to any tenancies referred to in
Item M a notice (prepared by the Vendor) in
conformity with Section 13 of the Residential
Tenancies Act 1975 (if that act applies) together
with the Vendor's executed and stamped copies of
all instruments (if any) evidencing such
tenancies. If the improvements sold may not be
lawfully occupied unless there has issued a
Certificate of Approval under the Fire Safety Act
1974 and/or a Certificate of Classification under
the Standard Building By-laws 1975 appropriate to
the uses stated in Item H the Vendor shall
procure and deliver to the Purchaser such or both
of those certificates as may be required to
permit occupation of the improvements sold for
such stated use and deliver the same to the
Purchaser in exchange for the balance of the
purchase price in addition to the documents
abovementioned. If the date stated in Item ''Q*
falls on a Saturday, Sunday or public holiday in
the place for completion then unless Item Q
designates such date as a Saturday a Sunday or by
the name of the pubic holiday completion shall
take place - (a) on such other day as may be
agreed by the parties; or in default of such
agreement - (b) on the day other than a Saturday
Sunday or public holiday next following the date
stated in Item Q."
Time was said to be of the essence.
-- 43 of 51 --
The contract in fact referred to the sale of : a cattle
property called "Alkoombie" . The respondent held the property
as lessee from the Crown under the Land Act 1962-1988. The
lease, subject to the events to which I am about to refer, had
been a "Pastoral Lease" (PL14-4623) for a term of 30. years
commencing 1 April, 1964. By Division I of Part VI of the Act
the Minister, on application by a lessee, was empowered to grant
a new lease for the whole or part of a holding under a Pastoral
Lease that has not more than 10 years to run; s. 155(1) of the
Act. It is unnecessary for the moment to deal with other
provisions of the Act called into play upon such an application
being made.
In March 1988 the respondent applied for a new lease and on
7 April in that year the Land Administration Commission, on the
Minister's behalf, offered a new lease of part of the Alkoombie
holding exclusive of a defined area to be included in another
lease holding but inclusive of another defined area to be
surrendered from that holding which was of an adjoining property.
The purpose of these exchanges seems to have been to deal with
problems arising from the shapes of the two properties. The new
lease offered by the Land Administration Commission's letter of
7 April was of a different kind to a Pastoral Lease. It was to
be a Grazing Perpetual Homestead Lease to commence on 1 July,
1988. In furtherance of this the letter of 7 April, 1988
required the defendant to execute a surrender of the existing
Pastoral Lease and forward it together with the instrument of
lease in respect of Alkoombie.
-- 44 of 51 --
The instrument of surrender required by the letter of 7
April, 1988 was executed by the respondent on 10 May, 1988 and
received by the Land Administration Commission on 23 of that
month. The Pastoral Lease 14-4623 was also received there.
There were delays- in preparing survey plans giving effect to the
exchange of the two areas to which I have earlier referred. In
the event the plans were received on 24 February, 1989. The new
Grazing Perpetual Homestead Lease 14-23 was executed on 30 March,
1989 and, pursuant to s. 160(2) of the Act commenced on 1 July,
1988.
It may be accepted that at the time of the execution of the
contract of 15 August, 1988 the parties to the contract were
aware of the developments in respect of the surrender of the
Pastoral Lease and the issue of the Grazing Perpetual Homestead
Lease to which I have referred. I should mention that it is true
that the appellants apparently learned of the exchange between
Alkoombie and the adjoining property later but nothing seems to
turn on that .
It appears that by the date of the contract the Pastoral
■r
Lease under which Alkoombie was held had been surrendered. The
new Grazing Perpetual Homestead lease, however confidently, its
issue was anticipated, had in fact not issued. There is an
endorsement oh the instrument of surrender of the surrender. It
goes on to provide "now being GHPL 14-231 Cooktown" . The events
to which I have earlier referred in context of s. 160 of the Act
had the consequence that the surrender took effect on 30 June,
1988 and the terms of the new lease commenced from 1 July of that
year.
-- 45 of 51 --
5
Although it would seem to follow that at the date of the
contract the lease interest to which it referred had ceased to
exist no one suggested that the contract was thereby rendered
invalid. It would seem that the parties to the transaction
regarded themselves as buying and selling Alkoombie under
whatever title it might be held and perhaps in confident
*
anticipation of the issue of the new lease. In this context I
might say that there was no issue as to the admissibility of
evidence of the state of knowledge of the parties from the point
of view of identifying the subject matter of their contract.
As the contractual date of settlement (15 February, 1989)
approached it was evident that the instrument of lease for the
new Grazing Perpetual Homestead Lease would not issue in time for
that completion date. The date for completion was extended
ultimately to 1 March, 1989, time remaining of the essence. In
this context in a letter of 22. February, 1989 the respondent's
solicitor advised the appellants that "the replacement GHPL" was
expected to be issued within the next few days. There was an
attempt by the appellant's solicitors to obtain an extension to
6 March, 1989 but the date remained fixed at 1 March.
On 1 March, 1989 the respondent's solicitors faxed the
appellants. They advised that "GHPL 231 replacing PH1 4-4623 in
respect of Alkoombie Station" was recorded in the register of the
Land Administration Commission and the respondent's executed
transfer would be accepted there for registration. The
communication went on that the mortgage and related release of
mortgage were also held at the Commission together with "the
lease P.H. 14-4623 (surrendered)". The documents lodged with the
-- 46 of 51 --
6
Land Administration Commission "would be available for inspection
should you require a search".
The transaction was not completed on 1 March, 1989. This
was essentially because the new instrument of lease in respect
of the Grazing Perpetual Homestead Lease had not issued and
might, it was then anticipated, not issue for some 12 weeks. As
we know it was. executed ("issued") on 30 March. On any view of
it it was not executed and not available on 1 March.
After an exchange of communications in which the appellant's
solicitors reiterated their desire to finalise the contract
although the respondent was not in a position to settle in
accordance with its terms the respondent gave notice dated 2
March, 1989. By this she elected to terminate the contract on
the ground of the appellant's failure to attend its settlement
and otherwise complete and to declare the deposit forfeit. This
termination was not accepted by the appellants who required
performance and ultimately instituted proceedings for specific
performance. After a trial judgment was given for the respondent
a^d the declaration made that she had validly terminated the
contract. It was held that the deposit was repayable to the
appellant who were ordered to pay the respondent ' s costs of the
action. It is of course from that decision that this appeal is
brought. ' '
The case seems to me to turn essentially on the consequences
of cl. 2 of the contract in the circumstances existing at the
date of settlement on 1 March, 1989. Clause 2 is expressed to
require the balance purchase price "in exchange for", among other
things, an executed transfer "accompanied by the instrument of
-- 47 of 51 --
title". I may say that it seems to me difficult to avoid the
inference that the "instrument of title" referred to in cl. 2 is
to be taken to be the Grazing Perpetual Homestead Lease.
The obligations of vendor and purchaser under a clause such
as cl. 2 are interdependent, concurrent or reciprocal; Dainford
Ltd, v. Juana Ptv. Ltd. (1986) 1 Qd. R. 396 401, Sunbird Plaza
Ptv. Ltd, v. Malonev (1988) 166 C.L.R. 245.
At this point I digress to say that it seems to me that the
effect of dealings with land under the Land Acts, in the areas
relevant to present concern, bear no comparison with the dealings
with land under the Real Property Acts. Under the latter
legislation title is by registration and conveyance by instrument
is effectual to past title only when registered; Real Property
Act 1861-1988 s. 43 and Breskvar v. Wall (1971) 126 C.L.R. 376.
Registered title is then protected by the indefeasibility
provisions of the legislation. Nothing like this applies in
respect of the transfer of leases under the Land Act. There is
nothing to give the "historical register sheet" kept at the Land
Administration Commission anything like the status in terms of
•i
conclusiveness and indefeasibility conferred by the Real Property
Act on registration under that legislation.
It is true that under the Land Act particulars of leases and
of transfers and of other dealings are, by s. 226 and 227 to be
recorded in a register or registers and that "priority of
registrations of the dealings" is to be maintained. That is
however as far as it goes . I cannot therefore persuade myself
that the historical register search was "an instrument of title"
within the meaning of cl. 2 of the contract. In fact as at the
-- 48 of 51 --
8
*>
0
date of settlement of 1 March, 1989 and as I have already said
the Perpetual Lease had been surrendered and the Grazing
Perpetual Homestead Lease had not issued. It may well be that
all the respondent had to offer was whatever obligation was
imposed on the Governor in Council to issue a new lease; see s.
160(1) of the Act that was subject to s. 162 which would seem to
impose serious inhibition on obtaining the intervention of the
Court to enforce such rights. Again that is as far as it could
go.
There seems to be no comfort in the description in the
contract particulars of the subject matter of the contract being
Pastoral Lease number 14-4623 located at the ANZ Bank, Mareeba.
That had been surrendered and was in the office of the Land
Administration Commission.
One may accept the learned trial judge's characterisation
of the transaction as a contract for the purchase of "the rights
or expectations of rights" that would be held by the respondent
in Alkoombie as at the date of settlement although to do so is
not without difficulty in the circumstances as I have outlined
them. In any event there seems to me to have been nothing
capable of satisfying the requirement of cl. 2 of the contract
that an instrument of title accompany the duly executed transfer.
The appellant ' s corresponding duty to tender was only capable of
arising when there was. It follows that on 1 March, 1989 the
respondent was not in a position to complete in terms of cl. 2
and settle the contract and the occasion for the appellant's
performance as contemplated by cl. 2 did not arise. The
-- 49 of 51 --
9
O 1
appellant's failure to settle therefore affords no basis for the
respondent's termination of the contract.
It seems to me not to the point for present purposes that
delay in the issue of the new Grazing Perpetual Homestead Lease
was not through-any default of the respondent. That may have
consequences in other circumstances but relevantly for present
purposes did not afford the respondent a basis to terminate the
contract. Any tender on the appellant's behalf on 1 May, 1989
would have been futile.
The respondents giving notice of termination of 2 March,
1989 constituted a repudiation on her part of the contract but
it was not accepted. The contract therefore continues on foot
and with it the appellant's entitlement to specific performance.
There are one or two other matters to be mentioned. One is
that I think it will be sufficiently clear by now that I regard
the subject matter of the contract as sufficiently certain to
admit of the contract ' s enforcement. The second point relates
to a special condition of contract making the sale subject to the
consent of the Minister for Land to the transfer of leaseholds
under the provisions of the Land Act. The Minister's delegate
consented on 3 December, 1988 on the basis of the issue of the
new Grazing Homestead Perpetual Lease. That would seem
sufficient. '
In any event cl. 16 of the standard conditions of contract
is to the effect that if necessary Ministerial consent is not
granted by the date of completion the parties have the option to
terminate the contract upon which the deposit becomes repayable.
Any rights which may have subsisted under the contract in respect
-- 50 of 51 --
10
of a failure of Ministerial approval were overtaken,- or so \it j
seems to me, when the respondent insisted on completion on 1
March. She gave notice of termination on grounds not referable
to cl. 16 and purported to forfeit the deposit inconsistently
with that clause*
In sum as to the Ministerial consent point it seems to me
that there was a consent within the meaning of the special
condition of contract. Clause 16 has no application.
The outcome of all this is, it seems to me, that the appeal
should be allowed, the judgment below should be set aside and the
plaintiffs should have specific performance of the contract.
J
t.
I
-- 51 of 51 --
Official source: https://www.sclqld.org.au/caselaw/QSCFC/1991/023